Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0477 WESTERN ENGINEERING COMPANY, INC.
Contract ID:8579
Estimate Number:0022
Pay Period End Date:10.27.2001
Contract Location:
BREWSTER NORTHEstimate Type:PROG
Contractor:
WESTERN ENGINEERING COMPANY, INC.Date Let:10.21.1999
1149 WEST HIGHWAY 44Date Awarded:10.28.1999
PO BOX 350Date Contract Executed:11.08.1999
Date Notice to Proceed:11.08.1999
HARLAN IA 51537Date Work Began:11.08.1999
Phone:Date Physical Work Completed:
(712)755-5191Date Accepted:
Escrow Agent:
Surety Co:
HARTFORD FIRE INSURANCE COMPANY
Counties
BLAINE
BROWN
Project Number PCT Fed State Project Number Description
80579 000B  0.000 S-7-3(1004)  GR CULV GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$3,997,901.00$3,997,029.37$871.63
$3,765,907.48Stockpiled Materials$63,149.17$63,149.17$.00
Original Contract AmtGross Earnings$4,061,050.17$4,060,178.54$871.63
$3,672,132.31Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
106.16%Net Earnings$4,036,050.17$4,035,178.54$871.63
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$14,607.03$14,607.03$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$14,607.03$14,607.03$.00
Payment$4,050,657.20$4,049,785.57$871.63
Project ManagerDiv. Head/Dist. Eng.
Rudnick, Michael10.30.2001Kovar, Mark11.02.2001
Constr. Estimate Eng.Materials Eng.
Bartos, Steve11.02.2001
Controller Div. Processed
Burling, Laurie11.05.2001
Detailed breakdown of stockpiled materials
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00529005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Initial Payment63,150.4810187
Crushed Rock 5/8"
S.P. Initial Payment28,703.9110191
2A Gravel
Total for estimate 0007:91,854.39
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00529005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-12,510.5410187
Crushed Rock 5/8"
S.P. Adjustment-12,277.7610191
2A Gravel
Total for estimate 0010:-24,788.30
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00529005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-50,639.9410187
Crushed Rock 5/8"
S.P. Adjustment-16,427.4610191
2A Gravel
Total for estimate 0011:-67,067.40
Total remaining for contract:-1.31
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.01 5.257,714.00040,498.50
EROSION CONTROL, TYPE A m2 7,714.00040,498.50
7,714.00040,498.50
0.0000.00

0002                          L020.09 8.75475.0004,156.25
EROSION CONTROL, TYPE AAA m2 475.0004,156.25
402.0003,517.50
0.0000.00

0003                          L020.10 1.75460.000805.00
EROSION CONTROL, TYPE HV m2 460.000805.00
460.000805.00
0.0000.00

0004                          L020.20 0.5288,888.00046,221.76
SLOPE PROTECTION NETTING m2 88,888.00046,221.76
107,191.30055,739.47
0.0000.00

0005                          L021.01 18.50264.0004,884.00
EROSION CHECKS, TYPE A BALE264.0004,884.00
404.0007,474.00
0.0000.00

0006                          L021.06 15.70654.00010,267.80
EROSION CHECKS, TYPE HV BALE654.00010,267.80
654.00010,267.80
0.0000.00

0007                          L022.25 7.253,435.00024,903.75
FABRIC SILT FENCE, TYPE COIR FIBER m 3,435.00024,903.75
3,435.00024,903.75
0.0000.00

0008                          0030.10 45,000.001.00045,000.00
MOBILIZATION LS 1.00045,000.00
1.00045,000.00
0.0000.00

0009                          1009.00 24,000.001.00024,000.00
GENERAL CLEARING AND GRUBBING LS 1.00024,000.00
1.00024,000.00
0.0000.00

0010                          1010.00 1.35559,407.000755,199.45
EXCAVATION m3 559,407.000755,199.45
577,550.000779,692.50
0.0000.00

0011                          1010.01 2.6232,107.00084,120.34
EXCAVATION (ESTABLISHED QUANTITY) m3 32,107.00084,120.34
49,630.274130,031.32
0.0000.00

0012                          1010.10 1.8540,642.00075,187.70
EXCAVATION, BORROW m3 40,642.00075,187.70
66,777.021123,537.49
0.0000.00

0013                          1011.00 1.006,322.0006,322.00
WATER kL 6,322.0006,322.00
1,754.2401,754.24
0.0000.00

0014                          1012.00 62.00340.00021,080.00
RIGHT-OF-WAY MARKERS EACH340.00021,080.00
343.00021,266.00
0.0000.00

0015                          1040.00 0.43406,571.000174,825.53
SLOPE PROTECTION m2 406,571.000174,825.53
530,689.000228,196.27
0.0000.00

0016                          1040.05 0.1127,386.0003,012.46
TEMPORARY SLOPE PROTECTION m2 27,386.0003,012.46
27,386.0003,012.46
0.0000.00

0017                          1040.06 114.00450.00051,300.00
SLOPE PROTECTION MULCH Mg 450.00051,300.00
828.12394,406.03
0.0000.00

0018                          1090.00 765.001.000765.00
ABANDON WELLS EACH1.000765.00
0.0000.00
0.0000.00

0019                          1701.24 57.00330.00018,810.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 330.00018,810.00
208.00011,856.00
0.0000.00

0020                          1701.30 77.0042.0003,234.00
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 42.0003,234.00
20.5001,578.50
0.0000.00

0021                          2020.00 7.5052.000390.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 52.000390.00
104.080780.60
0.0000.00

0022                          2021.00 55.003.000165.00
MAILBOX POST EACH3.000165.00
5.000275.00
0.0000.00

0023                          4310.30 260.004.0001,040.00
750 mm FLARED-END SECTION EACH4.0001,040.00
0.0000.00
0.0000.00

0024                          7151.65 1,050.001.0001,050.00
REMOVE AND RESET CATTLE GUARD EACH1.0001,050.00
2.0002,100.00
0.0000.00

0080                          1102.00 3.360.0000.00
REMOVE ASPHALT SURFACE m2 7,200.00024,192.00
Due to an error in the special provisions, the contractor had to remove additional asphalt surfacing. 7,200.00024,192.00
0.0000.00

4002                          1030.00 10.750.0000.00
EARTHWORK MEASURED IN EMBANKMENT m3 150.0001,612.50
Required to widen the intersection of N-7 & N-91 121.0001,300.75
0.0000.00

4007                          1040.00 1.2560.0000.00
SLOPE PROTECTION m2 6,500.0008,164.00
To Slope Protect the area where the surfacing from L-5B has been removed. 9,439.90011,856.51
0.0000.00

GROUP 1 GRADINGContracted1,397,238.54
Current1,431,207.04
In place1,648,041.69
This Estimate0.00

GROUP 4 CULVERTS
0025                          P312.06 82.0028.5002,337.00
150 mm CULVERT PIPE, TYPE 6,7 OR 8 m 28.5002,337.00
35.0002,870.00
0.0000.00

0026                          P312.12 78.0014.5001,131.00
300 mm CULVERT PIPE, TYPE 6,7 OR 8 m 14.5001,131.00
14.5001,131.00
0.0000.00

0027                          P600.24 100.0037.5003,750.00
600 mm CULVERT PIPE, TYPE 2,3,4,5,7 OR 8 m 37.5003,750.00
37.5003,750.00
0.0000.00

0028                          P600.36 135.00116.00015,660.00
900 mm CULVERT PIPE, TYPE 2,3,4,5,7 OR 8 m 116.00015,660.00
123.50016,672.50
0.0000.00

0029                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0030                          4050.01 89.00230.00020,470.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 230.00020,470.00
230.00020,470.00
0.0000.00

0031                          4100.06 235.0019.0004,465.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 19.0004,465.00
19.0004,465.00
0.0000.00

0032                          4310.24 265.004.0001,060.00
600 mm FLARED-END SECTION EACH4.0001,060.00
4.0001,060.00
0.0000.00

0033                          4310.36 430.007.0003,010.00
900 mm FLARED-END SECTION EACH7.0003,010.00
7.0003,010.00
0.0000.00

0082                          A900.10 787.500.0000.00
ADDITIONAL WORK EACH5.0003,937.50
Place additional concrete to raise the culvert inlets to the elevation shown in the plans. 5.0003,937.50
0.0000.00

4008                          4976.05 200.000.0000.00
ADDITIONAL WORK LS 1.000200.00
Plug temporary drainage pipe at the Blain/Brown county line 1.000200.00
0.0000.00

GROUP 4 CULVERTSContracted54,883.00
Current59,020.50
In place60,566.00
This Estimate0.00

GROUP 7 GUARDRAIL
0034                          0030.70 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0035                          7017.00 10.50320.8003,368.40
REMOVE GUARDRAIL m 320.8003,368.40
320.8003,368.40
0.0000.00

0036                          7018.01 132.0043.8005,781.60
RESET GUARDRAIL m 43.8005,781.60
43.8005,781.60
0.0000.00

0037                          7021.70 1,850.004.0007,400.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0007,400.00
4.0007,400.00
0.0000.00

GROUP 7 GUARDRAILContracted19,550.00
Current19,550.00
In place19,550.00
This Estimate0.00

GROUP 9 BITUMINOUS
0038                          P402.15 84.00160.50013,482.00
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 160.50013,482.00
160.50013,482.00
0.0000.00

0039                          0030.90 45,000.001.00045,000.00
MOBILIZATION LS 1.00045,000.00
1.00045,000.00
0.0000.00

0040                          2001.00 17.504,438.00077,665.00
GRAVEL SURFACE COURSE m3 4,438.00077,665.00
5,841.090102,219.08
0.0000.00

0041                          2005.50 11.408,760.00099,864.00
CLAY SURFACE COURSE m3 8,760.00099,864.00
10,373.350118,256.19
0.0000.00

0042                          2009.10 520.0064.90133,748.52
GRAVEL EMBEDMENT StaM64.90133,748.52
64.90133,748.52
0.0000.00

0043                          4024.55 103.0035.6803,675.04
FLUME SPILLWAY m 35.6803,675.04
36.4003,749.20
0.0000.00

0044                          4024.70 1,450.002.0002,900.00
CONCRETE FLUME, TYPE I EACH2.0002,900.00
2.0002,900.00
0.0000.00

0045                          4024.71 1,550.004.0006,200.00
CONCRETE FLUME, TYPE II EACH4.0006,200.00
5.0007,750.00
0.0000.00

0046                          4024.73 1,250.0010.00012,500.00
CONCRETE FLUME, TYPE IV EACH10.00012,500.00
10.00012,500.00
0.0000.00

0047                          8051.00 20.502,704.00055,432.00
SOIL BINDER m3 2,704.00055,432.00
5,816.750119,243.38
0.0000.00

0048                          8101.00 530.00138.17473,232.22
SUBGRADE STABILIZATION StaM138.17473,232.22
138.11673,201.48
0.0000.00

0049                          8111.00 620.007.3604,563.20
SHOULDER SUBGRADE PREPARATION StaM7.3604,563.20
7.3604,563.20
0.0000.00

0050                          9000.75 17.40100.0001,740.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 100.0001,740.00
SP1(12.5) 3.44059.86
0.0000.00

0051                          9005.00 24.50100.0002,450.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0002,450.00
SP1(12.5) 57.0801,398.46
0.0000.00

0052                          9005.25 20.3046,600.000945,980.00
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 46,600.000945,980.00
47,405.460962,330.83
0.0000.00

0053                          9009.00 3.402,510.0008,534.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 2,510.0008,534.00
2,500.0008,500.00
0.0000.00

0054                          9020.92 176.005.200915.20
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 5.200915.20
0.15727.63
0.0000.00

0055                          9021.03 176.002,428.400427,398.40
PERFORMANCE GRADED BINDER (58-28) Mg 2,428.400427,398.40
1,988.475349,971.60
0.0000.00

0056                          9030.00 6.502,210.00014,365.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 2,210.00014,365.00
2,350.52015,278.38
0.0000.00

0057                          9053.00 0.2940,740.00011,814.60
TACK COAT L 40,740.00011,814.60
56,303.04016,327.89
0.0000.00

0058                          9111.00 2.251,737.0003,908.25
WATER kL 1,737.0003,908.25
6,522.92514,676.58
0.0000.00

0059                          9170.00 104.00276.99128,807.06
EARTH SHOULDER CONSTRUCTION StaM276.99128,807.06
301.35131,340.50
0.0000.00

0060                          9179.23 570.0018.65010,630.50
COLD MILLING, CLASS 3 StaM18.65010,630.50
7.3004,161.00
0.0000.00

0061                          9179.24 1,800.00112.710202,878.00
COLD MILLING, CLASS 4 StaM112.710202,878.00
102.450184,410.00
0.0000.00

0062                          9188.50 21.8851.0001,115.88
SURFACING UNDER GUARDRAIL m2 51.0001,115.88
51.0001,115.88
0.0000.00

0063                          9300.50 5,000.001.0005,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0005,000.00
1.0005,000.00
0.0000.00

4000                          9300.56 0.2590.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 47,462.54012,292.80
Incentive for Air Voids and density 47,462.54012,292.80
0.0000.00

4001                          9005.25 34.450.0000.00
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 200.0006,890.00
For widening the radius at the junction of N-7 & N-91 118.1604,070.61
0.0000.00

4003                          9170.03 548.250.0000.00
EARTH SHOULDER CONSTRUCTION StaM0.350191.89
At the junction of N-7 & N-91 0.350191.89
0.0000.00

4004                          9179.56 3.180.0000.00
COLD MILLING, CLASS 4 m2 6,500.00020,670.00
To remove the surfacing from L-5B 4,539.60014,435.93
0.0000.00

4005                          0030.01 6,000.000.0000.00
ADDITIONAL MOBILIZATION LS 1.0006,000.00
To get equipment to the N-7 & N-91 Junction. 1.0006,000.00
0.0000.00

GROUP 9 BITUMINOUSContracted2,093,798.87
Current2,139,843.56
In place2,168,202.89
This Estimate0.00

GROUP 10 GENERAL ITEMS
0064                          0001.08 0.5014,000.0007,000.00
BARRICADE, TYPE II BDAY14,000.0007,000.00
19,235.0009,617.50
0.0000.00

0065                          0001.10 4.001,160.0004,640.00
BARRICADE, TYPE III BDAY1,160.0004,640.00
5,072.00020,288.00
90.000360.00

0066                          0001.30 4.00528.0002,112.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY528.0002,112.00
584.0002,336.00
0.0000.00

0067                          0001.90 0.9012,911.00011,619.90
SIGN DAY EACH12,911.00011,619.90
10,871.0009,783.90
90.00081.00

0068                          0002.30 1.032,800.0002,884.00
PAVEMENT MARKING REMOVAL m 2,800.0002,884.00
295.000303.85
0.0000.00

0069                          0002.31 1.032,000.0002,060.00
TEMPORARY PAVEMENT MARKING m 2,000.0002,060.00
1,574.0001,621.22
0.0000.00

0070                          0002.39 2.103,050.0006,405.00
TEMPORARY PAVEMENT MARKING, TYPE II m 3,050.0006,405.00
1,864.0003,914.40
0.0000.00

0071                          0002.45 21.00185.0003,885.00
TEMPORARY BROKEN LINES StaM185.0003,885.00
283.8255,960.33
0.0000.00

0072                          0002.48 2.10360.000756.00
TEMPORARY RAISED PAVEMENT MARKER EACH360.000756.00
320.000672.00
0.0000.00

0073                          0003.10 200.00190.00038,000.00
FLAGGING DAY 190.00038,000.00
36.5007,300.00
0.0000.00

0074                          0010.04 3,000.001.0003,000.00
FIELD OFFICE EACH1.0003,000.00
1.0003,000.00
0.0000.00

0075                          0030.00 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0076                          9110.01 60.0060.0003,600.00
RENTAL OF LOADER, FULLY OPERATED HOUR60.0003,600.00
51.5003,090.00
0.0000.00

0077                          9110.02 60.0010.000600.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000600.00
39.0002,340.00
0.0000.00

0078                          9110.03 45.0060.0002,700.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR60.0002,700.00
36.5001,642.50
0.0000.00

0079                          9110.07 40.0060.0002,400.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR60.0002,400.00
0.0000.00
0.0000.00

0081                          0002.40 24.150.0000.00
TEMPORARY SOLID LINES StaM370.0008,935.50
567.65113,708.77
0.0000.00

4006                          0002.75 3.4450.0000.00
PERMANENT PAVEMENT MARKING m 200.000689.00
To place the white edge line at the junctions of L-5B and N-7 & N-91 and around the radius at the N-7 & N-91 Jct. 279.230961.95
125.000430.63

GROUP 10 GENERAL ITEMSContracted106,661.90
Current116,286.40
In place101,540.42
This Estimate871.63

Totals for contractContracted3,672,132.31
Current3,765,907.50
In place3,997,901.00
This Estimate871.63