Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2252 PAULSEN, INC.
Contract ID:6977X
Estimate Number:0019
Pay Period End Date:05.18.2002
Contract Location:
NORTH PLATTE TRUCK SCALESEstimate Type:PROG
Contractor:
PAULSEN, INC.Date Let:06.07.2001
1116 EAST HWY 30Date Awarded:06.25.2001
P O BOX 17Date Contract Executed:07.02.2001
Date Notice to Proceed:07.02.2001
COZAD NE 69130Date Work Began:07.23.2001
Phone:Date Physical Work Completed:
(308)784-3333Date Accepted:
Escrow Agent:
Surety Co:
ST. PAUL FIRE AND MARINE INSURANCE COMPANY
Counties
LINCOLN
Project Number PCT Fed State Project Number Description
60977 X000  0.000 EACIM-80-4(109)  GRAD CONCPAVE CULV FENCE BUILDING ELEC SIGN
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,767,791.87$2,674,584.07$93,207.80
$5,943,662.30Stockpiled Materials$111,145.37$115,064.45$-3,919.08
Original Contract AmtGross Earnings$2,878,937.24$2,789,648.52$89,288.72
$5,930,442.78Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
46.57%Net Earnings$2,853,937.24$2,764,648.52$89,288.72
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$2,365.26$2,365.26$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$2,365.26$2,365.26$.00
Payment$2,856,302.50$2,767,013.78$89,288.72
Project ManagerDiv. Head/Dist. Eng.
Thomsen, Toby05.20.2002O'Donnell, Les05.20.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.20.2002
Controller Div. Processed
Burling, Laurie05.21.2002
Detailed breakdown of stockpiled materials
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00895820.55 STATIC TRUCK SCALE
S.P. Initial Payment78,206.08214953
Fairbanks scale componenets
Total for estimate 0005:78,206.08
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00895820.55 STATIC TRUCK SCALE
S.P. Adjustment-15,641.22214953
Fairbanks scale componenets
Total for estimate 0007:-15,641.22
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00895820.55 STATIC TRUCK SCALE
S.P. Adjustment-15,641.22214953
Fairbanks scale componenets
Total for estimate 0009:-15,641.22
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00855500.00 SCALE BUILDING
S.P. Initial Payment21,506.60varies
Lumber, anchors,storage tanks & bldg materials
S.P. Adjustment-430.13varies
Lumber, anchors,storage tanks & bldg materials
00865500.01 SCALE BUILDING
S.P. Initial Payment21,506.60varies
lumber, anchors, storage tanks & bldg materials
S.P. Adjustment-860.26varies
lumber, anchors, storage tanks & bldg materials
00875500.10 INSPECTION BUILDING
S.P. Initial Payment27,482.006-056141
Metal building components
S.P. Adjustment-549.646-056141
Metal building components
00885500.11 INSPECTION BUILDING
S.P. Initial Payment27,482.006-056141
metal building components
S.P. Adjustment-2,748.206-056141
metal building components
00915821.10 WEIGH-IN-MOTION SYSTEM
S.P. Initial Payment14,018.31varies
cable, coax, and fiber optic items
Total for estimate 0015:107,407.28
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00855500.00 SCALE BUILDING
S.P. Adjustment-430.13varies
Lumber, anchors,storage tanks & bldg materials
00865500.01 SCALE BUILDING
S.P. Adjustment-2,580.79varies
lumber, anchors, storage tanks & bldg materials
00875500.10 INSPECTION BUILDING
S.P. Adjustment-2,198.566-056141
Metal building components
00885500.11 INSPECTION BUILDING
S.P. Adjustment-3,297.846-056141
metal building components
Total for estimate 0016:-8,507.32
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00855500.00 SCALE BUILDING
S.P. Adjustment-1,290.40varies
Lumber, anchors,storage tanks & bldg materials
00865500.01 SCALE BUILDING
S.P. Adjustment-1,290.40varies
lumber, anchors, storage tanks & bldg materials
00875500.10 INSPECTION BUILDING
S.P. Adjustment-1,648.926-056141
Metal building components
00885500.11 INSPECTION BUILDING
S.P. Adjustment-1,099.286-056141
metal building components
00895820.55 STATIC TRUCK SCALE
S.P. Adjustment-7,820.61214953
Fairbanks scale componenets
Total for estimate 0017:-13,149.61
Est Nbr:0018
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00855500.00 SCALE BUILDING
S.P. Adjustment-860.26varies
Lumber, anchors,storage tanks & bldg materials
00865500.01 SCALE BUILDING
S.P. Adjustment-1,720.53varies
lumber, anchors, storage tanks & bldg materials
00875500.10 INSPECTION BUILDING
S.P. Adjustment-2,198.566-056141
Metal building components
00885500.11 INSPECTION BUILDING
S.P. Adjustment-1,099.286-056141
metal building components
00895820.55 STATIC TRUCK SCALE
S.P. Adjustment-11,730.91214953
Fairbanks scale componenets
Total for estimate 0018:-17,609.54
Est Nbr:0019
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00855500.00 SCALE BUILDING
S.P. Adjustment-860.26varies
Lumber, anchors,storage tanks & bldg materials
00865500.01 SCALE BUILDING
S.P. Adjustment-860.26varies
lumber, anchors, storage tanks & bldg materials
00875500.10 INSPECTION BUILDING
S.P. Adjustment-1,099.286-056141
Metal building components
00885500.11 INSPECTION BUILDING
S.P. Adjustment-1,099.286-056141
metal building components
Total for estimate 0019:-3,919.08
Total remaining for contract:111,145.37
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 500.005.3202,660.00
COVER CROP SEEDING ha 5.3202,660.00
0.0000.00
0.0000.00

0002                          L020.07 5.003,274.00016,370.00
EROSION CONTROL, TYPE B-1 m2 3,274.00016,370.00
0.0000.00
0.0000.00

0003                          L022.25 13.25587.0007,777.75
FABRIC SILT FENCE, TYPE COIR FIBER m 587.0007,777.75
514.0006,810.50
0.0000.00

0004                          0030.10 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0005                          1009.00 12,000.001.00012,000.00
GENERAL CLEARING AND GRUBBING LS 1.00012,000.00
1.00012,000.00
0.0000.00

0006                          1010.50 5.00140.000700.00
REMOVAL OF UNSUITABLE MATERIAL m3 140.000700.00
569.9602,849.80
0.0000.00

0007                          1011.00 5.00782.0003,910.00
WATER kL 782.0003,910.00
9,632.88348,164.42
0.0000.00

0008                          1012.00 75.0018.0001,350.00
RIGHT-OF-WAY MARKERS EACH18.0001,350.00
0.0000.00
0.0000.00

0009                          1030.00 10.2557,918.000593,659.50
EARTHWORK MEASURED IN EMBANKMENT m3 0.0000.00
0.0000.01
0.0000.00

0010                          1041.00 2.5088,505.000221,262.50
SALVAGING AND PLACING TOPSOIL m2 88,505.000221,262.50
66,380.000165,950.00
0.0000.00

0011                          1042.00 3.606,837.00024,613.20
SALVAGING AND PLACING HYDRIC SOIL m2 6,837.00024,613.20
5,575.00020,070.00
0.0000.00

0012                          1101.00 3.9018,409.00071,795.10
REMOVE PAVEMENT m2 18,409.00071,795.10
17,313.65367,523.25
0.0000.00

0013                          1111.00 10.001,714.00017,140.00
REMOVE FENCE m 1,714.00017,140.00
1,795.90017,959.00
0.0000.00

0014                          1123.95 3,500.001.0003,500.00
REMOVE SCALE EACH1.0003,500.00
AT STA. 15+65 1.0003,500.00
0.0000.00

0015                          1124.00 9,000.001.0009,000.00
REMOVE BUILDING EACH1.0009,000.00
AT STA. 15+65 RT. 1.0009,000.00
0.0000.00

0016                          1124.01 9,000.001.0009,000.00
REMOVE BUILDING EACH1.0009,000.00
AT STA. 45+65 RT. 1.0009,000.00
0.0000.00

0017                          1125.00 5,500.001.0005,500.00
CLEAR TRACT EACH1.0005,500.00
AT STA. 15+30-16+00 RT. 1.0005,500.00
0.0000.00

0018                          1125.01 5,500.001.0005,500.00
CLEAR TRACT EACH1.0005,500.00
AT STA. 45+30-46+00 RT. 1.0005,500.00
0.0000.00

0019                          1130.00 1,000.002.0002,000.00
REMOVE UNDERGROUND TANK EACH2.0002,000.00
2.0002,000.00
0.0000.00

0020                          1900.12 8,000.001.0008,000.00
ASBESTOS ABATEMENT LS 1.0008,000.00
AT STA. 15+65 RT 1.0008,000.00
0.0000.00

0021                          1900.13 8,000.001.0008,000.00
ASBESTOS ABATEMENT LS 1.0008,000.00
AT STA. 45+65 RT 1.0008,000.00
0.0000.00

0022                          6103.00 3.005,733.00017,199.00
GEOGRID m2 5,733.00017,199.00
0.0000.00
0.0000.00

0023                          8090.00 36.002,293.00082,548.00
GRANULAR FILL m3 2,293.00082,548.00
144.9605,218.56
0.0000.00

0153                          1030.00 9.8960.0000.00
EARTHWORK MEASURED IN EMBANKMENT m3 57,918.000573,156.53
Use of State ROW (VEP) 57,918.000573,156.53
0.0000.00

GROUP 1 GRADINGContracted1,138,485.05
Current1,117,982.08
In place985,202.07
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0024                          L001.02 2,100.005.32011,172.00
SEEDING, TYPE B ha 5.32011,172.00
0.0000.00
0.0000.00

0025                          L010.00 7.00720.0005,040.00
SODDING m2 720.0005,040.00
0.0000.00
0.0000.00

0026                          L032.75 120.0026.6003,192.00
MULCH Mg 26.6003,192.00
0.0000.00
0.0000.00

0027                          0030.30 30,000.001.00030,000.00
MOBILIZATION LS 1.00030,000.00
1.00030,000.00
0.0000.00

0028                          1020.06 50.0065.0003,250.00
FLEXIBLE POST DELINEATOR EACH65.0003,250.00
0.0000.00
0.0000.00

0029                          3008.05 4.00342.0001,368.00
TIE BARS EACH342.0001,368.00
0.0000.00
0.0000.00

0030                          3008.15 19.00120.0002,280.00
DOWEL BAR RETROFIT EACH120.0002,280.00
0.0000.00
0.0000.00

0031                          3017.40 28.0092.1602,580.48
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 92.1602,580.48
0.0000.00
0.0000.00

0032                          3050.15 225.00124.70028,057.50
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 124.70028,057.50
0.0000.00
0.0000.00

0033                          3051.10 1.458,053.00011,676.85
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,053.00011,676.85
0.0000.00
0.0000.00

0034                          3075.61 33.0024,047.000793,551.00
280 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 24,047.000793,551.00
0.0000.00
0.0000.00

0035                          3075.65 35.7013,760.000491,232.00
280 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 13,760.000491,232.00
2,315.08382,648.46
0.0000.00

0036                          3210.10 12.00728.0008,736.00
DIAMOND GRINDING AND TEXTURING CONCRETE PAVEMENT m2 728.0008,736.00
0.0000.00
0.0000.00

0037                          3211.00 16.00414.0006,624.00
SEALING TRANSVERSE JOINT m 414.0006,624.00
0.0000.00
0.0000.00

0038                          3300.50 0.001.0000.00
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.0000.00
0.0000.00
0.0000.00

0039                          6205.12 175.00128.40022,470.00
310 mm PRESTRESSED CONCRETE PILING m 128.40022,470.00
0.0000.00
0.0000.00

0040                          8029.86 2.1037,807.00079,394.70
BITUMINOUS FOUNDATION COURSE 150 mm m2 0.0000.00
0.0000.00
0.0000.00

0041                          9111.00 4.00728.0002,912.00
WATER kL 728.0002,912.00
0.0000.00
0.0000.00

0042                          9170.00 300.0070.92221,276.60
EARTH SHOULDER CONSTRUCTION StaM70.92221,276.60
0.0000.00
0.0000.00

0043                          9173.20 1.0037,807.00037,807.00
SUBGRADE PREPARATION m2 37,807.00037,807.00
28,000.00028,000.00
0.0000.00

0164                          8029.86 2.800.0000.00
BITUMINOUS FOUNDATION COURSE 150 mm m2 37,807.000105,859.60
( Revised- Provide millings from Maxwell) 26,075.00073,010.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,562,620.13
Current1,589,085.03
In place213,658.46
This Estimate0.00

GROUP 4 CULVERTS
0044                          P120.18 125.008.0001,000.00
450 mm CULVERT PIPE, TYPE 2 m 8.0001,000.00
12.4001,550.00
0.0000.00

0045                          P120.24 220.001.200264.00
600 mm CULVERT PIPE, TYPE 2 m 1.200264.00
2.800616.00
0.0000.00

0046                          P400.18 75.0069.3005,197.50
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 12.700952.50
17.3001,297.50
0.0000.00

0047                          P400.24 120.00104.40012,528.00
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 89.70010,764.00
92.90011,148.00
0.0000.00

0048                          P400.36 167.00109.00018,203.00
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 109.00018,203.00
112.10018,720.70
0.0000.00

0049                          0030.40 12,000.001.00012,000.00
MOBILIZATION LS 1.00012,000.00
0.91010,920.00
0.0000.00

0050                          1117.00 360.001.000360.00
REMOVE MANHOLE EACH1.000360.00
1.000360.00
0.0000.00

0051                          4003.00 5.00263.0001,315.00
CAST IRON COVER, FRAME, AND FLANGE kg 263.0001,315.00
263.0001,315.00
0.0000.00

0052                          4004.50 5.001,172.0005,860.00
CAST IRON GRATE AND FRAME kg 1,172.0005,860.00
1,172.0005,860.00
0.0000.00

0053                          4016.00 2,800.001.0002,800.00
MANHOLE EACH1.0002,800.00
AT STA. 15+70.1 LT. 1.0002,800.00
0.0000.00

0054                          4035.00 60.005.000300.00
REMOVE FLARED-END SECTION EACH5.000300.00
5.000300.00
3.000180.00

0055                          4035.25 120.003.000360.00
REMOVE AND SALVAGE FLARED-END SECTION EACH3.000360.00
2.000240.00
0.0000.00

0056                          4043.00 31.5014.300450.45
REMOVE CULVERT PIPE m 14.300450.45
14.300450.45
0.0000.00

0057                          4044.00 3,000.001.0003,000.00
PREPARATION OF STRUCTURE EACH1.0003,000.00
AT STA. 123+37.5 1.0003,000.00
0.0000.00

0058                          4050.01 14.00417.0005,838.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 417.0005,838.00
452.4666,334.52
0.0000.00

0059                          4051.01 24.0020.000480.00
EXCAVATION FOR BOX CULVERTS m3 20.000480.00
229.0005,496.00
7.663183.91

0060                          4101.06 450.0050.23022,603.50
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 50.23022,603.50
53.83024,223.50
0.0000.00

0061                          4105.59 640.005.9003,776.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 5.9003,776.00
9.6006,144.00
0.0000.00

0062                          4107.07 700.001.050735.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 1.050735.00
0.320224.00
0.0000.00

0063                          4151.00 2.003,355.0006,710.00
REINFORCING STEEL FOR BOX CULVERT kg 3,355.0006,710.00
3,809.0837,618.16
0.0000.00

0064                          4155.50 2.00202.000404.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 202.000404.00
634.0001,268.00
0.0000.00

0065                          4157.00 2.0054.000108.00
REINFORCING STEEL FOR COLLARS kg 54.000108.00
17.00034.00
0.0000.00

0066                          4310.18 200.003.000600.00
450 mm FLARED-END SECTION EACH1.000200.00
1.000200.00
0.0000.00

0067                          4310.24 225.0010.0002,250.00
600 mm FLARED-END SECTION EACH8.0001,800.00
8.0001,800.00
0.0000.00

0068                          4310.36 465.001.000465.00
900 mm FLARED-END SECTION EACH1.000465.00
1.000465.00
0.0000.00

0069                          4461.18 550.002.0001,100.00
INSTALL 450 mm CONCRETE FLARED-END SECTION EACH1.000550.00
1.000550.00
0.0000.00

0070                          4461.24 600.001.000600.00
INSTALL 600 mm CONCRETE FLARED-END SECTION EACH1.000600.00
1.000600.00
0.0000.00

0154                          4305.18 102.930.0000.00
450 mm ROUND EQUIVALENT CULVERT PIPE m 56.6005,825.84
Pipe locations # 5 & # 6. 56.6005,825.84
0.0000.00

0155                          4305.24 133.010.0000.00
600 mm ROUND EQUIVALENT CULVERT PIPE m 14.7001,955.25
Pipe location # 11 ( Westbound Ramp R2) 14.7001,955.25
0.0000.00

0156                          4320.18 194.250.0000.00
450 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.000388.50
At pipe locations # 5 & # 6 ( At EB Ramp R1) 2.000388.50
0.0000.00

0157                          4320.24 241.500.0000.00
600 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.000483.00
Pipe location # 11 ( WB ramp R2) 2.000483.00
0.0000.00

0158                          4460.18 840.000.0000.00
450 mm CONCRETE FLARED-END SECTION EACH1.000840.00
Original FES was damaged & had to be replaced. 1.000840.00
0.0000.00

0159                          4051.10 45.000.0000.00
GRANULAR BACKFILL FOR BOX CULVERT m3 85.5003,847.50
Station 123+ 37.5 Lt. 18.166817.47
0.0000.00

GROUP 4 CULVERTSContracted109,307.45
Current115,238.54
In place123,844.89
This Estimate363.91

GROUP 4A CONCRETE BOX CULVERT AT STA. 108+66.8
0071                          0030.40 2,400.001.0002,400.00
MOBILIZATION LS 1.0002,400.00
1.0002,400.00
0.0000.00

0072                          4044.01 2,100.001.0002,100.00
PREPARATION OF STRUCTURE EACH1.0002,100.00
AT STA. 108+66.8 1.0002,100.00
0.0000.00

0073                          4051.01 20.00105.0002,100.00
EXCAVATION FOR BOX CULVERTS m3 105.0002,100.00
156.0003,120.00
0.0000.00

0074                          4101.06 450.0054.70024,615.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 54.70024,615.00
52.54523,645.25
0.0000.00

0075                          4151.00 2.003,482.0006,964.00
REINFORCING STEEL FOR BOX CULVERT kg 3,482.0006,964.00
3,339.0006,678.00
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 108+66.8Contracted38,179.00
Current38,179.00
In place37,943.25
This Estimate0.00

GROUP 7B FENCE
0076                          0030.71 1,200.001.0001,200.00
MOBILIZATION LS 1.0001,200.00
1.0001,200.00
0.0000.00

0077                          7100.00 31.001,993.50061,798.50
RIGHT-OF-WAY FENCE m 1,993.50061,798.50
1,377.10042,690.10
0.0000.00

0078                          7101.00 300.001.000300.00
PRIVATE FENCE TERMINALS EACH1.000300.00
1.000300.00
0.0000.00

0079                          7102.02 1,800.001.0001,800.00
CHANNEL CROSSING, TYPE"B" EACH1.0001,800.00
0.0000.00
0.0000.00

0080                          7103.00 240.0012.0002,880.00
END POSTS EACH12.0002,880.00
10.0002,400.00
0.0000.00

0081                          7104.00 240.0011.0002,640.00
PULL POSTS EACH11.0002,640.00
11.0002,640.00
0.0000.00

0082                          7105.00 240.0010.0002,400.00
CORNER POSTS EACH10.0002,400.00
8.0001,920.00
0.0000.00

0083                          7106.12 500.002.0001,000.00
3.7 m VEHICLE GATE EACH2.0001,000.00
0.0000.00
0.0000.00

GROUP 7B FENCEContracted74,018.50
Current74,018.50
In place51,150.10
This Estimate0.00

GROUP 8A BUILDING CONSTRUCTION
0084                          0030.80 185,000.001.000185,000.00
MOBILIZATION LS 1.000185,000.00
1.000185,000.00
0.0000.00

0085                          5500.00 636,000.001.000636,000.00
SCALE BUILDING EACH1.000636,000.00
AT STA. 15+69.7 RT.(STEEL ROOF DESIGN) 0.380241,680.00
0.04025,440.00

0086                          5500.01 636,000.001.000636,000.00
SCALE BUILDING EACH1.000636,000.00
AT STA. 45+69.0 RT.(STEEL ROOF DESIGN) 0.600381,600.00
0.04025,440.00

0087                          5500.10 164,000.001.000164,000.00
INSPECTION BUILDING EACH1.000164,000.00
AT STA. 15+69.7 RT. 0.42068,880.00
0.0406,560.00

0088                          5500.11 164,000.001.000164,000.00
INSPECTION BUILDING EACH1.000164,000.00
AT STA. 45+69.0 RT. 0.700114,800.00
0.0406,560.00

0089                          5820.55 186,000.001.000186,000.00
STATIC TRUCK SCALE EACH1.000186,000.00
AT STA. 15+69.7 RT. 0.900167,400.00
0.0000.00

0090                          5820.60 8,000.001.0008,000.00
TRACKING SYSTEM EACH1.0008,000.00
AT STA. 107+80 0.0000.00
0.0000.00

0091                          5821.10 300,000.001.000300,000.00
WEIGH-IN-MOTION SYSTEM EACH1.000300,000.00
AT STA. 133+89 0.0000.00
0.0000.00

0092                          5822.00 34,500.001.00034,500.00
DEWATERING EASTBOUND SCALE PIT LS 1.00034,500.00
0.0000.00
0.0000.00

0093                          5822.02 10,000.001.00010,000.00
DEWATERING EASTBOUND INSPECTION PIT LS 1.00010,000.00
0.0000.00
0.0000.00

0094                          5822.03 10,000.001.00010,000.00
DEWATERING WESTBOUND INSPECTION PIT LS 1.00010,000.00
0.0000.00
0.0000.00

0160                          6960.02 3,159.500.0000.00
ADDITIONAL WORK LS 1.0003,159.50
Install drain system for the WB static scale. 1.0003,159.50
0.0000.00

0161                          6960.02 1,869.000.0000.00
ADDITIONAL WORK LS 1.0001,869.00
Additional data and electrical outlets in scale buildings. 1.0001,869.00
0.0000.00

0162                          7390.20 -575.000.0000.00
REVISION LS 1.000-575.00
Revision to overhead doors in inspection buildings. 1.000-575.00
0.0000.00

0163                          7390.20 -3,127.000.0000.00
REVISION LS 1.000-3,127.00
Eliminate security fixtures, and install standard fixtures in the Public use restrooms. 1.000-3,127.00
0.0000.00

GROUP 8A BUILDING CONSTRUCTIONContracted2,333,500.00
Current2,334,826.50
In place1,160,686.50
This Estimate64,000.00

GROUP 8B ELECTRICAL
0095                          A001.12 380.0080.00030,400.00
PULL BOX, TYPE PB-5 EACH80.00030,400.00
34.00012,920.00
6.0002,280.00

0096                          A001.16 420.0034.00014,280.00
PULL BOX, TYPE PB-6 EACH34.00014,280.00
14.0005,880.00
0.0000.00

0097                          A001.50 700.002.0001,400.00
PULL BOX EACH2.0001,400.00
TYPE 610 X 914 X 457 0.0000.00
0.0000.00

0098                          A008.72 2,400.0038.00091,200.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-0.3-0.25 EACH38.00091,200.00
0.0000.00
0.0000.00

0099                          A009.41 1,800.001.0001,800.00
STREET LIGHTING UNIT, TYPE SL-BT-13.7-0-0.00 EACH1.0001,800.00
0.0000.00
0.0000.00

0100                          A009.93 2,100.0046.00096,600.00
STREET LIGHTING UNIT, TYPE SL-A-12.2-0.3-0.25 EACH46.00096,600.00
0.0000.00
0.0000.00

0101                          A010.86 660.006.0003,960.00
LOW MOUNT LIGHTING UNIT EACH6.0003,960.00
0.0000.00
0.0000.00

0102                          A020.17 2,300.001.0002,300.00
LIGHTING CONTROL CENTER, TYPE P EACH1.0002,300.00
1.0002,300.00
0.0000.00

0103                          A020.48 1,700.005.0008,500.00
LIGHTING CONTROL CENTER, TYPE PD EACH5.0008,500.00
3.0005,100.00
0.0000.00

0104                          A069.10 54.0092.0004,968.00
38 mm CONDUIT ON STRUCTURE m 92.0004,968.00
32.0001,728.00
0.0000.00

0105                          A069.11 59.0092.0005,428.00
50 mm CONDUIT ON STRUCTURE m 92.0005,428.00
32.0001,888.00
0.0000.00

0106                          A069.14 7.7593.000720.75
25 mm CONDUIT IN TRENCH m 93.000720.75
0.0000.00
0.0000.00

0107                          A070.10 8.008,528.00068,224.00
38 mm CONDUIT IN TRENCH m 8,528.00068,224.00
6,314.95150,519.61
577.0004,616.00

0108                          A070.14 9.005,414.00048,726.00
50 mm CONDUIT IN TRENCH m 5,414.00048,726.00
3,574.51432,170.63
1,355.00012,195.00

0109                          A070.18 11.00130.0001,430.00
75 mm CONDUIT IN TRENCH m 130.0001,430.00
103.0001,133.00
10.808118.89

0110                          A072.10 8.00375.0003,000.00
38 mm CONDUIT UNDER ROADWAY m 375.0003,000.00
0.0000.00
0.0000.00

0111                          A072.14 9.00142.0001,278.00
50 mm CONDUIT UNDER ROADWAY m 142.0001,278.00
0.0000.00
0.0000.00

0112                          A072.18 11.0051.000561.00
75 mm CONDUIT UNDER ROADWAY m 51.000561.00
0.0000.00
0.0000.00

0113                          A074.14 60.0026.0001,560.00
50 mm CONDUIT, JACKED m 26.0001,560.00
0.0000.00
0.0000.00

0114                          A074.18 66.0026.0001,716.00
75 mm CONDUIT, JACKED m 26.0001,716.00
0.0000.00
0.0000.00

0115                          A079.15 9.002,847.00025,623.00
FIBER OPTIC CABLE m 2,847.00025,623.00
0.0000.00
0.0000.00

0116                          A079.16 3.60390.0001,404.00
CMS POWER AND SIGNAL CABLE m 390.0001,404.00
0.0000.00
0.0000.00

0117                          A079.17 2.90260.000754.00
CAMERA POWER AND SIGNAL CABLE m 260.000754.00
0.0000.00
0.0000.00

0118                          A079.18 1.801,904.0003,427.20
LOOP LEADS m 1,904.0003,427.20
0.0000.00
0.0000.00

0119                          A079.19 2.80337.000943.60
PIEZO LEADS m 337.000943.60
0.0000.00
0.0000.00

0120                          A080.10 2.80230.000644.00
STREET LIGHTING CABLE, NO. 2 USE m 230.000644.00
0.0000.00
0.0000.00

0121                          A080.11 2.40115.000276.00
STREET LIGHTING CABLE, NO. 2 BARE m 115.000276.00
0.0000.00
0.0000.00

0122                          A080.22 0.808,597.0006,877.60
STREET LIGHTING CABLE, NO. 6 BARE m 8,597.0006,877.60
0.0000.00
0.0000.00

0123                          A080.24 1.1017,194.00018,913.40
STREET LIGHTING CABLE, NO. 6 USE m 17,194.00018,913.40
0.0000.00
0.0000.00

0124                          A080.35 1.65600.000990.00
STREET LIGHTING CABLE, NO. 10 USE m 600.000990.00
0.0000.00
0.0000.00

0125                          A080.38 1.50300.000450.00
STREET LIGHTING CABLE, NO. 10 BARE m 300.000450.00
0.0000.00
0.0000.00

0126                          A600.00 420.0036.00015,120.00
REMOVE LIGHTING UNIT EACH36.00015,120.00
36.00015,120.00
0.0000.00

0127                          A630.20 300.0012.0003,600.00
REMOVE PULL BOX EACH12.0003,600.00
13.0003,900.00
0.0000.00

0128                          0030.81 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

GROUP 8B ELECTRICALContracted477,074.55
Current477,074.55
In place142,659.24
This Estimate19,209.89

GROUP 8C SIGNING
0129                          A007.15 600.0021.00012,600.00
VEHICLE DETECTOR, TYPE TD-5 EACH21.00012,600.00
0.0000.00
0.0000.00

0130                          0030.82 5,500.001.0005,500.00
MOBILIZATION LS 1.0005,500.00
0.5002,750.00
0.5002,750.00

0131                          7320.00 1,600.002.0003,200.00
INSTALL SIGN EACH2.0003,200.00
0.0000.00
0.0000.00

0132                          7322.01 300.0037.06011,118.00
TYPE B SIGN m2 37.06011,118.00
0.0000.00
0.0000.00

0133                          7340.00 4.501,819.4008,187.30
STRUCTURAL STEEL FOR SIGN SUPPORTS kg 1,819.4008,187.30
0.0000.00
0.0000.00

0134                          7360.24 575.0020.00011,500.00
600 mm SIGN SUPPORT FOOTING EACH20.00011,500.00
10.0005,750.00
10.0005,750.00

0135                          7390.10 600.004.0002,400.00
REMOVE SIGN, POST, AND FOOTING EACH4.0002,400.00
5.0003,000.00
0.0000.00

0136                          7500.42 310.002.000620.00
HANDICAPPED SYMBOL PREFORMED PAVEMENT MARKING, TYPE 4 EACH2.000620.00
0.0000.00
0.0000.00

0137                          7502.14 9.004,700.00042,300.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 4,700.00042,300.00
0.0000.00
0.0000.00

0138                          7503.14 9.003,500.00031,500.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 3,500.00031,500.00
0.0000.00
0.0000.00

0139                          7508.14 25.00750.00018,750.00
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 750.00018,750.00
0.0000.00
0.0000.00

GROUP 8C SIGNINGContracted147,675.30
Current147,675.30
In place11,500.00
This Estimate8,500.00

GROUP 10 GENERAL ITEMS
0140                          0001.08 0.50900.000450.00
BARRICADE, TYPE II BDAY900.000450.00
2,687.0001,343.50
504.000252.00

0141                          0001.10 3.001,314.0003,942.00
BARRICADE, TYPE III BDAY1,314.0003,942.00
3,913.00011,739.00
98.000294.00

0142                          0001.30 1.201,284.0001,540.80
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,284.0001,540.80
1,484.0001,780.80
70.00084.00

0143                          0001.75 9.00360.0003,240.00
TEMPORARY SIGN DAY EACH360.0003,240.00
14.000126.00
0.0000.00

0144                          0001.90 2.009,630.00019,260.00
SIGN DAY EACH9,630.00019,260.00
6,694.00013,388.00
252.000504.00

0145                          0002.97 90.0030.0002,700.00
FLASHING ARROW PANEL DAY 30.0002,700.00
10.000900.00
0.0000.00

0146                          0003.10 125.0020.0002,500.00
FLAGGING DAY 20.0002,500.00
0.0000.00
0.0000.00

0147                          0010.04 3,500.001.0003,500.00
FIELD OFFICE EACH1.0003,500.00
0.0000.00
0.0000.00

0148                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
0.5005,000.00
0.0000.00

0149                          9110.01 75.0010.000750.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000750.00
18.5001,387.50
0.0000.00

0150                          9110.03 50.0010.000500.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000500.00
27.7501,387.50
0.0000.00

0151                          9110.07 30.0010.000300.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000300.00
0.0000.00
0.0000.00

0152                          9110.09 90.0010.000900.00
RENTAL OF TRACTOR AND SCRAPER, FULLY OPERATED HOUR10.000900.00
45.5004,095.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted49,582.80
Current49,582.80
In place41,147.30
This Estimate1,134.00

Totals for contractContracted5,930,442.78
Current5,943,662.29
In place2,767,791.81
This Estimate93,207.80