Official State of Nebraska site logo

 



50 years of Interstate logo


Main I-80/Ogallala Flood Page

Bridge Damage Photos

Return to History
Return to Main NDOR

 

Regular Acrobat Reader Download
Help with PDF's for those with visual disabilities


 

Repair Efforts & Reopening

After the July 6, 2002, flood waters receded, NDOR employees and contractors worked 24 hours a day in oppressive heat to repair the damaged bridge approaches.

I-80 Flood logo-no action

The Repairs & Reopening
July 8-12, 2002

Repairs began Sunday, July 7th, to interchange ramps and overheads that were clear of water. Nebraska Department of Roads Director, John Craig declared that fixing the I-80 break was "priority No. 1." Gov. Mike Johanns toured the scene and declared the area a disaster, allowing the Roads Department to forgo the usual bidding process to find a contractor. Flooding receded sufficiently by Monday to allow engineers to determine that the bridges were structurally sound and only the approaches needed rebuilding.

At 1 pm. Monday, July 8, Les O'Donnell, NDOR District Engineer for District 6,  gave Dave Neill, the project manager, until 2:30 pm. to come up with a repair estimate. At 3 pm., they announced that the bridge approaches would be fixed by the following Monday at an estimated cost of less than $1 million. "Then it all just started falling into place," O'Donnell said.

The repairs occurred at a dizzying pace. Volunteers appeared. Lights were set up for night work. Scores of workers from the State Department of Roads and 11 construction and trucking companies labored around the clock. They hauled about 1,000 truckloads of fill material and laid hundreds of tons of asphalt. The State Patrol and the National Guard rerouted traffic.

"Whatever you needed, people were willing to pitch in," Neill said. Loaders. Trucks. Bulldozers. Excavators. Neill finally had to start turning down the offers: The project just wasn't big enough for all those machines.

The result of the furious, round-the-clock repair effort was that the connection was restored two days before the one-week target.

"It's just an unbelievable effort on a lot of people's parts," O'Donnell said Friday afternoon, July 12, 2002.

(Click on each thumbnail below to see a larger view)

Removing one of the obstructions

Rebuilding the banks

Another truck load of rock

Rebuilding the banks-stabilization

Bank stabilization

Bank stabilization

Using a nuclear density gauge to check the compaction

Setting a string line before laying another layer of asphalt.

Resurface work

Resurface work

Making sure there are no bumps

Aerial View Thursday afternoon, July 11th
The above photos were taken by Linda Wilson, NDOR Communication Division

Shortly after 9 pm CDT, Friday, July 12, 2002, traffic flows smoothly once more over the bridges that had been damaged by the flood waters.

Another photo taken right after I-80 reopened.
Re-opening photos by Roger Klasna, District 6, NDOR
Thanks to the Omaha World Herald for allowing us to use some material from their stories about the flood

Some of these photos were supplied by the Nebraska State Patrol
Thanks to the Omaha World Herald for allowing us to use some material from their stories about the flood

Questions/Comments