Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2853 SIMON CONTRACTORS AND SUBSIDIARIES |
Contract ID: | 6983 |
Estimate Number: | 0015 |
Pay Period End Date: | 12.07.2002 |
Contract Location: | ||
SUTHERLAND E. B. REST AREA | Estimate Type: | PROG |
Contractor: | ||
SIMON CONTRACTORS AND SUBSIDIARIES | Date Let: | 12.06.2001 |
4819 S INDUSTRIAL SERVICE RD | Date Awarded: | 12.18.2001 |
PO BOX 347 | Date Contract Executed: | 01.15.2002 |
Date Notice to Proceed: | 01.15.2002 | |
CHEYENNE WY 82003 | Date Work Began: | 04.01.2002 |
Phone: | Date Physical Work Completed: | |
(307)632-7900 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
LIBERTY MUTUAL INSURANCE COMPANY |
Counties |
---|
LINCOLN |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
60983 000 |   | 0.000 |   | EACIM-80-3(108) |   | BUILDING CONSTRUCTION |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $681,646.78 | $670,242.38 | $11,404.40 |
$682,845.00 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $681,646.78 | $670,242.38 | $11,404.40 |
$684,300.00 | Retainage | $-6,816.47 | $-6,702.43 | $-114.04 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
99.82% | Net Earnings | $674,830.31 | $663,539.95 | $11,290.36 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $674,830.31 | $663,539.95 | $11,290.36 | |
Project Manager | Div. Head/Dist. Eng. | |||
Wallin, Lance | 12.10.2002 | O'Donnell, Les | 12.11.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 12.12.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 12.12.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 8A, BUILDING CONSTRUCTION | |||
0001 L032.05 | 10.50 | 250.000 | 2,625.00 |
SHRUB BEDS | SY | 250.000 | 2,625.00 |
250.000 | 2,625.00 | ||
0.000 | 0.00 | ||
0002 0001.08 | 0.50 | 3,630.000 | 1,815.00 |
BARRICADE, TYPE II | BDAY | 3,630.000 | 1,815.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0003 0001.10 | 1.50 | 1,089.000 | 1,633.50 |
BARRICADE, TYPE III | BDAY | 1,089.000 | 1,633.50 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0004 0001.90 | 0.25 | 726.000 | 181.50 |
SIGN DAY | EACH | 726.000 | 181.50 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0005 0030.80 | 30,000.00 | 1.000 | 30,000.00 |
MOBILIZATION | LS | 1.000 | 30,000.00 |
1.000 | 30,000.00 | ||
0.000 | 0.00 | ||
0006 3016.21 | 73.00 | 325.000 | 23,725.00 |
CONCRETE CLASS 47B-3000 SIDEWALKS | SY | 325.000 | 23,725.00 |
358.312 | 26,156.78 | ||
0.000 | 0.00 | ||
0007 5100.00 | 35,400.00 | 1.000 | 35,400.00 |
REMOVAL OF EXISTING STRUCTURES | EACH | 1.000 | 35,400.00 |
1.000 | 35,400.00 | ||
0.000 | 0.00 | ||
0008 5815.00 | 358,220.00 | 1.000 | 358,220.00 |
GENERAL RESTROOM BUILDING CONSTRUCTION | EACH | 1.000 | 358,220.00 |
1.000 | 358,220.00 | ||
0.020 | 7,164.40 | ||
0009 5825.00 | 106,100.00 | 1.000 | 106,100.00 |
MECHANICAL WORK FOR RESTROOM BUILDING | EACH | 1.000 | 106,100.00 |
1.000 | 106,100.00 | ||
0.020 | 2,122.00 | ||
0010 5830.00 | 43,200.00 | 1.000 | 43,200.00 |
ELECTRICAL WORK FOR RESTROOM BUILDING | EACH | 1.000 | 43,200.00 |
1.000 | 43,200.00 | ||
0.020 | 864.00 | ||
0011 5875.10 | 18,700.00 | 1.000 | 18,700.00 |
SPRINKLER SYSTEM | EACH | 1.000 | 18,700.00 |
1.000 | 18,700.00 | ||
0.000 | 0.00 | ||
0012 5875.60 | 62,700.00 | 1.000 | 62,700.00 |
AREA LIGHTING | EACH | 1.000 | 62,700.00 |
1.000 | 62,700.00 | ||
0.020 | 1,254.00 | ||
0013 7390.20 | -1,455.00 | 0.000 | 0.00 |
REVISION | LS | 1.000 | -1,455.00 |
Revised controller | 1.000 | -1,455.00 | |
0.000 | 0.00 | ||
GROUP 8A, BUILDING CONSTRUCTION | Contracted | 684,300.00 | |
Current | 682,845.00 | ||
In place | 681,646.78 | ||
This Estimate | 11,404.40 | ||
Totals for contract | Contracted | 684,300.00 | |
Current | 682,845.00 | ||
In place | 681,646.78 | ||
This Estimate | 11,404.40 |