Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2853 SIMON CONTRACTORS AND SUBSIDIARIES
Contract ID:7781
Estimate Number:0001
Pay Period End Date:09.20.2003
Contract Location:
HENDLEY SOUTHEASTEstimate Type:PROG
Contractor:
SIMON CONTRACTORS AND SUBSIDIARIESDate Let:02.06.2003
4819 S INDUSTRIAL SERVICE RDDate Awarded:02.27.2003
PO BOX 347Date Contract Executed:03.25.2003
Date Notice to Proceed:03.25.2003
CHEYENNE WY 82003-0347Date Work Began:08.26.2003
Phone:Date Physical Work Completed:
(307)632-7900Date Accepted:
Escrow Agent:
Surety Co:
LIBERTY MUTUAL INSURANCE COMPANY
Counties
FURNAS
Project Number PCT Fed State Project Number Description
70781 000  0.000 BRO-7033(27)  BRIDGE
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,886.65$.00$2,886.65
$258,506.98Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,886.65$.00$2,886.65
$258,506.98Retainage$-28.87$.00$-28.87
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
1.12%Net Earnings$2,857.78$.00$2,857.78
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$2,857.78$.00$2,857.78
Project ManagerDiv. Head/Dist. Eng.
Quinn, Jerry09.22.2003Knott, James09.22.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.23.2003
Controller Div. Processed
Burling, Laurie09.23.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 6 BRIDGE AT STA. 3+35
0001                          0001.10 2.301,332.0003,063.60
BARRICADE, TYPE III BDAY1,332.0003,063.60
50.000115.00
50.000115.00

0002                          0001.90 0.581,554.000901.32
SIGN DAY EACH1,554.000901.32
30.00017.40
30.00017.40

0003                          0001.98 1.15666.000765.90
CONTRACTOR FURNISHED SIGN EACH666.000765.90
20.00023.00
20.00023.00

0004                          0030.60 24,230.501.00024,230.50
MOBILIZATION LS 1.00024,230.50
0.0000.00
0.0000.00

0005                          1000.00 201.2524.0004,830.00
LARGE TREE REMOVAL EACH24.0004,830.00
5.0001,006.25
5.0001,006.25

0006                          1009.00 1,725.001.0001,725.00
GENERAL CLEARING AND GRUBBING LS 1.0001,725.00
1.0001,725.00
1.0001,725.00

0007                          1010.01 5.463,230.00017,635.80
EXCAVATION (ESTABLISHED QUANTITY) m3 3,230.00017,635.80
0.0000.00
0.0000.00

0008                          1011.00 5.16100.000516.00
WATER kL 100.000516.00
0.0000.00
0.0000.00

0009                          4050.01 6.0471.000428.84
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 71.000428.84
0.0000.00
0.0000.00

0010                          4300.18 60.3625.3001,527.11
450 mm CULVERT PIPE m 25.3001,527.11
0.0000.00
0.0000.00

0011                          4310.18 161.001.000161.00
450 mm FLARED-END SECTION EACH1.000161.00
0.0000.00
0.0000.00

0012                          6000.10 2,587.501.0002,587.50
ABUTMENT NO.1 EXCAVATION LS 1.0002,587.50
0.0000.00
0.0000.00

0013                          6000.11 2,587.501.0002,587.50
ABUTMENT NO.2 EXCAVATION LS 1.0002,587.50
0.0000.00
0.0000.00

0014                          6001.50 3,162.501.0003,162.50
BENT NO.1 EXCAVATION LS 1.0003,162.50
0.0000.00
0.0000.00

0015                          6001.51 3,162.501.0003,162.50
BENT NO.2 EXCAVATION LS 1.0003,162.50
0.0000.00
0.0000.00

0016                          6010.22 473.94117.89055,872.79
CLASS 47B-20 CONCRETE FOR BRIDGE m3 117.89055,872.79
0.0000.00
0.0000.00

0017                          6010.26 507.47100.05050,772.37
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 100.05050,772.37
0.0000.00
0.0000.00

0018                          6020.00 1.4618,824.00027,483.04
REINFORCING STEEL FOR BRIDGE kg 18,824.00027,483.04
0.0000.00
0.0000.00

0019                          6040.00 2,242.501.0002,242.50
REMOVE STRUCTURE EACH1.0002,242.50
AT STA. 3+37.5 0.0000.00
0.0000.00

0020                          6080.00 3.31521.0001,724.51
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 521.0001,724.51
0.0000.00
0.0000.00

0021                          6105.02 56.99662.00037,727.38
ROCK RIPRAP, TYPE B Mg 662.00037,727.38
0.0000.00
0.0000.00

0022                          6210.12 67.87225.20015,284.32
HP 250 mm X 62 kg STEEL PILING m 225.20015,284.32
0.0000.00
0.0000.00

0023                          L006.00 115.001.000115.00
COVER CROP SEEDING ha 1.000115.00
0.0000.00
0.0000.00

GROUP 6 BRIDGE AT STA. 3+35Contracted258,506.98
Current258,506.98
In place2,886.65
This Estimate2,886.65

Totals for contractContracted258,506.98
Current258,506.98
In place2,886.65
This Estimate2,886.65