| | Detailed breakdown of stockpiled materials | |
|
---|
Est Nbr: | 0005 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0089 | 5820.55 | STATIC TRUCK SCALE | |
|
| | S.P. Initial Payment | 78,206.08 | 214953
|
| | Fairbanks scale componenets | |
|
| | Total for estimate 0005: | 78,206.08 |
|
Est Nbr: | 0007 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0089 | 5820.55 | STATIC TRUCK SCALE | |
|
| | S.P. Adjustment | -15,641.22 | 214953
|
| | Fairbanks scale componenets | |
|
| | Total for estimate 0007: | -15,641.22 |
|
Est Nbr: | 0009 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0089 | 5820.55 | STATIC TRUCK SCALE | |
|
| | S.P. Adjustment | -15,641.22 | 214953
|
| | Fairbanks scale componenets | |
|
| | Total for estimate 0009: | -15,641.22 |
|
Est Nbr: | 0015 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0085 | 5500.00 | SCALE BUILDING | |
|
| | S.P. Initial Payment | 21,506.60 | varies
|
| | Lumber, anchors,storage tanks & bldg materials | |
|
| | S.P. Adjustment | -430.13 | varies
|
| | Lumber, anchors,storage tanks & bldg materials | |
|
0086 | 5500.01 | SCALE BUILDING | |
|
| | S.P. Initial Payment | 21,506.60 | varies
|
| | lumber, anchors, storage tanks & bldg materials | |
|
| | S.P. Adjustment | -860.26 | varies
|
| | lumber, anchors, storage tanks & bldg materials | |
|
0087 | 5500.10 | INSPECTION BUILDING | |
|
| | S.P. Initial Payment | 27,482.00 | 6-056141
|
| | Metal building components | |
|
| | S.P. Adjustment | -549.64 | 6-056141
|
| | Metal building components | |
|
0088 | 5500.11 | INSPECTION BUILDING | |
|
| | S.P. Initial Payment | 27,482.00 | 6-056141
|
| | metal building components | |
|
| | S.P. Adjustment | -2,748.20 | 6-056141
|
| | metal building components | |
|
0091 | 5821.10 | WEIGH-IN-MOTION SYSTEM | |
|
| | S.P. Initial Payment | 14,018.31 | varies
|
| | cable, coax, and fiber optic items | |
|
| | Total for estimate 0015: | 107,407.28 |
|
Est Nbr: | 0016 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0085 | 5500.00 | SCALE BUILDING | |
|
| | S.P. Adjustment | -430.13 | varies
|
| | Lumber, anchors,storage tanks & bldg materials | |
|
0086 | 5500.01 | SCALE BUILDING | |
|
| | S.P. Adjustment | -2,580.79 | varies
|
| | lumber, anchors, storage tanks & bldg materials | |
|
0087 | 5500.10 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -2,198.56 | 6-056141
|
| | Metal building components | |
|
0088 | 5500.11 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -3,297.84 | 6-056141
|
| | metal building components | |
|
| | Total for estimate 0016: | -8,507.32 |
|
Est Nbr: | 0017 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0085 | 5500.00 | SCALE BUILDING | |
|
| | S.P. Adjustment | -1,290.40 | varies
|
| | Lumber, anchors,storage tanks & bldg materials | |
|
0086 | 5500.01 | SCALE BUILDING | |
|
| | S.P. Adjustment | -1,290.40 | varies
|
| | lumber, anchors, storage tanks & bldg materials | |
|
0087 | 5500.10 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -1,648.92 | 6-056141
|
| | Metal building components | |
|
0088 | 5500.11 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -1,099.28 | 6-056141
|
| | metal building components | |
|
0089 | 5820.55 | STATIC TRUCK SCALE | |
|
| | S.P. Adjustment | -7,820.61 | 214953
|
| | Fairbanks scale componenets | |
|
| | Total for estimate 0017: | -13,149.61 |
|
Est Nbr: | 0018 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0085 | 5500.00 | SCALE BUILDING | |
|
| | S.P. Adjustment | -860.26 | varies
|
| | Lumber, anchors,storage tanks & bldg materials | |
|
0086 | 5500.01 | SCALE BUILDING | |
|
| | S.P. Adjustment | -1,720.53 | varies
|
| | lumber, anchors, storage tanks & bldg materials | |
|
0087 | 5500.10 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -2,198.56 | 6-056141
|
| | Metal building components | |
|
0088 | 5500.11 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -1,099.28 | 6-056141
|
| | metal building components | |
|
0089 | 5820.55 | STATIC TRUCK SCALE | |
|
| | S.P. Adjustment | -11,730.91 | 214953
|
| | Fairbanks scale componenets | |
|
| | Total for estimate 0018: | -17,609.54 |
|
Est Nbr: | 0019 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0085 | 5500.00 | SCALE BUILDING | |
|
| | S.P. Adjustment | -860.26 | varies
|
| | Lumber, anchors,storage tanks & bldg materials | |
|
0086 | 5500.01 | SCALE BUILDING | |
|
| | S.P. Adjustment | -860.26 | varies
|
| | lumber, anchors, storage tanks & bldg materials | |
|
0087 | 5500.10 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -1,099.28 | 6-056141
|
| | Metal building components | |
|
0088 | 5500.11 | INSPECTION BUILDING | |
|
| | S.P. Adjustment | -1,099.28 | 6-056141
|
| | metal building components | |
|
| | Total for estimate 0019: | -3,919.08 |
|
| | Total remaining for contract: | 111,145.37 |
|
---|
| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 1 GRADING | | |
|
0001 L006.00 | 500.00 | 5.320 | 2,660.00
|
COVER CROP SEEDING | ha | 5.320 | 2,660.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 L020.07 | 5.00 | 3,274.000 | 16,370.00
|
EROSION CONTROL, TYPE B-1 | m2 | 3,274.000 | 16,370.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0003 L022.25 | 13.25 | 587.000 | 7,777.75
|
FABRIC SILT FENCE, TYPE COIR FIBER | m | 587.000 | 7,777.75
|
| | 514.000 | 6,810.50
|
| | 0.000 | 0.00
|
| | |
|
0004 0030.10 | 15,000.00 | 1.000 | 15,000.00
|
MOBILIZATION | LS | 1.000 | 15,000.00
|
| | 1.000 | 15,000.00
|
| | 0.000 | 0.00
|
| | |
|
0005 1009.00 | 12,000.00 | 1.000 | 12,000.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 12,000.00
|
| | 1.000 | 12,000.00
|
| | 0.000 | 0.00
|
| | |
|
0006 1010.50 | 5.00 | 140.000 | 700.00
|
REMOVAL OF UNSUITABLE MATERIAL | m3 | 140.000 | 700.00
|
| | 569.960 | 2,849.80
|
| | 0.000 | 0.00
|
| | |
|
0007 1011.00 | 5.00 | 782.000 | 3,910.00
|
WATER | kL | 782.000 | 3,910.00
|
| | 9,632.883 | 48,164.42
|
| | 0.000 | 0.00
|
| | |
|
0008 1012.00 | 75.00 | 18.000 | 1,350.00
|
RIGHT-OF-WAY MARKERS | EACH | 18.000 | 1,350.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 1030.00 | 10.25 | 57,918.000 | 593,659.50
|
EARTHWORK MEASURED IN EMBANKMENT | m3 | 0.000 | 0.00
|
| | 0.000 | 0.01
|
| | 0.000 | 0.00
|
| | |
|
0010 1041.00 | 2.50 | 88,505.000 | 221,262.50
|
SALVAGING AND PLACING TOPSOIL | m2 | 88,505.000 | 221,262.50
|
| | 66,380.000 | 165,950.00
|
| | 0.000 | 0.00
|
| | |
|
0011 1042.00 | 3.60 | 6,837.000 | 24,613.20
|
SALVAGING AND PLACING HYDRIC SOIL | m2 | 6,837.000 | 24,613.20
|
| | 5,575.000 | 20,070.00
|
| | 0.000 | 0.00
|
| | |
|
0012 1101.00 | 3.90 | 18,409.000 | 71,795.10
|
REMOVE PAVEMENT | m2 | 18,409.000 | 71,795.10
|
| | 17,313.653 | 67,523.25
|
| | 0.000 | 0.00
|
| | |
|
0013 1111.00 | 10.00 | 1,714.000 | 17,140.00
|
REMOVE FENCE | m | 1,714.000 | 17,140.00
|
| | 1,795.900 | 17,959.00
|
| | 0.000 | 0.00
|
| | |
|
0014 1123.95 | 3,500.00 | 1.000 | 3,500.00
|
REMOVE SCALE | EACH | 1.000 | 3,500.00
|
AT STA. 15+65 | | 1.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | |
|
0015 1124.00 | 9,000.00 | 1.000 | 9,000.00
|
REMOVE BUILDING | EACH | 1.000 | 9,000.00
|
AT STA. 15+65 RT. | | 1.000 | 9,000.00
|
| | 0.000 | 0.00
|
| | |
|
0016 1124.01 | 9,000.00 | 1.000 | 9,000.00
|
REMOVE BUILDING | EACH | 1.000 | 9,000.00
|
AT STA. 45+65 RT. | | 1.000 | 9,000.00
|
| | 0.000 | 0.00
|
| | |
|
0017 1125.00 | 5,500.00 | 1.000 | 5,500.00
|
CLEAR TRACT | EACH | 1.000 | 5,500.00
|
AT STA. 15+30-16+00 RT. | | 1.000 | 5,500.00
|
| | 0.000 | 0.00
|
| | |
|
0018 1125.01 | 5,500.00 | 1.000 | 5,500.00
|
CLEAR TRACT | EACH | 1.000 | 5,500.00
|
AT STA. 45+30-46+00 RT. | | 1.000 | 5,500.00
|
| | 0.000 | 0.00
|
| | |
|
0019 1130.00 | 1,000.00 | 2.000 | 2,000.00
|
REMOVE UNDERGROUND TANK | EACH | 2.000 | 2,000.00
|
| | 2.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0020 1900.12 | 8,000.00 | 1.000 | 8,000.00
|
ASBESTOS ABATEMENT | LS | 1.000 | 8,000.00
|
AT STA. 15+65 RT | | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
0021 1900.13 | 8,000.00 | 1.000 | 8,000.00
|
ASBESTOS ABATEMENT | LS | 1.000 | 8,000.00
|
AT STA. 45+65 RT | | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6103.00 | 3.00 | 5,733.000 | 17,199.00
|
GEOGRID | m2 | 5,733.000 | 17,199.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0023 8090.00 | 36.00 | 2,293.000 | 82,548.00
|
GRANULAR FILL | m3 | 2,293.000 | 82,548.00
|
| | 144.960 | 5,218.56
|
| | 0.000 | 0.00
|
| | |
|
0153 1030.00 | 9.896 | 0.000 | 0.00
|
EARTHWORK MEASURED IN EMBANKMENT | m3 | 57,918.000 | 573,156.53
|
Use of State ROW (VEP) | | 57,918.000 | 573,156.53
|
| | 0.000 | 0.00
|
| | |
|
GROUP 1 GRADING | | Contracted | 1,138,485.05
|
| | Current | 1,117,982.08
|
| | In place | 985,202.07
|
| | This Estimate | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | |
|
0024 L001.02 | 2,100.00 | 5.320 | 11,172.00
|
SEEDING, TYPE B | ha | 5.320 | 11,172.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0025 L010.00 | 7.00 | 720.000 | 5,040.00
|
SODDING | m2 | 720.000 | 5,040.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0026 L032.75 | 120.00 | 26.600 | 3,192.00
|
MULCH | Mg | 26.600 | 3,192.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0027 0030.30 | 30,000.00 | 1.000 | 30,000.00
|
MOBILIZATION | LS | 1.000 | 30,000.00
|
| | 1.000 | 30,000.00
|
| | 0.000 | 0.00
|
| | |
|
0028 1020.06 | 50.00 | 65.000 | 3,250.00
|
FLEXIBLE POST DELINEATOR | EACH | 65.000 | 3,250.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0029 3008.05 | 4.00 | 342.000 | 1,368.00
|
TIE BARS | EACH | 342.000 | 1,368.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0030 3008.15 | 19.00 | 120.000 | 2,280.00
|
DOWEL BAR RETROFIT | EACH | 120.000 | 2,280.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0031 3017.40 | 28.00 | 92.160 | 2,580.48
|
CONCRETE CLASS 47B-20 MEDIAN SURFACING | m2 | 92.160 | 2,580.48
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0032 3050.15 | 225.00 | 124.700 | 28,057.50
|
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 | m3 | 124.700 | 28,057.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0033 3051.10 | 1.45 | 8,053.000 | 11,676.85
|
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | kg | 8,053.000 | 11,676.85
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0034 3075.61 | 33.00 | 24,047.000 | 793,551.00
|
280 mm CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 24,047.000 | 793,551.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0035 3075.65 | 35.70 | 13,760.000 | 491,232.00
|
280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 13,760.000 | 491,232.00
|
| | 2,315.083 | 82,648.46
|
| | 0.000 | 0.00
|
| | |
|
0036 3210.10 | 12.00 | 728.000 | 8,736.00
|
DIAMOND GRINDING AND TEXTURING CONCRETE PAVEMENT | m2 | 728.000 | 8,736.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0037 3211.00 | 16.00 | 414.000 | 6,624.00
|
SEALING TRANSVERSE JOINT | m | 414.000 | 6,624.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0038 3300.50 | 0.00 | 1.000 | 0.00
|
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING | LS | 1.000 | 0.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0039 6205.12 | 175.00 | 128.400 | 22,470.00
|
310 mm PRESTRESSED CONCRETE PILING | m | 128.400 | 22,470.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0040 8029.86 | 2.10 | 37,807.000 | 79,394.70
|
BITUMINOUS FOUNDATION COURSE 150 mm | m2 | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0041 9111.00 | 4.00 | 728.000 | 2,912.00
|
WATER | kL | 728.000 | 2,912.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0042 9170.00 | 300.00 | 70.922 | 21,276.60
|
EARTH SHOULDER CONSTRUCTION | StaM | 70.922 | 21,276.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0043 9173.20 | 1.00 | 37,807.000 | 37,807.00
|
SUBGRADE PREPARATION | m2 | 37,807.000 | 37,807.00
|
| | 28,000.000 | 28,000.00
|
| | 0.000 | 0.00
|
| | |
|
0164 8029.86 | 2.80 | 0.000 | 0.00
|
BITUMINOUS FOUNDATION COURSE 150 mm | m2 | 37,807.000 | 105,859.60
|
( Revised- Provide millings from Maxwell) | | 26,075.000 | 73,010.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | Contracted | 1,562,620.13
|
| | Current | 1,589,085.03
|
| | In place | 213,658.46
|
| | This Estimate | 0.00
|
| | |
|
GROUP 4 CULVERTS | | |
|
0044 P120.18 | 125.00 | 8.000 | 1,000.00
|
450 mm CULVERT PIPE, TYPE 2 | m | 8.000 | 1,000.00
|
| | 12.400 | 1,550.00
|
| | 0.000 | 0.00
|
| | |
|
0045 P120.24 | 220.00 | 1.200 | 264.00
|
600 mm CULVERT PIPE, TYPE 2 | m | 1.200 | 264.00
|
| | 2.800 | 616.00
|
| | 0.000 | 0.00
|
| | |
|
0046 P400.18 | 75.00 | 69.300 | 5,197.50
|
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 | m | 12.700 | 952.50
|
| | 17.300 | 1,297.50
|
| | 0.000 | 0.00
|
| | |
|
0047 P400.24 | 120.00 | 104.400 | 12,528.00
|
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 | m | 89.700 | 10,764.00
|
| | 92.900 | 11,148.00
|
| | 0.000 | 0.00
|
| | |
|
0048 P400.36 | 167.00 | 109.000 | 18,203.00
|
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 | m | 109.000 | 18,203.00
|
| | 112.100 | 18,720.70
|
| | 0.000 | 0.00
|
| | |
|
0049 0030.40 | 12,000.00 | 1.000 | 12,000.00
|
MOBILIZATION | LS | 1.000 | 12,000.00
|
| | 0.910 | 10,920.00
|
| | 0.000 | 0.00
|
| | |
|
0050 1117.00 | 360.00 | 1.000 | 360.00
|
REMOVE MANHOLE | EACH | 1.000 | 360.00
|
| | 1.000 | 360.00
|
| | 0.000 | 0.00
|
| | |
|
0051 4003.00 | 5.00 | 263.000 | 1,315.00
|
CAST IRON COVER, FRAME, AND FLANGE | kg | 263.000 | 1,315.00
|
| | 263.000 | 1,315.00
|
| | 0.000 | 0.00
|
| | |
|
0052 4004.50 | 5.00 | 1,172.000 | 5,860.00
|
CAST IRON GRATE AND FRAME | kg | 1,172.000 | 5,860.00
|
| | 1,172.000 | 5,860.00
|
| | 0.000 | 0.00
|
| | |
|
0053 4016.00 | 2,800.00 | 1.000 | 2,800.00
|
MANHOLE | EACH | 1.000 | 2,800.00
|
AT STA. 15+70.1 LT. | | 1.000 | 2,800.00
|
| | 0.000 | 0.00
|
| | |
|
0054 4035.00 | 60.00 | 5.000 | 300.00
|
REMOVE FLARED-END SECTION | EACH | 5.000 | 300.00
|
| | 5.000 | 300.00
|
| | 3.000 | 180.00
|
| | |
|
0055 4035.25 | 120.00 | 3.000 | 360.00
|
REMOVE AND SALVAGE FLARED-END SECTION | EACH | 3.000 | 360.00
|
| | 2.000 | 240.00
|
| | 0.000 | 0.00
|
| | |
|
0056 4043.00 | 31.50 | 14.300 | 450.45
|
REMOVE CULVERT PIPE | m | 14.300 | 450.45
|
| | 14.300 | 450.45
|
| | 0.000 | 0.00
|
| | |
|
0057 4044.00 | 3,000.00 | 1.000 | 3,000.00
|
PREPARATION OF STRUCTURE | EACH | 1.000 | 3,000.00
|
AT STA. 123+37.5 | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
0058 4050.01 | 14.00 | 417.000 | 5,838.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 417.000 | 5,838.00
|
| | 452.466 | 6,334.52
|
| | 0.000 | 0.00
|
| | |
|
0059 4051.01 | 24.00 | 20.000 | 480.00
|
EXCAVATION FOR BOX CULVERTS | m3 | 20.000 | 480.00
|
| | 229.000 | 5,496.00
|
| | 7.663 | 183.91
|
| | |
|
0060 4101.06 | 450.00 | 50.230 | 22,603.50
|
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 50.230 | 22,603.50
|
| | 53.830 | 24,223.50
|
| | 0.000 | 0.00
|
| | |
|
0061 4105.59 | 640.00 | 5.900 | 3,776.00
|
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX | m3 | 5.900 | 3,776.00
|
| | 9.600 | 6,144.00
|
| | 0.000 | 0.00
|
| | |
|
0062 4107.07 | 700.00 | 1.050 | 735.00
|
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS | m3 | 1.050 | 735.00
|
| | 0.320 | 224.00
|
| | 0.000 | 0.00
|
| | |
|
0063 4151.00 | 2.00 | 3,355.000 | 6,710.00
|
REINFORCING STEEL FOR BOX CULVERT | kg | 3,355.000 | 6,710.00
|
| | 3,809.083 | 7,618.16
|
| | 0.000 | 0.00
|
| | |
|
0064 4155.50 | 2.00 | 202.000 | 404.00
|
REINFORCING STEEL FOR INLET AND JUNCTION BOX | kg | 202.000 | 404.00
|
| | 634.000 | 1,268.00
|
| | 0.000 | 0.00
|
| | |
|
0065 4157.00 | 2.00 | 54.000 | 108.00
|
REINFORCING STEEL FOR COLLARS | kg | 54.000 | 108.00
|
| | 17.000 | 34.00
|
| | 0.000 | 0.00
|
| | |
|
0066 4310.18 | 200.00 | 3.000 | 600.00
|
450 mm FLARED-END SECTION | EACH | 1.000 | 200.00
|
| | 1.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
0067 4310.24 | 225.00 | 10.000 | 2,250.00
|
600 mm FLARED-END SECTION | EACH | 8.000 | 1,800.00
|
| | 8.000 | 1,800.00
|
| | 0.000 | 0.00
|
| | |
|
0068 4310.36 | 465.00 | 1.000 | 465.00
|
900 mm FLARED-END SECTION | EACH | 1.000 | 465.00
|
| | 1.000 | 465.00
|
| | 0.000 | 0.00
|
| | |
|
0069 4461.18 | 550.00 | 2.000 | 1,100.00
|
INSTALL 450 mm CONCRETE FLARED-END SECTION | EACH | 1.000 | 550.00
|
| | 1.000 | 550.00
|
| | 0.000 | 0.00
|
| | |
|
0070 4461.24 | 600.00 | 1.000 | 600.00
|
INSTALL 600 mm CONCRETE FLARED-END SECTION | EACH | 1.000 | 600.00
|
| | 1.000 | 600.00
|
| | 0.000 | 0.00
|
| | |
|
0154 4305.18 | 102.93 | 0.000 | 0.00
|
450 mm ROUND EQUIVALENT CULVERT PIPE | m | 56.600 | 5,825.84
|
Pipe locations # 5 & # 6. | | 56.600 | 5,825.84
|
| | 0.000 | 0.00
|
| | |
|
0155 4305.24 | 133.01 | 0.000 | 0.00
|
600 mm ROUND EQUIVALENT CULVERT PIPE | m | 14.700 | 1,955.25
|
Pipe location # 11 ( Westbound Ramp R2) | | 14.700 | 1,955.25
|
| | 0.000 | 0.00
|
| | |
|
0156 4320.18 | 194.25 | 0.000 | 0.00
|
450 mm ROUND EQUIVALENT FLARED-END SECTION | EACH | 2.000 | 388.50
|
At pipe locations # 5 & # 6 ( At EB Ramp R1) | | 2.000 | 388.50
|
| | 0.000 | 0.00
|
| | |
|
0157 4320.24 | 241.50 | 0.000 | 0.00
|
600 mm ROUND EQUIVALENT FLARED-END SECTION | EACH | 2.000 | 483.00
|
Pipe location # 11 ( WB ramp R2) | | 2.000 | 483.00
|
| | 0.000 | 0.00
|
| | |
|
0158 4460.18 | 840.00 | 0.000 | 0.00
|
450 mm CONCRETE FLARED-END SECTION | EACH | 1.000 | 840.00
|
Original FES was damaged & had to be replaced. | | 1.000 | 840.00
|
| | 0.000 | 0.00
|
| | |
|
0159 4051.10 | 45.00 | 0.000 | 0.00
|
GRANULAR BACKFILL FOR BOX CULVERT | m3 | 85.500 | 3,847.50
|
Station 123+ 37.5 Lt. | | 18.166 | 817.47
|
| | 0.000 | 0.00
|
| | |
|
GROUP 4 CULVERTS | | Contracted | 109,307.45
|
| | Current | 115,238.54
|
| | In place | 123,844.89
|
| | This Estimate | 363.91
|
| | |
|
GROUP 4A CONCRETE BOX CULVERT AT STA. 108+66.8 | | |
|
0071 0030.40 | 2,400.00 | 1.000 | 2,400.00
|
MOBILIZATION | LS | 1.000 | 2,400.00
|
| | 1.000 | 2,400.00
|
| | 0.000 | 0.00
|
| | |
|
0072 4044.01 | 2,100.00 | 1.000 | 2,100.00
|
PREPARATION OF STRUCTURE | EACH | 1.000 | 2,100.00
|
AT STA. 108+66.8 | | 1.000 | 2,100.00
|
| | 0.000 | 0.00
|
| | |
|
0073 4051.01 | 20.00 | 105.000 | 2,100.00
|
EXCAVATION FOR BOX CULVERTS | m3 | 105.000 | 2,100.00
|
| | 156.000 | 3,120.00
|
| | 0.000 | 0.00
|
| | |
|
0074 4101.06 | 450.00 | 54.700 | 24,615.00
|
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 54.700 | 24,615.00
|
| | 52.545 | 23,645.25
|
| | 0.000 | 0.00
|
| | |
|
0075 4151.00 | 2.00 | 3,482.000 | 6,964.00
|
REINFORCING STEEL FOR BOX CULVERT | kg | 3,482.000 | 6,964.00
|
| | 3,339.000 | 6,678.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 4A CONCRETE BOX CULVERT AT STA. 108+66.8 | | Contracted | 38,179.00
|
| | Current | 38,179.00
|
| | In place | 37,943.25
|
| | This Estimate | 0.00
|
| | |
|
GROUP 7B FENCE | | |
|
0076 0030.71 | 1,200.00 | 1.000 | 1,200.00
|
MOBILIZATION | LS | 1.000 | 1,200.00
|
| | 1.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | |
|
0077 7100.00 | 31.00 | 1,993.500 | 61,798.50
|
RIGHT-OF-WAY FENCE | m | 1,993.500 | 61,798.50
|
| | 1,377.100 | 42,690.10
|
| | 0.000 | 0.00
|
| | |
|
0078 7101.00 | 300.00 | 1.000 | 300.00
|
PRIVATE FENCE TERMINALS | EACH | 1.000 | 300.00
|
| | 1.000 | 300.00
|
| | 0.000 | 0.00
|
| | |
|
0079 7102.02 | 1,800.00 | 1.000 | 1,800.00
|
CHANNEL CROSSING, TYPE"B" | EACH | 1.000 | 1,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0080 7103.00 | 240.00 | 12.000 | 2,880.00
|
END POSTS | EACH | 12.000 | 2,880.00
|
| | 10.000 | 2,400.00
|
| | 0.000 | 0.00
|
| | |
|
0081 7104.00 | 240.00 | 11.000 | 2,640.00
|
PULL POSTS | EACH | 11.000 | 2,640.00
|
| | 11.000 | 2,640.00
|
| | 0.000 | 0.00
|
| | |
|
0082 7105.00 | 240.00 | 10.000 | 2,400.00
|
CORNER POSTS | EACH | 10.000 | 2,400.00
|
| | 8.000 | 1,920.00
|
| | 0.000 | 0.00
|
| | |
|
0083 7106.12 | 500.00 | 2.000 | 1,000.00
|
3.7 m VEHICLE GATE | EACH | 2.000 | 1,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 7B FENCE | | Contracted | 74,018.50
|
| | Current | 74,018.50
|
| | In place | 51,150.10
|
| | This Estimate | 0.00
|
| | |
|
GROUP 8A BUILDING CONSTRUCTION | | |
|
0084 0030.80 | 185,000.00 | 1.000 | 185,000.00
|
MOBILIZATION | LS | 1.000 | 185,000.00
|
| | 1.000 | 185,000.00
|
| | 0.000 | 0.00
|
| | |
|
0085 5500.00 | 636,000.00 | 1.000 | 636,000.00
|
SCALE BUILDING | EACH | 1.000 | 636,000.00
|
AT STA. 15+69.7 RT.(STEEL ROOF DESIGN) | | 0.380 | 241,680.00
|
| | 0.040 | 25,440.00
|
| | |
|
0086 5500.01 | 636,000.00 | 1.000 | 636,000.00
|
SCALE BUILDING | EACH | 1.000 | 636,000.00
|
AT STA. 45+69.0 RT.(STEEL ROOF DESIGN) | | 0.600 | 381,600.00
|
| | 0.040 | 25,440.00
|
| | |
|
0087 5500.10 | 164,000.00 | 1.000 | 164,000.00
|
INSPECTION BUILDING | EACH | 1.000 | 164,000.00
|
AT STA. 15+69.7 RT. | | 0.420 | 68,880.00
|
| | 0.040 | 6,560.00
|
| | |
|
0088 5500.11 | 164,000.00 | 1.000 | 164,000.00
|
INSPECTION BUILDING | EACH | 1.000 | 164,000.00
|
AT STA. 45+69.0 RT. | | 0.700 | 114,800.00
|
| | 0.040 | 6,560.00
|
| | |
|
0089 5820.55 | 186,000.00 | 1.000 | 186,000.00
|
STATIC TRUCK SCALE | EACH | 1.000 | 186,000.00
|
AT STA. 15+69.7 RT. | | 0.900 | 167,400.00
|
| | 0.000 | 0.00
|
| | |
|
0090 5820.60 | 8,000.00 | 1.000 | 8,000.00
|
TRACKING SYSTEM | EACH | 1.000 | 8,000.00
|
AT STA. 107+80 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0091 5821.10 | 300,000.00 | 1.000 | 300,000.00
|
WEIGH-IN-MOTION SYSTEM | EACH | 1.000 | 300,000.00
|
AT STA. 133+89 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0092 5822.00 | 34,500.00 | 1.000 | 34,500.00
|
DEWATERING EASTBOUND SCALE PIT | LS | 1.000 | 34,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0093 5822.02 | 10,000.00 | 1.000 | 10,000.00
|
DEWATERING EASTBOUND INSPECTION PIT | LS | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0094 5822.03 | 10,000.00 | 1.000 | 10,000.00
|
DEWATERING WESTBOUND INSPECTION PIT | LS | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0160 6960.02 | 3,159.50 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 3,159.50
|
Install drain system for the WB static scale. | | 1.000 | 3,159.50
|
| | 0.000 | 0.00
|
| | |
|
0161 6960.02 | 1,869.00 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 1,869.00
|
Additional data and electrical outlets in scale buildings. | | 1.000 | 1,869.00
|
| | 0.000 | 0.00
|
| | |
|
0162 7390.20 | -575.00 | 0.000 | 0.00
|
REVISION | LS | 1.000 | -575.00
|
Revision to overhead doors in inspection buildings. | | 1.000 | -575.00
|
| | 0.000 | 0.00
|
| | |
|
0163 7390.20 | -3,127.00 | 0.000 | 0.00
|
REVISION | LS | 1.000 | -3,127.00
|
Eliminate security fixtures, and install standard fixtures in the Public use restrooms. | | 1.000 | -3,127.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 8A BUILDING CONSTRUCTION | | Contracted | 2,333,500.00
|
| | Current | 2,334,826.50
|
| | In place | 1,160,686.50
|
| | This Estimate | 64,000.00
|
| | |
|
GROUP 8B ELECTRICAL | | |
|
0095 A001.12 | 380.00 | 80.000 | 30,400.00
|
PULL BOX, TYPE PB-5 | EACH | 80.000 | 30,400.00
|
| | 34.000 | 12,920.00
|
| | 6.000 | 2,280.00
|
| | |
|
0096 A001.16 | 420.00 | 34.000 | 14,280.00
|
PULL BOX, TYPE PB-6 | EACH | 34.000 | 14,280.00
|
| | 14.000 | 5,880.00
|
| | 0.000 | 0.00
|
| | |
|
0097 A001.50 | 700.00 | 2.000 | 1,400.00
|
PULL BOX | EACH | 2.000 | 1,400.00
|
TYPE 610 X 914 X 457 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0098 A008.72 | 2,400.00 | 38.000 | 91,200.00
|
STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.25 | EACH | 38.000 | 91,200.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0099 A009.41 | 1,800.00 | 1.000 | 1,800.00
|
STREET LIGHTING UNIT, TYPE SL-BT-13.7-0-0.00 | EACH | 1.000 | 1,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0100 A009.93 | 2,100.00 | 46.000 | 96,600.00
|
STREET LIGHTING UNIT, TYPE SL-A-12.2-0.3-0.25 | EACH | 46.000 | 96,600.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0101 A010.86 | 660.00 | 6.000 | 3,960.00
|
LOW MOUNT LIGHTING UNIT | EACH | 6.000 | 3,960.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0102 A020.17 | 2,300.00 | 1.000 | 2,300.00
|
LIGHTING CONTROL CENTER, TYPE P | EACH | 1.000 | 2,300.00
|
| | 1.000 | 2,300.00
|
| | 0.000 | 0.00
|
| | |
|
0103 A020.48 | 1,700.00 | 5.000 | 8,500.00
|
LIGHTING CONTROL CENTER, TYPE PD | EACH | 5.000 | 8,500.00
|
| | 3.000 | 5,100.00
|
| | 0.000 | 0.00
|
| | |
|
0104 A069.10 | 54.00 | 92.000 | 4,968.00
|
38 mm CONDUIT ON STRUCTURE | m | 92.000 | 4,968.00
|
| | 32.000 | 1,728.00
|
| | 0.000 | 0.00
|
| | |
|
0105 A069.11 | 59.00 | 92.000 | 5,428.00
|
50 mm CONDUIT ON STRUCTURE | m | 92.000 | 5,428.00
|
| | 32.000 | 1,888.00
|
| | 0.000 | 0.00
|
| | |
|
0106 A069.14 | 7.75 | 93.000 | 720.75
|
25 mm CONDUIT IN TRENCH | m | 93.000 | 720.75
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0107 A070.10 | 8.00 | 8,528.000 | 68,224.00
|
38 mm CONDUIT IN TRENCH | m | 8,528.000 | 68,224.00
|
| | 6,314.951 | 50,519.61
|
| | 577.000 | 4,616.00
|
| | |
|
0108 A070.14 | 9.00 | 5,414.000 | 48,726.00
|
50 mm CONDUIT IN TRENCH | m | 5,414.000 | 48,726.00
|
| | 3,574.514 | 32,170.63
|
| | 1,355.000 | 12,195.00
|
| | |
|
0109 A070.18 | 11.00 | 130.000 | 1,430.00
|
75 mm CONDUIT IN TRENCH | m | 130.000 | 1,430.00
|
| | 103.000 | 1,133.00
|
| | 10.808 | 118.89
|
| | |
|
0110 A072.10 | 8.00 | 375.000 | 3,000.00
|
38 mm CONDUIT UNDER ROADWAY | m | 375.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0111 A072.14 | 9.00 | 142.000 | 1,278.00
|
50 mm CONDUIT UNDER ROADWAY | m | 142.000 | 1,278.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0112 A072.18 | 11.00 | 51.000 | 561.00
|
75 mm CONDUIT UNDER ROADWAY | m | 51.000 | 561.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0113 A074.14 | 60.00 | 26.000 | 1,560.00
|
50 mm CONDUIT, JACKED | m | 26.000 | 1,560.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0114 A074.18 | 66.00 | 26.000 | 1,716.00
|
75 mm CONDUIT, JACKED | m | 26.000 | 1,716.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0115 A079.15 | 9.00 | 2,847.000 | 25,623.00
|
FIBER OPTIC CABLE | m | 2,847.000 | 25,623.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0116 A079.16 | 3.60 | 390.000 | 1,404.00
|
CMS POWER AND SIGNAL CABLE | m | 390.000 | 1,404.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0117 A079.17 | 2.90 | 260.000 | 754.00
|
CAMERA POWER AND SIGNAL CABLE | m | 260.000 | 754.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0118 A079.18 | 1.80 | 1,904.000 | 3,427.20
|
LOOP LEADS | m | 1,904.000 | 3,427.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0119 A079.19 | 2.80 | 337.000 | 943.60
|
PIEZO LEADS | m | 337.000 | 943.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0120 A080.10 | 2.80 | 230.000 | 644.00
|
STREET LIGHTING CABLE, NO. 2 USE | m | 230.000 | 644.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0121 A080.11 | 2.40 | 115.000 | 276.00
|
STREET LIGHTING CABLE, NO. 2 BARE | m | 115.000 | 276.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0122 A080.22 | 0.80 | 8,597.000 | 6,877.60
|
STREET LIGHTING CABLE, NO. 6 BARE | m | 8,597.000 | 6,877.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0123 A080.24 | 1.10 | 17,194.000 | 18,913.40
|
STREET LIGHTING CABLE, NO. 6 USE | m | 17,194.000 | 18,913.40
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0124 A080.35 | 1.65 | 600.000 | 990.00
|
STREET LIGHTING CABLE, NO. 10 USE | m | 600.000 | 990.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0125 A080.38 | 1.50 | 300.000 | 450.00
|
STREET LIGHTING CABLE, NO. 10 BARE | m | 300.000 | 450.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0126 A600.00 | 420.00 | 36.000 | 15,120.00
|
REMOVE LIGHTING UNIT | EACH | 36.000 | 15,120.00
|
| | 36.000 | 15,120.00
|
| | 0.000 | 0.00
|
| | |
|
0127 A630.20 | 300.00 | 12.000 | 3,600.00
|
REMOVE PULL BOX | EACH | 12.000 | 3,600.00
|
| | 13.000 | 3,900.00
|
| | 0.000 | 0.00
|
| | |
|
0128 0030.81 | 10,000.00 | 1.000 | 10,000.00
|
MOBILIZATION | LS | 1.000 | 10,000.00
|
| | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 8B ELECTRICAL | | Contracted | 477,074.55
|
| | Current | 477,074.55
|
| | In place | 142,659.24
|
| | This Estimate | 19,209.89
|
| | |
|
GROUP 8C SIGNING | | |
|
0129 A007.15 | 600.00 | 21.000 | 12,600.00
|
VEHICLE DETECTOR, TYPE TD-5 | EACH | 21.000 | 12,600.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0130 0030.82 | 5,500.00 | 1.000 | 5,500.00
|
MOBILIZATION | LS | 1.000 | 5,500.00
|
| | 0.500 | 2,750.00
|
| | 0.500 | 2,750.00
|
| | |
|
0131 7320.00 | 1,600.00 | 2.000 | 3,200.00
|
INSTALL SIGN | EACH | 2.000 | 3,200.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0132 7322.01 | 300.00 | 37.060 | 11,118.00
|
TYPE B SIGN | m2 | 37.060 | 11,118.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0133 7340.00 | 4.50 | 1,819.400 | 8,187.30
|
STRUCTURAL STEEL FOR SIGN SUPPORTS | kg | 1,819.400 | 8,187.30
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0134 7360.24 | 575.00 | 20.000 | 11,500.00
|
600 mm SIGN SUPPORT FOOTING | EACH | 20.000 | 11,500.00
|
| | 10.000 | 5,750.00
|
| | 10.000 | 5,750.00
|
| | |
|
0135 7390.10 | 600.00 | 4.000 | 2,400.00
|
REMOVE SIGN, POST, AND FOOTING | EACH | 4.000 | 2,400.00
|
| | 5.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
0136 7500.42 | 310.00 | 2.000 | 620.00
|
HANDICAPPED SYMBOL PREFORMED PAVEMENT MARKING, TYPE 4 | EACH | 2.000 | 620.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0137 7502.14 | 9.00 | 4,700.000 | 42,300.00
|
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | m | 4,700.000 | 42,300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0138 7503.14 | 9.00 | 3,500.000 | 31,500.00
|
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | m | 3,500.000 | 31,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0139 7508.14 | 25.00 | 750.000 | 18,750.00
|
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED | m | 750.000 | 18,750.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 8C SIGNING | | Contracted | 147,675.30
|
| | Current | 147,675.30
|
| | In place | 11,500.00
|
| | This Estimate | 8,500.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0140 0001.08 | 0.50 | 900.000 | 450.00
|
BARRICADE, TYPE II | BDAY | 900.000 | 450.00
|
| | 2,687.000 | 1,343.50
|
| | 504.000 | 252.00
|
| | |
|
0141 0001.10 | 3.00 | 1,314.000 | 3,942.00
|
BARRICADE, TYPE III | BDAY | 1,314.000 | 3,942.00
|
| | 3,913.000 | 11,739.00
|
| | 98.000 | 294.00
|
| | |
|
0142 0001.30 | 1.20 | 1,284.000 | 1,540.80
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 1,284.000 | 1,540.80
|
| | 1,484.000 | 1,780.80
|
| | 70.000 | 84.00
|
| | |
|
0143 0001.75 | 9.00 | 360.000 | 3,240.00
|
TEMPORARY SIGN DAY | EACH | 360.000 | 3,240.00
|
| | 14.000 | 126.00
|
| | 0.000 | 0.00
|
| | |
|
0144 0001.90 | 2.00 | 9,630.000 | 19,260.00
|
SIGN DAY | EACH | 9,630.000 | 19,260.00
|
| | 6,694.000 | 13,388.00
|
| | 252.000 | 504.00
|
| | |
|
0145 0002.97 | 90.00 | 30.000 | 2,700.00
|
FLASHING ARROW PANEL | DAY | 30.000 | 2,700.00
|
| | 10.000 | 900.00
|
| | 0.000 | 0.00
|
| | |
|
0146 0003.10 | 125.00 | 20.000 | 2,500.00
|
FLAGGING | DAY | 20.000 | 2,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0147 0010.04 | 3,500.00 | 1.000 | 3,500.00
|
FIELD OFFICE | EACH | 1.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0148 0030.00 | 10,000.00 | 1.000 | 10,000.00
|
MOBILIZATION | LS | 1.000 | 10,000.00
|
| | 0.500 | 5,000.00
|
| | 0.000 | 0.00
|
| | |
|
0149 9110.01 | 75.00 | 10.000 | 750.00
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 10.000 | 750.00
|
| | 18.500 | 1,387.50
|
| | 0.000 | 0.00
|
| | |
|
0150 9110.03 | 50.00 | 10.000 | 500.00
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 10.000 | 500.00
|
| | 27.750 | 1,387.50
|
| | 0.000 | 0.00
|
| | |
|
0151 9110.07 | 30.00 | 10.000 | 300.00
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 10.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0152 9110.09 | 90.00 | 10.000 | 900.00
|
RENTAL OF TRACTOR AND SCRAPER, FULLY OPERATED | HOUR | 10.000 | 900.00
|
| | 45.500 | 4,095.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 49,582.80
|
| | Current | 49,582.80
|
| | In place | 41,147.30
|
| | This Estimate | 1,134.00
|
| | |
|
Totals for contract | | Contracted | 5,930,442.78
|
---|
| | Current | 5,943,662.29
|
---|
| | In place | 2,767,791.81
|
---|
| | This Estimate | 93,207.80
|
---|