Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0574 CONSTRUCTORS, INC.
Contract ID:6937
Estimate Number:0004
Pay Period End Date:05.30.2002
Contract Location:
ANSELMO - MERNAEstimate Type:PROG
Contractor:
CONSTRUCTORS, INC.Date Let:02.07.2002
1815 Y STREETDate Awarded:02.14.2002
PO BOX 80268Date Contract Executed:02.20.2002
Date Notice to Proceed:02.20.2002
LINCOLN NE 68501Date Work Began:03.25.2002
Phone:Date Physical Work Completed:
(402)434-1764Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
CUSTER
Project Number PCT Fed State Project Number Description
60937 000  0.000 EACNH-2-3(116)  GR CULV SEED GDRL ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$613,887.73$438,006.92$175,880.81
$3,986,213.77Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$613,887.73$438,006.92$175,880.81
$3,986,213.77Retainage$-6,138.88$-4,380.07$-1,758.81
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
15.40%Net Earnings$607,748.85$433,626.85$174,122.00
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$1,844.23$1,240.16$604.07
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$1,844.23$1,240.16$604.07
Payment$609,593.08$434,867.01$174,726.07
Project ManagerDiv. Head/Dist. Eng.
White, Dennis06.03.2002O'Donnell, Les06.05.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve06.06.2002
Controller Div. Processed
Burling, Laurie06.06.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L022.11 6.255,431.00033,943.75
FABRIC SILT FENCE-LOW POROSITY m 5,431.00033,943.75
4,783.00029,893.75
0.0000.00

0002                          0030.10 4,100.001.0004,100.00
MOBILIZATION LS 1.0004,100.00
1.0004,100.00
0.0000.00

0003                          1009.00 1,025.001.0001,025.00
GENERAL CLEARING AND GRUBBING LS 1.0001,025.00
0.500512.50
0.500512.50

0004                          1011.00 2.7011,690.00031,563.00
WATER kL 11,690.00031,563.00
27,923.05275,392.24
9,195.19724,827.03

0005                          1030.00 3.55111,349.000395,288.95
EARTHWORK MEASURED IN EMBANKMENT m3 111,349.000395,288.95
53,718.850190,701.92
17,662.85062,703.12

0006                          1101.00 8.20416.0003,411.20
REMOVE PAVEMENT m2 416.0003,411.20
0.0000.00
0.0000.00

0007                          1102.00 8.203,657.00029,987.40
REMOVE ASPHALT SURFACE m2 3,657.00029,987.40
3,341.59727,401.10
2,174.58617,831.61

0008                          1106.00 8.202,491.00020,426.20
REMOVE DRIVEWAY m2 2,491.00020,426.20
1,836.83515,062.05
503.6884,130.24

0009                          1108.00 20.50576.00011,808.00
REMOVE COMBINATION CURB AND GUTTER m 576.00011,808.00
0.0000.00
0.0000.00

0010                          1701.24 76.90237.10018,232.99
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 237.10018,232.99
215.00016,533.50
215.00016,533.50

0011                          1701.30 92.2510.500968.63
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 10.500968.63
12.0001,107.00
12.0001,107.00

0012                          1701.36 102.5048.0004,920.00
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 48.0004,920.00
14.0001,435.00
14.0001,435.00

0013                          1703.48 123.0016.0001,968.00
1200 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4 OR 5 m 16.0001,968.00
0.0000.00
0.0000.00

0014                          4040.00 410.001.000410.00
REMOVE HEADWALLS FROM CULVERTS EACH1.000410.00
1.000410.00
1.000410.00

GROUP 1 GRADINGContracted558,053.12
Current558,053.12
In place362,549.06
This Estimate129,490.00

GROUP 4 CULVERTS
0015                          P300.24 53.3049.6002,643.68
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 49.6002,643.68
44.6002,377.18
0.0000.00

0016                          P300.30 72.8023.3001,696.24
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 23.3001,696.24
20.0001,456.00
0.0000.00

0017                          P300.36 86.0014.2001,221.20
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 14.2001,221.20
12.0001,032.00
0.0000.00

0018                          P300.48 132.2573.8009,760.05
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 73.8009,760.05
62.5008,265.63
0.0000.00

0019                          P300.60 187.609.4001,763.44
1500 mm CULVERT PIPE, TYPE 3,4 OR 5 m 9.4001,763.44
7.0001,313.20
0.0000.00

0020                          P372.30 109.7014.5001,590.65
750 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2,4 OR 5 m 14.5001,590.65
21.0002,303.70
21.0002,303.70

0021                          P500.24 72.8069.9005,088.72
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 69.9005,088.72
108.5007,898.80
82.5006,006.00

0022                          P500.36 118.0047.0005,546.00
900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 47.0005,546.00
64.0007,552.00
46.0005,428.00

0023                          0030.40 6,420.001.0006,420.00
MOBILIZATION LS 1.0006,420.00
1.0006,420.00
0.0000.00

0024                          1119.00 153.801.000153.80
REMOVE INLET EACH1.000153.80
1.000153.80
1.000153.80

0025                          4035.00 51.2547.0002,408.75
REMOVE FLARED-END SECTION EACH47.0002,408.75
50.0002,562.50
10.000512.50

0026                          4040.00 143.506.000861.00
REMOVE HEADWALLS FROM CULVERTS EACH6.000861.00
6.000861.00
2.000287.00

0027                          4043.00 15.40131.3002,022.02
REMOVE CULVERT PIPE m 131.3002,022.02
148.4002,285.36
98.9001,523.06

0028                          4044.00 1,025.001.0001,025.00
PREPARATION OF STRUCTURE EACH1.0001,025.00
AT STA. 33+79.30 1.0001,025.00
0.0000.00

0029                          4044.01 1,025.001.0001,025.00
PREPARATION OF STRUCTURE EACH1.0001,025.00
AT STA. 50+22.30 1.0001,025.00
0.0000.00

0030                          4044.02 717.701.000717.70
PREPARATION OF STRUCTURE EACH1.000717.70
AT STA. 75+23 1.000717.70
0.0000.00

0031                          4044.03 666.001.000666.00
PREPARATION OF STRUCTURE EACH1.000666.00
AT STA. 89+71.20 1.000666.00
0.0000.00

0032                          4044.04 666.001.000666.00
PREPARATION OF STRUCTURE EACH1.000666.00
AT STA. 102+33.60 1.000666.00
0.0000.00

0033                          4044.05 666.001.000666.00
PREPARATION OF STRUCTURE EACH1.000666.00
AT STA. 120+72.30 1.000666.00
0.0000.00

0034                          4044.06 615.001.000615.00
PREPARATION OF STRUCTURE EACH1.000615.00
AT STA. 129+66.90 1.000615.00
0.0000.00

0035                          4050.01 8.20563.0004,616.60
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 563.0004,616.60
600.0004,920.00
354.0002,902.80

0036                          4051.01 9.20121.0001,113.20
EXCAVATION FOR BOX CULVERTS m3 121.0001,113.20
121.0001,113.20
0.0000.00

0037                          4101.06 358.8090.27532,390.67
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 90.27532,390.67
93.16133,426.16
0.0000.00

0038                          4151.00 1.555,002.0007,753.10
REINFORCING STEEL FOR BOX CULVERT kg 5,002.0007,753.10
5,256.0808,146.92
0.0000.00

0039                          4310.24 175.0026.0004,550.00
600 mm FLARED-END SECTION EACH26.0004,550.00
28.0004,900.00
8.0001,400.00

0040                          4310.30 251.006.0001,506.00
750 mm FLARED-END SECTION EACH6.0001,506.00
6.0001,506.00
0.0000.00

0041                          4310.36 333.0010.0003,330.00
900 mm FLARED-END SECTION EACH10.0003,330.00
12.0003,996.00
6.0001,998.00

0042                          4310.48 718.0010.0007,180.00
1200 mm FLARED-END SECTION EACH10.0007,180.00
10.0007,180.00
0.0000.00

0043                          4310.60 1,130.002.0002,260.00
1500 mm FLARED-END SECTION EACH2.0002,260.00
2.0002,260.00
0.0000.00

0044                          4320.30 287.002.000574.00
750 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.000574.00
2.000574.00
2.000574.00

GROUP 4 CULVERTSContracted111,829.82
Current111,829.82
In place117,884.15
This Estimate23,088.86

GROUP 4A CULVERT AT STA. 83+97.40
0045                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0046                          4044.07 1,850.001.0001,850.00
PREPARATION OF STRUCTURE EACH1.0001,850.00
AT STA. 83+97.40 1.0001,850.00
0.0000.00

0047                          4051.01 9.2541.000379.25
EXCAVATION FOR BOX CULVERTS m3 41.000379.25
41.000379.25
0.0000.00

0048                          4101.06 340.0046.00015,640.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 46.00015,640.00
47.08816,009.92
0.0000.00

0049                          4151.00 1.552,683.0004,158.65
REINFORCING STEEL FOR BOX CULVERT kg 2,683.0004,158.65
2,792.1184,327.78
0.0000.00

GROUP 4A CULVERT AT STA. 83+97.40Contracted24,027.90
Current24,027.90
In place24,566.95
This Estimate0.00

GROUP 4B CULVERT AT STA. 145+54.00
0050                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0051                          4044.07 2,565.001.0002,565.00
PREPARATION OF STRUCTURE EACH1.0002,565.00
AT STA. 145+54.00 1.0002,565.00
0.0000.00

0052                          4051.01 9.2567.000619.75
EXCAVATION FOR BOX CULVERTS m3 67.000619.75
67.000619.75
0.0000.00

0053                          4101.06 340.0053.20018,088.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 53.20018,088.00
52.32017,788.80
0.0000.00

0054                          4151.00 1.553,053.0004,732.15
REINFORCING STEEL FOR BOX CULVERT kg 3,053.0004,732.15
2,990.6284,635.47
0.0000.00

GROUP 4B CULVERT AT STA. 145+54.00Contracted28,004.90
Current28,004.90
In place27,609.02
This Estimate0.00

GROUP 4C CULVERT AT STA. 171+56.40
0055                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0056                          4044.07 2,100.001.0002,100.00
PREPARATION OF STRUCTURE EACH1.0002,100.00
AT STA. 171+56.40 1.0002,100.00
0.0000.00

0057                          4051.01 9.2560.000555.00
EXCAVATION FOR BOX CULVERTS m3 60.000555.00
60.000555.00
0.0000.00

0058                          4101.06 340.0053.00018,020.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 53.00018,020.00
52.79317,949.62
0.0000.00

0059                          4151.00 1.553,442.0005,335.10
REINFORCING STEEL FOR BOX CULVERT kg 3,442.0005,335.10
3,477.1095,389.52
0.0000.00

GROUP 4C CULVERT AT STA. 171+56.40Contracted28,010.10
Current28,010.10
In place27,994.14
This Estimate0.00

GROUP 5 SEEDING
0060                          L001.01 1,230.0014.60017,958.00
SEEDING, TYPE A ha 14.60017,958.00
0.0000.00
0.0000.00

0061                          L001.02 975.0014.00013,650.00
SEEDING, TYPE B ha 14.00013,650.00
0.0000.00
0.0000.00

0062                          L032.75 72.00143.00010,296.00
MULCH Mg 143.00010,296.00
0.0000.00
0.0000.00

0063                          0030.50 1,100.001.0001,100.00
MOBILIZATION LS 1.0001,100.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted43,004.00
Current43,004.00
In place0.00
This Estimate0.00

GROUP 7 GUARDRAIL
0064                          0030.70 500.001.000500.00
MOBILIZATION LS 1.000500.00
0.0000.00
0.0000.00

0065                          7015.00 20.50700.00014,350.00
CABLE GUARDRAIL m 700.00014,350.00
0.0000.00
0.0000.00

0066                          7023.00 1,250.002.0002,500.00
TERMINAL ANCHORAGE SECTIONS EACH2.0002,500.00
0.0000.00
0.0000.00

0067                          7024.00 2,500.001.0002,500.00
INTERMEDIATE ANCHORAGE SECTIONS EACH1.0002,500.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted19,850.00
Current19,850.00
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0068                          A001.12 410.001.000410.00
PULL BOX, TYPE PB-5 EACH1.000410.00
0.0000.00
0.0000.00

0069                          A009.14 1,850.002.0003,700.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH2.0003,700.00
0.0000.00
0.0000.00

0070                          A020.10 1,400.001.0001,400.00
LIGHTING CONTROL CENTER, TYPE D EACH1.0001,400.00
0.0000.00
0.0000.00

0071                          A070.10 7.7096.000739.20
38 mm CONDUIT IN TRENCH m 96.000739.20
0.0000.00
0.0000.00

0072                          A072.10 10.2525.000256.25
38 mm CONDUIT UNDER ROADWAY m 25.000256.25
0.0000.00
0.0000.00

0073                          A080.22 1.85121.000223.85
STREET LIGHTING CABLE, NO. 6 BARE m 121.000223.85
0.0000.00
0.0000.00

0074                          A080.24 2.05242.000496.10
STREET LIGHTING CABLE, NO. 6 USE m 242.000496.10
0.0000.00
0.0000.00

0075                          0030.81 2,100.001.0002,100.00
MOBILIZATION LS 1.0002,100.00
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted9,325.40
Current9,325.40
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0076                          0002.55 21.50592.68012,742.62
OVERLAY BROKEN LINES StaM592.68012,742.62
0.0000.00
0.0000.00

0077                          0002.60 21.501,185.36025,485.24
OVERLAY SOLID LINES StaM1,185.36025,485.24
0.0000.00
0.0000.00

0078                          0030.90 117,500.001.000117,500.00
MOBILIZATION LS 1.000117,500.00
0.0000.00
0.0000.00

0079                          1020.02 8.2074.000606.80
DELINEATOR, TYPE II EACH74.000606.80
0.0000.00
0.0000.00

0080                          1020.03 8.2023.000188.60
DELINEATOR, TYPE III EACH23.000188.60
0.0000.00
0.0000.00

0081                          1020.20 25.608.000204.80
INSTALL CHEVRONS EACH8.000204.80
0.0000.00
0.0000.00

0082                          2001.00 18.40230.0004,232.00
GRAVEL SURFACE COURSE m3 230.0004,232.00
54.000993.60
54.000993.60

0083                          2021.00 51.253.000153.75
MAILBOX POST EACH3.000153.75
0.0000.00
0.0000.00

0084                          3012.04 76.35128.0009,772.80
CONCRETE 47B-25 MEDIAN CURB m 128.0009,772.80
0.0000.00
0.0000.00

0085                          3013.15 77.3563.8004,934.93
CONCRETE CLASS 47B-25 BARRIER CURB m 63.8004,934.93
0.0000.00
0.0000.00

0086                          3014.11 70.65494.00034,901.10
COMBINATION CONCRETE CLASS 47B-25 CURB AND GUTTER m 494.00034,901.10
0.0000.00
0.0000.00

0087                          3017.39 40.00265.00010,600.00
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 265.00010,600.00
0.0000.00
0.0000.00

0088                          3019.24 666.451.000666.45
CONCRETE CLASS 47B-25 ISLAND NOSE EACH1.000666.45
0.0000.00
0.0000.00

0089                          3020.24 37.65226.0008,508.90
CONCRETE CLASS 47B-25 DRIVEWAY m2 226.0008,508.90
0.0000.00
0.0000.00

0090                          3075.32 40.65503.00020,446.95
205 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 503.00020,446.95
0.0000.00
0.0000.00

0091                          4003.00 1.55265.000410.75
CAST IRON COVER, FRAME, AND FLANGE kg 265.000410.75
0.0000.00
0.0000.00

0092                          4015.00 310.002.000620.00
ADJUST MANHOLE TO GRADE EACH2.000620.00
0.0000.00
0.0000.00

0093                          7502.04 6.40800.0005,120.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4 m 800.0005,120.00
0.0000.00
0.0000.00

0094                          7503.04 6.401,100.0007,040.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4 m 1,100.0007,040.00
0.0000.00
0.0000.00

0095                          7508.04 19.2575.0001,443.75
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4 m 75.0001,443.75
0.0000.00
0.0000.00

0096                          7509.04 19.25650.00012,512.50
300 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4 m 650.00012,512.50
0.0000.00
0.0000.00

0097                          7512.04 38.4542.0001,614.90
600 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4 m 42.0001,614.90
0.0000.00
0.0000.00

0098                          8111.00 306.20366.816112,319.06
SHOULDER SUBGRADE PREPARATION StaM366.816112,319.06
0.0000.00
0.0000.00

0099                          9000.73 11.85500.0005,925.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.0005,925.00
SPS 0.0000.00
0.0000.00

0100                          9005.00 46.00250.00011,500.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 250.00011,500.00
SP4 0.0000.00
0.0000.00

0101                          9005.23 13.4036,350.000487,090.00
ASPHALTIC CONCRETE, TYPE SPS Mg 36,350.000487,090.00
0.0000.00
0.0000.00

0102                          9005.45 22.6050,910.0001,150,566.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 50,910.0001,150,566.00
0.0000.00
0.0000.00

0103                          9009.00 2.8511,096.00031,623.60
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 11,096.00031,623.60
0.0000.00
0.0000.00

0104                          9020.92 158.0027.0004,266.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 27.0004,266.00
0.0000.00
0.0000.00

0105                          9021.01 158.002,762.640436,497.12
PERFORMANCE GRADED BINDER (64-22) Mg 2,762.640436,497.12
0.0000.00
0.0000.00

0106                          9021.03 158.001,962.900310,138.20
PERFORMANCE GRADED BINDER (58-28) Mg 1,962.900310,138.20
0.0000.00
0.0000.00

0107                          9034.00 1.1511,096.00012,760.40
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 11,096.00012,760.40
0.0000.00
0.0000.00

0108                          9053.00 0.19166,050.00031,549.50
TACK COAT L 166,050.00031,549.50
0.0000.00
0.0000.00

0109                          9111.00 2.452,300.0005,635.00
WATER kL 2,300.0005,635.00
0.0000.00
0.0000.00

0110                          9140.00 164.006.2731,028.77
JOINT SEALING - ASPHALT TO CONCRETE StaM6.2731,028.77
0.0000.00
0.0000.00

0111                          9170.00 154.0028.2984,357.89
EARTH SHOULDER CONSTRUCTION StaM28.2984,357.89
0.0000.00
0.0000.00

0112                          9173.20 3.651,004.0003,664.60
SUBGRADE PREPARATION m2 1,004.0003,664.60
0.0000.00
0.0000.00

0113                          9179.23 457.20212.31797,071.33
COLD MILLING, CLASS 3 StaM212.31797,071.33
0.0000.00
0.0000.00

0114                          9188.50 14.701,260.00018,522.00
SURFACING UNDER GUARDRAIL m2 1,260.00018,522.00
0.0000.00
0.0000.00

0115                          9300.50 5,000.001.0005,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0005,000.00
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted3,009,221.32
Current3,009,221.32
In place993.60
This Estimate993.60

GROUP 10 GENERAL ITEMS
0116                          0001.08 0.5022,000.00011,000.00
BARRICADE, TYPE II BDAY22,000.00011,000.00
96.00048.00
96.00048.00

0117                          0001.10 2.051,952.0004,001.60
BARRICADE, TYPE III BDAY1,952.0004,001.60
1,249.0002,560.45
283.000580.15

0118                          0001.30 2.30976.0002,244.80
TYPE B HIGH INTENSITY WARNING LIGHT LDAY976.0002,244.80
240.000552.00
60.000138.00

0119                          0001.75 5.102,295.00011,704.50
TEMPORARY SIGN DAY EACH2,295.00011,704.50
486.0002,478.60
162.000826.20

0120                          0001.90 0.2230,256.0006,656.32
SIGN DAY EACH30,256.0006,656.32
3,608.000793.76
900.000198.00

0121                          0003.10 180.00200.00036,000.00
FLAGGING DAY 200.00036,000.00
76.50013,770.00
13.5002,430.00

0122                          0003.20 235.0050.00011,750.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 50.00011,750.00
0.0000.00
0.0000.00

0123                          0010.04 3,750.001.0003,750.00
FIELD OFFICE EACH1.0003,750.00
1.0003,750.00
0.0000.00

0124                          0030.10 1,500.001.0001,500.00
MOBILIZATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0125                          1017.00 35,000.001.00035,000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00035,000.00
0.75026,250.00
0.50017,500.00

0126                          9110.01 54.00200.00010,800.00
RENTAL OF LOADER, FULLY OPERATED HOUR200.00010,800.00
3.000162.00
3.000162.00

0127                          9110.02 68.0060.0004,080.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR60.0004,080.00
3.500238.00
3.500238.00

0128                          9110.03 47.00200.0009,400.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR200.0009,400.00
4.000188.00
4.000188.00

0129                          9110.07 35.00200.0007,000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR200.0007,000.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted154,887.22
Current154,887.22
In place52,290.81
This Estimate22,308.35

Totals for contractContracted3,986,213.77
Current3,986,213.77
In place613,887.73
This Estimate175,880.81