Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2252 PAULSEN, INC.
Contract ID:7589
Estimate Number:0042
Pay Period End Date:05.09.2002
Contract Location:
BEAVER CITY EAST AND WESTEstimate Type:PROG
Contractor:
PAULSEN, INC.Date Let:04.27.2000
1116 EAST HWY 30Date Awarded:05.04.2000
P O BOX 17Date Contract Executed:05.12.2000
Date Notice to Proceed:05.12.2000
COZAD NE 69130Date Work Began:06.02.2000
Phone:Date Physical Work Completed:
(308)784-3333Date Accepted:
Escrow Agent:
Surety Co:
ST. PAUL FIRE AND MARINE INSURANCE COMPANY
Counties
FURNAS
Project Number PCT Fed State Project Number Description
70589 000  0.000 S-89-2(1001)  GR CULV SEED BR GDRL ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$4,776,443.74$4,776,503.69$-59.95
$4,814,044.32Stockpiled Materials$-.02$-.02$.00
Original Contract AmtGross Earnings$4,776,443.72$4,776,503.67$-59.95
$4,591,420.19Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.22%Net Earnings$4,751,443.72$4,751,503.67-$59.95
Liquidated Damages-$34,440.00-$43,624.00$9,184.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$106.85$106.85$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$34,333.15-$43,517.15$9,184.00
Payment$4,717,110.57$4,707,986.52$9,124.05
Project ManagerDiv. Head/Dist. Eng.
Sell, Tim05.09.2002Knott, James05.09.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.10.2002
Controller Div. Processed
Burling, Laurie05.14.2002
Detailed breakdown of stockpiled materials
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Initial Payment66,396.651178
3/4 X #4 Rock
Total for estimate 0015:66,396.65
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01446071.12 STEEL SUPERSTRUCTURE
S.P. Initial Payment63,100.0000036762
Steel Superstructure
Total for estimate 0016:63,100.00
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01446071.12 STEEL SUPERSTRUCTURE
S.P. Adjustment-47,325.0000036762
Steel Superstructure
Total for estimate 0020:-47,325.00
Est Nbr:0021
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01446071.12 STEEL SUPERSTRUCTURE
S.P. Adjustment-15,775.0000036762
Steel Superstructure
Total for estimate 0021:-15,775.00
Est Nbr:0028
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Adjustment-8,447.251178
3/4 X #4 Rock
Total for estimate 0028:-8,447.25
Est Nbr:0029
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Adjustment-6,942.621178
3/4 X #4 Rock
Total for estimate 0029:-6,942.62
Est Nbr:0030
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Adjustment-12,329.731178
3/4 X #4 Rock
Total for estimate 0030:-12,329.73
Est Nbr:0031
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Adjustment-13,994.931178
3/4 X #4 Rock
Total for estimate 0031:-13,994.93
Est Nbr:0032
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Adjustment-15,751.591178
3/4 X #4 Rock
Total for estimate 0032:-15,751.59
Est Nbr:0033
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01869005.30 ASPHALTIC CONCRETE, TYPE SP2(12.5)
S.P. Adjustment-8,930.551178
3/4 X #4 Rock
Total for estimate 0033:-8,930.55
Total remaining for contract:-0.02
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 120.0029.0003,480.00
COVER CROP SEEDING ha 29.0003,480.00
22.6742,720.88
0.0000.00

0002                          L020.00 1.363,473.0004,723.28
EROSION CONTROL m2 3,473.0004,723.28
5,015.7596,821.42
0.0000.00

0003                          L020.01 5.7316,709.00095,742.57
EROSION CONTROL, TYPE A m2 16,709.00095,742.57
15,209.65287,151.31
0.0000.00

0004                          L020.09 11.981,193.50014,298.13
EROSION CONTROL, TYPE AAA m2 1,193.50014,298.13
724.4058,678.37
0.0000.00

0005                          L020.10 1.545,333.6008,213.74
EROSION CONTROL, TYPE HV m2 5,333.6008,213.74
1,390.4332,141.27
0.0000.00

0006                          L021.00 11.00150.0001,650.00
EROSION CHECKS BALE150.0001,650.00
57.000627.00
0.0000.00

0007                          L021.01 19.00864.00016,416.00
EROSION CHECKS, TYPE A BALE864.00016,416.00
1,231.00023,389.00
0.0000.00

0008                          L021.06 14.0024.000336.00
EROSION CHECKS, TYPE HV BALE24.000336.00
102.0001,428.00
0.0000.00

0009                          L021.11 22.00108.0002,376.00
EROSION CHECKS, TYPE ST-A BALE108.0002,376.00
111.0002,442.00
0.0000.00

0010                          L021.15 18.00234.0004,212.00
EROSION CHECKS, TYPE ST-HV BALE234.0004,212.00
177.0003,186.00
0.0000.00

0011                          L022.11 7.32767.0005,614.44
FABRIC SILT FENCE-LOW POROSITY m 767.0005,614.44
224.7001,644.80
0.0000.00

0012                          L022.12 8.54436.0003,723.44
FABRIC SILT FENCE-HIGH POROSITY m 436.0003,723.44
397.9003,398.07
0.0000.00

0013                          L022.25 10.24714.0007,311.36
FABRIC SILT FENCE, TYPE COIR FIBER m 714.0007,311.36
111.3001,139.71
0.0000.00

0014                          0030.10 13,500.001.00013,500.00
MOBILIZATION LS 1.00013,500.00
1.00013,500.00
0.0000.00

0015                          1009.00 15,000.001.00015,000.00
GENERAL CLEARING AND GRUBBING LS 1.00015,000.00
1.00015,000.00
0.0000.00

0016                          1010.00 1.46293,143.000427,988.78
EXCAVATION m3 297,113.000433,784.98
300,412.000438,601.52
0.0000.00

0017                          1011.00 2.6412,135.00032,036.40
WATER kL 12,299.00032,469.36
17,950.21247,388.57
0.0000.00

0018                          1012.00 56.00166.0009,296.00
RIGHT-OF-WAY MARKERS EACH166.0009,296.00
149.0008,344.00
0.0000.00

0019                          1021.10 4.0017.00068.00
REMOVE DELINEATOR UNITS EACH17.00068.00
17.00068.00
0.0000.00

0020                          1030.00 5.803,752.00021,761.60
EARTHWORK MEASURED IN EMBANKMENT m3 4,766.00027,642.80
4,766.00027,642.80
0.0000.00

0021                          1043.50 3.33100.000333.00
RIPRAP FILTER FABRIC m2 100.000333.00
114.300380.62
0.0000.00

0022                          1101.00 4.50759.3003,416.85
REMOVE PAVEMENT m2 759.3003,416.85
4,775.64721,490.42
0.0000.00

0023                          1107.00 5.3016.00084.80
REMOVE WALK m2 16.00084.80
40.990217.25
0.0000.00

0024                          1124.00 1,500.001.0001,500.00
REMOVE BUILDING EACH1.0001,500.00
AT STA. 63+36 LT. 1.0001,500.00
0.0000.00

0025                          1125.00 1,500.001.0001,500.00
CLEAR TRACT EACH1.0001,500.00
AT STA. 63+02 TO STA. 64+20 LT. 1.0001,500.00
0.0000.00

0026                          1701.24 40.00356.80014,272.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 356.80014,272.00
356.60014,264.00
0.0000.00

0027                          1701.30 100.0040.8004,080.00
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 0.0000.00
0.0000.00
0.0000.00

0028                          2001.00 14.20149.0002,115.80
GRAVEL SURFACE COURSE m3 149.0002,115.80
200.9402,853.35
0.0000.00

0029                          2009.10 205.002.810576.05
GRAVEL EMBEDMENT StaM2.810576.05
2.138438.29
0.0000.00

0030                          4040.00 175.002.000350.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000350.00
2.000350.00
0.0000.00

0031                          6104.00 15.0060.000900.00
BROKEN CONCRETE RIPRAP Mg 60.000900.00
60.000900.00
0.0000.00

0032                          7017.00 3.00338.5001,015.50
REMOVE GUARDRAIL m 338.5001,015.50
338.5001,015.50
0.0000.00

0219                          1089.99 500.000.0000.00
ABANDON WELLS EACH1.000500.00
1.000500.00
0.0000.00

4007                          1701.36 100.000.0000.00
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 43.8004,380.00
60.8006,080.00
0.0000.00

4009                          1010.50 2.920.0000.00
REMOVAL OF UNSUITABLE MATERIAL m3 5,500.00016,060.00
Unsuitably Wet Soil Paid At 2 Times The Bid Price For Exc. 5,704.53816,657.24
0.0000.00

4010                          1101.25 8.200.0000.00
SAWING PAVEMENT m 100.000820.00
Sawing Pavement 47.370388.44
0.0000.00

4011                          1701.24 26.398130.0000.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 13.400353.73
600 mm Driveway Culvert Pipe Type 2,3,4,5,6,7, or 8 "Delivered Only" 13.400353.73
0.0000.00

4012                          1701.30 38.979930.0000.00
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 40.8001,590.38
750 mm Driveway Culvert Pipe Type 2,3,4,5,6,7 or 8"Delivered Only" 40.8001,590.38
0.0000.00

4013                          1012.00 29.9750.0000.00
RIGHT-OF-WAY MARKERS EACH11.000329.73
RIGHT-OF-WAY-MARKERS "Delivered Only" 9.000269.78
-2.000-59.95

GROUP 1 GRADINGContracted717,891.74
Current749,955.95
In place766,061.72
This Estimate-59.95

GROUP 4 CULVERTS
0033                          P300.24 61.0084.5005,154.50
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 84.5005,154.50
47.0002,867.00
0.0000.00

0034                          P310.54 181.0026.2004,742.20
1350 mm CULVERT PIPE, TYPE 2,4 OR 5 m 0.0000.00
0.0000.00
0.0000.00

0035                          P500.24 76.0050.2003,815.20
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 50.2003,815.20
101.7007,729.20
0.0000.00

0036                          P500.30 98.008.300813.40
750 mm CULVERT PIPE, TYPE 2,4,5,7 or 8 m 8.500833.00
18.2001,783.60
0.0000.00

0037                          P500.36 118.0021.5002,537.00
900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 21.5002,537.00
21.5002,537.00
0.0000.00

0038                          P700.18 80.007.700616.00
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 7.700616.00
7.300584.00
0.0000.00

0039                          P700.24 82.0042.3003,468.60
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 42.3003,468.60
51.2604,203.32
0.0000.00

0040                          P700.30 117.005.700666.90
750 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 5.700666.90
6.350742.95
0.0000.00

0041                          P700.36 200.004.000800.00
900 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 4.000800.00
8.0001,600.00
0.0000.00

0042                          0030.40 8,800.001.0008,800.00
MOBILIZATION LS 1.0008,800.00
1.0008,800.00
0.0000.00

0043                          1119.00 150.007.0001,050.00
REMOVE INLET EACH7.0001,050.00
7.0001,050.00
0.0000.00

0044                          4002.00 3.75741.0002,778.75
CAST IRON COVER AND FRAME kg 741.0002,778.75
741.0002,778.75
0.0000.00

0045                          4015.50 2,850.001.0002,850.00
RECONSTRUCT MANHOLE EACH1.0002,850.00
1.0002,850.00
0.0000.00

0046                          4040.00 100.0016.0001,600.00
REMOVE HEADWALLS FROM CULVERTS EACH16.0001,600.00
28.0002,800.00
0.0000.00

0047                          4043.50 26.0020.900543.40
REMOVE SEWER PIPE m 20.900543.40
34.150887.90
0.0000.00

0048                          4044.00 1,850.001.0001,850.00
PREPARATION OF STRUCTURE EACH1.0001,850.00
AT STA. 45+17.9 1.0001,850.00
0.0000.00

0049                          4044.02 1,600.001.0001,600.00
PREPARATION OF STRUCTURE EACH1.0001,600.00
AT STA. 85+27 1.0001,600.00
0.0000.00

0050                          4044.03 2,600.001.0002,600.00
PREPARATION OF STRUCTURE EACH1.0002,600.00
AT STA. 86+86.1 1.0002,600.00
0.0000.00

0051                          4044.04 1,400.001.0001,400.00
PREPARATION OF STRUCTURE EACH1.0001,400.00
AT STA. 96+73.1 1.0001,400.00
0.0000.00

0052                          4044.05 950.001.000950.00
PREPARATION OF STRUCTURE EACH1.000950.00
AT STA. 98+36.6 1.000950.00
0.0000.00

0053                          4044.06 950.001.000950.00
PREPARATION OF STRUCTURE EACH1.000950.00
AT STA. 104+22.9 1.000950.00
0.0000.00

0054                          4044.07 2,200.001.0002,200.00
PREPARATION OF STRUCTURE EACH1.0002,200.00
AT STA. 107+04.6 1.0002,200.00
0.0000.00

0055                          4050.01 16.001,035.00016,560.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 1,378.10022,049.60
1,514.50024,232.00
0.0000.00

0056                          4051.01 15.00657.0009,855.00
EXCAVATION FOR BOX CULVERTS m3 619.0009,285.00
238.0003,570.00
0.0000.00

0057                          4100.06 1,100.000.420462.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 2.4202,662.00
2.8403,124.00
0.0000.00

0058                          4101.06 338.00278.37094,089.06
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 249.11284,199.86
259.12487,583.92
0.0000.00

0059                          4105.59 580.0027.93016,199.40
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 27.93016,199.40
24.72514,340.50
0.0000.00

0060                          4107.07 580.002.0001,160.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 2.0001,160.00
3.2781,901.24
0.0000.00

0061                          4150.00 2.0020.00040.00
REINFORCING STEEL FOR HEADWALL kg 191.000382.00
211.000422.00
0.0000.00

0062                          4151.00 1.0818,842.00020,349.36
REINFORCING STEEL FOR BOX CULVERT kg 16,569.68717,895.26
17,308.38118,693.06
0.0000.00

0063                          4155.50 1.60648.0001,036.80
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 648.0001,036.80
648.0001,036.80
0.0000.00

0064                          4157.00 1.6086.000137.60
REINFORCING STEEL FOR COLLARS kg 86.000137.60
145.000232.00
0.0000.00

0065                          4310.24 150.0017.0002,550.00
600 mm FLARED-END SECTION EACH17.0002,550.00
16.0002,400.00
0.0000.00

0066                          4310.30 240.002.000480.00
750 mm FLARED-END SECTION EACH2.000480.00
4.000960.00
0.0000.00

0067                          4310.36 340.002.000680.00
900 mm FLARED-END SECTION EACH2.000680.00
4.0001,360.00
0.0000.00

0068                          4310.54 850.002.0001,700.00
1350 mm FLARED-END SECTION EACH0.0000.00
0.0000.00
0.0000.00

0069                          6040.01 500.001.000500.00
REMOVE STRUCTURE EACH1.000500.00
AT STA. 9000+13.7 1.000500.00
0.0000.00

4005                          P500.48 275.000.0000.00
1200 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 63.00017,325.00
63.00017,325.00
0.0000.00

4006                          4200.48 4,575.000.0000.00
1200 mm AUTOMATIC FLOOD CONTROL GATE EACH2.0009,150.00
2.0009,150.00
0.0000.00

4008                          1119.50 150.000.0000.00
REMOVE JUNCTION BOX EACH1.000150.00
Remove Jct Box at Sta.52+48 7.7m Lt. 1.000150.00
0.0000.00

GROUP 4 CULVERTSContracted217,585.17
Current232,905.87
In place239,744.24
This Estimate0.00

GROUP 4A CULVERT AT STA. 15+93.9
0070                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0071                          4045.00 3,900.001.0003,900.00
REMOVE STRUCTURE EACH1.0003,900.00
AT STA. 15+93.9 1.0003,900.00
0.0000.00

0072                          4051.01 10.001,357.00013,570.00
EXCAVATION FOR BOX CULVERTS m3 1,357.00013,570.00
1,357.00013,570.00
0.0000.00

0073                          4101.06 328.00675.550221,580.40
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 673.680220,967.04
695.911228,258.82
0.0000.00

0074                          4151.00 1.2434,058.00042,231.92
REINFORCING STEEL FOR BOX CULVERT kg 33,973.00042,126.52
34,399.28042,655.11
0.0000.00

GROUP 4A CULVERT AT STA. 15+93.9Contracted283,782.32
Current283,063.56
In place290,883.93
This Estimate0.00

GROUP 4B CULVERT AT STA. 80+84
0075                          0030.40 1,400.001.0001,400.00
MOBILIZATION LS 1.0001,400.00
1.0001,400.00
0.0000.00

0076                          4044.01 2,600.001.0002,600.00
PREPARATION OF STRUCTURE EACH1.0002,600.00
AT STA. 80+84 1.0002,600.00
0.0000.00

0077                          4051.01 14.00209.0002,926.00
EXCAVATION FOR BOX CULVERTS m3 209.0002,926.00
237.0003,318.00
0.0000.00

0078                          4101.06 355.0076.26027,072.30
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 76.26027,072.30
85.78130,452.26
0.0000.00

0079                          4151.00 1.324,527.0005,975.64
REINFORCING STEEL FOR BOX CULVERT kg 4,527.0005,975.64
5,176.8116,833.39
0.0000.00

GROUP 4B CULVERT AT STA. 80+84Contracted39,973.94
Current39,973.94
In place44,603.65
This Estimate0.00

GROUP 5 SEEDING
0080                          L001.01 1,405.0021.00029,505.00
SEEDING, TYPE A ha 21.00029,505.00
24.50034,422.50
0.0000.00

0081                          L001.02 1,121.008.0008,968.00
SEEDING, TYPE B ha 8.0008,968.00
9.90011,097.90
0.0000.00

0082                          L032.75 70.00145.00010,150.00
MULCH Mg 145.00010,150.00
172.00012,040.00
0.0000.00

0083                          0030.50 1,400.001.0001,400.00
MOBILIZATION LS 1.0001,400.00
1.0001,400.00
0.0000.00

GROUP 5 SEEDINGContracted50,023.00
Current50,023.00
In place58,960.40
This Estimate0.00

GROUP 6 BRIDGE AT STA. 30+90
0084                          0030.60 9,500.001.0009,500.00
MOBILIZATION LS 1.0009,500.00
1.0009,500.00
0.0000.00

0085                          1043.50 4.00148.000592.00
RIPRAP FILTER FABRIC m2 148.000592.00
108.100432.40
0.0000.00

0086                          3050.15 265.00118.00031,270.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 118.00031,270.00
117.00031,005.00
0.0000.00

0087                          3051.10 1.307,640.0009,932.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 7,640.0009,932.00
7,640.0009,932.00
0.0000.00

0088                          6000.10 2,100.001.0002,100.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,100.00
1.0002,100.00
0.0000.00

0089                          6000.11 2,400.001.0002,400.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,400.00
1.0002,400.00
0.0000.00

0090                          6000.20 4,600.001.0004,600.00
PIER NO.1 EXCAVATION LS 1.0004,600.00
1.0004,600.00
0.0000.00

0091                          6000.21 4,600.001.0004,600.00
PIER NO.2 EXCAVATION LS 1.0004,600.00
1.0004,600.00
0.0000.00

0092                          6005.35 176.0024.5004,312.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 24.5004,312.00
24.4764,307.78
0.0000.00

0093                          6005.60 720.0020.00014,400.00
ELASTOMERIC BEARING EACH20.00014,400.00
20.00014,400.00
0.0000.00

0094                          6010.22 380.00177.90067,602.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 177.90067,602.00
177.90067,602.00
0.0000.00

0095                          6010.26 360.00132.80047,808.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 132.80047,808.00
132.80047,808.00
0.0000.00

0096                          6040.00 11,000.001.00011,000.00
REMOVE STRUCTURE EACH1.00011,000.00
AT STA. 30+59.5 1.00011,000.00
0.0000.00

0097                          6071.12 83,000.001.00083,000.00
STEEL SUPERSTRUCTURE LS 1.00083,000.00
AT STA. 30+90 1.00083,000.00
0.0000.00

0098                          6080.00 4.602,385.00010,971.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 2,385.00010,971.00
2,385.00010,971.00
0.0000.00

0099                          6105.02 49.00570.00027,930.00
ROCK RIPRAP, TYPE B Mg 985.00048,265.00
762.13937,344.81
0.0000.00

0100                          6131.50 1.3024,170.00031,421.00
EPOXY COATED REINFORCING STEEL kg 24,190.00031,447.00
24,190.00031,447.00
0.0000.00

0101                          6139.50 22.0048.4001,064.80
SUBSURFACE DRAINAGE MATTING m2 48.4001,064.80
48.4001,064.80
0.0000.00

0102                          6210.12 98.00212.80020,854.40
HP 250 mm X 62 kg STEEL PILING m 212.80020,854.40
224.51522,002.47
0.0000.00

0103                          6251.40 1,400.0021.00029,400.00
ROCK SOCKET m 21.00029,400.00
21.03029,442.00
0.0000.00

0104                          6251.50 1,500.001.8002,700.00
DRILLED SHAFT m 1.8002,700.00
4.1106,165.00
0.0000.00

0105                          6310.00 129.00201.20025,954.80
STEEL SHEET PILING m2 201.20025,954.80
201.20025,954.80
0.0000.00

0106                          8091.00 24.00164.7003,952.80
GRANULAR BACKFILL m3 164.7003,952.80
164.7003,952.80
0.0000.00

0218                          6210.42 196.000.0000.00
HP 250 mm X 62 kg, PILE SPLICES EACH10.0001,960.00
In accordance with paragraph 3 of subsection 703.05 10.0001,960.00
0.0000.00

0220                          1010.04 5.500.0000.00
CHANNEL EXCAVATION m3 1,702.0009,361.00
PLAN REVISION 1,702.0009,361.00
0.0000.00

GROUP 6 BRIDGE AT STA. 30+90Contracted447,364.80
Current479,046.80
In place472,352.86
This Estimate0.00

GROUP 6A BRIDGE AT STA. 41+93
0107                          0030.60 12,500.001.00012,500.00
MOBILIZATION LS 1.00012,500.00
1.00012,500.00
0.0000.00

0108                          1043.50 4.0095.000380.00
RIPRAP FILTER FABRIC m2 95.000380.00
47.400189.60
0.0000.00

0109                          3050.15 315.00116.80036,792.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 116.80036,792.00
116.80036,792.00
0.0000.00

0110                          3051.10 1.307,645.0009,938.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 7,645.0009,938.50
7,645.0009,938.50
0.0000.00

0111                          6000.10 2,800.001.0002,800.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,800.00
1.0002,800.00
0.0000.00

0112                          6000.11 3,300.001.0003,300.00
ABUTMENT NO.2 EXCAVATION LS 1.0003,300.00
1.0003,300.00
0.0000.00

0113                          6000.20 2,400.001.0002,400.00
PIER NO.1 EXCAVATION LS 1.0002,400.00
1.0002,400.00
0.0000.00

0114                          6000.21 3,000.001.0003,000.00
PIER NO.2 EXCAVATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0115                          6005.35 167.0023.4003,907.80
PRECOMPRESSED POLYURETHANE FOAM JOINT m 23.4003,907.80
23.3543,900.12
0.0000.00

0116                          6005.60 775.0020.00015,500.00
ELASTOMERIC BEARING EACH20.00015,500.00
20.00015,500.00
0.0000.00

0117                          6010.22 395.00179.20070,784.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 179.20070,784.00
179.20070,784.01
0.0000.00

0118                          6010.26 385.00158.90061,176.50
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 158.90061,176.50
158.90061,176.50
0.0000.00

0119                          6040.00 13,500.001.00013,500.00
REMOVE STRUCTURE EACH1.00013,500.00
AT STA. 41+79 1.00013,500.00
0.0000.00

0120                          6071.12 118,000.001.000118,000.00
STEEL SUPERSTRUCTURE LS 1.000118,000.00
AT STA. 41+93 1.000118,000.00
0.0000.00

0121                          6080.00 4.602,685.00012,351.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 2,685.00012,351.00
2,685.00012,351.00
0.0000.00

0122                          6105.02 49.00445.50021,829.50
ROCK RIPRAP, TYPE B Mg 860.50042,164.50
602.28129,511.76
0.0000.00

0123                          6131.50 1.3029,270.00038,051.00
EPOXY COATED REINFORCING STEEL kg 29,270.00038,051.00
29,270.00038,051.00
0.0000.00

0124                          6139.50 26.0038.000988.00
SUBSURFACE DRAINAGE MATTING m2 38.000988.00
38.000988.00
0.0000.00

0125                          6210.12 88.00341.60030,060.80
HP 250 mm X 62 kg STEEL PILING m 340.60029,972.80
340.60029,972.80
0.0000.00

0126                          6251.40 1,450.0021.00030,450.00
ROCK SOCKET m 21.00030,450.00
21.47131,132.95
0.0000.00

0127                          6251.50 1,450.0021.90031,755.00
DRILLED SHAFT m 21.90031,755.00
19.94928,926.05
0.0000.00

0128                          6310.00 137.00320.00043,840.00
STEEL SHEET PILING m2 320.00043,840.00
320.00043,840.00
0.0000.00

0129                          8091.00 22.00135.0002,970.00
GRANULAR BACKFILL m3 135.0002,970.00
135.0002,970.00
0.0000.00

0216                          6210.32 52.800.0000.00
PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING m 1.00052.80
In accordance with paragraph 2 of subsection 703.05 1.00052.80
0.0000.00

0221                          1010.04 5.500.0000.00
CHANNEL EXCAVATION m3 2,166.00011,913.00
PLAN REVISION 2,166.00011,913.00
0.0000.00

0223                          6003.00 33.800.0000.00
GRANULAR MATERIAL FOR BRIDGE FOUNDATIONS m3 5.112172.79
I n accordance with Para.6A of Subsection 702.05 5.112172.78
0.0000.00

GROUP 6A BRIDGE AT STA. 41+93Contracted566,274.10
Current598,659.69
In place583,662.87
This Estimate0.00

GROUP 6B BRIDGE AT STA. 64+24.82
0130                          0030.60 12,500.001.00012,500.00
MOBILIZATION LS 1.00012,500.00
1.00012,500.00
0.0000.00

0131                          1043.50 4.00249.000996.00
RIPRAP FILTER FABRIC m2 249.000996.00
101.754407.02
0.0000.00

0132                          3050.15 315.00118.80037,422.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 118.80037,422.00
116.50036,697.50
0.0000.00

0133                          3051.10 1.308,565.00011,134.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,565.00011,134.50
8,565.00011,134.50
0.0000.00

0134                          6000.10 2,500.001.0002,500.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0135                          6000.11 2,800.001.0002,800.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,800.00
1.0002,800.00
0.0000.00

0136                          6000.20 2,300.001.0002,300.00
PIER NO.1 EXCAVATION LS 1.0002,300.00
1.0002,300.00
0.0000.00

0137                          6000.21 2,500.001.0002,500.00
PIER NO.2 EXCAVATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0138                          6005.35 178.0023.0004,094.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 23.0004,094.00
23.0004,094.00
0.0000.00

0139                          6005.78 800.0015.00012,000.00
EXPANSION BEARING, TFE TYPE EACH15.00012,000.00
15.00012,000.00
0.0000.00

0140                          6005.83 880.005.0004,400.00
FIXED BEARING EACH5.0004,400.00
5.0004,400.00
0.0000.00

0141                          6010.22 388.00173.20067,201.60
CLASS 47B-20 CONCRETE FOR BRIDGE m3 173.20067,201.60
173.20067,201.60
0.0000.00

0142                          6010.26 380.00142.90054,302.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 142.90054,302.00
142.90054,302.00
0.0000.00

0143                          6040.00 11,500.001.00011,500.00
REMOVE STRUCTURE EACH1.00011,500.00
AT STA. 64+14.95 1.00011,500.00
0.0000.00

0144                          6071.12 94,500.001.00094,500.00
STEEL SUPERSTRUCTURE LS 1.00094,500.00
AT STA. 64+24.82 1.00094,500.00
0.0000.00

0145                          6080.00 5.25820.0004,305.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 820.0004,305.00
820.0004,305.00
0.0000.00

0146                          6105.02 49.00410.00020,090.00
ROCK RIPRAP, TYPE B Mg 525.00025,725.00
537.37526,331.38
0.0000.00

0147                          6131.50 1.3228,045.00037,019.40
EPOXY COATED REINFORCING STEEL kg 28,080.00037,065.60
28,080.00037,065.60
0.0000.00

0148                          6139.50 29.0034.000986.00
SUBSURFACE DRAINAGE MATTING m2 34.000986.00
34.000986.00
0.0000.00

0149                          6210.12 94.00362.70034,093.80
HP 250 mm X 62 kg STEEL PILING m 362.70034,093.80
367.01034,498.94
0.0000.00

0150                          6251.40 1,500.0019.20028,800.00
ROCK SOCKET m 19.20028,800.00
21.18631,779.00
0.0000.00

0151                          6251.50 1,500.0022.70034,050.00
DRILLED SHAFT m 22.70034,050.00
22.05733,085.50
0.0000.00

0152                          6310.00 137.00112.00015,344.00
STEEL SHEET PILING m2 224.00030,688.00
224.00030,688.00
0.0000.00

0153                          8091.00 22.00145.0003,190.00
GRANULAR BACKFILL m3 145.0003,190.00
145.0003,190.00
0.0000.00

0222                          1010.04 5.500.0000.00
CHANNEL EXCAVATION m3 1,978.00010,879.00
PLAN REVISION 1,978.00010,879.00
0.0000.00

4004                          6210.42 188.000.0000.00
HP 250 mm X 62 kg, PILE SPLICES EACH6.0001,128.00
In accordance with paragraph 3 of subsection 703.05 6.0001,128.00
0.0000.00

GROUP 6B BRIDGE AT STA. 64+24.82Contracted498,028.30
Current531,060.50
In place532,773.04
This Estimate0.00

GROUP 7 GUARDRAIL
0154                          0030.70 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0155                          7011.20 45.00251.46011,315.70
W-BEAM GUARDRAIL m 251.46011,315.70
251.46011,315.70
0.0000.00

0156                          7020.00 1,050.0012.00012,600.00
BRIDGE APPROACH SECTIONS EACH12.00012,600.00
12.00012,600.00
0.0000.00

0157                          7021.70 1,600.0012.00019,200.00
GUARDRAIL END TREATMENT, SRT-350 EACH12.00019,200.00
12.00019,200.00
0.0000.00

GROUP 7 GUARDRAILContracted45,615.70
Current45,615.70
In place45,615.70
This Estimate0.00

GROUP 8B ELECTRICAL
0158                          A001.12 310.0010.0003,100.00
PULL BOX, TYPE PB-5 EACH10.0003,100.00
10.0003,100.00
0.0000.00

0159                          A009.29 1,580.0021.00033,180.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-1.8-0.25 EACH19.00030,020.00
19.00030,020.00
0.0000.00

0160                          A020.30 1,250.001.0001,250.00
LIGHTING CONTROL CENTER, TYPE R EACH1.0001,250.00
1.0001,250.00
0.0000.00

0161                          A070.10 7.00900.0006,300.00
38 mm CONDUIT IN TRENCH m 900.0006,300.00
1,009.4107,065.87
0.0000.00

0162                          A074.12 25.00250.0006,250.00
38 mm CONDUIT, JACKED m 250.0006,250.00
198.9404,973.50
0.0000.00

0163                          A080.22 1.251,150.0001,437.50
STREET LIGHTING CABLE, NO. 6 BARE m 1,150.0001,437.50
1,208.3501,510.44
0.0000.00

0164                          A080.24 1.502,300.0003,450.00
STREET LIGHTING CABLE, NO. 6 USE m 2,300.0003,450.00
2,416.7003,625.05
0.0000.00

0165                          0030.81 981.001.000981.00
MOBILIZATION LS 1.000981.00
1.000981.00
0.0000.00

0217                          A009.29 1,780.000.0000.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-1.8-0.25 EACH2.0003,560.00
Additional cost for raised pole foundation 2.0003,560.00
0.0000.00

GROUP 8B ELECTRICALContracted55,948.50
Current56,348.50
In place56,085.86
This Estimate0.00

GROUP 9 BITUMINOUS
0166                          P402.15 87.15267.70023,330.06
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 267.70023,330.06
217.70018,972.56
0.0000.00

0167                          P500.15 87.1578.4006,832.56
375 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 78.4006,832.56
78.4006,832.56
0.0000.00

0168                          0002.75 0.1828,000.0005,040.00
PERMANENT PAVEMENT MARKING m 28,000.0005,040.00
29,051.7885,229.32
0.0000.00

0169                          0030.90 56,200.001.00056,200.00
MOBILIZATION LS 1.00056,200.00
1.00056,200.00
0.0000.00

0170                          1020.03 24.6517.000419.05
DELINEATOR, TYPE III EACH17.000419.05
51.0001,257.15
0.0000.00

0171                          2001.00 17.90517.0009,254.30
GRAVEL SURFACE COURSE m3 517.0009,254.30
420.2567,522.57
0.0000.00

0172                          2009.10 202.257.0501,425.86
GRAVEL EMBEDMENT StaM7.0501,425.86
7.9781,613.55
0.0000.00

0173                          2020.00 3.50414.0001,449.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 414.0001,449.00
289.5001,013.25
0.0000.00

0174                          2021.00 45.005.000225.00
MAILBOX POST EACH5.000225.00
6.000270.00
0.0000.00

0175                          3016.21 33.0048.0001,584.00
CONCRETE CLASS 47B-20 SIDEWALKS m2 48.0001,584.00
58.3021,923.97
0.0000.00

0176                          3075.31 43.00856.10036,812.30
205 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 856.10036,812.30
1,248.67253,692.90
0.0000.00

0177                          4024.55 143.50110.00015,785.00
FLUME SPILLWAY m 110.00015,785.00
117.30016,832.56
0.0000.00

0178                          4024.70 1,540.0024.00036,960.00
CONCRETE FLUME, TYPE I EACH24.00036,960.00
24.00036,960.00
0.0000.00

0179                          4024.73 1,540.0022.00033,880.00
CONCRETE FLUME, TYPE IV EACH22.00033,880.00
19.00029,260.00
0.0000.00

0180                          8029.84 1.7059,490.000101,133.00
BITUMINOUS FOUNDATION COURSE 100 mm m2 59,490.000101,133.00
51,860.01188,162.02
0.0000.00

0181                          8060.05 43.50156.0006,786.00
GRANULAR SUBDRAIN EACH156.0006,786.00
149.0006,481.50
0.0000.00

0182                          8111.00 297.0046.90013,929.30
SHOULDER SUBGRADE PREPARATION StaM46.90013,929.30
48.52214,411.05
0.0000.00

0183                          9000.75 19.73100.0001,973.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 100.0001,973.00
SP2(12.5) 0.0000.00
0.0000.00

0184                          9004.91 1,092.5043.25047,250.63
HOT IN-PLACE RECYCLING StaM43.25047,250.63
43.25047,250.63
0.0000.00

0185                          9005.00 26.25100.0002,625.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0002,625.00
SP2(12.5) 68.0901,787.36
0.0000.00

0186                          9005.30 19.7329,600.000584,008.00
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 29,600.000584,008.00
30,762.789606,949.82
0.0000.00

0187                          9009.00 2.155,355.00011,513.25
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 5,355.00011,513.25
5,372.72811,551.37
0.0000.00

0188                          9020.75 481.0014.0136,740.25
REJUVENATING AGENT Mg 14.0136,740.25
0.970466.57
0.0000.00

0189                          9020.92 252.405.2001,312.48
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 5.2001,312.48
0.0000.00
0.0000.00

0190                          9021.03 252.401,544.400389,806.56
PERFORMANCE GRADED BINDER (58-28) Mg 1,544.400389,806.56
1,329.633335,599.36
0.0000.00

0191                          9030.00 5.054,162.00021,018.10
CONSTRUCTING ASPHALTIC CONCRETE CURB m 4,162.00021,018.10
3,858.30019,484.42
0.0000.00

0192                          9034.00 1.603,989.0006,382.40
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 3,989.0006,382.40
5,027.3498,043.77
0.0000.00

0193                          9053.00 0.2347,967.00011,032.41
TACK COAT L 47,967.00011,032.41
59,052.71213,582.13
0.0000.00

0194                          9111.00 2.501,671.0004,177.50
WATER kL 1,671.0004,177.50
824.6002,061.50
0.0000.00

0195                          9170.00 132.65160.79821,329.85
EARTH SHOULDER CONSTRUCTION StaM113.89815,108.57
103.86213,777.29
0.0000.00

0196                          9173.00 517.5060.29931,204.73
SUBGRADE PREPARATION StaM60.29931,204.73
57.20329,602.56
0.0000.00

0197                          9173.10 98.0010.180997.64
SUBGRADE PREPARATION FOR WIDENING StaM10.180997.64
4.330424.34
0.0000.00

0198                          9179.24 1,233.4060.29974,372.79
COLD MILLING, CLASS 4 StaM60.29974,372.79
58.60872,287.10
0.0000.00

0199                          9179.33 1.066,605.0007,001.30
COLD MILLING, CLASS 3 m2 6,605.0007,001.30
8,851.4909,382.58
0.0000.00

0200                          9188.50 16.25864.00014,040.00
SURFACING UNDER GUARDRAIL m2 864.00014,040.00
1,059.92417,223.77
0.0000.00

0201                          9300.50 2,500.001.0002,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0002,500.00
1.0002,500.00
0.0000.00

1011                          9179.00 -5.500.0000.00
ASPHALT MILLINGS Mg 100.000-550.00
Asphalt Millings, (Rebate) 727.968-4,003.82
0.0000.00

1012                          9400.05 -11.000.0000.00
RECYCLED ASPHALTIC CONCRETE FOR PRIVATE WORK CREDIT Mg 20.000-220.00
Recycled Asphalt Concrete for private Work , Credit 171.150-1,882.65
0.0000.00

4000                          4015.11 350.000.0000.00
ADJUST MANHOLE TO GRADE EACH5.0001,750.00
6.0002,100.00
0.0000.00

4001                          4003.00 2.250.0000.00
CAST IRON COVER, FRAME, & FLANGE kg 1,145.0002,576.25
1,145.0002,576.25
0.0000.00

4002                          W600.03 275.000.0000.00
ADJUST VALVE BOX TO GRADE EACH1.000275.00
2.000550.00
0.0000.00

4014                          9300.56 0.79710.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 32,040.78225,539.71
ASPHALTIC CONCRETE TYPE SP2 (12.5) 32,040.78225,539.71
0.0000.00

4015                          9300.68 0.42220.0000.00
SMOOTHNESS INCENTIVE Mg 16,166.9026,825.67
SP2 (12.5) 16,166.9026,825.67
0.0000.00

4016                          9300.77 5.4010.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 727.5113,929.29
PG Binder (58-28) 727.5113,929.29
0.0000.00

GROUP 9 BITUMINOUSContracted1,590,331.32
Current1,624,235.94
In place1,574,243.98
This Estimate0.00

GROUP 10 GENERAL ITEMS
0202                          0001.08 0.506,662.0003,331.00
BARRICADE, TYPE II BDAY6,662.0003,331.00
12,135.0006,067.50
0.0000.00

0203                          0001.10 3.157,134.00022,472.10
BARRICADE, TYPE III BDAY12,778.00040,250.70
12,778.00040,250.70
0.0000.00

0204                          0001.30 3.701,386.0005,128.20
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,386.0005,128.20
1,482.0005,483.40
0.0000.00

0205                          0001.90 0.5018,788.0009,394.00
SIGN DAY EACH37,156.00018,578.00
37,156.00018,578.00
0.0000.00

0206                          0002.30 1.95400.000780.00
PAVEMENT MARKING REMOVAL m 400.000780.00
276.000538.20
0.0000.00

0207                          0002.31 2.401,780.0004,272.00
TEMPORARY PAVEMENT MARKING m 1,780.0004,272.00
791.0001,898.40
0.0000.00

0208                          0002.45 20.75272.0005,644.00
TEMPORARY BROKEN LINES StaM272.0005,644.00
271.1115,625.55
0.0000.00

0209                          0003.10 169.0060.00010,140.00
FLAGGING DAY 99.00016,731.00
99.00016,731.00
0.0000.00

0210                          0010.04 1,750.001.0001,750.00
FIELD OFFICE EACH1.0001,750.00
1.0001,750.00
0.0000.00

0211                          0030.00 4,100.001.0004,100.00
MOBILIZATION LS 1.0004,100.00
1.0004,100.00
0.0000.00

0212                          9110.01 50.0080.0004,000.00
RENTAL OF LOADER, FULLY OPERATED HOUR80.0004,000.00
55.5002,775.00
0.0000.00

0213                          9110.02 50.0035.0001,750.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR35.0001,750.00
26.5001,325.00
0.0000.00

0214                          9110.03 41.0080.0003,280.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR80.0003,280.00
5.000205.00
0.0000.00

0215                          9110.07 32.0080.0002,560.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR80.0002,560.00
9.000288.00
0.0000.00

4003                          0002.40 20.000.0000.00
TEMPORARY SOLID LINE StaM550.00011,000.00
291.9875,839.74
0.0000.00

GROUP 10 GENERAL ITEMSContracted78,601.30
Current123,154.90
In place111,455.49
This Estimate0.00

Totals for contractContracted4,591,420.19
Current4,814,044.34
In place4,776,443.74
This Estimate-59.95