Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0477 WESTERN ENGINEERING COMPANY, INC.
Contract ID:8620
Estimate Number:0015
Pay Period End Date:12.19.2001
Contract Location:
THEDFORD - VALENTINEEstimate Type:PROG
Contractor:
WESTERN ENGINEERING COMPANY, INC.Date Let:02.22.2001
1149 WEST HIGHWAY 44Date Awarded:03.01.2001
PO BOX 350Date Contract Executed:03.27.2001
Date Notice to Proceed:03.27.2001
HARLAN IA 51537Date Work Began:04.02.2001
Phone:Date Physical Work Completed:
(712)755-5191Date Accepted:
Escrow Agent:
Surety Co:
HARTFORD FIRE INSURANCE COMPANY
Counties
CHERRY
Project Number PCT Fed State Project Number Description
80620 000  0.000 EACNH-STPB-83-4(111)  GR CULV FENCE BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$3,618,923.39$3,616,759.59$2,163.80
$3,835,255.47Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$3,618,923.39$3,616,759.59$2,163.80
$3,765,861.48Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
94.36%Net Earnings$3,593,923.39$3,591,759.59$2,163.80
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-139.28$-139.28$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$139.28-$139.28$.00
Payment$3,593,784.11$3,591,620.31$2,163.80
Project ManagerDiv. Head/Dist. Eng.
Kovar, Mark12.19.2001Kovar, Mark12.19.2001
Constr. Estimate Eng.Materials Eng.
Bartos, Steve12.21.2001
Controller Div. Processed
Burling, Laurie12.21.2001
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.01 10.003,210.00032,100.00
EROSION CONTROL, TYPE A m2 3,210.00032,100.00
3,362.60033,626.00
0.0000.00

0002                          L020.03 2.5034,458.00086,145.00
EROSION CONTROL, TYPE C m2 34,458.00086,145.00
35,516.70088,791.75
0.0000.00

0003                          L020.20 0.6522,672.00014,736.80
SLOPE PROTECTION NETTING m2 22,672.00014,736.80
33,124.50021,530.93
0.0000.00

0004                          L021.01 30.00105.0003,150.00
EROSION CHECKS, TYPE A BALE105.0003,150.00
105.0003,150.00
0.0000.00

0005                          L021.03 25.001,652.00041,300.00
EROSION CHECKS, TYPE C BALE1,652.00041,300.00
1,591.00039,775.00
0.0000.00

0006                          L021.11 25.00133.0003,325.00
EROSION CHECKS, TYPE ST-A BALE133.0003,325.00
135.0003,375.00
0.0000.00

0007                          L021.14 25.00280.0007,000.00
EROSION CHECKS, TYPE ST-C BALE280.0007,000.00
251.0006,275.00
0.0000.00

0008                          L022.25 9.0010,102.00090,918.00
FABRIC SILT FENCE, TYPE COIR FIBER m 10,102.00090,918.00
10,575.00095,175.00
0.0000.00

0009                          L022.75 17.00864.80014,701.60
TEMPORARY SILT CHECK m 864.80014,701.60
943.00016,031.00
0.0000.00

0010                          0030.10 23,500.001.00023,500.00
MOBILIZATION LS 1.00023,500.00
1.00023,500.00
0.0000.00

0011                          1009.00 7,500.001.0007,500.00
GENERAL CLEARING AND GRUBBING LS 1.0007,500.00
1.0007,500.00
0.0000.00

0012                          1010.00 1.37426,783.000584,692.71
EXCAVATION m3 426,783.000584,692.71
426,783.000584,692.71
0.0000.00

0013                          1010.01 1.2835,475.00045,408.00
EXCAVATION (ESTABLISHED QUANTITY) m3 35,475.00045,408.00
35,475.00045,408.00
0.0000.00

0014                          1011.00 0.254,268.0001,067.00
WATER kL 4,268.0001,067.00
0.0000.00
0.0000.00

0015                          1012.00 60.00160.0009,600.00
RIGHT-OF-WAY MARKERS EACH160.0009,600.00
159.0009,540.00
0.0000.00

0016                          1040.00 0.241,030,000.000247,200.00
SLOPE PROTECTION m2 0.0000.00
0.0000.00
0.0000.00

0017                          1040.05 0.2062,455.00012,491.00
TEMPORARY SLOPE PROTECTION m2 62,455.00012,491.00
56,000.00011,200.00
0.0000.00

0018                          1040.06 70.001,133.00079,310.00
SLOPE PROTECTION MULCH Mg 0.0000.00
0.0000.00
0.0000.00

0019                          1041.00 0.725,683.0004,091.76
SALVAGING AND PLACING TOPSOIL m2 5,683.0004,091.76
5,807.6004,181.47
0.0000.00

0020                          1042.00 2.407,400.00017,760.00
SALVAGING AND PLACING HYDRIC SOIL m2 7,400.00017,760.00
18,006.30043,215.12
0.0000.00

0021                          1111.00 1.3211,255.00014,856.60
REMOVE FENCE m 10,040.00013,252.80
9,989.70013,186.40
0.0000.00

0022                          7017.00 6.501,737.00011,290.50
REMOVE GUARDRAIL m 1,737.00011,290.50
1,737.00011,290.50
0.0000.00

4000                          1010.50 2.740.0000.00
REMOVAL OF UNSUITABLE MATERIAL m3 1,552.0004,252.48
Removal of unsuitably wet material at Sta. 238-+ 2,989.0008,189.86
0.0000.00

4010                          1300.15 22.950.0000.00
375 mm DRIVEWAY CULVERT PIPE m 24.400559.98
Station 302+00 on the Right 24.400559.98
0.0000.00

4011                          1300.36 45.900.0000.00
900 mm DRIVEWAY CULVERT PIPE m 13.400615.06
Station 320+79 on the right 13.400615.06
0.0000.00

4012                          1041.00 0.610.0000.00
SALVAGING AND PLACING TOPSOIL m2 157,300.00095,953.00
Soil that is NOT of the Prairie Fringed Orchid Seedbank 130,389.15079,537.38
0.0000.00

4013                          1040.00 0.3660.0000.00
SLOPE PROTECTION m2 425,000.000155,550.00
This item replaces item 0016 401,225.710146,848.61
0.0000.00

4014                          1040.06 80.500.0000.00
SLOPE PROTECTION MULCH Mg 468.00037,674.00
This item replaces item 0018 382.99030,830.70
0.0000.00

4017                          1905.03 263.460.0000.00
MATERIAL DELIVERED NOT INCORPORATED EACH99.00026,082.54
Slope Protection Seeding which was not used on the project. 89.00023,447.94
-10.000-2,634.60

GROUP 1 GRADINGContracted1,352,143.97
Current1,344,717.23
In place1,351,473.41
This Estimate-2,634.60

GROUP 4 CULVERTS
0023                          0030.40 4,500.001.0004,500.00
MOBILIZATION LS 1.0004,500.00
1.0004,500.00
0.0000.00

0024                          4035.00 100.002.000200.00
REMOVE FLARED-END SECTION EACH2.000200.00
2.000200.00
0.0000.00

0025                          4050.01 12.0038.000456.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 38.000456.00
38.000456.00
0.0000.00

0026                          4350.24 56.008.400470.40
600 mm CORRUGATED METAL PIPE m 8.400470.40
8.400470.40
0.0000.00

0027                          4350.30 82.0054.0004,428.00
750 mm CORRUGATED METAL PIPE m 54.0004,428.00
54.0004,428.00
0.0000.00

0028                          4350.36 98.0016.0001,568.00
900 mm CORRUGATED METAL PIPE m 16.0001,568.00
16.0001,568.00
0.0000.00

0029                          4350.48 268.003.200857.60
1200 mm CORRUGATED METAL PIPE m 3.200857.60
3.200857.60
0.0000.00

0030                          4360.24 150.004.000600.00
600 mm METAL FLARED-END SECTION EACH4.000600.00
4.000600.00
0.0000.00

0031                          4360.30 230.004.000920.00
750 mm METAL FLARED-END SECTION EACH4.000920.00
4.000920.00
0.0000.00

0032                          4360.36 355.002.000710.00
900 mm METAL FLARED-END SECTION EACH2.000710.00
2.000710.00
0.0000.00

0033                          4360.48 850.002.0001,700.00
1200 mm METAL FLARED-END SECTION EACH2.0001,700.00
2.0001,700.00
0.0000.00

4002                          4300.15 34.440.0000.00
375 mm CULVERT PIPE m 34.4001,184.74
Temporary culvert pipe to provide for drainage between the shoo-fly & new roadway. 34.4001,184.74
0.0000.00

4003                          4976.05 3,937.500.0000.00
ADDITIONAL WORK LS 1.0003,937.50
Extending culvert at south end of project which was not shown on the plans. 1.0003,937.50
0.0000.00

4004                          4024.73 2,100.000.0000.00
CONCRETE FLUME, TYPE IV EACH1.0002,100.00
1.0002,100.00
0.0000.00

4005                          4024.74 2,100.000.0000.00
CONCRETE FLUME, TYPE V EACH3.0006,300.00
3.0006,300.00
0.0000.00

4006                          4300.15 155.500.0000.00
375 mm CULVERT PIPE m 53.6608,344.13
For Flumes 58.2909,064.10
0.0000.00

GROUP 4 CULVERTSContracted16,410.00
Current38,276.37
In place38,996.34
This Estimate0.00

GROUP 7B FENCING
0034                          0030.70 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
1.0001,000.00
0.0000.00

0035                          7101.00 70.005.000350.00
PRIVATE FENCE TERMINALS EACH5.000350.00
8.000560.00
0.0000.00

0036                          7104.00 100.0082.0008,200.00
PULL POSTS EACH93.0009,300.00
93.0009,300.00
0.0000.00

0037                          7105.00 70.007.000490.00
CORNER POSTS EACH5.000350.00
16.0001,120.00
0.0000.00

0038                          7106.15 200.002.000400.00
4.5 m VEHICLE GATE EACH4.000800.00
4.000800.00
0.0000.00

0039                          7110.02 15.331,650.00025,294.50
0.9 METER CHAIN-LINK FENCE m 1,650.00025,294.50
1,607.00024,635.31
0.0000.00

0040                          7112.03 50.006.000300.00
TAKE DOWN PANEL FOR 0.9 METER CHAIN-LINK FENCE EACH6.000300.00
6.000300.00
0.0000.00

0041                          7115.02 75.0024.0001,800.00
END POST FOR 0.9 METER CHAIN-LINK FENCE EACH24.0001,800.00
22.0001,650.00
0.0000.00

0042                          7116.02 75.0024.0001,800.00
CORNER POST FOR 0.9 m CHAIN-LINK FENCE EACH24.0001,800.00
24.0001,800.00
0.0000.00

0043                          7117.02 100.0024.0002,400.00
PULL POST FOR 0.9 METER CHAIN-LINK FENCE EACH24.0002,400.00
18.0001,800.00
0.0000.00

0044                          7130.00 2.9912,278.00036,711.22
BARBED WIRE FENCE m 10,675.00031,918.25
11,504.40034,398.16
0.0000.00

4015                          6960.02 7,764.250.0000.00
ADDITIONAL WORK LS 1.0007,764.25
For modification of the fence around culvert ends 1.0007,764.25
0.0000.00

4016                          6960.06 2.660.0000.00
ADDITIONAL WORK m 1,650.0004,389.00
To dig a trench and bury the bottom of the chain link fence 80mm below the surface of the ground. 1,607.0004,274.62
0.0000.00

4021                          1905.00 2,184.400.0000.00
MATERIAL DELIVERED NOT INCORPORATED LS 1.0002,184.40
Fencing Material (Posts, Wire & Ties) Delivered but not incorporated at wetland site number 1. 1.0002,184.40
1.0002,184.40

4022                          6960.02 2,614.000.0000.00
ADDITIONAL WORK LS 1.0002,614.00
For labor costs which the contractor incurred placing a portion of the fence on wetland site number 1. 1.0002,614.00
1.0002,614.00

GROUP 7B FENCINGContracted78,745.72
Current92,264.40
In place94,200.74
This Estimate4,798.40

GROUP 9 BITUMINOUS
0045                          0002.40 23.10425.9009,838.29
TEMPORARY SOLID LINES StaM425.9009,838.29
897.10020,723.01
0.0000.00

0046                          0002.45 23.10212.9504,919.15
TEMPORARY BROKEN LINES StaM212.9504,919.15
245.8005,677.98
0.0000.00

0047                          0002.75 0.1531,500.0004,725.00
PERMANENT PAVEMENT MARKING m 31,500.0004,725.00
37,800.0005,670.00
0.0000.00

0048                          0030.90 24,000.001.00024,000.00
MOBILIZATION LS 1.00024,000.00
1.00024,000.00
0.0000.00

0049                          2021.00 50.004.000200.00
MAILBOX POST EACH4.000200.00
4.000200.00
0.0000.00

0050                          8008.00 23.55540.00012,717.00
ARMOR COAT AGGREGATE m3 540.00012,717.00
527.54012,423.57
0.0000.00

0051                          8029.84 1.5563,474.00098,384.70
BITUMINOUS FOUNDATION COURSE 100 mm m2 63,474.00098,384.70
63,036.00097,705.80
0.0000.00

0052                          8111.00 175.00252.00044,100.00
SHOULDER SUBGRADE PREPARATION StaM252.00044,100.00
252.00044,100.00
0.0000.00

0053                          9000.75 12.00100.0001,200.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 100.0001,200.00
SPS 0.0000.00
0.0000.00

0054                          9005.00 22.00100.0002,200.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0002,200.00
SP2 0.0000.00
0.0000.00

0055                          9005.23 13.9222,750.000316,680.00
ASPHALTIC CONCRETE, TYPE SPS Mg 22,750.000316,680.00
22,744.100316,597.88
0.0000.00

0056                          9005.30 20.0035,080.000701,600.00
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 35,080.000701,600.00
35,218.220704,364.40
0.0000.00

0057                          9009.00 4.152,014.0008,358.10
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 2,014.0008,358.10
1,921.5007,974.23
0.0000.00

0058                          9020.92 177.255.400957.15
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 5.400957.15
0.0000.00
0.0000.00

0059                          9021.01 177.251,899.720336,725.37
PERFORMANCE GRADED BINDER (64-22) Mg 3,138.220556,249.50
2,064.800365,985.81
0.0000.00

0060                          9021.03 177.251,228.500217,751.63
PERFORMANCE GRADED BINDER (58-28) Mg 0.0000.00
0.0000.00
0.0000.00

0061                          9034.00 2.502,014.0005,035.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 2,014.0005,035.00
1,921.5004,803.75
0.0000.00

0062                          9052.00 260.00107.42027,929.20
ARMOR COAT EMULSIFIED ASPHALT kL 107.42027,929.20
115.95930,149.34
0.0000.00

0063                          9053.00 0.3068,779.00020,633.70
TACK COAT L 68,779.00020,633.70
153,673.00046,101.90
0.0000.00

0064                          9110.01 50.0040.0002,000.00
RENTAL OF LOADER, FULLY OPERATED HOUR40.0002,000.00
4.000200.00
0.0000.00

0065                          9110.02 50.0040.0002,000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR40.0002,000.00
13.000650.00
0.0000.00

0066                          9110.03 40.0040.0001,600.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR40.0001,600.00
14.000560.00
0.0000.00

0067                          9110.07 35.0040.0001,400.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR40.0001,400.00
0.0000.00
0.0000.00

0068                          9111.00 2.002,849.0005,698.00
WATER kL 2,849.0005,698.00
786.7901,573.58
0.0000.00

0069                          9170.00 80.0098.1077,848.56
EARTH SHOULDER CONSTRUCTION StaM98.1077,848.56
98.1077,848.56
0.0000.00

0070                          9173.00 285.00136.00238,760.57
SUBGRADE PREPARATION StaM136.00238,760.57
136.00238,760.58
0.0000.00

0071                          9179.23 400.0039.35015,740.00
COLD MILLING, CLASS 3 StaM39.35015,740.00
39.35015,740.00
0.0000.00

0072                          9179.24 2,245.0086.950195,202.75
COLD MILLING, CLASS 4 StaM86.950195,202.75
86.950195,202.75
0.0000.00

0073                          9188.01 2.3535,809.00084,151.15
BITUMINOUS SURFACE COURSE m2 35,809.00084,151.15
35,807.96084,148.70
0.0000.00

0074                          9300.50 3,500.001.0003,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0003,500.00
1.0003,500.00
0.0000.00

4007                          9173.10 370.7140.0000.00
SUBGRADE PREPARATION FOR WIDENING StaM5.3952,000.00
For Placing Asphalt Curb 5.3952,000.00
0.0000.00

4008                          9005.81 30.000.0000.00
ASPHALTIC CONCRETE, TYPE SPS Mg 215.0006,450.00
For widening to place curb 120.0003,600.00
0.0000.00

4009                          9030.00 8.000.0000.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 539.5004,316.00
539.5004,316.00
0.0000.00

4018                          9300.56 0.4350.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 35,218.22015,319.93
INCENTIVE FOR AIRVOIDS AND DENSITY 35,218.22015,319.93
0.0000.00

4019                          9300.77 3.2260.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 494.7071,595.92
494.7071,595.92
0.0000.00

4020                          9300.60 0.3640.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 10,525.6903,831.35
10,525.6903,831.35
0.0000.00

GROUP 9 BITUMINOUSContracted2,195,855.31
Current2,231,141.01
In place2,065,325.04
This Estimate0.00

GROUP 10 GENERAL ITEMS
0075                          0001.08 0.5011,260.0005,630.00
BARRICADE, TYPE II BDAY11,260.0005,630.00
5,348.0002,674.00
0.0000.00

0076                          0001.10 4.002,416.0009,664.00
BARRICADE, TYPE III BDAY2,416.0009,664.00
1,545.0006,180.00
0.0000.00

0077                          0001.30 3.98376.0001,496.48
TYPE B HIGH INTENSITY WARNING LIGHT LDAY376.0001,496.48
247.000983.06
0.0000.00

0078                          0001.90 0.8017,520.00014,016.00
SIGN DAY EACH17,520.00014,016.00
8,786.0007,028.80
0.0000.00

0079                          0002.30 3.00900.0002,700.00
PAVEMENT MARKING REMOVAL m 900.0002,700.00
900.0002,700.00
0.0000.00

0080                          0002.44 0.5019,200.0009,600.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 19,200.0009,600.00
19,404.0009,702.00
0.0000.00

0081                          0003.10 195.00360.00070,200.00
FLAGGING DAY 360.00070,200.00
128.00024,960.00
0.0000.00

0082                          0010.04 800.001.000800.00
FIELD OFFICE EACH1.000800.00
1.000800.00
0.0000.00

0083                          0030.10 8,600.001.0008,600.00
MOBILIZATION LS 1.0008,600.00
1.0008,600.00
0.0000.00

4001                          0001.06 0.250.0000.00
VERTICAL PANELS BDAY24,600.0006,150.00
vercial panels for use on temporary roads 21,200.0005,300.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted122,706.48
Current128,856.48
In place68,927.86
This Estimate0.00

Totals for contractContracted3,765,861.48
Current3,835,255.49
In place3,618,923.39
This Estimate2,163.80