Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2119 TOPKOTE, INC. |
Contract ID: | 8903B |
Estimate Number: | 0004 |
Pay Period End Date: | 12.06.2002 |
Contract Location: | ||
SHERIDAN/CHERRY CO. LINE EAST | Estimate Type: | PROG |
Contractor: | ||
TOPKOTE, INC. | Date Let: | 05.23.2002 |
43439 SD HWY 50 | Date Awarded: | 05.30.2002 |
Date Contract Executed: | 06.11.2002 | |
Date Notice to Proceed: | 06.11.2002 | |
YANKTON SD 57078 | Date Work Began: | 08.19.2002 |
Phone: | Date Physical Work Completed: | |
(605)665-8106 | Date Accepted: | 10.02.2002 |
Escrow Agent: | ||
Surety Co: | ||
FIDELITY AND DEPOSIT COMPANY OF MARYLAND |
Counties |
---|
CHERRY |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
89903B 000 |   | 0.000 |   | PM-20-2(1027) |   | BITUMINOUS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $135,627.28 | $130,627.28 | $5,000.00 |
$85,626.90 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $135,627.28 | $130,627.28 | $5,000.00 |
$80,626.90 | Retainage | $-1,356.27 | $-1,306.27 | $-50.00 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
158.39% | Net Earnings | $134,271.01 | $129,321.01 | $4,950.00 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $134,271.01 | $129,321.01 | $4,950.00 | |
Project Manager | Div. Head/Dist. Eng. | |||
Rudnick, Michael | 12.06.2002 | Kovar, Mark | 12.06.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 12.09.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 12.09.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 9 BITUMINOUS | |||
0001 0001.10 | 3.00 | 24.000 | 72.00 |
BARRICADE, TYPE III | BDAY | 24.000 | 72.00 |
14.000 | 42.00 | ||
0.000 | 0.00 | ||
0002 0001.30 | 3.00 | 12.000 | 36.00 |
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 12.000 | 36.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0003 0001.75 | 3.00 | 30.000 | 90.00 |
TEMPORARY SIGN DAY | EACH | 30.000 | 90.00 |
24.000 | 72.00 | ||
0.000 | 0.00 | ||
0004 0001.90 | 3.00 | 294.000 | 882.00 |
SIGN DAY | EACH | 294.000 | 882.00 |
749.000 | 2,247.00 | ||
0.000 | 0.00 | ||
0005 0002.45 | 3.00 | 333.000 | 999.00 |
TEMPORARY BROKEN LINES | STA | 333.000 | 999.00 |
333.170 | 999.51 | ||
0.000 | 0.00 | ||
0006 0003.10 | 5.00 | 10.000 | 50.00 |
FLAGGING | DAY | 10.000 | 50.00 |
5.000 | 25.00 | ||
0.000 | 0.00 | ||
0007 0003.20 | 10.00 | 5.000 | 50.00 |
FURNISHING AND OPERATING PILOT VEHICLE | DAY | 5.000 | 50.00 |
2.500 | 25.00 | ||
0.000 | 0.00 | ||
0008 0030.90 | 10,000.00 | 1.000 | 10,000.00 |
MOBILIZATION | LS | 1.000 | 10,000.00 |
1.000 | 10,000.00 | ||
0.000 | 0.00 | ||
0009 8008.00 | 62.98 | 680.000 | 42,826.40 |
ARMOR COAT AGGREGATE | CY | 680.000 | 42,826.40 |
1,305.000 | 82,188.90 | ||
0.000 | 0.00 | ||
0010 9052.00 | 0.93 | 27,550.000 | 25,621.50 |
ARMOR COAT EMULSIFIED ASPHALT | GAL | 27,550.000 | 25,621.50 |
37,664.380 | 35,027.87 | ||
0.000 | 0.00 | ||
4000 0030.90 | 1.000 | ||
MOBILIZATION | LS | 2.000 | 0.00 |
For additionial mobilization | 1.000 | 5,000.00 | |
1.000 | 5,000.00 | ||
GROUP 9 BITUMINOUS | Contracted | 80,626.90 | |
Current | 85,626.90 | ||
In place | 135,627.28 | ||
This Estimate | 5,000.00 | ||
Totals for contract | Contracted | 80,626.90 | |
Current | 80,626.90 | ||
In place | 135,627.28 | ||
This Estimate | 5,000.00 |