Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:8619
Estimate Number:0010
Pay Period End Date:09.20.2003
Contract Location:
O'NEILL NORTHEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:03.13.2003
129 E 2ND STDate Awarded:03.20.2003
PO BOX 1087Date Contract Executed:03.25.2003
Date Notice to Proceed:03.25.2003
HASTINGS NE 68902-1087Date Work Began:04.07.2003
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
HOLT
Project Number PCT Fed State Project Number Description
80619 000  0.000 EACSTPD-281-4(114)  GRAD, CULV, SEED, BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,187,646.03$1,088,735.33$98,910.70
$5,275,787.49Stockpiled Materials$363,224.37$363,224.37$.00
Original Contract AmtGross Earnings$1,550,870.40$1,451,959.70$98,910.70
$5,268,204.49Retainage$-11,876.46$-10,887.35$-989.11
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
22.51%Net Earnings$1,538,993.94$1,441,072.35$97,921.59
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-3,534.38$-3,255.25$-279.13
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$3,534.38-$3,255.25-$279.13
Payment$1,535,459.56$1,437,817.10$97,642.46
Project ManagerDiv. Head/Dist. Eng.
Ziska, Dan09.22.2003Kovar, Mark09.22.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.23.2003
Controller Div. Processed
Burling, Laurie09.23.2003
Detailed breakdown of stockpiled materials
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01059005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Initial Payment71,871.700320-1
Central 3A
S.P. Initial Payment34,498.420320-2
Central 3A
S.P. Initial Payment33,378.490320-3
Spencer 3/4" Rock
S.P. Initial Payment28,748.660320-4
Central 3A
S.P. Initial Payment6,263.860320-6
Spencer 3/4" Rock
S.P. Initial Payment40,248.160320-7
Central 3A
S.P. Initial Payment34,470.900320-7
Spencer 3/4" Rock
Total for estimate 0006:249,480.19
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01059005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Initial Payment7,960.970320-9
Spencer 3/4" Rock
S.P. Initial Payment16,007.020320-9
2A Gravel
S.P. Initial Payment43,123.120320-9
Central 3A
S.P. Initial Payment19,000.380320-10
2A Gravel
S.P. Initial Payment27,652.690320-10
Central 3A
Total for estimate 0008:113,744.18
Total remaining for contract:363,224.37
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 8,000.001.0008,000.00
MOBILIZATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0002                          1000.00 110.0010.0001,100.00
LARGE TREE REMOVAL EACH10.0001,100.00
11.0001,210.00
0.0000.00

0003                          1009.00 9,000.001.0009,000.00
GENERAL CLEARING AND GRUBBING LS 1.0009,000.00
0.6505,850.00
0.0000.00

0004                          1010.00 1.2669,015.00086,958.90
EXCAVATION m3 69,015.00086,958.90
69,944.80088,130.45
7,250.0009,135.00

0005                          1010.01 2.2012,605.00027,731.00
EXCAVATION (ESTABLISHED QUANTITY) m3 12,605.00027,731.00
0.0000.00
0.0000.00

0006                          1010.10 2.48158,029.000391,911.92
EXCAVATION, BORROW m3 158,029.000391,911.92
77,100.000191,208.00
6,500.00016,120.00

0007                          1010.50 15.00137.0002,055.00
REMOVAL OF UNSUITABLE MATERIAL m3 137.0002,055.00
0.0000.00
0.0000.00

0008                          1011.00 1.505,179.0007,768.50
WATER kL 5,179.0007,768.50
1,658.1492,487.22
454.260681.39

0009                          1012.00 53.00520.00027,560.00
RIGHT-OF-WAY MARKERS EACH189.00010,017.00
192.00010,176.00
0.0000.00

0010                          1016.00 230.0023.0005,290.00
RE-ESTABLISH PROPERTY CORNER EACH23.0005,290.00
13.5003,105.00
0.0000.00

0011                          1021.10 10.0090.000900.00
REMOVE DELINEATOR UNITS EACH90.000900.00
0.0000.00
0.0000.00

0012                          1040.00 0.1636,366.0005,818.56
SLOPE PROTECTION m2 36,366.0005,818.56
0.0000.00
0.0000.00

0013                          1040.05 0.0622,425.0001,345.50
TEMPORARY SLOPE PROTECTION m2 22,425.0001,345.50
0.0000.00
0.0000.00

0014                          1040.06 68.0040.0002,720.00
SLOPE PROTECTION MULCH Mg 40.0002,720.00
0.0000.00
0.0000.00

0015                          1102.00 2.0014,070.00028,140.00
REMOVE ASPHALT SURFACE m2 14,070.00028,140.00
1,930.1003,860.20
180.000360.00

0016                          1106.00 2.004,099.0008,198.00
REMOVE DRIVEWAY m2 4,099.0008,198.00
0.0000.00
0.0000.00

0017                          1143.00 10.0019.200192.00
REMOVE DRIVEWAY CULVERT PIPE m 19.200192.00
0.0000.00
0.0000.00

0018                          1701.24 50.00340.00017,000.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 340.00017,000.00
0.0000.00
0.0000.00

0019                          1701.30 67.0012.000804.00
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 12.000804.00
0.0000.00
0.0000.00

0020                          1702.24 52.0048.0002,496.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 3,4 OR 5 m 48.0002,496.00
0.0000.00
0.0000.00

0021                          1706.24 154.00249.00038,346.00
600 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2 m 249.00038,346.00
0.0000.00
0.0000.00

0022                          2030.01 8.50137.0001,164.50
AGGREGATE FOR SUB-SURFACE DRAINAGE m3 137.0001,164.50
0.0000.00
0.0000.00

0023                          3017.50 64.6091.0005,878.60
INTERLOCKING CONCRETE PAVER BLOCK m2 91.0005,878.60
0.0000.00
0.0000.00

0024                          4040.00 50.004.000200.00
REMOVE HEADWALLS FROM CULVERTS EACH4.000200.00
0.0000.00
0.0000.00

0025                          4763.26 180.001.000180.00
UNDERDRAIN HEADWALL EACH1.000180.00
0.0000.00
0.0000.00

0026                          4764.34 9.003.00027.00
100 mm NONPERFORATED PIPE UNDERDRAIN m 3.00027.00
0.0000.00
0.0000.00

0027                          4764.35 9.509.00085.50
100 mm PERFORATED PIPE UNDERDRAIN m 9.00085.50
0.0000.00
0.0000.00

0028                          L006.00 150.0042.0006,300.00
COVER CROP SEEDING ha 42.0006,300.00
0.0000.00
0.0000.00

0029                          L020.01 4.864,002.00019,449.72
EROSION CONTROL, TYPE A m2 4,002.00019,449.72
0.0000.00
0.0000.00

0030                          L020.03 1.7217,562.00030,206.64
EROSION CONTROL, TYPE C m2 17,562.00030,206.64
0.0000.00
0.0000.00

0031                          L020.08 4.829,654.00046,532.28
EROSION CONTROL, TYPE AA m2 9,654.00046,532.28
0.0000.00
0.0000.00

0032                          L020.09 11.40285.0003,249.00
EROSION CONTROL, TYPE AAA m2 285.0003,249.00
0.0000.00
0.0000.00

0033                          L020.20 0.1036,366.0003,636.60
SLOPE PROTECTION NETTING m2 36,366.0003,636.60
0.0000.00
0.0000.00

0034                          L021.01 15.00266.0003,990.00
EROSION CHECKS, TYPE A BALE266.0003,990.00
0.0000.00
0.0000.00

0035                          L021.03 15.00721.00010,815.00
EROSION CHECKS, TYPE C BALE721.00010,815.00
0.0000.00
0.0000.00

0036                          L021.06 15.00126.0001,890.00
EROSION CHECKS, TYPE HV BALE126.0001,890.00
0.0000.00
0.0000.00

0037                          L021.21 15.50539.0008,354.50
EROSION CHECKS, TYPE AA BALE539.0008,354.50
0.0000.00
0.0000.00

0038                          L022.11 6.005,459.00032,754.00
FABRIC SILT FENCE-LOW POROSITY m 5,459.00032,754.00
4,858.90029,153.40
0.0000.00

0039                          L022.14 6.00250.0001,500.00
FABRIC SILT FENCE-LOW PROFILE LOW POROSITY m 250.0001,500.00
245.7001,474.20
0.0000.00

0040                          L022.25 8.0025.000200.00
FABRIC SILT FENCE, TYPE COIR FIBER m 25.000200.00
30.000240.00
0.0000.00

0041                          L022.75 10.001,176.05011,760.50
TEMPORARY SILT CHECK m 1,176.05011,760.50
47.300473.00
0.0000.00

0042                          P300.48 100.00124.00012,400.00
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 124.00012,400.00
124.00012,400.00
0.0000.00

4000                          1013.00 53.000.0000.00
RESET RIGHT-OF-WAY MARKERS EACH92.0004,876.00
Remove and reset ROW Markers. 55.0002,915.00
0.0000.00

GROUP 1 GRADINGContracted873,909.22
Current861,242.22
In place360,682.47
This Estimate26,296.39

GROUP 4 CULVERTS
0043                          0030.40 22,500.001.00022,500.00
MOBILIZATION LS 1.00022,500.00
1.00022,500.00
0.0000.00

0044                          1043.50 3.50697.0002,439.50
RIPRAP FILTER FABRIC m2 697.0002,439.50
627.1902,195.17
0.0000.00

0045                          4035.00 135.006.000810.00
REMOVE FLARED-END SECTION EACH6.000810.00
6.000810.00
0.0000.00

0046                          4040.00 150.0080.00012,000.00
REMOVE HEADWALLS FROM CULVERTS EACH80.00012,000.00
80.00012,000.00
0.0000.00

0047                          4044.00 3,100.001.0003,100.00
PREPARATION OF STRUCTURE EACH1.0003,100.00
AT STA. 10045+86.98 1.0003,100.00
0.0000.00

0048                          4044.01 3,100.001.0003,100.00
PREPARATION OF STRUCTURE EACH1.0003,100.00
AT STA. 10089+87.47 1.0003,100.00
0.0000.00

0049                          4044.02 2,075.001.0002,075.00
PREPARATION OF STRUCTURE EACH1.0002,075.00
AT STA. 10109+29.66 1.0002,075.00
0.0000.00

0050                          4044.03 2,075.001.0002,075.00
PREPARATION OF STRUCTURE EACH1.0002,075.00
AT STA. 10130+83.99 1.0002,075.00
0.0000.00

0051                          4044.04 1,750.001.0001,750.00
PREPARATION OF STRUCTURE EACH1.0001,750.00
AT STA. 10142+46.50 1.0001,750.00
0.0000.00

0052                          4044.05 1,750.001.0001,750.00
PREPARATION OF STRUCTURE EACH1.0001,750.00
AT STA. 10143+68.96 1.0001,750.00
0.0000.00

0053                          4044.06 2,075.001.0002,075.00
PREPARATION OF STRUCTURE EACH1.0002,075.00
AT STA. 10148+52.17 1.0002,075.00
0.0000.00

0054                          4044.07 2,280.001.0002,280.00
PREPARATION OF STRUCTURE EACH1.0002,280.00
AT STA. 10205+55.25 1.0002,280.00
0.0000.00

0055                          4045.00 12,400.001.00012,400.00
REMOVE STRUCTURE EACH1.00012,400.00
AT STA. 10109+47.84 1.00012,400.00
0.0000.00

0056                          4045.01 8,250.001.0008,250.00
REMOVE STRUCTURE EACH1.0008,250.00
AT STA. 10123+87.32 1.0008,250.00
0.0000.00

0057                          4050.01 12.90916.00011,816.40
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 916.00011,816.40
979.00012,629.10
0.0000.00

0058                          4051.01 25.75475.00012,231.25
EXCAVATION FOR BOX CULVERTS m3 475.00012,231.25
475.00012,231.25
0.0000.00

0059                          4101.06 417.51579.490241,942.87
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 579.490241,942.87
613.250256,038.01
0.0000.00

0060                          4151.00 1.3534,321.00046,333.35
REINFORCING STEEL FOR BOX CULVERT kg 34,321.00046,333.35
37,046.00050,012.10
0.0000.00

0061                          4310.18 198.0010.0001,980.00
450 mm FLARED-END SECTION EACH10.0001,980.00
10.0001,980.00
0.0000.00

0062                          4310.24 238.0054.00012,852.00
600 mm FLARED-END SECTION EACH54.00012,852.00
56.00013,328.00
0.0000.00

0063                          4310.30 314.0012.0003,768.00
750 mm FLARED-END SECTION EACH12.0003,768.00
8.0002,512.00
0.0000.00

0064                          4310.36 400.004.0001,600.00
900 mm FLARED-END SECTION EACH4.0001,600.00
10.0004,000.00
0.0000.00

0065                          4310.42 625.008.0005,000.00
1050 mm FLARED-END SECTION EACH8.0005,000.00
8.0005,000.00
0.0000.00

0066                          4310.54 770.004.0003,080.00
1350 mm FLARED-END SECTION EACH4.0003,080.00
4.0003,080.00
0.0000.00

0067                          4320.24 595.004.0002,380.00
600 mm ROUND EQUIVALENT FLARED-END SECTION EACH4.0002,380.00
0.0000.00
0.0000.00

0068                          6105.01 42.0097.0004,074.00
ROCK RIPRAP, TYPE A Mg 97.0004,074.00
111.4004,678.80
0.0000.00

0069                          6105.02 42.00350.00014,700.00
ROCK RIPRAP, TYPE B Mg 350.00014,700.00
370.17015,547.14
0.0000.00

0070                          6105.03 42.00167.0007,014.00
ROCK RIPRAP, TYPE C Mg 167.0007,014.00
0.0000.00
0.0000.00

0071                          P127.24 166.7028.5004,750.95
600 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 28.5004,750.95
0.0000.00
0.0000.00

0072                          P300.18 72.9057.0004,155.30
450 mm CULVERT PIPE, TYPE 3,4 OR 5 m 57.0004,155.30
48.5003,535.65
0.0000.00

0073                          P300.24 78.25267.20020,908.40
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 267.20020,908.40
235.00018,388.76
0.0000.00

0074                          P300.30 90.2552.0004,693.00
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 52.0004,693.00
30.5002,752.63
0.0000.00

0075                          P300.36 96.7532.4003,134.70
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 32.4003,134.70
30.0002,902.50
0.0000.00

0076                          P300.42 119.2063.7007,593.04
1050 mm CULVERT PIPE, TYPE 3,4 OR 5 m 63.7007,593.04
57.5006,854.00
0.0000.00

0077                          P300.54 285.0031.9009,091.50
1350 mm CULVERT PIPE, TYPE 3,4 OR 5 m 31.9009,091.50
27.0007,695.00
0.0000.00

0078                          P400.24 98.2579.0007,761.75
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 79.0007,761.75
98.0009,628.51
0.0000.00

0079                          P400.30 115.0013.0001,495.00
750 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 13.0001,495.00
13.5001,552.50
0.0000.00

0080                          P402.24 72.3096.1006,948.03
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 96.1006,948.03
91.5006,615.45
0.0000.00

0081                          P402.30 102.2530.0003,067.50
750 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 30.0003,067.50
30.0003,067.50
0.0000.00

4002                          4061.01 25.750.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 300.0007,725.00
Excavation of Unsuitable Material for Box Culverts and Culvert Pipe. 338.5108,716.63
0.0000.00

4003                          4051.12 41.750.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 285.00011,898.75
Granular Material for Foundation of Box Culverts 330.91013,815.49
0.0000.00

4004                          4051.13 41.750.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF PIPE CULVERT ANDHEADWALL m3 15.000626.25
Granular Material for Foundation of Culvert Pipes. 7.600317.30
0.0000.00

GROUP 4 CULVERTSContracted518,975.54
Current539,225.54
In place543,238.49
This Estimate0.00

GROUP 5 SEEDING
0082                          0030.50 3,750.001.0003,750.00
MOBILIZATION LS 1.0003,750.00
0.0000.00
0.0000.00

0083                          L001.01 1,248.0027.00033,696.00
SEEDING, TYPE A ha 27.00033,696.00
0.0000.00
0.0000.00

0084                          L001.02 835.0015.00012,525.00
SEEDING, TYPE B ha 15.00012,525.00
0.0000.00
0.0000.00

0085                          L010.00 5.002,203.00011,015.00
SODDING m2 2,203.00011,015.00
0.0000.00
0.0000.00

0086                          L032.75 68.00189.00012,852.00
MULCH Mg 189.00012,852.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted73,838.00
Current73,838.00
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0087                          0002.55 23.00625.50014,386.50
OVERLAY BROKEN LINES StaM625.50014,386.50
59.4501,367.35
59.4501,367.35

0088                          0002.60 26.001,251.00032,526.00
OVERLAY SOLID LINES StaM1,251.00032,526.00
59.4501,545.70
59.4501,545.70

0089                          0030.90 69,000.001.00069,000.00
MOBILIZATION LS 1.00069,000.00
0.24717,043.00
0.0000.00

0090                          2001.00 7.80394.0003,073.20
GRAVEL SURFACE COURSE m3 394.0003,073.20
0.0000.00
0.0000.00

0091                          2009.10 400.002.9201,168.00
GRAVEL EMBEDMENT StaM2.9201,168.00
0.0000.00
0.0000.00

0092                          2010.00 33.80134.0004,529.20
CRUSHED ROCK SURFACE COURSE m3 134.0004,529.20
0.0000.00
0.0000.00

0093                          2021.00 50.0028.0001,400.00
MAILBOX POST EACH28.0001,400.00
0.0000.00
0.0000.00

0094                          3020.30 50.00123.0006,150.00
CONCRETE CLASS 47B-25 DRIVEWAY m2 123.0006,150.00
0.0000.00
0.0000.00

0095                          7502.04 7.00150.0001,050.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4 m 150.0001,050.00
0.0000.00
0.0000.00

0096                          7503.04 7.001,175.0008,225.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4 m 1,175.0008,225.00
0.0000.00
0.0000.00

0097                          7509.04 14.00175.0002,450.00
300 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4 m 175.0002,450.00
0.0000.00
0.0000.00

0098                          7512.04 28.0020.000560.00
600 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4 m 20.000560.00
0.0000.00
0.0000.00

0099                          8022.00 101.20593.00060,011.60
HYDRATED LIME Mg 593.00060,011.60
63.0996,385.62
63.0996,385.62

0100                          8110.50 1,268.00203.650258,228.20
HYDRATED LIME SLURRY STABILIZATION StaM203.650258,228.20
29.72537,691.30
29.72537,691.30

0101                          8111.00 225.00371.90083,677.50
SHOULDER SUBGRADE PREPARATION StaM371.90083,677.50
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted546,435.20
Current546,435.20
In place64,032.97
This Estimate46,989.97

GROUP 9 BITUIMINOUS
0102                          9000.75 13.19500.0006,595.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.0006,595.00
SPS 0.0000.00
0.0000.00

GROUP 9 BITUIMINOUSContracted6,595.00
Current6,595.00
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0103                          9005.00 27.86500.00013,930.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 500.00013,930.00
SP4(12.5) 0.0000.00
0.0000.00

0104                          9005.23 13.1938,550.000508,474.50
ASPHALTIC CONCRETE, TYPE SPS Mg 38,550.000508,474.50
4,577.34060,375.11
0.0000.00

0105                          9005.45 19.1053,360.0001,019,176.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 53,360.0001,019,176.00
0.0000.00
0.0000.00

0106                          9009.00 3.007,233.00021,699.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 7,233.00021,699.00
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted1,563,279.50
Current1,563,279.50
In place60,375.11
This Estimate0.00

GROUP 9 BITUIMINOUS
0107                          9020.92 233.0027.0006,291.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 27.0006,291.00
0.0000.00
0.0000.00

GROUP 9 BITUIMINOUSContracted6,291.00
Current6,291.00
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0108                          9021.03 233.002,081.700485,036.10
PERFORMANCE GRADED BINDER (58-28) Mg 2,081.700485,036.10
237.45655,327.25
0.0000.00

0109                          9021.08 266.002,908.440773,645.04
PERFORMANCE GRADED BINDER (64-28) Mg 2,908.440773,645.04
0.0000.00
0.0000.00

0110                          9052.15 0.23601,580.000138,363.40
EMULSIFIED ASPHALT FOR HYDRATED LIME SLURRY STABILIZATION L 601,580.000138,363.40
94,208.00021,667.84
94,208.00021,667.84

0111                          9053.00 0.26168,180.00043,726.80
TACK COAT L 168,180.00043,726.80
5,015.0001,303.90
0.0000.00

0112                          9111.00 1.502,720.0004,080.00
WATER kL 2,720.0004,080.00
0.0000.00
0.0000.00

0113                          9170.00 113.0071.6308,094.19
EARTH SHOULDER CONSTRUCTION StaM71.6308,094.19
25.5002,881.50
0.0000.00

0114                          9173.20 1.0020,462.00020,462.00
SUBGRADE PREPARATION m2 20,462.00020,462.00
11,475.00011,475.00
0.0000.00

0115                          9300.52 6,000.001.0006,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0006,000.00
0.0000.00
0.0000.00

0116                          W600.03 175.007.0001,225.00
ADJUST VALVE BOX TO GRADE EACH7.0001,225.00
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted1,480,632.53
Current1,480,632.53
In place92,655.49
This Estimate21,667.84

GROUP 10 GENERAL ITEMS
0117                          0001.08 0.5083,550.00041,775.00
BARRICADE, TYPE II BDAY83,550.00041,775.00
7,213.0003,606.50
322.000161.00

0118                          0001.10 1.508,920.00013,380.00
BARRICADE, TYPE III BDAY8,920.00013,380.00
4,652.0006,978.00
166.000249.00

0119                          0001.75 1.003,300.0003,300.00
TEMPORARY SIGN DAY EACH3,300.0003,300.00
16.00016.00
6.0006.00

0120                          0001.90 0.5028,577.00014,288.50
SIGN DAY EACH28,577.00014,288.50
11,169.0005,584.50
916.000458.00

0121                          0001.99 1.00280.000280.00
CONTRACTOR FURNISHED SIGN DAY EACH280.000280.00
0.0000.00
0.0000.00

0122                          0002.30 2.00750.0001,500.00
PAVEMENT MARKING REMOVAL m 750.0001,500.00
497.000994.00
0.0000.00

0123                          0002.39 2.508,250.00020,625.00
TEMPORARY PAVEMENT MARKING, TYPE II m 8,250.00020,625.00
9,399.00023,497.50
0.0000.00

0124                          0002.47 1.751,200.0002,100.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 1,200.0002,100.00
0.0000.00
0.0000.00

0125                          0003.10 185.00160.00029,600.00
FLAGGING DAY 160.00029,600.00
123.00022,755.00
10.5001,942.50

0126                          0003.20 285.0080.00022,800.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 80.00022,800.00
4.0001,140.00
4.0001,140.00

0127                          0010.04 1,000.001.0001,000.00
FIELD OFFICE EACH1.0001,000.00
0.0000.00
0.0000.00

0128                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
0.0000.00
0.0000.00

0129                          9110.01 50.00200.00010,000.00
RENTAL OF LOADER, FULLY OPERATED HOUR200.00010,000.00
0.0000.00
0.0000.00

0130                          9110.02 65.0040.0002,600.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR40.0002,600.00
3.000195.00
0.0000.00

0131                          9110.03 45.00200.0009,000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR200.0009,000.00
5.000225.00
0.0000.00

0132                          9110.06 50.00160.0008,000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR160.0008,000.00
19.000950.00
0.0000.00

0133                          9110.07 40.00200.0008,000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR200.0008,000.00
18.000720.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted198,248.50
Current198,248.50
In place66,661.50
This Estimate3,956.50

Totals for contractContracted5,268,204.49
Current5,275,787.49
In place1,187,646.03
This Estimate98,910.70