Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:8635
Estimate Number:0010
Pay Period End Date:12.14.2002
Contract Location:
AMELIA SOUTHEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:04.18.2002
129 E 2ND STDate Awarded:04.29.2002
PO BOX 1087Date Contract Executed:05.07.2002
Date Notice to Proceed:05.07.2002
HASTINGS NE 68902-1087Date Work Began:05.28.2002
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
GARFIELD
HOLT
Project Number PCT Fed State Project Number Description
80635 000  0.000 EACSTPD-11-4(111)  GR CULV ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,784,617.40$2,782,286.73$2,330.67
$2,756,717.93Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,784,617.40$2,782,286.73$2,330.67
$2,671,256.70Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
101.01%Net Earnings$2,759,617.40$2,757,286.73$2,330.67
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$162.39$162.39$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$162.39$162.39$.00
Payment$2,759,779.79$2,757,449.12$2,330.67
Project ManagerDiv. Head/Dist. Eng.
Ziska, Dan12.17.2002Kovar, Mark12.18.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve12.19.2002
Controller Div. Processed
Burling, Laurie12.19.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
Group 10 GENERAL ITEMS
4017                          0096.00 -5,500.000.0000.00
DEDUCTION LS 1.000-5,500.00
Deduction for destroying the "SWAN", HARN Control Station Marker. 1.000-5,500.00
1.000-5,500.00

4019                          0096.10 -5.000.0000.00
DEDUCTION Mg 150.000-750.00
Deduction for NDOR millings hauled to the plant site but not used as RAP during Asphalt production. 150.000-750.00
150.000-750.00

Group 10 GENERAL ITEMSContracted0.00
Current-6,250.00
In place-6,250.00
This Estimate-6,250.00

GROUP 1 GRADING
0001                          L020.01 6.005,774.70034,648.20
EROSION CONTROL, TYPE A m2 5,774.70034,648.20
5,264.23031,585.38
-1,637.500-9,825.00

0002                          L020.20 0.602,300.0001,380.00
SLOPE PROTECTION NETTING m2 5,300.0003,180.00
3,016.1301,809.68
0.0000.00

0003                          L021.01 25.0091.0002,275.00
EROSION CHECKS, TYPE A BALE91.0002,275.00
91.0002,275.00
0.0000.00

0004                          L022.25 11.50170.0001,955.00
FABRIC SILT FENCE, TYPE COIR FIBER m 170.0001,955.00
127.3001,463.95
0.0000.00

0005                          L030.75 7.505,993.00044,947.50
MANURE TOPDRESSING m3 5,993.00044,947.50
5,993.28744,949.65
-0.104-0.78

0006                          P300.24 65.0069.5004,517.50
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 69.5004,517.50
69.5004,517.50
0.0000.00

0007                          0030.10 9,600.001.0009,600.00
MOBILIZATION LS 1.0009,600.00
1.0009,600.00
0.0000.00

0008                          1000.00 150.0015.0002,250.00
LARGE TREE REMOVAL EACH15.0002,250.00
19.0002,850.00
0.0000.00

0009                          1009.00 8,000.001.0008,000.00
GENERAL CLEARING AND GRUBBING LS 1.0008,000.00
1.0008,000.00
0.0000.00

0010                          1010.00 1.87162,496.000303,867.52
EXCAVATION m3 162,496.000303,867.52
162,496.000303,867.52
0.0000.00

0011                          1010.01 2.0023,193.00046,386.00
EXCAVATION (ESTABLISHED QUANTITY) m3 23,193.00046,386.00
18,220.00036,440.00
0.0000.00

0012                          1011.00 1.401,415.0001,981.00
WATER kL 1,415.0001,981.00
713.560998.98
0.0000.00

0013                          1012.00 70.00240.00016,800.00
RIGHT-OF-WAY MARKERS EACH240.00016,800.00
284.00019,880.00
2.000140.00

0014                          1040.00 0.30450,000.000135,000.00
SLOPE PROTECTION m2 564,400.000169,320.00
564,404.000169,321.20
0.0000.00

0015                          1040.05 0.207,352.0001,470.40
TEMPORARY SLOPE PROTECTION m2 7,352.0001,470.40
0.0000.00
0.0000.00

0016                          1040.06 110.00495.00054,450.00
SLOPE PROTECTION MULCH Mg 495.00054,450.00
652.05071,725.50
0.0000.00

0017                          1042.00 1.1029,653.00032,618.30
SALVAGING AND PLACING HYDRIC SOIL m2 29,653.00032,618.30
29,653.00032,618.30
0.0000.00

0018                          1102.00 3.759,307.00034,901.25
REMOVE ASPHALT SURFACE m2 9,307.00034,901.25
9,121.96434,207.36
0.0000.00

0019                          1136.08 5.00122.000610.00
REMOVE m3 122.000610.00
& SALVAGE GRAVEL SURFACE COURSE 0.0000.00
0.0000.00

0020                          1701.24 45.00427.00019,215.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 427.00019,215.00
454.00020,430.00
0.0000.00

4016                          1900.10 9.9750.0000.00
PLACING m3 100.000997.50
Placing Manure on Backslopes in high erosion area. 95.550953.11
0.0000.00

GROUP 1 GRADINGContracted756,872.67
Current793,990.17
In place797,493.13
This Estimate-9,685.78

GROUP 4 CULVERTS
0021                          P200.48 205.0052.00010,660.00
1200 mm CULVERT PIPE, TYPE 2 OR 5 m 52.00010,660.00
52.20010,701.00
0.0000.00

0022                          P277.24 89.0012.5001,112.50
600 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 OR 5 m 12.5001,112.50
12.5001,112.50
0.0000.00

0023                          P277.42 251.0041.00010,291.00
1050 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 OR 5 m 41.00010,291.00
41.00010,291.00
0.0000.00

0024                          P400.24 73.00139.50010,183.50
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 139.50010,183.50
167.60012,234.80
0.0000.00

0025                          P400.36 152.0034.0005,168.00
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 34.0005,168.00
34.0005,168.00
0.0000.00

0026                          P420.48 181.0012.0002,172.00
1200 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2,3,4 OR 5 m 12.0002,172.00
13.5002,443.50
0.0000.00

0027                          0030.40 3,500.001.0003,500.00
MOBILIZATION LS 1.0003,500.00
1.0003,500.00
0.0000.00

0028                          4050.01 18.00448.0008,064.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 568.00010,224.00
641.00011,538.00
0.0000.00

0029                          4100.06 900.002.2001,980.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 0.0000.00
0.0000.00
0.0000.00

0030                          4150.00 2.35192.000451.20
REINFORCING STEEL FOR HEADWALL kg 0.0000.00
0.0000.00
0.0000.00

0031                          4310.24 96.0018.0001,728.00
600 mm FLARED-END SECTION EACH18.0001,728.00
20.0001,920.00
0.0000.00

0032                          4310.36 300.004.0001,200.00
900 mm FLARED-END SECTION EACH4.0001,200.00
4.0001,200.00
0.0000.00

0033                          4310.48 652.002.0001,304.00
1200 mm FLARED-END SECTION EACH2.0001,304.00
2.0001,304.00
0.0000.00

0034                          4320.24 96.002.000192.00
600 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.000192.00
2.000192.00
0.0000.00

0035                          4320.42 500.004.0002,000.00
1050 mm ROUND EQUIVALENT FLARED-END SECTION EACH4.0002,000.00
4.0002,000.00
0.0000.00

0036                          4320.48 600.002.0001,200.00
1200 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0001,200.00
2.0001,200.00
0.0000.00

4007                          4315.48 995.580.0000.00
METAL HEADWALL FOR 1200 mm CULVERT PIPE EACH2.0001,991.16
Replace concrete headwalls with Metal Headwalls at 10240+26. 2.0001,991.16
0.0000.00

4008                          0025.10 220.020.0000.00
VALUE ENGINEERING ADJUSTMENT LS 1.000220.02
Value Engineering AdjusmentReplace concrete headwalls with Metal Headwalls at 10240+26. 1.000220.02
0.0000.00

4012                          4976.05 25,594.500.0000.00
ADDITIONAL WORK LS 1.00025,594.50
Install 900mmx20.5 Triple RE Reinforced Concrete Pipe.Install 6-900mm RE Reinforced Concrete FES. 1.00025,594.50
0.0000.00

4013                          0030.01 997.500.0000.00
ADDITIONAL MOBILIZATION LS 1.000997.50
Mobilization to install 900mm RE-RCCP 1.000997.50
0.0000.00

4014                          8092.50 32.46610.0000.00
GRANULAR BEDDING m3 53.4001,733.69
Granular Bedding for foundation of RCCP at station 140+25. 53.4001,733.69
0.0000.00

GROUP 4 CULVERTSContracted61,206.20
Current91,471.87
In place95,341.67
This Estimate0.00

GROUP 4A CULVERT AT STA. 246+19.45
0037                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0038                          4044.00 4,215.001.0004,215.00
PREPARATION OF STRUCTURE EACH1.0004,215.00
AT STA. 246+19.45 1.0004,215.00
0.0000.00

0039                          4051.01 21.0030.000630.00
EXCAVATION FOR BOX CULVERTS m3 30.000630.00
30.000630.00
0.0000.00

0040                          4101.06 419.8951.24021,515.16
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 51.24021,515.16
51.24021,515.16
0.0000.00

0041                          4151.00 1.682,917.0004,900.56
REINFORCING STEEL FOR BOX CULVERT kg 2,917.0004,900.56
2,917.0004,900.56
0.0000.00

4004                          4061.01 21.000.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 29.050610.05
Excavation of unsuitable material.Group 4A, concrete box culvert at 10246+19.45. 29.050610.05
0.0000.00

4005                          4051.12 41.9890.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 29.0501,219.78
Granular material for foundation of box culverts.Group 4A, Concrete box culvert at 10246+19.45. 29.0501,219.78
0.0000.00

GROUP 4A CULVERT AT STA. 246+19.45Contracted33,760.72
Current35,590.55
In place35,590.55
This Estimate0.00

GROUP 4B CULVERT AT STA. 259+30.027
0042                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0043                          4044.00 3,500.001.0003,500.00
PREPARATION OF STRUCTURE EACH1.0003,500.00
AT STA. 259+30.027 1.0003,500.00
0.0000.00

0044                          4051.01 19.0061.0001,159.00
EXCAVATION FOR BOX CULVERTS m3 61.0001,159.00
61.0001,159.00
0.0000.00

0045                          4101.06 419.0057.12023,933.28
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 57.12023,933.28
53.22022,299.18
0.0000.00

0046                          4151.00 1.193,329.0003,961.51
REINFORCING STEEL FOR BOX CULVERT kg 3,329.0003,961.51
3,329.0003,961.52
0.0000.00

4002                          4061.01 19.000.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 29.580562.02
Excavation of unsuitable material.Group 4B, station 10259+30.027 29.580562.02
0.0000.00

4003                          4051.12 41.900.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 29.5801,239.40
Granular material for foundation of box culverts.Group 4B, box culvert at 10259+30.027. 29.5801,239.40
0.0000.00

GROUP 4B CULVERT AT STA. 259+30.027Contracted35,053.79
Current36,855.21
In place35,221.12
This Estimate0.00

GROUP 4C CULVERT AT STA. 283+69.276
0047                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0048                          4044.00 3,980.001.0003,980.00
PREPARATION OF STRUCTURE EACH1.0003,980.00
AT STA. 283+69.276 1.0003,980.00
0.0000.00

0049                          4051.01 18.0055.000990.00
EXCAVATION FOR BOX CULVERTS m3 55.000990.00
55.000990.00
0.0000.00

0050                          4101.06 419.0065.64027,503.16
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 65.64027,503.16
65.64027,503.16
0.0000.00

0051                          4151.00 1.194,046.0004,814.74
REINFORCING STEEL FOR BOX CULVERT kg 4,046.0004,814.74
4,046.0004,814.74
0.0000.00

4000                          4061.01 18.000.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 31.240562.32
GROUP 4C, STATION 10283+69.276 31.240562.32
0.0000.00

4001                          4051.12 41.900.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 31.2401,308.96
Granular material for foundation of Box Culvert, Group 4C. 31.2401,308.96
0.0000.00

GROUP 4C CULVERT AT STA. 283+69.276Contracted39,787.90
Current41,659.18
In place41,659.18
This Estimate0.00

GROUP 8B ELECTRICAL
0052                          A001.10 350.001.000350.00
PULL BOX, TYPE PB-4 EACH1.000350.00
1.000350.00
0.0000.00

0053                          A009.14 1,800.003.0005,400.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH3.0005,400.00
3.0005,400.00
0.0000.00

0054                          A020.10 454.001.000454.00
LIGHTING CONTROL CENTER, TYPE D EACH1.000454.00
1.000454.00
0.0000.00

0055                          A070.10 7.5071.000532.50
38 mm CONDUIT IN TRENCH m 71.000532.50
96.900726.75
0.0000.00

0056                          A074.12 45.0033.0001,485.00
38 mm CONDUIT, JACKED m 33.0001,485.00
20.700931.50
0.0000.00

0057                          A080.22 2.10104.000218.40
STREET LIGHTING CABLE, NO. 6 BARE m 104.000218.40
117.600246.96
0.0000.00

0058                          A080.24 2.40208.000499.20
STREET LIGHTING CABLE, NO. 6 USE m 208.000499.20
235.200564.48
0.0000.00

0059                          0030.81 1,750.001.0001,750.00
MOBILIZATION LS 1.0001,750.00
1.0001,750.00
0.0000.00

GROUP 8B ELECTRICALContracted10,689.10
Current10,689.10
In place10,423.69
This Estimate0.00

GROUP 9 BITUMINOUS
0060                          P402.15 132.0083.10010,969.20
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 83.10010,969.20
50.6006,679.20
0.0000.00

0061                          0002.55 23.00395.3809,093.74
OVERLAY BROKEN LINES StaM395.3809,093.74
732.53116,848.21
-1.017-23.39

0062                          0002.60 26.00790.76020,559.76
OVERLAY SOLID LINES StaM790.76020,559.76
1,220.31331,728.14
1.92350.00

0063                          0030.90 68,000.001.00068,000.00
MOBILIZATION LS 1.00068,000.00
1.00068,000.00
0.0000.00

0064                          1020.03 11.50104.0001,196.00
DELINEATOR, TYPE III EACH104.0001,196.00
112.0001,288.00
0.0000.00

0065                          1020.20 17.5047.000822.50
INSTALL CHEVRONS EACH47.000822.50
43.000752.50
0.0000.00

0066                          2001.00 18.001,400.00025,200.00
GRAVEL SURFACE COURSE m3 344.0006,192.00
74.0001,332.00
0.0000.00

0067                          2005.50 7.502,890.00021,675.00
CLAY SURFACE COURSE m3 779.0005,842.50
0.0000.00
0.0000.00

0068                          2009.10 450.0018.8678,490.15
GRAVEL EMBEDMENT StaM3.2271,452.15
0.0000.00
0.0000.00

0069                          2020.00 7.50104.000780.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 104.000780.00
104.000780.00
0.0000.00

0070                          2021.00 50.006.000300.00
MAILBOX POST EACH6.000300.00
6.000300.00
0.0000.00

0071                          4024.55 150.0037.6005,640.00
FLUME SPILLWAY m 37.6005,640.00
43.8006,570.00
0.0000.00

0072                          4024.70 1,900.008.00015,200.00
CONCRETE FLUME, TYPE I EACH8.00015,200.00
9.00017,100.00
0.0000.00

0073                          4024.73 1,700.006.00010,200.00
CONCRETE FLUME, TYPE IV EACH0.0000.00
0.0000.00
0.0000.00

0074                          8022.00 121.00480.00058,080.00
HYDRATED LIME Mg 480.00058,080.00
451.40954,620.49
0.0000.00

0075                          8110.50 1,300.00188.010244,413.00
HYDRATED LIME SLURRY STABILIZATION StaM188.010244,413.00
187.292243,479.60
-0.021-27.30

0076                          9000.75 16.61100.0001,661.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 100.0001,661.00
SP1(9.5) 18.200302.30
0.0000.00

0077                          9005.00 26.61380.00010,111.80
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 380.00010,111.80
SP1(9.5) 88.6602,359.25
0.0000.00

0078                          9005.26 16.6129,680.000492,984.80
ASPHALTIC CONCRETE, TYPE SP1(9.5) Mg 29,680.000492,984.80
33,780.450561,093.27
0.0000.00

0079                          9009.00 2.503,876.0009,690.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 3,876.0009,690.00
2,855.0007,137.50
0.0000.00

0080                          9020.91 204.005.4001,101.60
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 5.4001,101.60
0.880179.52
0.0000.00

0081                          9021.01 204.001,623.240331,140.96
PERFORMANCE GRADED BINDER (64-22) Mg 1,623.240331,140.96
1,642.014334,970.86
0.0000.00

0082                          9030.00 6.661,555.00010,356.30
CONSTRUCTING ASPHALTIC CONCRETE CURB m 1,555.00010,356.30
1,806.00012,027.96
0.0000.00

0083                          9034.00 2.50703.0001,757.50
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 703.0001,757.50
1,377.0003,442.50
90.000225.00

0084                          9052.15 0.225482,070.000108,465.75
EMULSIFIED ASPHALT FOR HYDRATED LIME SLURRY STABILIZATION L 482,070.000108,465.75
530,559.089119,375.80
0.0000.00

0085                          9053.00 0.26113,770.00029,580.20
TACK COAT L 113,770.00029,580.20
172,428.00044,831.28
2,082.000541.32

0086                          9111.00 2.001,353.0002,706.00
WATER kL 1,353.0002,706.00
0.0000.00
0.0000.00

0087                          9170.00 180.00401.00172,180.18
EARTH SHOULDER CONSTRUCTION StaM401.00172,180.18
399.56071,920.80
0.0000.00

0088                          9173.00 450.0016.1237,255.35
SUBGRADE PREPARATION StaM16.1237,255.35
16.1237,255.35
0.0000.00

0089                          9173.15 25.00376.0219,400.53
TRENCHED WIDENING StaM376.0219,400.53
374.6019,365.02
-0.027-0.68

0090                          9300.50 6,000.001.0006,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0006,000.00
1.0006,000.00
0.0000.00

4006                          9188.01 1.931340.0000.00
BITUMINOUS SURFACE COURSE m2 11,417.00022,050.11
VEP- Temporary Road at 7000+47 to 7009+65 and 7100+54 to 7107+00. 11,417.00022,050.11
0.0000.00

4009                          0025.10 9,914.200.0000.00
VALUE ENGINEERING ADJUSTMENT LS 1.0009,914.20
VEP- Temporary Road at 7000+47 to 7009+65 and 7100+54 to 7107+00. 1.0009,914.20
0.0000.00

4010                          9300.60 0.5780.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 13,833.6307,995.84
SP 1 (9.5) 13,833.6307,995.84
0.0000.00

4011                          9300.77 7.0990.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 698.6004,959.36
PG Binder 64-22 698.6004,959.36
0.0000.00

4015                          4024.76 1,700.000.0000.00
CONCRETE FLUME, TYPE VII EACH5.0008,500.00
Replace Type IV Flumes with Type VII Flumes as per the contractors request. Built at same contract unit price. 5.0008,500.00
0.0000.00

4018                          9300.56 0.517150.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 33,809.47017,484.57
Air voids Incentive-disincentive 0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted1,595,011.32
Current1,613,836.89
In place1,683,159.06
This Estimate764.95

GROUP 10 GENERAL ITEMS
0091                          0001.08 0.5051,750.00025,875.00
BARRICADE, TYPE II BDAY51,750.00025,875.00
2,995.0001,497.50
0.0000.00

0092                          0001.10 2.501,210.0003,025.00
BARRICADE, TYPE III BDAY1,210.0003,025.00
1,675.0004,187.50
0.0000.00

0093                          0001.30 2.50520.0001,300.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY520.0001,300.00
184.000460.00
0.0000.00

0094                          0001.75 5.501,410.0007,755.00
TEMPORARY SIGN DAY EACH1,410.0007,755.00
101.000555.50
0.0000.00

0095                          0001.90 0.5011,050.0005,525.00
SIGN DAY EACH11,050.0005,525.00
7,698.0003,849.00
3.0001.50

0096                          0002.30 2.80700.0001,960.00
PAVEMENT MARKING REMOVAL m 700.0001,960.00
0.0000.00
0.0000.00

0097                          0002.38 2.30700.0001,610.00
TEMPORARY PAVEMENT MARKING, TYPE I m 700.0001,610.00
865.0001,989.50
0.0000.00

0098                          0003.10 175.00130.00022,750.00
FLAGGING DAY 130.00022,750.00
164.00028,700.00
0.0000.00

0099                          0003.20 275.0050.00013,750.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 50.00013,750.00
34.0009,350.00
0.0000.00

0100                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
0.0000.00
0.0000.00

0101                          0030.00 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0102                          1017.00 35,000.001.00035,000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00035,000.00
1.00035,000.00
0.50017,500.00

0103                          9110.01 65.0060.0003,900.00
RENTAL OF LOADER, FULLY OPERATED HOUR60.0003,900.00
16.0001,040.00
0.0000.00

0104                          9110.02 60.0060.0003,600.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR60.0003,600.00
0.0000.00
0.0000.00

0105                          9110.03 50.0060.0003,000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR60.0003,000.00
0.0000.00
0.0000.00

0106                          9110.07 45.0060.0002,700.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR60.0002,700.00
5.000225.00
0.0000.00

0107                          9110.09 125.005.000625.00
RENTAL OF TRACTOR AND SCRAPER, FULLY OPERATED HOUR5.000625.00
1.000125.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted138,875.00
Current138,875.00
In place91,979.00
This Estimate17,501.50

Totals for contractContracted2,671,256.70
Current2,756,717.97
In place2,784,617.40
This Estimate2,330.67