Project Overview

Kearney West
Project #: STPD-30-4(147)
Control #: 42339

Project Contacts:
Dawn Allen, NDOR Assistant Design Engineer, 402-479-4663
Tony Kessler
, NDOR Design Consultant Coordinator, 402-479-3994

Views of Proposed Construction

We have tried to provide the map info in the best format for fastest download/viewing. Most are in DjVu, which reduces them even more. JPG format is provided for those who wish to download and reproduce the info, however the files are very large, so please allow for sufficient download time.

If you do not have the DjVu reader, please download the FREE READER by clicking on the DjVu button above.

Proposed Construction : Construction of a four lane divided highway of existing US 30 west of the Kearney city limits. The project will begin approximately 1/2 mile west of Dove Hill Road and extend east 3 1/2 miles to just west of 30th Ave. Several connecting roadways will be constructed along the route to provide access at: Dove Hill Road, 65th Ave. PL, Riverdale Road, Cottonmill Lake Road, 46th Ave, and Rolling Hills Road.

Lighting/Signals/Signing: Roadway Lighting will be provided through the urban section and at all intersections with the proposed construction..

Right-of-Way: Right of Way and access control will be acquired along the entire project.

Phasing: Traffic will be maintained on existing US 30 at all times. Staging will be required at all tie-in locations.

Schedule: September 3, 2009, Bid Letting

Estimated Cost: 10.2 Million