Silver Creek Bridge STR-77-2(1070) cn 13005 (East of Wahoo)
The project consists of removing and replacing the deck and approach slab, driving sheet pile behind the existing abutment and replacing abutment turn down. The bridge is approximately 60 feet long and 32 feet wide.
NDOR anticipates posting plans Wednesday and accepting bids on Monday. Work is expected to start July 28 and last 3 to 4 weeks.
|