Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:8663
Estimate Number:0018
Pay Period End Date:08.11.2001
Contract Location:
STAFFORD TO L-45BEstimate Type:FINL
Contractor:
WERNER CONSTRUCTION, INC.Date Let:02.17.2000
129 E 2ND STDate Awarded:03.02.2000
PO BOX 1087Date Contract Executed:03.08.2000
Date Notice to Proceed:03.08.2000
HASTINGS NE 68902-1087Date Work Began:03.23.2000
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:11.06.2001
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
HOLT
Project Number PCT Fed State Project Number Description
80663 000B  0.000 EACNH-BR-20-4(119)  GRAD CULV BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$3,068,513.23$3,068,513.23$.00
$3,005,931.34Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$3,068,513.23$3,068,513.23$.00
$2,885,117.51Retainage$.00$-25,000.00$25,000.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
102.08%Net Earnings$3,068,513.23$3,043,513.23$25,000.00
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$3,068,513.23$3,043,513.23$25,000.00
Project ManagerDiv. Head/Dist. Eng.
Ziska, Dan08.14.2001Kovar, Mark08.15.2001
Constr. Estimate Eng.Materials Eng.
Davis, Carl01.24.2002DeButts, Rhonda01.25.2002
Controller Div. Processed
Harring, Joyce04.24.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.00 1.751,080.0001,890.00
EROSION CONTROL m2 1,080.0001,890.00
760.4001,330.70
0.0000.00

0002                          L020.01 5.707,311.00041,672.70
EROSION CONTROL, TYPE A m2 7,311.00041,672.70
7,773.80044,310.66
0.0000.00

0003                          L020.09 12.00698.0008,376.00
EROSION CONTROL, TYPE AAA m2 698.0008,376.00
607.0007,284.00
0.0000.00

0004                          L020.10 1.752,071.0003,624.25
EROSION CONTROL, TYPE HV m2 2,071.0003,624.25
1,864.0003,262.00
0.0000.00

0005                          L021.01 20.00138.0002,760.00
EROSION CHECKS, TYPE A BALE138.0002,760.00
170.0003,400.00
0.0000.00

0006                          L021.06 18.00300.0005,400.00
EROSION CHECKS, TYPE HV BALE300.0005,400.00
301.0005,418.00
0.0000.00

0007                          L021.11 30.00366.00010,980.00
EROSION CHECKS, TYPE ST-A BALE366.00010,980.00
403.00012,090.00
0.0000.00

0008                          L021.15 27.5024.000660.00
EROSION CHECKS, TYPE ST-HV BALE24.000660.00
24.000660.00
0.0000.00

0009                          L022.11 6.751,177.0007,944.75
FABRIC SILT FENCE-LOW POROSITY m 1,177.0007,944.75
943.0006,365.25
0.0000.00

0010                          L022.12 8.501,710.00014,535.00
FABRIC SILT FENCE-HIGH POROSITY m 1,710.00014,535.00
1,359.00011,551.50
0.0000.00

0011                          L022.25 9.755,987.00058,373.25
FABRIC SILT FENCE, TYPE COIR FIBER m 5,987.00058,373.25
5,837.00056,910.75
0.0000.00

0012                          P402.24 66.00127.0008,382.00
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 127.0008,382.00
127.0008,382.00
0.0000.00

0013                          0030.10 9,600.001.0009,600.00
MOBILIZATION LS 1.0009,600.00
1.0009,600.00
0.0000.00

0014                          1000.00 80.00367.00029,360.00
LARGE TREE REMOVAL EACH367.00029,360.00
370.00029,600.00
0.0000.00

0015                          1010.00 0.9618,466.00017,727.36
EXCAVATION m3 18,466.00017,727.36
32,280.28030,989.07
0.0000.00

0016                          1010.01 3.20315.0001,008.00
EXCAVATION (ESTABLISHED QUANTITY) m3 315.0001,008.00
300.000960.00
0.0000.00

0017                          1010.10 2.4551,022.000125,003.90
EXCAVATION, BORROW m3 51,022.000125,003.90
54,388.000133,250.60
0.0000.00

0018                          1011.00 2.001,737.0003,474.00
WATER kL 1,737.0003,474.00
4.1708.34
0.0000.00

0019                          1012.00 70.00120.0008,400.00
RIGHT-OF-WAY MARKERS EACH120.0008,400.00
120.0008,400.00
0.0000.00

0020                          1040.00 0.37223,000.00082,510.00
SLOPE PROTECTION m2 223,000.00082,510.00
276,168.000102,182.16
0.0000.00

0021                          1040.06 70.00101.0007,070.00
SLOPE PROTECTION MULCH Mg 101.0007,070.00
259.71018,179.70
0.0000.00

0022                          1102.00 3.202,349.0007,516.80
REMOVE ASPHALT SURFACE m2 2,349.0007,516.80
937.0002,998.40
0.0000.00

0023                          1109.00 6.00728.0004,368.00
REMOVE CURB m 728.0004,368.00
728.0004,368.00
0.0000.00

0024                          1300.48 138.4434.0004,706.96
1200 mm DRIVEWAY CULVERT PIPE m 34.0004,706.96
TYPE 2,3,4,5 OR 6 34.0004,706.96
0.0000.00

0025                          1500.36 22.0021.400470.80
INSTALL 900 mm CORRUGATED METAL PIPE m 21.400470.80
17.600387.20
0.0000.00

0026                          1701.24 66.00130.0008,580.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 130.0008,580.00
130.0008,580.00
0.0000.00

0027                          1701.36 93.9317.0001,596.81
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 17.0001,596.81
32.2003,024.55
0.0000.00

0028                          4050.01 10.00323.0003,230.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 323.0003,230.00
323.0003,230.00
0.0000.00

0029                          4100.06 500.001.680840.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 1.680840.00
1.680840.00
0.0000.00

0030                          4150.00 2.0080.000160.00
REINFORCING STEEL FOR HEADWALL kg 80.000160.00
80.000160.00
0.0000.00

0031                          4310.24 180.004.000720.00
600 mm FLARED-END SECTION EACH4.000720.00
4.000720.00
0.0000.00

0032                          7017.00 4.50186.000837.00
REMOVE GUARDRAIL m 186.000837.00
186.000837.00
0.0000.00

GROUP 1 GRADINGContracted481,777.58
Current481,777.58
In place523,986.84
This Estimate0.00

GROUP 4 CULVERTS
0033                          P300.18 46.569.000419.04
450 mm CULVERT PIPE, TYPE 3,4 OR 5 m 9.000419.04
3.000139.68
0.0000.00

0034                          P300.24 55.005.000275.00
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 5.000275.00
11.000605.00
0.0000.00

0035                          P300.30 87.005.000435.00
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 5.000435.00
5.000435.00
0.0000.00

0036                          P300.36 86.004.000344.00
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 4.000344.00
4.000344.00
0.0000.00

0037                          P300.48 110.0013.0001,430.00
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 13.0001,430.00
13.0001,430.00
0.0000.00

0038                          P311.24 86.0020.0001,720.00
600 mm CULVERT PIPE, TYPE 2, 7 OR 8 m 20.0001,720.00
20.0001,720.00
0.0000.00

0039                          P600.24 47.0045.5002,138.50
600 mm CULVERT PIPE, TYPE 2,3,4,5,7 OR 8 m 45.5002,138.50
45.5002,138.50
0.0000.00

0040                          P600.30 73.5277.0005,661.04
750 mm CULVERT PIPE, TYPE 2, 3, 4, 5, 7 OR 8 m 77.0005,661.04
77.0005,661.04
0.0000.00

0041                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0042                          4035.00 108.0019.0002,052.00
REMOVE FLARED-END SECTION EACH19.0002,052.00
19.0002,052.00
0.0000.00

0043                          4040.00 123.002.000246.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000246.00
2.000246.00
0.0000.00

0044                          4044.00 900.001.000900.00
PREPARATION OF STRUCTURE EACH1.000900.00
AT STA 11+25.10 1.000900.00
0.0000.00

0045                          4050.01 10.46474.0004,958.04
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 474.0004,958.04
474.0004,958.04
0.0000.00

0046                          4051.01 15.69154.0002,416.26
EXCAVATION FOR BOX CULVERTS m3 154.0002,416.26
154.0002,416.26
0.0000.00

0047                          4101.06 296.0098.12029,043.52
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 98.12029,043.52
98.12029,043.52
0.0000.00

0048                          4151.00 1.345,314.0007,120.76
REINFORCING STEEL FOR BOX CULVERT kg 5,314.0007,120.76
5,314.0007,120.76
0.0000.00

0049                          4310.18 65.004.000260.00
450 mm FLARED-END SECTION EACH4.000260.00
2.000130.00
0.0000.00

0050                          4310.24 82.008.000656.00
600 mm FLARED-END SECTION EACH8.000656.00
10.000820.00
0.0000.00

0051                          4310.30 135.008.0001,080.00
750 mm FLARED-END SECTION EACH8.0001,080.00
8.0001,080.00
0.0000.00

0052                          4310.36 205.002.000410.00
900 mm FLARED-END SECTION EACH2.000410.00
2.000410.00
0.0000.00

0053                          4310.48 550.002.0001,100.00
1200 mm FLARED-END SECTION EACH2.0001,100.00
2.0001,100.00
0.0000.00

0132                          4061.01 15.690.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 53.000831.57
Group 4 Station 11+25.1Group 4 Station 11+37.1-30m Lt. 53.000831.57
0.0000.00

0136                          4976.05 1,548.750.0000.00
ADDITIONAL WORK LS 1.0001,548.75
Relocation of approx. 56 meters of street lighting conduit and cable due to the box culvert extension at Sta. 11+25.1 1.0001,548.75
0.0000.00

133                           4051.12 29.600.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 53.0001,568.80
Group 4 Station 11+25Group 4 Station 11+37.1-30m Lt. 53.0001,568.80
0.0000.00

GROUP 4 CULVERTSContracted65,165.16
Current69,114.28
In place69,198.92
This Estimate0.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 32+58.45
0054                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0055                          4051.01 21.00199.0004,179.00
EXCAVATION FOR BOX CULVERTS m3 199.0004,179.00
199.0004,179.00
0.0000.00

0056                          4101.06 380.00242.43092,123.40
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 242.43092,123.40
242.43092,123.40
0.0000.00

0057                          4151.00 1.2016,257.00019,508.40
REINFORCING STEEL FOR BOX CULVERT kg 16,257.00019,508.40
16,257.00019,508.40
0.0000.00

0058                          6040.00 2,000.001.0002,000.00
REMOVE STRUCTURE EACH1.0002,000.00
AT STA. 32+58.45 1.0002,000.00
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 32+58.45Contracted119,810.80
Current119,810.80
In place119,810.80
This Estimate0.00

GROUP 4B CONCRETE BOX CULVERT AT STA. 36+25
0059                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0060                          4051.01 16.00994.00015,904.00
EXCAVATION FOR BOX CULVERTS m3 994.00015,904.00
994.00015,904.00
0.0000.00

0061                          4101.06 380.00242.43092,123.40
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 242.43092,123.40
242.43092,123.40
0.0000.00

0062                          4151.00 1.2016,257.00019,508.40
REINFORCING STEEL FOR BOX CULVERT kg 16,257.00019,508.40
16,257.00019,508.40
0.0000.00

0134                          4061.01 16.000.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 132.0002,112.00
Group 4B - Station 36+25 126.0002,016.00
0.0000.00

0135                          4051.12 38.000.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 132.0005,016.00
Group 4B - Station 36+25 126.0004,788.00
0.0000.00

GROUP 4B CONCRETE BOX CULVERT AT STA. 36+25Contracted129,535.80
Current136,663.80
In place136,339.80
This Estimate0.00

GROUP 4C CONCRETE BOX CULVERT AT STA. 46+02.3
0063                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0064                          4044.00 1,500.001.0001,500.00
PREPARATION OF STRUCTURE EACH1.0001,500.00
AT STA 46+02.3 1.0001,500.00
0.0000.00

0065                          4051.01 21.00101.0002,121.00
EXCAVATION FOR BOX CULVERTS m3 101.0002,121.00
101.0002,121.00
0.0000.00

0066                          4101.06 380.0066.58025,300.40
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 66.58025,300.40
66.58025,300.40
0.0000.00

0067                          4151.00 1.204,632.0005,558.40
REINFORCING STEEL FOR BOX CULVERT kg 4,632.0005,558.40
4,632.0005,558.40
0.0000.00

0130                          4061.01 21.000.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 50.0001,050.00
Group 4C Sta. 46+02.3 50.0001,050.00
0.0000.00

0131                          4051.12 38.000.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 50.0001,900.00
Group 4C Sta. 46+02.3 50.0001,900.00
0.0000.00

0139                          4976.05 2,538.420.0000.00
ADDITIONAL WORK LS 1.0002,538.42
Cleanout Silt from inside the box culvert at Station 46+02.3 1.0002,538.42
0.0000.00

GROUP 4C CONCRETE BOX CULVERT AT STA. 46+02.3Contracted36,479.80
Current41,968.22
In place41,968.22
This Estimate0.00

GROUP 6 BRIDGE AT STA. 26+96.8
0068                          0030.60 36,000.001.00036,000.00
MOBILIZATION LS 1.00036,000.00
1.00036,000.00
0.0000.00

0069                          1043.50 7.0052.000364.00
RIPRAP FILTER FABRIC m2 52.000364.00
340.0002,380.00
0.0000.00

0070                          3050.15 262.00142.00037,204.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 142.00037,204.00
142.00037,204.00
0.0000.00

0071                          3051.10 1.459,000.00013,050.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,000.00013,050.00
9,000.00013,050.00
0.0000.00

0072                          6000.10 2,700.001.0002,700.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,700.00
1.0002,700.00
0.0000.00

0073                          6000.11 2,700.001.0002,700.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,700.00
1.0002,700.00
0.0000.00

0074                          6001.50 10,000.001.00010,000.00
BENT NO.1 EXCAVATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

0075                          6001.51 10,000.001.00010,000.00
BENT NO.2 EXCAVATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

0076                          6010.22 435.00113.40049,329.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 113.40049,329.00
113.40049,329.00
0.0000.00

0077                          6010.26 380.00115.80044,004.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 115.80044,004.00
115.80044,004.00
0.0000.00

0078                          6011.11 126,000.001.000126,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000126,000.00
AT STA. 26+96.8 1.000126,000.00
0.0000.00

0079                          6040.00 24,000.001.00024,000.00
REMOVE STRUCTURE EACH1.00024,000.00
AT STA. 26+93 1.00024,000.00
0.0000.00

0080                          6080.00 4.002,130.0008,520.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 2,130.0008,520.00
2,130.0008,520.00
0.0000.00

0081                          6104.00 25.00269.0006,725.00
BROKEN CONCRETE RIPRAP Mg 269.0006,725.00
269.0006,725.00
0.0000.00

0082                          6131.50 1.5323,815.00036,436.95
EPOXY COATED REINFORCING STEEL kg 23,815.00036,436.95
23,815.00036,436.96
0.0000.00

0083                          6210.50 80.00722.00057,760.00
PIPE PILING m 722.00057,760.00
722.00057,760.00
0.0000.00

0084                          6310.00 120.00330.00039,600.00
STEEL SHEET PILING m2 330.00039,600.00
330.00039,600.00
0.0000.00

0085                          8091.00 25.00235.0005,875.00
GRANULAR BACKFILL m3 235.0005,875.00
235.0005,875.00
0.0000.00

GROUP 6 BRIDGE AT STA. 26+96.8Contracted510,267.95
Current510,267.95
In place512,283.96
This Estimate0.00

GROUP 7 GUARDRAIL
0086                          0030.70 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0087                          7011.20 50.0030.4801,524.00
W-BEAM GUARDRAIL m 30.4801,524.00
30.4801,524.00
0.0000.00

0088                          7020.00 1,500.004.0006,000.00
BRIDGE APPROACH SECTIONS EACH4.0006,000.00
4.0006,000.00
0.0000.00

0089                          7021.70 1,600.004.0006,400.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0006,400.00
4.0006,400.00
0.0000.00

GROUP 7 GUARDRAILContracted15,424.00
Current15,424.00
In place15,424.00
This Estimate0.00

GROUP 9 BITUMINOUS
0090                          P402.15 89.00162.50014,462.50
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 162.50014,462.50
162.50014,462.50
0.0000.00

0091                          0002.45 26.00294.0007,644.00
TEMPORARY BROKEN LINES StaM294.0007,644.00
115.0602,991.56
0.0000.00

0092                          0030.90 60,000.001.00060,000.00
MOBILIZATION LS 1.00060,000.00
1.00060,000.00
0.0000.00

0093                          2001.00 12.5083.0001,037.50
GRAVEL SURFACE COURSE m3 83.0001,037.50
116.0001,450.00
0.0000.00

0094                          4024.55 165.0065.30010,774.50
FLUME SPILLWAY m 65.30010,774.50
65.30010,774.50
0.0000.00

0095                          4024.70 1,700.004.0006,800.00
CONCRETE FLUME, TYPE I EACH4.0006,800.00
4.0006,800.00
0.0000.00

0096                          4024.71 1,750.008.00014,000.00
CONCRETE FLUME, TYPE II EACH8.00014,000.00
8.00014,000.00
0.0000.00

0097                          4024.73 1,700.0012.00020,400.00
CONCRETE FLUME, TYPE IV EACH12.00020,400.00
12.00020,400.00
0.0000.00

0098                          9000.75 16.27100.0001,627.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 100.0001,627.00
SPS 0.0000.00
0.0000.00

0099                          9005.00 21.902,700.00059,130.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 2,700.00059,130.00
SP2(12.5) 684.65014,993.84
0.0000.00

0100                          9005.23 16.2713,560.000220,621.20
ASPHALTIC CONCRETE, TYPE SPS Mg 13,560.000220,621.20
15,459.970251,533.71
0.0000.00

0101                          9005.30 21.9021,320.000466,908.00
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 21,320.000466,908.00
25,994.000569,268.60
0.0000.00

0102                          9009.00 2.742,358.0006,460.92
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 2,358.0006,460.92
2,502.0006,855.48
0.0000.00

0103                          9020.92 205.005.2001,066.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 5.2001,066.00
0.0000.00
0.0000.00

0104                          9021.03 205.001,934.960396,666.80
PERFORMANCE GRADED BINDER (58-28) Mg 1,934.960396,666.80
1,807.235370,483.18
0.0000.00

0105                          9030.00 5.003,014.00015,070.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 3,014.00015,070.00
3,320.00016,600.00
0.0000.00

0106                          9034.00 2.501,675.0004,187.50
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,675.0004,187.50
302.000755.00
0.0000.00

0107                          9053.00 0.26136,220.00035,417.20
TACK COAT L 136,220.00035,417.20
152,481.00039,645.06
0.0000.00

0108                          9111.00 2.001,251.0002,502.00
WATER kL 1,251.0002,502.00
0.0000.00
0.0000.00

0109                          9170.00 220.00214.66647,226.52
EARTH SHOULDER CONSTRUCTION StaM214.66647,226.52
209.47446,084.28
0.0000.00

0110                          9173.10 140.00196.01127,441.54
SUBGRADE PREPARATION FOR WIDENING StaM196.01127,441.54
187.55526,257.70
0.0000.00

0111                          9173.20 5.00386.0001,930.00
SUBGRADE PREPARATION m2 386.0001,930.00
0.0000.00
0.0000.00

0112                          9179.23 280.0098.33327,533.24
COLD MILLING, CLASS 3 StaM98.33327,533.24
96.98627,156.08
0.0000.00

0113                          9188.50 25.00166.0004,150.00
SURFACING UNDER GUARDRAIL m2 166.0004,150.00
166.0004,150.00
0.0000.00

0114                          9300.01 25.006.000150.00
ASPHALT CONCRETE THICKNESS CORE EACH6.000150.00
0.0000.00
0.0000.00

0115                          9300.50 3,000.001.0003,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0003,000.00
1.0003,000.00
0.0000.00

0137                          4976.05 2,100.000.0000.00
ADDITIONAL WORK LS 1.0002,100.00
Milling of outside edge of shoulder to replace deteriorated asphalt. 1.0002,100.00
0.0000.00

0138                          9179.43 1,763.280.0000.00
COLD MILLING, CLASS 3 StaM10.25018,073.62
To remove approx. 175mm of existing asphalt which was rutting. 9.30016,398.50
0.0000.00

0140                          9190.50 25.750.0000.00
FLY ASH Mg 255.0206,566.77
Material for use in fly ash stabilization 255.0206,566.77
0.0000.00

0141                          9190.10 7.340.0000.00
FLY ASH STABILIZED BITUMINOUS m2 3,044.50022,346.63
Incorporation and compacting fly ash 3,044.50022,346.63
0.0000.00

0142                          0030.00 1.000
MOBILIZATION LS 2.0000.00
For Subcontractor (Brown & Borwn) to mobilize to the project 1.00010,500.00
0.0000.00

0143                          9300.56 0.8850.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 25,994.00023,004.69
SP2 (12.5) 25,994.00023,004.69
0.0000.00

0144                          9300.77 8.960.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 421.6403,777.89
Smoothness Incentive Asph Cement (58-28) 421.6403,777.89
0.0000.00

0145                          9300.60 0.960.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 8,604.9008,260.70
Smooth Incentive-Asphaltic Concrete SP2(12.5) 8,604.9008,260.70
0.0000.00

GROUP 9 BITUMINOUSContracted1,456,206.42
Current1,550,836.72
In place1,600,616.67
This Estimate0.00

GROUP 10 GENERAL ITEMS
0116                          0001.10 3.502,896.00010,136.00
BARRICADE, TYPE III BDAY4,894.00017,129.00
4,403.00015,410.50
0.0000.00

0117                          0001.30 3.50724.0002,534.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY724.0002,534.00
703.0002,460.50
0.0000.00

0118                          0001.90 1.005,430.0005,430.00
SIGN DAY EACH5,430.0005,430.00
5,153.0005,153.00
0.0000.00

0119                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
1.0001,500.00
0.0000.00

0120                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
1.00010,000.02
0.0000.00

0121                          9110.01 60.00230.00013,800.00
RENTAL OF LOADER, FULLY OPERATED HOUR230.00013,800.00
40.5002,430.00
0.0000.00

0122                          9110.02 65.0080.0005,200.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR80.0005,200.00
40.5002,632.50
0.0000.00

0123                          9110.03 50.00230.00011,500.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR230.00011,500.00
32.5001,625.00
0.0000.00

0124                          9110.07 45.00230.00010,350.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR230.00010,350.00
13.000585.00
0.0000.00

0129                          0003.10 175.000.0000.00
FLAGGING DAY 15.0002,625.00
40.5007,087.50
0.0000.00

GROUP 10 GENERAL ITEMSContracted70,450.00
Current80,068.00
In place48,884.02
This Estimate0.00

Totals for contractContracted2,885,117.51
Current2,995,431.35
In place3,068,513.23
This Estimate0.00