Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2252 PAULSEN, INC.
Contract ID:6893
Estimate Number:0015
Pay Period End Date:08.30.2003
Contract Location:
BRULE - OGALLALAEstimate Type:PROG
Contractor:
PAULSEN, INC.Date Let:11.14.2002
1116 EAST HWY 30Date Awarded:11.21.2002
P O BOX 17Date Contract Executed:11.27.2002
Date Notice to Proceed:11.27.2002
COZAD NE 69130Date Work Began:02.03.2003
Phone:Date Physical Work Completed:
(308)784-3333Date Accepted:08.05.2003
Escrow Agent:
Surety Co:
ST. PAUL FIRE AND MARINE INSURANCE COMPANY
Counties
KEITH
Project Number PCT Fed State Project Number Description
60893 000  0.000 EACSTPD-30-2(132)  GR CULV SEED GDRL ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,929,792.71$1,928,788.85$1,003.86
$2,016,236.66Stockpiled Materials$-.01$-.01$.00
Original Contract AmtGross Earnings$1,929,792.70$1,928,788.84$1,003.86
$2,017,141.00Retainage$-19,297.93$-19,287.89$-10.04
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
95.71%Net Earnings$1,910,494.77$1,909,500.95$993.82
Liquidated Damages$.00$.00$.00
Incentives$5,500.00$5,500.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$53.34$53.34$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$5,553.34$5,553.34$.00
Payment$1,916,048.11$1,915,054.29$993.82
Project ManagerDiv. Head/Dist. Eng.
Sawyer, Harlan09.02.2003Thayer, Gary09.02.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.02.2003
Controller Div. Processed
Burling, Laurie09.03.2003
Detailed breakdown of stockpiled materials
Est Nbr:0002
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01169000.75 ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE
S.P. Initial Payment1,180.50Varies
Asphalt Rock
01179005.00 ASPHALTIC CONCRETE FOR PATCHING, TYPE
S.P. Initial Payment236.10Varies
Asphalt Rock
01189005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Initial Payment60,394.38Varies
Asphalt Rock
Total for estimate 0002:61,810.98
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01189005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Adjustment-365.18Varies
Asphalt Rock
Total for estimate 0007:-365.18
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01189005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Adjustment-6,910.67Varies
Asphalt Rock
Total for estimate 0008:-6,910.67
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01179005.00 ASPHALTIC CONCRETE FOR PATCHING, TYPE
S.P. Adjustment-33.43Varies
Asphalt Rock
01189005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Adjustment-44,693.31Varies
Asphalt Rock
Total for estimate 0009:-44,726.74
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01169000.75 ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE
S.P. Closure-1,180.50Varies
Asphalt Rock
01179005.00 ASPHALTIC CONCRETE FOR PATCHING, TYPE
S.P. Closure-202.67Varies
Asphalt Rock
01189005.45 ASPHALTIC CONCRETE, TYPE SP4(12.5)
S.P. Adjustment-8,425.23Varies
Asphalt Rock
Total for estimate 0010:-9,808.40
Total remaining for contract:-0.01
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 6,250.001.0006,250.00
MOBILIZATION LS 1.0006,250.00
1.0006,250.00
0.0000.00

0002                          1009.00 5,000.001.0005,000.00
GENERAL CLEARING AND GRUBBING LS 1.0005,000.00
1.0005,000.00
0.0000.00

0003                          1011.00 2.60805.0002,093.00
WATER kL 805.0002,093.00
0.0000.00
0.0000.00

0004                          1012.00 74.50179.00013,335.50
RIGHT-OF-WAY MARKERS EACH268.00019,966.00
268.00019,966.00
0.0000.00

0005                          1030.00 7.057,160.00050,478.00
EARTHWORK MEASURED IN EMBANKMENT m3 7,160.00050,478.00
7,160.00050,478.02
0.0000.00

0006                          1102.00 4.75238.0001,130.50
REMOVE ASPHALT SURFACE m2 238.0001,130.50
484.6442,302.06
0.0000.00

0007                          1109.00 8.6031.550271.33
REMOVE CURB m 31.550271.33
32.470279.24
0.0000.00

0008                          4300.18 69.0011.600800.40
450 mm CULVERT PIPE m 11.600800.40
38.4002,649.60
0.0000.00

0009                          7017.00 7.35274.2602,015.81
REMOVE GUARDRAIL m 274.2602,015.81
274.3202,016.26
0.0000.00

0010                          L020.00 1.85502.000928.70
EROSION CONTROL m2 502.000928.70
1,293.3892,392.77
0.0000.00

0011                          L020.10 2.204,710.00010,362.00
EROSION CONTROL, TYPE HV m2 4,710.00010,362.00
1,241.8322,732.03
0.0000.00

0012                          L021.06 19.55234.0004,574.70
EROSION CHECKS, TYPE HV BALE30.000586.50
30.000586.50
0.0000.00

0013                          L022.12 9.503,575.20033,964.40
FABRIC SILT FENCE-HIGH POROSITY m 18.000171.00
18.000171.00
0.0000.00

0014                          L022.25 17.0050.000850.00
FABRIC SILT FENCE, TYPE COIR FIBER m 50.000850.00
38.250650.25
0.0000.00

4007                          0095.00 150.000.0000.00
ADDITIONAL FREIGHT LS 1.000150.00
450 mm Culvert Pipe 1.000150.00
0.0000.00

4013                          1905.00 1,003.860.0000.00
MATERIAL DELIVERED NOT INCORPORATED LS 1.0001,003.86
Straw Bales For Erosion Checks, Type HV 1.0001,003.86
1.0001,003.86

GROUP 1 GRADINGContracted132,054.34
Current102,057.10
In place96,627.59
This Estimate1,003.86

GROUP 4 CULVERTS
0015                          0030.40 12,000.001.00012,000.00
MOBILIZATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0016                          4039.20 70.0017.7101,239.70
REMOVE AND RELAY CULVERT PIPE m 17.7101,239.70
17.6701,236.90
0.0000.00

0017                          4040.00 155.0010.0001,550.00
REMOVE HEADWALLS FROM CULVERTS EACH10.0001,550.00
10.0001,550.00
0.0000.00

0018                          4041.00 890.001.000890.00
CULVERT CLEANOUT EACH1.000890.00
AT STA. 157+58.73 1.000890.00
0.0000.00

0019                          4044.00 1,700.001.0001,700.00
PREPARATION OF STRUCTURE EACH1.0001,700.00
AT STA. 110+30.42 1.0001,700.00
0.0000.00

0020                          4044.01 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 136+86.46 1.0002,000.00
0.0000.00

0021                          4044.02 2,100.001.0002,100.00
PREPARATION OF STRUCTURE EACH1.0002,100.00
AT STA. 141+19.6 1.0002,100.00
0.0000.00

0022                          4044.03 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 179+77.67 1.0002,500.00
0.0000.00

0023                          4044.04 1,400.001.0001,400.00
PREPARATION OF STRUCTURE EACH1.0001,400.00
AT STA. 235+00.72 1.0001,400.00
0.0000.00

0024                          4044.05 2,100.001.0002,100.00
PREPARATION OF STRUCTURE EACH1.0002,100.00
AT STA. 258+24.29 1.0002,100.00
0.0000.00

0025                          4050.01 10.0067.000670.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 67.000670.00
98.000980.00
0.0000.00

0026                          4051.01 13.00366.0004,758.00
EXCAVATION FOR BOX CULVERTS m3 366.0004,758.00
390.6005,077.80
0.0000.00

0027                          4100.06 850.002.8802,448.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 2.8802,448.00
2.8802,448.00
0.0000.00

0028                          4101.06 375.00228.97085,863.75
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 226.15984,809.63
228.36085,635.00
0.0000.00

0029                          4107.07 750.002.3601,770.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 2.3601,770.00
2.3601,770.00
0.0000.00

0030                          4150.00 1.80230.000414.00
REINFORCING STEEL FOR HEADWALL kg 230.000414.00
230.000414.00
0.0000.00

0031                          4151.00 1.5014,479.00021,718.50
REINFORCING STEEL FOR BOX CULVERT kg 14,329.00021,493.50
14,498.00021,747.00
0.0000.00

0032                          4157.00 1.8096.000172.80
REINFORCING STEEL FOR COLLARS kg 96.000172.80
96.000172.80
0.0000.00

0033                          4350.30 100.004.600460.00
750 mm CORRUGATED METAL PIPE m 4.600460.00
5.200520.00
0.0000.00

0034                          4350.36 150.002.200330.00
900 mm CORRUGATED METAL PIPE m 2.200330.00
8.6001,290.00
0.0000.00

0035                          4360.30 370.002.000740.00
750 mm METAL FLARED-END SECTION EACH2.000740.00
2.000740.00
0.0000.00

0036                          4360.36 490.004.0001,960.00
900 mm METAL FLARED-END SECTION EACH4.0001,960.00
4.0001,960.00
0.0000.00

0037                          4450.36 200.0012.4002,480.00
900 mm REINFORCED CONCRETE PIPE m 12.4002,480.00
13.2002,640.00
0.0000.00

4003                          4051.12 37.500.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 21.600810.00
Group 4 21.600810.00
0.0000.00

4005                          4350.24 132.000.0000.00
600 mm CORRUGATED METAL PIPE m 5.200686.40
5.200686.40
0.0000.00

4006                          4360.24 380.000.0000.00
600 mm METAL FLARED-END SECTION EACH2.000760.00
2.000760.00
0.0000.00

GROUP 4 CULVERTSContracted151,264.75
Current152,242.03
In place155,127.90
This Estimate0.00

GROUP 4A CULVERT AT STA. 107+60.06
0038                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0039                          4044.06 3,000.001.0003,000.00
PREPARATION OF STRUCTURE EACH1.0003,000.00
AT STA. 107+60.06 1.0003,000.00
0.0000.00

0040                          4051.01 15.0043.000645.00
EXCAVATION FOR BOX CULVERTS m3 43.000645.00
63.450951.75
0.0000.00

0041                          4101.06 378.0054.69020,672.82
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 54.69020,672.82
55.21020,869.38
0.0000.00

0042                          4151.00 1.203,840.0004,608.00
REINFORCING STEEL FOR BOX CULVERT kg 3,840.0004,608.00
3,880.0004,656.00
0.0000.00

4004                          4051.12 37.800.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 20.450773.01
Group 4A Culvert At Station 107+60.06 20.450773.01
0.0000.00

GROUP 4A CULVERT AT STA. 107+60.06Contracted31,925.82
Current32,698.83
In place33,250.14
This Estimate0.00

GROUP 4B CULVERT AT STA. 112+48.03
0043                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0044                          4044.07 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 112+48.03 1.0003,200.00
0.0000.00

0045                          4051.01 15.0051.000765.00
EXCAVATION FOR BOX CULVERTS m3 51.000765.00
51.000765.00
0.0000.00

0046                          4101.06 378.0056.21021,247.38
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 56.21021,247.38
57.16021,606.48
0.0000.00

0047                          4151.00 1.203,720.0004,464.00
REINFORCING STEEL FOR BOX CULVERT kg 3,720.0004,464.00
3,785.0004,542.00
0.0000.00

GROUP 4B CULVERT AT STA. 112+48.03Contracted32,676.38
Current32,676.38
In place33,113.48
This Estimate0.00

GROUP 4C CULVERT AT STA. 122+38.66
0048                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0049                          4044.08 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 122+38.66 1.0003,200.00
0.0000.00

0050                          4051.01 15.00109.0001,635.00
EXCAVATION FOR BOX CULVERTS m3 109.0001,635.00
109.0001,635.00
0.0000.00

0051                          4101.06 378.0074.29028,081.62
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 74.29028,081.62
73.56027,805.68
0.0000.00

0052                          4151.00 1.205,626.0006,751.20
REINFORCING STEEL FOR BOX CULVERT kg 5,626.0006,751.20
5,566.0006,679.20
0.0000.00

GROUP 4C CULVERT AT STA. 122+38.66Contracted42,667.82
Current42,667.82
In place42,319.88
This Estimate0.00

GROUP 4D CULVERT AT STA. 133+01.25
0053                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0054                          4044.09 3,000.001.0003,000.00
PREPARATION OF STRUCTURE EACH1.0003,000.00
AT STA. 133+01.25 1.0003,000.00
0.0000.00

0055                          4051.01 15.0058.000870.00
EXCAVATION FOR BOX CULVERTS m3 58.000870.00
58.000870.00
0.0000.00

0056                          4101.06 378.0062.66023,685.48
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 62.66023,685.48
62.66023,685.48
0.0000.00

0057                          4151.00 1.204,466.0005,359.20
REINFORCING STEEL FOR BOX CULVERT kg 4,466.0005,359.20
4,466.0005,359.20
0.0000.00

GROUP 4D CULVERT AT STA. 133+01.25Contracted35,914.68
Current35,914.68
In place35,914.68
This Estimate0.00

GROUP 4E CULVERT AT STA. 154+37.53
0058                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0059                          4044.10 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 154+37.53 1.0003,200.00
0.0000.00

0060                          4051.01 15.00147.0002,205.00
EXCAVATION FOR BOX CULVERTS m3 147.0002,205.00
147.0002,205.00
0.0000.00

0061                          4101.06 378.0071.73027,113.94
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 71.73027,113.94
72.38027,359.64
0.0000.00

0062                          4151.00 1.204,698.0005,637.60
REINFORCING STEEL FOR BOX CULVERT kg 4,698.0005,637.60
4,745.0005,694.00
0.0000.00

GROUP 4E CULVERT AT STA. 154+37.53Contracted41,156.54
Current41,156.54
In place41,458.64
This Estimate0.00

GROUP 4F CULVERT AT STA. 170+38.59
0063                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0064                          4044.11 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 170+38.59 1.0003,200.00
0.0000.00

0065                          4051.01 15.0077.0001,155.00
EXCAVATION FOR BOX CULVERTS m3 77.0001,155.00
77.0001,155.00
0.0000.00

0066                          4101.06 378.0061.36023,194.08
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 61.36023,194.08
62.55023,643.90
0.0000.00

0067                          4151.00 1.204,307.0005,168.40
REINFORCING STEEL FOR BOX CULVERT kg 4,307.0005,168.40
4,395.0005,274.00
0.0000.00

GROUP 4F CULVERT AT STA. 170+38.59Contracted35,717.48
Current35,717.48
In place36,272.90
This Estimate0.00

GROUP 4G CULVERT AT STA. 184+95.78
0068                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0069                          4044.12 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 184+95.78 1.0003,200.00
0.0000.00

0070                          4051.01 15.0050.000750.00
EXCAVATION FOR BOX CULVERTS m3 50.000750.00
50.000750.00
0.0000.00

0071                          4101.06 378.0039.08014,772.24
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 39.08014,772.24
40.90015,460.20
0.0000.00

0072                          4151.00 1.202,285.0002,742.00
REINFORCING STEEL FOR BOX CULVERT kg 2,285.0002,742.00
2,406.0002,887.20
0.0000.00

GROUP 4G CULVERT AT STA. 184+95.78Contracted24,464.24
Current24,464.24
In place25,297.40
This Estimate0.00

GROUP 4H CULVERT AT STA. 201+21.11
0073                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0074                          4044.13 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 201+21.11 1.0003,200.00
0.0000.00

0075                          4051.01 15.00137.0002,055.00
EXCAVATION FOR BOX CULVERTS m3 137.0002,055.00
137.0002,055.00
0.0000.00

0076                          4101.06 378.0072.39027,363.42
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 72.39027,363.42
72.38027,359.64
0.0000.00

0077                          4151.00 1.204,745.0005,694.00
REINFORCING STEEL FOR BOX CULVERT kg 4,745.0005,694.00
4,745.0005,694.00
0.0000.00

GROUP 4H CULVERT AT STA. 201+21.11Contracted41,312.42
Current41,312.42
In place41,308.64
This Estimate0.00

GROUP 4I CULVERT AT STA. 251+38.52
0078                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0079                          4044.14 3,200.001.0003,200.00
PREPARATION OF STRUCTURE EACH1.0003,200.00
AT STA. 251+38.52 1.0003,200.00
0.0000.00

0080                          4051.01 15.00140.0002,100.00
EXCAVATION FOR BOX CULVERTS m3 140.0002,100.00
140.0002,100.00
0.0000.00

0081                          4101.06 378.0078.61029,714.58
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 78.61029,714.58
81.47030,795.66
0.0000.00

0082                          4151.00 1.204,822.0005,786.40
REINFORCING STEEL FOR BOX CULVERT kg 4,822.0005,786.40
5,019.0006,022.80
0.0000.00

GROUP 4I CULVERT AT STA. 251+38.52Contracted43,800.98
Current43,800.98
In place45,118.46
This Estimate0.00

GROUP 4J CULVERT AT STA. 1100+16
0083                          0030.40 7,800.001.0007,800.00
MOBILIZATION LS 1.0007,800.00
1.0007,800.00
0.0000.00

0084                          4049.00 980.0087.84086,083.20
PRECAST REINFORCED CONCRETE BOX CULVERT m 87.84086,083.20
2.4 M X 1.2 M 87.84086,083.20
0.0000.00

0085                          4051.01 14.00315.0004,410.00
EXCAVATION FOR BOX CULVERTS m3 315.0004,410.00
510.0507,140.70
0.0000.00

0086                          4101.09 470.0023.04010,828.80
CLASS 47B-HE-20 OR AX-HE-20 CONCRETE FOR BOX CULVERT m3 23.04010,828.80
23.04010,828.80
0.0000.00

0087                          4151.00 1.701,130.0001,921.00
REINFORCING STEEL FOR BOX CULVERT kg 1,130.0001,921.00
1,130.0001,921.00
0.0000.00

0088                          6040.00 5,000.001.0005,000.00
REMOVE STRUCTURE EACH1.0005,000.00
AT STA. 1100+16 1.0005,000.00
0.0000.00

4002                          4051.12 47.000.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 195.0509,167.35
Group 4J Culvert at Station 1100+16 195.0509,167.35
0.0000.00

GROUP 4J CULVERT AT STA. 1100+16Contracted116,043.00
Current125,210.35
In place127,941.05
This Estimate0.00

GROUP 5 SEEDING
0089                          0030.50 1,200.001.0001,200.00
MOBILIZATION LS 1.0001,200.00
1.0001,200.00
0.0000.00

0090                          L001.02 1,040.0012.30012,792.00
SEEDING, TYPE B ha 18.25018,980.00
18.25018,980.00
0.0000.00

0091                          L020.02 1.322,392.0003,157.44
EROSION CONTROL, TYPE B m2 2,392.0003,157.44
2,294.8283,029.17
0.0000.00

0092                          L032.75 75.0062.0004,650.00
MULCH Mg 90.1006,757.50
90.1006,757.50
0.0000.00

GROUP 5 SEEDINGContracted21,799.44
Current30,094.94
In place29,966.67
This Estimate0.00

GROUP 7 GUARDRAIL
0093                          0030.70 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0094                          6010.26 2,000.003.2006,400.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 0.0000.00
0.0000.00
0.0000.00

0095                          6020.00 10.00608.7006,087.00
REINFORCING STEEL FOR BRIDGE kg 0.0000.00
0.0000.00
0.0000.00

0096                          6086.00 50.0021.5001,075.00
STRUCTURAL STEEL kg 0.0000.00
0.0000.00
0.0000.00

0097                          7011.20 42.0057.1602,400.72
W-BEAM GUARDRAIL m 57.1602,400.72
57.1602,400.72
0.0000.00

0098                          7020.00 3,000.004.00012,000.00
BRIDGE APPROACH SECTIONS EACH0.0000.00
0.0000.00
0.0000.00

0099                          7024.27 1,650.004.0006,600.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0006,600.00
4.0006,600.00
0.0000.00

4009                          7020.30 3,150.000.0000.00
BRIDGE APPROACH SECTION (MODIFIED) EACH4.00012,600.00
4.00012,600.00
0.0000.00

4010                          6960.02 4,000.000.0000.00
ADDITIONAL WORK LS 1.0004,000.00
(W-Beam Backup Plate) 1.0004,000.00
0.0000.00

4011                          6960.02 262.500.0000.00
ADDITIONAL WORK LS 1.000262.50
(Replace Guardrail Bolts) 1.000262.50
0.0000.00

GROUP 7 GUARDRAILContracted36,562.72
Current27,863.22
In place27,863.22
This Estimate0.00

GROUP 8B ELECTRICAL
0100                          0030.81 400.001.000400.00
MOBILIZATION LS 1.000400.00
1.000400.00
0.0000.00

0101                          A077.88 3.0020.00060.00
3/C #14 AWG TRAFFIC SIGNAL CABLE, AERIAL m 20.00060.00
0.0000.00
0.0000.00

0102                          A079.70 3.0015.00045.00
SERVICE CABLE, NO. 6, AERIAL m 15.00045.00
0.0000.00
0.0000.00

0103                          A080.27 3.0039.000117.00
STREET LIGHT CABLE, NO. 6 AERIAL m 39.000117.00
45.060135.18
0.0000.00

0104                          A500.00 200.001.000200.00
INSTALL TRAFFIC SIGNAL CONTROLLER EACH1.000200.00
TYPE FLASHER 1.000200.00
0.0000.00

0105                          A501.40 200.001.000200.00
INSTALL TRAFFIC SIGNAL, TYPE TS-4 EACH1.000200.00
1.000200.00
0.0000.00

0106                          A505.85 1,600.002.0003,200.00
INSTALL COMBINATION SPAN WIRE SIGNAL AND LIGHTING POLE EACH2.0003,200.00
TYPE SWP-14.6-3.7 2.0003,200.00
0.0000.00

0107                          A610.00 2,000.001.0002,000.00
REMOVE TRAFFIC SIGNAL EACH1.0002,000.00
AT US-30 & L-51A 1.0002,000.00
0.0000.00

GROUP 8B ELECTRICALContracted6,222.00
Current6,222.00
In place6,135.18
This Estimate0.00

GROUP 9 BITUMINOUS
0108                          0030.90 13,800.001.00013,800.00
MOBILIZATION LS 1.00013,800.00
1.00013,800.00
0.0000.00

0109                          1020.02 14.6024.000350.40
DELINEATOR, TYPE II EACH24.000350.40
24.000350.40
0.0000.00

0110                          2001.00 11.85117.0001,386.45
GRAVEL SURFACE COURSE m3 117.0001,386.45
147.5501,748.47
0.0000.00

0111                          2020.00 4.0066.000264.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 66.000264.00
60.000240.00
0.0000.00

0112                          2021.00 50.005.000250.00
MAILBOX POST EACH5.000250.00
4.000200.00
0.0000.00

0113                          3013.07 110.5015.9001,756.95
CONCRETE CLASS 47B-25 BARRIER CURB, TYPE I m 15.9001,756.95
15.6901,733.75
0.0000.00

0114                          8008.00 16.9030.000507.00
ARMOR COAT AGGREGATE m3 30.000507.00
30.000507.00
0.0000.00

0115                          8029.84 2.00387.000774.00
BITUMINOUS FOUNDATION COURSE 100 mm m2 387.000774.00
413.470826.94
0.0000.00

0116                          9000.75 19.73500.0009,865.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.0009,865.00
SP4(12.5) 18.310361.26
0.0000.00

0117                          9005.00 23.65100.0002,365.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0002,365.00
SP4(12.5) 14.160334.88
0.0000.00

0118                          9005.45 19.7525,580.000505,205.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 25,580.000505,205.00
25,774.570509,047.76
0.0000.00

0119                          9009.00 2.004,302.0008,604.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 4,302.0008,604.00
4,819.7009,639.40
0.0000.00

0120                          9020.94 271.7527.0007,337.25
PERFORMANCE GRADED BINDER (64-28) FOR STATE MAINTENANCEPATCHING Mg 27.0007,337.25
0.930252.73
0.0000.00

0121                          9021.08 271.751,386.720376,841.16
PERFORMANCE GRADED BINDER (64-28) Mg 1,386.720376,841.16
1,413.433384,100.42
0.0000.00

0122                          9034.00 2.35765.0001,797.75
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 765.0001,797.75
1,177.8002,767.83
0.0000.00

0123                          9052.03 0.525,440.0002,828.80
ARMOR COAT EMULSIFIED ASPHALT L 0.0000.00
0.0000.00
0.0000.00

0124                          9053.00 0.23107,816.00024,797.68
TACK COAT L 107,816.00024,797.68
75,514.00017,368.22
0.0000.00

0125                          9053.20 0.2311,498.0002,644.54
FOG SEAL L 11,498.0002,644.54
15,239.0003,504.97
0.0000.00

0126                          9111.00 2.401,024.0002,457.60
WATER kL 1,024.0002,457.60
0.0000.00
0.0000.00

0127                          9170.00 118.50339.61940,244.85
EARTH SHOULDER CONSTRUCTION StaM339.61940,244.85
345.99941,000.88
0.0000.00

0128                          9173.15 66.0089.6805,918.88
TRENCHED WIDENING StaM89.6805,918.88
81.6975,392.00
0.0000.00

0129                          9173.20 0.85387.000328.95
SUBGRADE PREPARATION m2 387.000328.95
176.462149.99
0.0000.00

0130                          9179.23 475.0046.26121,973.98
COLD MILLING, CLASS 3 StaM46.26121,973.98
46.45822,067.55
0.0000.00

0131                          9179.24 2,300.002.1524,949.60
COLD MILLING, CLASS 4 StaM2.1524,949.60
2.6005,980.00
0.0000.00

0132                          9188.01 1.004,599.0004,599.00
BITUMINOUS SURFACE COURSE m2 4,599.0004,599.00
4,566.3594,566.36
0.0000.00

0133                          9188.50 24.00204.0004,896.00
SURFACING UNDER GUARDRAIL m2 204.0004,896.00
346.8058,323.32
0.0000.00

0134                          9300.50 2,600.001.0002,600.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0002,600.00
1.0002,600.00
0.0000.00

0135                          9300.52 1,100.001.0001,100.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0001,100.00
1.0001,100.00
0.0000.00

0136                          W600.03 225.003.000675.00
ADJUST VALVE BOX TO GRADE EACH3.000675.00
3.000675.00
0.0000.00

4001                          9013.00 0.520.0000.00
ASPHALTIC OIL FOR ARMOR COAT, APPLIED L 5,440.0002,828.80
5,387.0002,801.24
0.0000.00

4008                          9030.00 10.000.0000.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 25.000250.00
25.110251.10
0.0000.00

4012                          9300.56 0.6750.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 25,807.04017,419.75
Asphaltic Concrete, Type SP4(12.5) 25,807.04017,419.75
0.0000.00

4014                          9300.60 0.1480.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 4,281.000633.59
Smoothness Pay Factor = 100.75% 4,281.000633.59
0.0000.00

4015                          9300.77 2.0380.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 248.298506.03
Smoothness Pay Factor = 100.75% 248.298506.03
0.0000.00

4016                          1905.00 302.470.0000.00
MATERIAL DELIVERED NOT INCORPORATED LS 1.000302.47
750 mm CMP and Connecting Band 0.0000.00
0.0000.00

4017                          0096.00 -638.820.0000.00
DEDUCTION LS 1.000-638.82
Signs Not Returned 0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted1,051,118.84
Current1,069,591.86
In place1,060,250.84
This Estimate0.00

GROUP 10 GENERAL ITEMS
0137                          0001.08 0.50600.000300.00
BARRICADE, TYPE II BDAY600.000300.00
3,216.0001,608.00
0.0000.00

0138                          0001.10 3.702,379.0008,802.30
BARRICADE, TYPE III BDAY2,379.0008,802.30
6,333.00023,432.10
0.0000.00

0139                          0001.75 5.601,800.00010,080.00
TEMPORARY SIGN DAY EACH1,800.00010,080.00
506.0002,833.60
0.0000.00

0140                          0001.90 0.3825,521.0009,697.98
SIGN DAY EACH25,521.0009,697.98
8,638.0003,282.44
0.0000.00

0141                          0002.55 19.60475.2309,314.51
OVERLAY BROKEN LINES StaM475.2309,314.51
265.5015,203.82
0.0000.00

0142                          0002.60 19.65950.46018,676.54
OVERLAY SOLID LINES StaM950.46018,676.54
524.94210,315.11
0.0000.00

0143                          0003.10 176.00262.00046,112.00
FLAGGING DAY 262.00046,112.00
93.50016,456.00
0.0000.00

0144                          0003.20 270.0030.0008,100.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 30.0008,100.00
21.5005,805.00
0.0000.00

0145                          0003.51 32.00103.6323,316.22
INSTALL CONCRETE PROTECTION BARRIER m 103.6323,316.22
103.6323,316.22
0.0000.00

0146                          0005.10 95.00348.00033,060.00
TRAFFIC CONTROL MANAGEMENT DAY 348.00033,060.00
118.00011,210.00
0.0000.00

0147                          0010.04 1,200.001.0001,200.00
FIELD OFFICE EACH1.0001,200.00
1.0001,200.00
0.0000.00

0148                          0030.00 4,500.001.0004,500.00
MOBILIZATION LS 1.0004,500.00
1.0004,500.00
0.0000.00

0149                          9110.01 45.00120.0005,400.00
RENTAL OF LOADER, FULLY OPERATED HOUR120.0005,400.00
26.5001,192.50
0.0000.00

0150                          9110.02 49.0020.000980.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR20.000980.00
5.000245.00
0.0000.00

0151                          9110.03 39.00120.0004,680.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR120.0004,680.00
12.250477.75
0.0000.00

0152                          9110.06 45.00100.0004,500.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR100.0004,500.00
13.000585.00
0.0000.00

0153                          9110.07 31.00120.0003,720.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR120.0003,720.00
1.00031.00
0.0000.00

4000                          0001.99 1.250.0000.00
CONTRACTOR FURNISHED SIGN DAY EACH85.000106.25
106.000132.50
0.0000.00

GROUP 10 GENERAL ITEMSContracted172,439.55
Current172,545.80
In place91,826.04
This Estimate0.00

Totals for contractContracted2,017,141.00
Current2,016,236.66
In place1,929,792.71
This Estimate1,003.86