| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 6 BRIDGE AT STA. 3+35 | | |
|
| 0001 0001.10 | 2.30 | 1,332.000 | 3,063.60
|
| BARRICADE, TYPE III | BDAY | 1,332.000 | 3,063.60
|
| | | 50.000 | 115.00
|
| | 50.000 | 115.00
|
| | |
|
| 0002 0001.90 | 0.58 | 1,554.000 | 901.32
|
| SIGN DAY | EACH | 1,554.000 | 901.32
|
| | | 30.000 | 17.40
|
| | 30.000 | 17.40
|
| | |
|
| 0003 0001.98 | 1.15 | 666.000 | 765.90
|
| CONTRACTOR FURNISHED SIGN | EACH | 666.000 | 765.90
|
| | | 20.000 | 23.00
|
| | 20.000 | 23.00
|
| | |
|
| 0004 0030.60 | 24,230.50 | 1.000 | 24,230.50
|
| MOBILIZATION | LS | 1.000 | 24,230.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0005 1000.00 | 201.25 | 24.000 | 4,830.00
|
| LARGE TREE REMOVAL | EACH | 24.000 | 4,830.00
|
| | | 5.000 | 1,006.25
|
| | 5.000 | 1,006.25
|
| | |
|
| 0006 1009.00 | 1,725.00 | 1.000 | 1,725.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 1,725.00
|
| | | 1.000 | 1,725.00
|
| | 1.000 | 1,725.00
|
| | |
|
| 0007 1010.01 | 5.46 | 3,230.000 | 17,635.80
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 3,230.000 | 17,635.80
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0008 1011.00 | 5.16 | 100.000 | 516.00
|
| WATER | kL | 100.000 | 516.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0009 4050.01 | 6.04 | 71.000 | 428.84
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 71.000 | 428.84
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0010 4300.18 | 60.36 | 25.300 | 1,527.11
|
| 450 mm CULVERT PIPE | m | 25.300 | 1,527.11
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 4310.18 | 161.00 | 1.000 | 161.00
|
| 450 mm FLARED-END SECTION | EACH | 1.000 | 161.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0012 6000.10 | 2,587.50 | 1.000 | 2,587.50
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,587.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0013 6000.11 | 2,587.50 | 1.000 | 2,587.50
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,587.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0014 6001.50 | 3,162.50 | 1.000 | 3,162.50
|
| BENT NO.1 EXCAVATION | LS | 1.000 | 3,162.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 6001.51 | 3,162.50 | 1.000 | 3,162.50
|
| BENT NO.2 EXCAVATION | LS | 1.000 | 3,162.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 6010.22 | 473.94 | 117.890 | 55,872.79
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 117.890 | 55,872.79
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 6010.26 | 507.47 | 100.050 | 50,772.37
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 100.050 | 50,772.37
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 6020.00 | 1.46 | 18,824.000 | 27,483.04
|
| REINFORCING STEEL FOR BRIDGE | kg | 18,824.000 | 27,483.04
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 6040.00 | 2,242.50 | 1.000 | 2,242.50
|
| REMOVE STRUCTURE | EACH | 1.000 | 2,242.50
|
| AT STA. 3+37.5 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 6080.00 | 3.31 | 521.000 | 1,724.51
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 521.000 | 1,724.51
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 6105.02 | 56.99 | 662.000 | 37,727.38
|
| ROCK RIPRAP, TYPE B | Mg | 662.000 | 37,727.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 6210.12 | 67.87 | 225.200 | 15,284.32
|
| HP 250 mm X 62 kg STEEL PILING | m | 225.200 | 15,284.32
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0023 L006.00 | 115.00 | 1.000 | 115.00
|
| COVER CROP SEEDING | ha | 1.000 | 115.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 3+35 | | Contracted | 258,506.98
|
| | Current | 258,506.98
|
| | In place | 2,886.65
|
| | This Estimate | 2,886.65
|
| | |
|
| Totals for contract | | Contracted | 258,506.98
|
|---|
| | Current | 258,506.98
|
|---|
| | In place | 2,886.65
|
|---|
| | This Estimate | 2,886.65
|
|---|