| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 1 GRADING | | |
|
| 0001 0030.10 | 6,250.00 | 1.000 | 6,250.00
|
| MOBILIZATION | LS | 1.000 | 6,250.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 1009.00 | 5,000.00 | 1.000 | 5,000.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 5,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0003 1011.00 | 2.60 | 805.000 | 2,093.00
|
| WATER | kL | 805.000 | 2,093.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0004 1012.00 | 74.50 | 179.000 | 13,335.50
|
| RIGHT-OF-WAY MARKERS | EACH | 179.000 | 13,335.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0005 1030.00 | 7.05 | 7,160.000 | 50,478.00
|
| EARTHWORK MEASURED IN EMBANKMENT | m3 | 7,160.000 | 50,478.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 1102.00 | 4.75 | 238.000 | 1,130.50
|
| REMOVE ASPHALT SURFACE | m2 | 238.000 | 1,130.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0007 1109.00 | 8.60 | 31.550 | 271.33
|
| REMOVE CURB | m | 31.550 | 271.33
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0008 4300.18 | 69.00 | 11.600 | 800.40
|
| 450 mm CULVERT PIPE | m | 11.600 | 800.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0009 7017.00 | 7.35 | 274.260 | 2,015.81
|
| REMOVE GUARDRAIL | m | 274.260 | 2,015.81
|
| | | 60.960 | 448.06
|
| | 0.000 | 0.00
|
| | |
|
| 0010 L020.00 | 1.85 | 502.000 | 928.70
|
| EROSION CONTROL | m2 | 502.000 | 928.70
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 L020.10 | 2.20 | 4,710.000 | 10,362.00
|
| EROSION CONTROL, TYPE HV | m2 | 4,710.000 | 10,362.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0012 L021.06 | 19.55 | 234.000 | 4,574.70
|
| EROSION CHECKS, TYPE HV | BALE | 234.000 | 4,574.70
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0013 L022.12 | 9.50 | 3,575.200 | 33,964.40
|
| FABRIC SILT FENCE-HIGH POROSITY | m | 3,575.200 | 33,964.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0014 L022.25 | 17.00 | 50.000 | 850.00
|
| FABRIC SILT FENCE, TYPE COIR FIBER | m | 50.000 | 850.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 1 GRADING | | Contracted | 132,054.34
|
| | Current | 132,054.34
|
| | In place | 448.06
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4 CULVERTS | | |
|
| 0015 0030.40 | 12,000.00 | 1.000 | 12,000.00
|
| MOBILIZATION | LS | 1.000 | 12,000.00
|
| | | 1.000 | 12,000.00
|
| | 1.000 | 12,000.00
|
| | |
|
| 0016 4039.20 | 70.00 | 17.710 | 1,239.70
|
| REMOVE AND RELAY CULVERT PIPE | m | 17.710 | 1,239.70
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 4040.00 | 155.00 | 10.000 | 1,550.00
|
| REMOVE HEADWALLS FROM CULVERTS | EACH | 10.000 | 1,550.00
|
| | | 2.000 | 310.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 4041.00 | 890.00 | 1.000 | 890.00
|
| CULVERT CLEANOUT | EACH | 1.000 | 890.00
|
| AT STA. 157+58.73 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 4044.00 | 1,700.00 | 1.000 | 1,700.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 1,700.00
|
| AT STA. 110+30.42 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 4044.01 | 2,000.00 | 1.000 | 2,000.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 2,000.00
|
| AT STA. 136+86.46 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 4044.02 | 2,100.00 | 1.000 | 2,100.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 2,100.00
|
| AT STA. 141+19.6 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 4044.03 | 2,500.00 | 1.000 | 2,500.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 2,500.00
|
| AT STA. 179+77.67 | | 1.000 | 2,500.00
|
| | 1.000 | 2,500.00
|
| | |
|
| 0023 4044.04 | 1,400.00 | 1.000 | 1,400.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 1,400.00
|
| AT STA. 235+00.72 | | 1.000 | 1,400.00
|
| | 1.000 | 1,400.00
|
| | |
|
| 0024 4044.05 | 2,100.00 | 1.000 | 2,100.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 2,100.00
|
| AT STA. 258+24.29 | | 1.000 | 2,100.00
|
| | 1.000 | 2,100.00
|
| | |
|
| 0025 4050.01 | 10.00 | 67.000 | 670.00
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 67.000 | 670.00
|
| | | 28.000 | 280.00
|
| | 0.000 | 0.00
|
| | |
|
| 0026 4051.01 | 13.00 | 366.000 | 4,758.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 366.000 | 4,758.00
|
| | | 239.000 | 3,107.00
|
| | 146.000 | 1,898.00
|
| | |
|
| 0027 4100.06 | 850.00 | 2.880 | 2,448.00
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL | m3 | 2.880 | 2,448.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0028 4101.06 | 375.00 | 228.970 | 85,863.75
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 228.970 | 85,863.75
|
| | | 96.610 | 36,228.75
|
| | 92.110 | 34,541.25
|
| | |
|
| 0029 4107.07 | 750.00 | 2.360 | 1,770.00
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS | m3 | 2.360 | 1,770.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0030 4150.00 | 1.80 | 230.000 | 414.00
|
| REINFORCING STEEL FOR HEADWALL | kg | 230.000 | 414.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0031 4151.00 | 1.50 | 14,479.000 | 21,718.50
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 14,479.000 | 21,718.50
|
| | | 6,465.000 | 9,697.50
|
| | 6,265.000 | 9,397.50
|
| | |
|
| 0032 4157.00 | 1.80 | 96.000 | 172.80
|
| REINFORCING STEEL FOR COLLARS | kg | 96.000 | 172.80
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0033 4350.30 | 100.00 | 4.600 | 460.00
|
| 750 mm CORRUGATED METAL PIPE | m | 4.600 | 460.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0034 4350.36 | 150.00 | 2.200 | 330.00
|
| 900 mm CORRUGATED METAL PIPE | m | 2.200 | 330.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0035 4360.30 | 370.00 | 2.000 | 740.00
|
| 750 mm METAL FLARED-END SECTION | EACH | 2.000 | 740.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0036 4360.36 | 490.00 | 4.000 | 1,960.00
|
| 900 mm METAL FLARED-END SECTION | EACH | 4.000 | 1,960.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0037 4450.36 | 200.00 | 12.400 | 2,480.00
|
| 900 mm REINFORCED CONCRETE PIPE | m | 12.400 | 2,480.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4 CULVERTS | | Contracted | 151,264.75
|
| | Current | 151,264.75
|
| | In place | 67,623.25
|
| | This Estimate | 63,836.75
|
| | |
|
| GROUP 4A CULVERT AT STA. 107+60.06 | | |
|
| 0038 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0039 4044.06 | 3,000.00 | 1.000 | 3,000.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,000.00
|
| AT STA. 107+60.06 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0040 4051.01 | 15.00 | 43.000 | 645.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 43.000 | 645.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0041 4101.06 | 378.00 | 54.690 | 20,672.82
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 54.690 | 20,672.82
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0042 4151.00 | 1.20 | 3,840.000 | 4,608.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 3,840.000 | 4,608.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4A CULVERT AT STA. 107+60.06 | | Contracted | 31,925.82
|
| | Current | 31,925.82
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4B CULVERT AT STA. 112+48.03 | | |
|
| 0043 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0044 4044.07 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 112+48.03 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0045 4051.01 | 15.00 | 51.000 | 765.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 51.000 | 765.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0046 4101.06 | 378.00 | 56.210 | 21,247.38
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 56.210 | 21,247.38
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0047 4151.00 | 1.20 | 3,720.000 | 4,464.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 3,720.000 | 4,464.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4B CULVERT AT STA. 112+48.03 | | Contracted | 32,676.38
|
| | Current | 32,676.38
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4C CULVERT AT STA. 122+38.66 | | |
|
| 0048 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0049 4044.08 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 122+38.66 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0050 4051.01 | 15.00 | 109.000 | 1,635.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 109.000 | 1,635.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0051 4101.06 | 378.00 | 74.290 | 28,081.62
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 74.290 | 28,081.62
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0052 4151.00 | 1.20 | 5,626.000 | 6,751.20
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 5,626.000 | 6,751.20
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4C CULVERT AT STA. 122+38.66 | | Contracted | 42,667.82
|
| | Current | 42,667.82
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4D CULVERT AT STA. 133+01.25 | | |
|
| 0053 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0054 4044.09 | 3,000.00 | 1.000 | 3,000.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,000.00
|
| AT STA. 133+01.25 | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0055 4051.01 | 15.00 | 58.000 | 870.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 58.000 | 870.00
|
| | | 58.000 | 870.00
|
| | 0.000 | 0.00
|
| | |
|
| 0056 4101.06 | 378.00 | 62.660 | 23,685.48
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 62.660 | 23,685.48
|
| | | 62.660 | 23,685.48
|
| | 17.160 | 6,486.48
|
| | |
|
| 0057 4151.00 | 1.20 | 4,466.000 | 5,359.20
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 4,466.000 | 5,359.20
|
| | | 4,466.000 | 5,359.20
|
| | 1,166.000 | 1,399.20
|
| | |
|
| GROUP 4D CULVERT AT STA. 133+01.25 | | Contracted | 35,914.68
|
| | Current | 35,914.68
|
| | In place | 35,914.68
|
| | This Estimate | 7,885.68
|
| | |
|
| GROUP 4E CULVERT AT STA. 154+37.53 | | |
|
| 0058 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0059 4044.10 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 154+37.53 | | 1.000 | 3,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0060 4051.01 | 15.00 | 147.000 | 2,205.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 147.000 | 2,205.00
|
| | | 147.000 | 2,205.00
|
| | 72.000 | 1,080.00
|
| | |
|
| 0061 4101.06 | 378.00 | 71.730 | 27,113.94
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 71.730 | 27,113.94
|
| | | 72.380 | 27,359.64
|
| | 55.480 | 20,971.44
|
| | |
|
| 0062 4151.00 | 1.20 | 4,698.000 | 5,637.60
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 4,698.000 | 5,637.60
|
| | | 4,745.000 | 5,694.00
|
| | 3,570.000 | 4,284.00
|
| | |
|
| GROUP 4E CULVERT AT STA. 154+37.53 | | Contracted | 41,156.54
|
| | Current | 41,156.54
|
| | In place | 41,458.64
|
| | This Estimate | 26,335.44
|
| | |
|
| GROUP 4F CULVERT AT STA. 170+38.59 | | |
|
| 0063 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 1.000 | 3,000.00
|
| | |
|
| 0064 4044.11 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 170+38.59 | | 1.000 | 3,200.00
|
| | 1.000 | 3,200.00
|
| | |
|
| 0065 4051.01 | 15.00 | 77.000 | 1,155.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 77.000 | 1,155.00
|
| | | 77.000 | 1,155.00
|
| | 77.000 | 1,155.00
|
| | |
|
| 0066 4101.06 | 378.00 | 61.360 | 23,194.08
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 61.360 | 23,194.08
|
| | | 43.900 | 16,594.20
|
| | 43.900 | 16,594.20
|
| | |
|
| 0067 4151.00 | 1.20 | 4,307.000 | 5,168.40
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 4,307.000 | 5,168.40
|
| | | 3,158.000 | 3,789.60
|
| | 3,158.000 | 3,789.60
|
| | |
|
| GROUP 4F CULVERT AT STA. 170+38.59 | | Contracted | 35,717.48
|
| | Current | 35,717.48
|
| | In place | 27,738.80
|
| | This Estimate | 27,738.80
|
| | |
|
| GROUP 4G CULVERT AT STA. 184+95.78 | | |
|
| 0068 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 0.815 | 2,445.00
|
| | 0.815 | 2,445.00
|
| | |
|
| 0069 4044.12 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 184+95.78 | | 1.000 | 3,200.00
|
| | 1.000 | 3,200.00
|
| | |
|
| 0070 4051.01 | 15.00 | 50.000 | 750.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 50.000 | 750.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0071 4101.06 | 378.00 | 39.080 | 14,772.24
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 39.080 | 14,772.24
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0072 4151.00 | 1.20 | 2,285.000 | 2,742.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 2,285.000 | 2,742.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4G CULVERT AT STA. 184+95.78 | | Contracted | 24,464.24
|
| | Current | 24,464.24
|
| | In place | 5,645.00
|
| | This Estimate | 5,645.00
|
| | |
|
| GROUP 4H CULVERT AT STA. 201+21.11 | | |
|
| 0073 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0074 4044.13 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 201+21.11 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0075 4051.01 | 15.00 | 137.000 | 2,055.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 137.000 | 2,055.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0076 4101.06 | 378.00 | 72.390 | 27,363.42
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 72.390 | 27,363.42
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0077 4151.00 | 1.20 | 4,745.000 | 5,694.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 4,745.000 | 5,694.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4H CULVERT AT STA. 201+21.11 | | Contracted | 41,312.42
|
| | Current | 41,312.42
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4I CULVERT AT STA. 251+38.52 | | |
|
| 0078 0030.40 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0079 4044.14 | 3,200.00 | 1.000 | 3,200.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 3,200.00
|
| AT STA. 251+38.52 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0080 4051.01 | 15.00 | 140.000 | 2,100.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 140.000 | 2,100.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0081 4101.06 | 378.00 | 78.610 | 29,714.58
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 78.610 | 29,714.58
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0082 4151.00 | 1.20 | 4,822.000 | 5,786.40
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 4,822.000 | 5,786.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4I CULVERT AT STA. 251+38.52 | | Contracted | 43,800.98
|
| | Current | 43,800.98
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 4J CULVERT AT STA. 1100+16 | | |
|
| 0083 0030.40 | 7,800.00 | 1.000 | 7,800.00
|
| MOBILIZATION | LS | 1.000 | 7,800.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0084 4049.00 | 980.00 | 87.840 | 86,083.20
|
| PRECAST REINFORCED CONCRETE BOX CULVERT | m | 87.840 | 86,083.20
|
| 2.4 M X 1.2 M | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0085 4051.01 | 14.00 | 315.000 | 4,410.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 315.000 | 4,410.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0086 4101.09 | 470.00 | 23.040 | 10,828.80
|
| CLASS 47B-HE-20 OR AX-HE-20 CONCRETE FOR BOX CULVERT | m3 | 23.040 | 10,828.80
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0087 4151.00 | 1.70 | 1,130.000 | 1,921.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 1,130.000 | 1,921.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0088 6040.00 | 5,000.00 | 1.000 | 5,000.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 5,000.00
|
| AT STA. 1100+16 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4J CULVERT AT STA. 1100+16 | | Contracted | 116,043.00
|
| | Current | 116,043.00
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 5 SEEDING | | |
|
| 0089 0030.50 | 1,200.00 | 1.000 | 1,200.00
|
| MOBILIZATION | LS | 1.000 | 1,200.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0090 L001.02 | 1,040.00 | 12.300 | 12,792.00
|
| SEEDING, TYPE B | ha | 12.300 | 12,792.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0091 L020.02 | 1.32 | 2,392.000 | 3,157.44
|
| EROSION CONTROL, TYPE B | m2 | 2,392.000 | 3,157.44
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0092 L032.75 | 75.00 | 62.000 | 4,650.00
|
| MULCH | Mg | 62.000 | 4,650.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 5 SEEDING | | Contracted | 21,799.44
|
| | Current | 21,799.44
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | |
|
| 0093 0030.70 | 2,000.00 | 1.000 | 2,000.00
|
| MOBILIZATION | LS | 1.000 | 2,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0094 6010.26 | 2,000.00 | 3.200 | 6,400.00
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 3.200 | 6,400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0095 6020.00 | 10.00 | 608.700 | 6,087.00
|
| REINFORCING STEEL FOR BRIDGE | kg | 608.700 | 6,087.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0096 6086.00 | 50.00 | 21.500 | 1,075.00
|
| STRUCTURAL STEEL | kg | 21.500 | 1,075.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0097 7011.20 | 42.00 | 57.160 | 2,400.72
|
| W-BEAM GUARDRAIL | m | 57.160 | 2,400.72
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0098 7020.00 | 3,000.00 | 4.000 | 12,000.00
|
| BRIDGE APPROACH SECTIONS | EACH | 4.000 | 12,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0099 7024.27 | 1,650.00 | 4.000 | 6,600.00
|
| GUARDRAIL END TREATMENT, TYPE II | EACH | 4.000 | 6,600.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | Contracted | 36,562.72
|
| | Current | 36,562.72
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 8B ELECTRICAL | | |
|
| 0100 0030.81 | 400.00 | 1.000 | 400.00
|
| MOBILIZATION | LS | 1.000 | 400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0101 A077.88 | 3.00 | 20.000 | 60.00
|
| 3/C #14 AWG TRAFFIC SIGNAL CABLE, AERIAL | m | 20.000 | 60.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0102 A079.70 | 3.00 | 15.000 | 45.00
|
| SERVICE CABLE, NO. 6, AERIAL | m | 15.000 | 45.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0103 A080.27 | 3.00 | 39.000 | 117.00
|
| STREET LIGHT CABLE, NO. 6 AERIAL | m | 39.000 | 117.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0104 A500.00 | 200.00 | 1.000 | 200.00
|
| INSTALL TRAFFIC SIGNAL CONTROLLER | EACH | 1.000 | 200.00
|
| TYPE FLASHER | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0105 A501.40 | 200.00 | 1.000 | 200.00
|
| INSTALL TRAFFIC SIGNAL, TYPE TS-4 | EACH | 1.000 | 200.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0106 A505.85 | 1,600.00 | 2.000 | 3,200.00
|
| INSTALL COMBINATION SPAN WIRE SIGNAL AND LIGHTING POLE | EACH | 2.000 | 3,200.00
|
| TYPE SWP-14.6-3.7 | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0107 A610.00 | 2,000.00 | 1.000 | 2,000.00
|
| REMOVE TRAFFIC SIGNAL | EACH | 1.000 | 2,000.00
|
| AT US-30 & L-51A | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 8B ELECTRICAL | | Contracted | 6,222.00
|
| | Current | 6,222.00
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 9 BITUMINOUS | | |
|
| 0108 0030.90 | 13,800.00 | 1.000 | 13,800.00
|
| MOBILIZATION | LS | 1.000 | 13,800.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0109 1020.02 | 14.60 | 24.000 | 350.40
|
| DELINEATOR, TYPE II | EACH | 24.000 | 350.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0110 2001.00 | 11.85 | 117.000 | 1,386.45
|
| GRAVEL SURFACE COURSE | m3 | 117.000 | 1,386.45
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0111 2020.00 | 4.00 | 66.000 | 264.00
|
| SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS | m2 | 66.000 | 264.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0112 2021.00 | 50.00 | 5.000 | 250.00
|
| MAILBOX POST | EACH | 5.000 | 250.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0113 3013.07 | 110.50 | 15.900 | 1,756.95
|
| CONCRETE CLASS 47B-25 BARRIER CURB, TYPE I | m | 15.900 | 1,756.95
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0114 8008.00 | 16.90 | 30.000 | 507.00
|
| ARMOR COAT AGGREGATE | m3 | 30.000 | 507.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0115 8029.84 | 2.00 | 387.000 | 774.00
|
| BITUMINOUS FOUNDATION COURSE 100 mm | m2 | 387.000 | 774.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0116 9000.75 | 19.73 | 500.000 | 9,865.00
|
| ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | Mg | 500.000 | 9,865.00
|
| SP4(12.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0117 9005.00 | 23.65 | 100.000 | 2,365.00
|
| ASPHALTIC CONCRETE FOR PATCHING, TYPE | Mg | 100.000 | 2,365.00
|
| SP4(12.5) | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0118 9005.45 | 19.75 | 25,580.000 | 505,205.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 25,580.000 | 505,205.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0119 9009.00 | 2.00 | 4,302.000 | 8,604.00
|
| PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS | m2 | 4,302.000 | 8,604.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0120 9020.94 | 271.75 | 27.000 | 7,337.25
|
| PERFORMANCE GRADED BINDER (64-28) FOR STATE MAINTENANCEPATCHING | Mg | 27.000 | 7,337.25
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0121 9021.08 | 271.75 | 1,386.720 | 376,841.16
|
| PERFORMANCE GRADED BINDER (64-28) | Mg | 1,386.720 | 376,841.16
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0122 9034.00 | 2.35 | 765.000 | 1,797.75
|
| PREPARATION OF INTERSECTIONS AND DRIVEWAYS | m2 | 765.000 | 1,797.75
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0123 9052.03 | 0.52 | 5,440.000 | 2,828.80
|
| ARMOR COAT EMULSIFIED ASPHALT | L | 5,440.000 | 2,828.80
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0124 9053.00 | 0.23 | 107,816.000 | 24,797.68
|
| TACK COAT | L | 107,816.000 | 24,797.68
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0125 9053.20 | 0.23 | 11,498.000 | 2,644.54
|
| FOG SEAL | L | 11,498.000 | 2,644.54
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0126 9111.00 | 2.40 | 1,024.000 | 2,457.60
|
| WATER | kL | 1,024.000 | 2,457.60
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0127 9170.00 | 118.50 | 339.619 | 40,244.85
|
| EARTH SHOULDER CONSTRUCTION | StaM | 339.619 | 40,244.85
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0128 9173.15 | 66.00 | 89.680 | 5,918.88
|
| TRENCHED WIDENING | StaM | 89.680 | 5,918.88
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0129 9173.20 | 0.85 | 387.000 | 328.95
|
| SUBGRADE PREPARATION | m2 | 387.000 | 328.95
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0130 9179.23 | 475.00 | 46.261 | 21,973.98
|
| COLD MILLING, CLASS 3 | StaM | 46.261 | 21,973.98
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0131 9179.24 | 2,300.00 | 2.152 | 4,949.60
|
| COLD MILLING, CLASS 4 | StaM | 2.152 | 4,949.60
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0132 9188.01 | 1.00 | 4,599.000 | 4,599.00
|
| BITUMINOUS SURFACE COURSE | m2 | 4,599.000 | 4,599.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0133 9188.50 | 24.00 | 204.000 | 4,896.00
|
| SURFACING UNDER GUARDRAIL | m2 | 204.000 | 4,896.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0134 9300.50 | 2,600.00 | 1.000 | 2,600.00
|
| ASPHALT PAVEMENT SMOOTHNESS TESTING | LS | 1.000 | 2,600.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0135 9300.52 | 1,100.00 | 1.000 | 1,100.00
|
| ASPHALT PAVEMENT SMOOTHNESS TESTING I/D | LS | 1.000 | 1,100.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0136 W600.03 | 225.00 | 3.000 | 675.00
|
| ADJUST VALVE BOX TO GRADE | EACH | 3.000 | 675.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 9 BITUMINOUS | | Contracted | 1,051,118.84
|
| | Current | 1,051,118.84
|
| | In place | 0.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | |
|
| 0137 0001.08 | 0.50 | 600.000 | 300.00
|
| BARRICADE, TYPE II | BDAY | 600.000 | 300.00
|
| | | 547.000 | 273.50
|
| | 242.000 | 121.00
|
| | |
|
| 0138 0001.10 | 3.70 | 2,379.000 | 8,802.30
|
| BARRICADE, TYPE III | BDAY | 2,379.000 | 8,802.30
|
| | | 1,238.000 | 4,580.60
|
| | 636.000 | 2,353.20
|
| | |
|
| 0139 0001.75 | 5.60 | 1,800.000 | 10,080.00
|
| TEMPORARY SIGN DAY | EACH | 1,800.000 | 10,080.00
|
| | | 4.000 | 22.40
|
| | 4.000 | 22.40
|
| | |
|
| 0140 0001.90 | 0.38 | 25,521.000 | 9,697.98
|
| SIGN DAY | EACH | 25,521.000 | 9,697.98
|
| | | 1,546.000 | 587.48
|
| | 554.000 | 210.52
|
| | |
|
| 0141 0002.55 | 19.60 | 475.230 | 9,314.51
|
| OVERLAY BROKEN LINES | StaM | 475.230 | 9,314.51
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0142 0002.60 | 19.65 | 950.460 | 18,676.54
|
| OVERLAY SOLID LINES | StaM | 950.460 | 18,676.54
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0143 0003.10 | 176.00 | 262.000 | 46,112.00
|
| FLAGGING | DAY | 262.000 | 46,112.00
|
| | | 1.000 | 176.00
|
| | 1.000 | 176.00
|
| | |
|
| 0144 0003.20 | 270.00 | 30.000 | 8,100.00
|
| FURNISHING AND OPERATING PILOT VEHICLE | DAY | 30.000 | 8,100.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0145 0003.51 | 32.00 | 103.632 | 3,316.22
|
| INSTALL CONCRETE PROTECTION BARRIER | m | 103.632 | 3,316.22
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0146 0005.10 | 95.00 | 348.000 | 33,060.00
|
| TRAFFIC CONTROL MANAGEMENT | DAY | 348.000 | 33,060.00
|
| | | 24.000 | 2,280.00
|
| | 14.000 | 1,330.00
|
| | |
|
| 0147 0010.04 | 1,200.00 | 1.000 | 1,200.00
|
| FIELD OFFICE | EACH | 1.000 | 1,200.00
|
| | | 0.060 | 72.00
|
| | 0.060 | 72.00
|
| | |
|
| 0148 0030.00 | 4,500.00 | 1.000 | 4,500.00
|
| MOBILIZATION | LS | 1.000 | 4,500.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0149 9110.01 | 45.00 | 120.000 | 5,400.00
|
| RENTAL OF LOADER, FULLY OPERATED | HOUR | 120.000 | 5,400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0150 9110.02 | 49.00 | 20.000 | 980.00
|
| RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 20.000 | 980.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0151 9110.03 | 39.00 | 120.000 | 4,680.00
|
| RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 120.000 | 4,680.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0152 9110.06 | 45.00 | 100.000 | 4,500.00
|
| RENTAL OF BACKHOE, FULLY OPERATED | HOUR | 100.000 | 4,500.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0153 9110.07 | 31.00 | 120.000 | 3,720.00
|
| RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 120.000 | 3,720.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 4000 0001.99 | 1.25 | 0.000 | 0.00
|
| CONTRACTOR FURNISHED SIGN DAY | EACH | 85.000 | 106.25
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | Contracted | 172,439.55
|
| | Current | 172,545.80
|
| | In place | 7,991.98
|
| | This Estimate | 4,285.12
|
| | |
|
| Totals for contract | | Contracted | 2,017,141.00
|
|---|
| | Current | 2,017,247.25
|
|---|
| | In place | 186,820.41
|
|---|
| | This Estimate | 135,726.79
|
|---|