| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 1 GRADING | | |
|
| 0001 L006.00 | 200.00 | 22.000 | 4,400.00
|
| COVER CROP SEEDING | ha | 23.000 | 4,600.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 L020.00 | 3.50 | 1,710.000 | 5,985.00
|
| EROSION CONTROL | m2 | 1,710.000 | 5,985.00
|
| | | 1,771.650 | 6,200.78
|
| | 0.000 | 0.00
|
| | |
|
| 0003 L022.25 | 20.00 | 1,037.000 | 20,740.00
|
| FABRIC SILT FENCE, TYPE COIR FIBER | m | 1,037.000 | 20,740.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0004 0030.10 | 10,700.00 | 1.000 | 10,700.00
|
| MOBILIZATION | LS | 1.000 | 10,700.00
|
| | | 1.000 | 10,700.00
|
| | 0.000 | 0.00
|
| | |
|
| 0005 1000.00 | 625.00 | 9.000 | 5,625.00
|
| LARGE TREE REMOVAL | EACH | 9.000 | 5,625.00
|
| | | 15.000 | 9,375.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 1009.00 | 7,000.00 | 1.000 | 7,000.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 7,000.00
|
| | | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0007 1010.00 | 3.15 | 58,956.000 | 185,711.40
|
| EXCAVATION | m3 | 71,881.000 | 226,425.15
|
| | | 71,871.690 | 226,395.82
|
| | 0.000 | 0.00
|
| | |
|
| 0008 1010.10 | 7.50 | 42,359.000 | 317,692.50
|
| EXCAVATION, BORROW | m3 | 42,359.001 | 317,692.51
|
| | | 42,359.000 | 317,692.50
|
| | 0.000 | 0.00
|
| | |
|
| 0009 1011.00 | 2.00 | 7,599.000 | 15,198.00
|
| WATER | kL | 7,599.000 | 15,198.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0010 1021.10 | 2.50 | 11.000 | 27.50
|
| REMOVE DELINEATOR UNITS | EACH | 11.000 | 27.50
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 1041.00 | 0.55 | 51,300.000 | 28,215.00
|
| SALVAGING AND PLACING TOPSOIL | m2 | 51,300.000 | 28,215.00
|
| | | 53,376.000 | 29,356.80
|
| | 0.000 | 0.00
|
| | |
|
| 0012 1042.00 | 0.85 | 9,955.000 | 8,461.75
|
| SALVAGING AND PLACING HYDRIC SOIL | m2 | 9,955.000 | 8,461.75
|
| | | 9,828.860 | 8,354.53
|
| | 0.000 | 0.00
|
| | |
|
| 0013 1043.50 | 2.30 | 2,621.000 | 6,028.30
|
| RIPRAP FILTER FABRIC | m2 | 2,621.000 | 6,028.30
|
| | | 1,825.060 | 4,197.64
|
| | 0.000 | 0.00
|
| | |
|
| 0014 1101.00 | 3.50 | 2,545.000 | 8,907.50
|
| REMOVE PAVEMENT | m2 | 1,405.000 | 4,917.50
|
| | | 1,199.000 | 4,196.50
|
| | 0.000 | 0.00
|
| | |
|
| 0015 1102.00 | 3.50 | 10,527.000 | 36,844.50
|
| REMOVE ASPHALT SURFACE | m2 | 10,527.000 | 36,844.50
|
| | | 10,851.044 | 37,978.66
|
| | 0.000 | 0.00
|
| | |
|
| 0016 1106.00 | 3.50 | 2,691.000 | 9,418.50
|
| REMOVE DRIVEWAY | m2 | 2,691.000 | 9,418.50
|
| | | 3,021.492 | 10,575.23
|
| | 0.000 | 0.00
|
| | |
|
| 0017 1107.00 | 2.00 | 533.000 | 1,066.00
|
| REMOVE WALK | m2 | 533.000 | 1,066.00
|
| | | 494.317 | 988.63
|
| | 0.120 | 0.24
|
| | |
|
| 0018 1705.42 | 190.00 | 30.000 | 5,700.00
|
| 1050 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2,3,4OR 5 | m | 30.000 | 5,700.00
|
| | | 43.900 | 8,341.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 6104.00 | 9.65 | 68.000 | 656.20
|
| BROKEN CONCRETE RIPRAP | Mg | 68.000 | 656.20
|
| | | 266.540 | 2,572.11
|
| | 0.000 | 0.00
|
| | |
|
| 0020 6105.02 | 49.00 | 1,845.000 | 90,405.00
|
| ROCK RIPRAP, TYPE B | Mg | 0.000 | 0.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 7017.00 | 11.00 | 31.400 | 345.40
|
| REMOVE GUARDRAIL | m | 31.400 | 345.40
|
| | | 30.700 | 337.70
|
| | 0.000 | 0.00
|
| | |
|
| 0022 9110.09 | 70.00 | 15.000 | 1,050.00
|
| RENTAL OF TRACTOR AND SCRAPER, FULLY OPERATED | HOUR | 15.000 | 1,050.00
|
| | | 15.000 | 1,050.00
|
| | 0.000 | 0.00
|
| | |
|
| 4002 1012.00 | 66.15 | 0.000 | 0.00
|
| RIGHT-OF-WAY MARKER | EACH | 163.000 | 10,782.45
|
| | | 159.000 | 10,517.85
|
| | 0.000 | 0.00
|
| | |
|
| 4003 1013.00 | 49.35 | 0.000 | 0.00
|
| RESET RIGHT-OF-WAY MARKER | EACH | 10.000 | 493.50
|
| | | 2.000 | 98.70
|
| | 0.000 | 0.00
|
| | |
|
| 4010 1305.24 | 78.75 | 0.000 | 0.00
|
| 600 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE | m | 28.000 | 2,205.00
|
| | | 42.670 | 3,360.26
|
| | 0.000 | 0.00
|
| | |
|
| 4011 1300.30 | 103.95 | 0.000 | 0.00
|
| 750 mm DRIVEWAY CULVERT PIPE | m | 57.000 | 5,925.15
|
| | | 56.610 | 5,884.61
|
| | 0.000 | 0.00
|
| | |
|
| 4012 1300.48 | 229.95 | 0.000 | 0.00
|
| 1200 mm DRIVEWAY CULVERT PIPE | m | 14.600 | 3,357.27
|
| | | 14.630 | 3,364.17
|
| | 0.000 | 0.00
|
| | |
|
| 4025 6104.00 | 22.30 | 0.000 | 0.00
|
| BROKEN CONCRETE RIPRAP | Mg | 1,845.000 | 41,143.50
|
| BROKEN CONCRETE RIPRAP HAULED FROM NORTH PLATTE STOCKPILE SITE | | 1,506.063 | 33,585.20
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 1 GRADING | | Contracted | 770,177.55
|
| | Current | 780,603.18
|
| | In place | 742,123.69
|
| | This Estimate | 0.24
|
| | |
|
| GROUP 4 CULVERTS | | |
|
| 0023 P300.36 | 99.00 | 34.800 | 3,445.20
|
| 900 mm CULVERT PIPE, TYPE 3,4 OR 5 | m | 51.500 | 5,098.50
|
| | | 33.140 | 3,280.86
|
| | 0.000 | 0.00
|
| | |
|
| 0024 P372.36 | 116.00 | 69.500 | 8,062.00
|
| 900 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2,4 OR 5 | m | 53.700 | 6,229.20
|
| | | 48.140 | 5,584.24
|
| | 0.000 | 0.00
|
| | |
|
| 0025 P500.24 | 67.00 | 14.500 | 971.50
|
| 600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 | m | 14.500 | 971.50
|
| | | 14.640 | 980.88
|
| | 0.000 | 0.00
|
| | |
|
| 0026 P500.36 | 99.00 | 43.300 | 4,286.70
|
| 900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 | m | 43.300 | 4,286.70
|
| | | 40.870 | 4,046.13
|
| | 0.000 | 0.00
|
| | |
|
| 0027 0030.40 | 2,500.00 | 1.000 | 2,500.00
|
| MOBILIZATION | LS | 1.000 | 2,500.00
|
| | | 1.000 | 2,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0028 4035.00 | 100.00 | 2.000 | 200.00
|
| REMOVE FLARED-END SECTION | EACH | 2.000 | 200.00
|
| | | 1.000 | 100.00
|
| | 0.000 | 0.00
|
| | |
|
| 0029 4040.00 | 100.00 | 5.000 | 500.00
|
| REMOVE HEADWALLS FROM CULVERTS | EACH | 6.000 | 600.00
|
| | | 7.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
| 0030 4044.00 | 1,525.00 | 1.000 | 1,525.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 1,525.00
|
| AT STA. 23+74.65 | | 1.000 | 1,525.00
|
| | 0.000 | 0.00
|
| | |
|
| 0031 4044.01 | 2,525.00 | 1.000 | 2,525.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 2,525.00
|
| AT STA. 68+22.8 | | 1.000 | 2,525.00
|
| | 0.000 | 0.00
|
| | |
|
| 0032 4044.02 | 2,525.00 | 1.000 | 2,525.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 2,525.00
|
| AT STA. 94+21.7 | | 1.000 | 2,525.00
|
| | 0.000 | 0.00
|
| | |
|
| 0033 4045.00 | 3,025.00 | 1.000 | 3,025.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 3,025.00
|
| AT STA. 16+38.2-10.4 m RT. | | 1.000 | 3,025.00
|
| | 0.000 | 0.00
|
| | |
|
| 0034 4045.01 | 3,025.00 | 1.000 | 3,025.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 3,025.00
|
| AT STA. 57+64.5-14.1 m LT. | | 1.000 | 3,025.00
|
| | 0.000 | 0.00
|
| | |
|
| 0035 4045.02 | 3,025.00 | 1.000 | 3,025.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 3,025.00
|
| AT STA. 74+70.18 | | 1.000 | 3,025.00
|
| | 0.000 | 0.00
|
| | |
|
| 0036 4045.03 | 3,025.00 | 1.000 | 3,025.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 3,025.00
|
| AT STA. 92+21.3 | | 1.000 | 3,025.00
|
| | 0.000 | 0.00
|
| | |
|
| 0037 4050.01 | 20.00 | 455.000 | 9,100.00
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 430.000 | 8,600.00
|
| | | 429.810 | 8,596.20
|
| | 0.000 | 0.00
|
| | |
|
| 0038 4051.01 | 20.00 | 205.000 | 4,100.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 355.000 | 7,100.00
|
| | | 636.674 | 12,733.48
|
| | 123.700 | 2,474.00
|
| | |
|
| 0039 4101.06 | 330.00 | 200.940 | 66,310.20
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 230.150 | 75,949.50
|
| | | 239.248 | 78,951.84
|
| | 0.000 | 0.00
|
| | |
|
| 0040 4151.00 | 1.65 | 11,578.000 | 19,103.70
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 13,167.000 | 21,725.55
|
| | | 14,340.539 | 23,661.90
|
| | 0.000 | 0.00
|
| | |
|
| 0041 4310.24 | 180.00 | 2.000 | 360.00
|
| 600 mm FLARED-END SECTION | EACH | 5.000 | 900.00
|
| | | 2.000 | 360.00
|
| | 0.000 | 0.00
|
| | |
|
| 0042 4310.36 | 255.00 | 6.000 | 1,530.00
|
| 900 mm FLARED-END SECTION | EACH | 6.000 | 1,530.00
|
| | | 6.000 | 1,530.00
|
| | 0.000 | 0.00
|
| | |
|
| 0043 4320.36 | 255.00 | 8.000 | 2,040.00
|
| 900 mm ROUND EQUIVALENT FLARED-END SECTION | EACH | 4.000 | 1,020.00
|
| | | 4.000 | 1,020.00
|
| | 0.000 | 0.00
|
| | |
|
| 4013 4450.24 | 199.50 | 0.000 | 0.00
|
| 600 mm REINFORCED CONCRETE PIPE | m | 7.000 | 1,396.50
|
| | | 7.000 | 1,396.50
|
| | 0.000 | 0.00
|
| | |
|
| 4014 4460.24 | 577.50 | 0.000 | 0.00
|
| 600 mm CONCRETE FLARED END SECTION | EACH | 1.000 | 577.50
|
| | | 1.000 | 577.50
|
| | 0.000 | 0.00
|
| | |
|
| 4015 4305.24 | 78.75 | 0.000 | 0.00
|
| 600 mm ROUND EQUIVALENT CULVERT PIPE | m | 33.500 | 2,638.13
|
| | | 33.520 | 2,639.70
|
| | 0.000 | 0.00
|
| | |
|
| 4016 4320.24 | 262.50 | 0.000 | 0.00
|
| 600 mm ROUND EQUIVALENT FLARED END SECTION | EACH | 2.000 | 525.00
|
| | | 2.000 | 525.00
|
| | 0.000 | 0.00
|
| | |
|
| 4017 0095.00 | 320.25 | 0.000 | 0.00
|
| ADDITIONAL FREIGHT COSTS | LS | 1.000 | 320.25
|
| FREIGHT COSTS FOR REINFORCED CONCRETE CULVERT AND F.E.S. | | 1.000 | 320.25
|
| | 0.000 | 0.00
|
| | |
|
| 4031 4976.05 | 843.38 | 0.000 | 0.00
|
| ADDITIONAL WORK | LS | 1.000 | 843.38
|
| | | 1.000 | 843.38
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4 CULVERTS | | Contracted | 141,184.30
|
| | Current | 161,686.70
|
| | In place | 169,022.86
|
| | This Estimate | 2,474.00
|
| | |
|
| GROUP 4A CULVERT AT STA. 129+56.4 | | |
|
| 0044 0030.40 | 5,250.00 | 1.000 | 5,250.00
|
| MOBILIZATION | LS | 1.000 | 5,250.00
|
| | | 1.000 | 5,250.00
|
| | 0.140 | 735.00
|
| | |
|
| 0045 4044.03 | 4,500.00 | 1.000 | 4,500.00
|
| PREPARATION OF STRUCTURE | EACH | 1.000 | 4,500.00
|
| AT STA. 129+56.4 | | 1.000 | 4,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0046 4051.01 | 20.00 | 37.000 | 740.00
|
| EXCAVATION FOR BOX CULVERTS | m3 | 37.000 | 740.00
|
| | | 117.630 | 2,352.60
|
| | 0.000 | 0.00
|
| | |
|
| 0047 4101.06 | 330.00 | 80.700 | 26,631.00
|
| CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT | m3 | 80.700 | 26,631.00
|
| | | 83.756 | 27,639.48
|
| | 0.000 | 0.00
|
| | |
|
| 0048 4151.00 | 1.50 | 5,420.000 | 8,130.00
|
| REINFORCING STEEL FOR BOX CULVERT | kg | 5,420.000 | 8,130.00
|
| | | 5,648.250 | 8,472.38
|
| | 0.000 | 0.00
|
| | |
|
| 4030 4976.05 | 12,695.03 | 0.000 | 0.00
|
| ADDITIONAL WORK | LS | 1.000 | 12,695.03
|
| REPAIR OF BOX CULVERT 129+56 | | 1.000 | 12,695.03
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 4A CULVERT AT STA. 129+56.4 | | Contracted | 45,251.00
|
| | Current | 57,946.03
|
| | In place | 60,909.49
|
| | This Estimate | 735.00
|
| | |
|
| GROUP 5 SEEDING | | |
|
| 0049 L001.01 | 1,300.00 | 9.000 | 11,700.00
|
| SEEDING, TYPE A | ha | 22.654 | 29,450.20
|
| | | 22.654 | 29,450.20
|
| | 0.000 | 0.00
|
| | |
|
| 0050 L001.02 | 1,000.00 | 13.000 | 13,000.00
|
| SEEDING, TYPE B | ha | 13.000 | 13,000.00
|
| | | 8.990 | 8,990.00
|
| | 0.000 | 0.00
|
| | |
|
| 0051 L001.18 | 1,450.00 | 2.040 | 2,958.00
|
| SEEDING, TYPE WETLAND-HIGH | ha | 2.040 | 2,958.00
|
| | | 2.612 | 3,787.40
|
| | 0.000 | 0.00
|
| | |
|
| 0052 L001.19 | 2,035.00 | 3.100 | 6,308.50
|
| SEEDING, TYPE WETLAND-LOW | ha | 3.100 | 6,308.50
|
| | | 2.725 | 5,545.37
|
| | 0.000 | 0.00
|
| | |
|
| 0053 L032.75 | 85.00 | 99.000 | 8,415.00
|
| MULCH | Mg | 142.398 | 12,103.83
|
| | | 142.398 | 12,103.83
|
| | 0.000 | 0.00
|
| | |
|
| 0054 0030.50 | 1,600.00 | 1.000 | 1,600.00
|
| MOBILIZATION | LS | 1.000 | 1,600.00
|
| | | 1.000 | 1,600.00
|
| | 0.000 | 0.00
|
| | |
|
| 4029 1905.00 | 3,311.23 | 0.000 | 0.00
|
| MATERIAL DELIVERED NOT INCORPORATED | LS | 1.000 | 3,311.23
|
| TYPE "A" SEED TAKEN INTO STATE INVENTORY | | 1.000 | 3,311.23
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 5 SEEDING | | Contracted | 43,981.50
|
| | Current | 68,731.76
|
| | In place | 64,788.03
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 9 BITUMINOUS | | |
|
| 0055 L010.00 | 6.10 | 5,683.000 | 34,666.30
|
| SODDING | m2 | 5,683.000 | 34,666.30
|
| | | 3,626.913 | 22,124.17
|
| | 726.913 | 4,434.17
|
| | |
|
| 0056 W600.03 | 230.00 | 9.000 | 2,070.00
|
| ADJUST VALVE BOX TO GRADE | EACH | 9.000 | 2,070.00
|
| | | 10.000 | 2,300.00
|
| | 0.000 | 0.00
|
| | |
|
| 0057 W600.16 | 250.00 | 11.000 | 2,750.00
|
| ADJUST METER PIT TO GRADE | EACH | 11.000 | 2,750.00
|
| | | 13.000 | 3,250.00
|
| | 3.000 | 750.00
|
| | |
|
| 0058 W600.21 | 1,200.00 | 2.000 | 2,400.00
|
| ADJUST FIRE HYDRANT TO GRADE | EACH | 2.000 | 2,400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0059 0030.90 | 40,000.00 | 1.000 | 40,000.00
|
| MOBILIZATION | LS | 1.000 | 40,000.00
|
| | | 1.000 | 40,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0060 2001.00 | 12.00 | 365.000 | 4,380.00
|
| GRAVEL SURFACE COURSE | m3 | 365.000 | 4,380.00
|
| | | 208.330 | 2,499.96
|
| | 0.000 | 0.00
|
| | |
|
| 0061 2021.00 | 50.00 | 4.000 | 200.00
|
| MAILBOX POST | EACH | 4.000 | 200.00
|
| | | 8.000 | 400.00
|
| | 0.000 | 0.00
|
| | |
|
| 0062 3008.05 | 35.00 | 24.000 | 840.00
|
| TIE BARS | EACH | 24.000 | 840.00
|
| | | 17.000 | 595.00
|
| | 0.000 | 0.00
|
| | |
|
| 0063 3013.07 | 75.50 | 383.600 | 28,961.80
|
| CONCRETE CLASS 47B-25 BARRIER CURB, TYPE I | m | 383.600 | 28,961.80
|
| | | 425.605 | 32,133.19
|
| | 0.000 | 0.00
|
| | |
|
| 0064 3016.21 | 31.25 | 540.000 | 16,875.00
|
| CONCRETE CLASS 47B-20 SIDEWALKS | m2 | 540.000 | 16,875.00
|
| | | 546.513 | 17,078.54
|
| | 0.120 | 3.75
|
| | |
|
| 0065 3031.14 | 152.00 | 141.000 | 21,432.00
|
| 205 mm CONCRETE BASE COURSE | m2 | 141.000 | 21,432.00
|
| CLASS PR-25 | | 141.000 | 21,432.00
|
| | 0.000 | 0.00
|
| | |
|
| 0066 3040.11 | 152.00 | 3.600 | 547.20
|
| CONCRETE PAVEMENT REPAIR, TYPE A, FULL DEPTH | m2 | 3.600 | 547.20
|
| | | 11.130 | 1,691.76
|
| | 0.000 | 0.00
|
| | |
|
| 0067 3040.12 | 152.00 | 34.500 | 5,244.00
|
| CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH | m2 | 34.500 | 5,244.00
|
| | | 34.040 | 5,174.08
|
| | 0.000 | 0.00
|
| | |
|
| 0068 3040.13 | 152.00 | 34.000 | 5,168.00
|
| CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH | m2 | 34.000 | 5,168.00
|
| | | 17.390 | 2,643.28
|
| | 0.000 | 0.00
|
| | |
|
| 0069 3221.05 | 152.00 | 147.400 | 22,404.80
|
| CONCRETE PAVEMENT, CLASS PR-25 | m2 | 147.400 | 22,404.80
|
| JOINT REPAIR | | 230.150 | 34,982.80
|
| | 0.000 | 0.00
|
| | |
|
| 0070 4015.00 | 500.00 | 5.000 | 2,500.00
|
| ADJUST MANHOLE TO GRADE | EACH | 5.000 | 2,500.00
|
| | | 4.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0071 8029.85 | 2.25 | 75,749.000 | 170,435.25
|
| BITUMINOUS FOUNDATION COURSE 125 mm | m2 | 75,749.000 | 170,435.25
|
| | | 75,739.200 | 170,413.20
|
| | 0.000 | 0.00
|
| | |
|
| 0072 8111.00 | 350.00 | 315.620 | 110,467.00
|
| SHOULDER SUBGRADE PREPARATION | StaM | 315.620 | 110,467.00
|
| | | 315.580 | 110,453.00
|
| | 0.000 | 0.00
|
| | |
|
| 0073 9000.01 | 40.00 | 254.000 | 10,160.00
|
| ASPHALTIC CONCRETE | Mg | 0.000 | 0.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0074 9005.00 | 24.00 | 100.000 | 2,400.00
|
| ASPHALTIC CONCRETE FOR PATCHING, TYPE | Mg | 100.000 | 2,400.00
|
| SP4(12.5) | | 8.000 | 192.00
|
| | 0.000 | 0.00
|
| | |
|
| 0075 9005.23 | 12.60 | 23,925.000 | 301,455.00
|
| ASPHALTIC CONCRETE, TYPE SPS | Mg | 23,900.000 | 301,140.00
|
| | | 24,169.880 | 304,540.49
|
| | 0.000 | 0.00
|
| | |
|
| 0076 9005.45 | 20.90 | 30,440.000 | 636,196.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 22,740.000 | 475,266.00
|
| | | 22,932.430 | 479,287.79
|
| | 0.000 | 0.00
|
| | |
|
| 0077 9009.00 | 4.35 | 8,959.000 | 38,971.65
|
| PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS | m2 | 8,879.000 | 38,623.65
|
| | | 8,991.784 | 39,114.26
|
| | 0.000 | 0.00
|
| | |
|
| 0078 9021.01 | 182.50 | 1,649.160 | 300,971.70
|
| PERFORMANCE GRADED BINDER (64-22) | Mg | 1,649.160 | 300,971.70
|
| | | 1,488.662 | 271,680.81
|
| | 0.000 | 0.00
|
| | |
|
| 0079 9021.03 | 182.50 | 1,300.000 | 237,250.00
|
| PERFORMANCE GRADED BINDER (58-28) | Mg | 1,299.000 | 237,067.50
|
| | | 883.010 | 161,149.32
|
| | 0.000 | 0.00
|
| | |
|
| 0080 9030.00 | 14.00 | 491.000 | 6,874.00
|
| CONSTRUCTING ASPHALTIC CONCRETE CURB | m | 0.000 | 0.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0081 9034.00 | 1.11 | 8,959.000 | 9,944.49
|
| PREPARATION OF INTERSECTIONS AND DRIVEWAYS | m2 | 8,879.000 | 9,855.69
|
| | | 7,877.784 | 8,744.34
|
| | 0.000 | 0.00
|
| | |
|
| 0082 9053.00 | 0.28 | 121,960.000 | 34,148.80
|
| TACK COAT | L | 121,960.000 | 34,148.80
|
| | | 176,401.000 | 49,392.28
|
| | 0.000 | 0.00
|
| | |
|
| 0083 9111.00 | 2.50 | 1,894.000 | 4,735.00
|
| WATER | kL | 1,894.000 | 4,735.00
|
| | | 2,279.740 | 5,699.35
|
| | 0.000 | 0.00
|
| | |
|
| 0084 9179.24 | 1,330.00 | 158.410 | 210,685.30
|
| COLD MILLING, CLASS 4 | StaM | 158.410 | 210,685.30
|
| | | 157.820 | 209,900.60
|
| | 0.000 | 0.00
|
| | |
|
| 0085 9300.50 | 4,500.00 | 1.000 | 4,500.00
|
| ASPHALT PAVEMENT SMOOTHNESS TESTING | LS | 1.000 | 4,500.00
|
| | | 1.000 | 4,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 4004 3017.39 | 38.85 | 0.000 | 0.00
|
| CONCRETE CLASS 47B-20 MEDIAN SURFACING | m2 | 1,086.000 | 42,191.10
|
| | | 1,092.184 | 42,431.35
|
| | 0.000 | 0.00
|
| | |
|
| 4005 3012.05 | 73.50 | 0.000 | 0.00
|
| CONCRETE CLASS 47B-20 MEDIAN CURB | m | 491.000 | 36,088.50
|
| | | 491.860 | 36,151.71
|
| | 0.000 | 0.00
|
| | |
|
| 4006 9179.33 | 1.33 | 0.000 | 0.00
|
| COLD MILLING, CLASS 3 | m2 | 1,140.000 | 1,516.20
|
| Class 3 Cold Milling of Intersections | | 1,114.000 | 1,481.62
|
| | 0.000 | 0.00
|
| | |
|
| 4007 3900.22 | 217.027 | 0.000 | 0.00
|
| ADDITIONAL COST | m3 | 45.000 | 9,766.22
|
| Additional Concrete for Median Surfacing | | 40.807 | 8,856.22
|
| | 0.000 | 0.00
|
| | |
|
| 4008 6960.06 | 2.07 | 0.000 | 0.00
|
| ADDITIONAL WORK | m | 400.000 | 828.00
|
| Additional 1"x4" Expansion Material for Median Surfacing | | 491.860 | 1,018.15
|
| | 0.000 | 0.00
|
| | |
|
| 4009 3041.25 | 272.16 | 0.000 | 0.00
|
| BITUMINOUS PATCHING | Mg | 11.000 | 2,993.76
|
| | | 7.258 | 1,975.34
|
| | 0.000 | 0.00
|
| | |
|
| 4018 3900.22 | 50.20 | 0.000 | 0.00
|
| ADDITIONAL COST | m3 | 20.000 | 1,004.00
|
| ADD. CONC. FOR 205MM CONCRETE BASE COURSE PR-25 | | 19.060 | 956.81
|
| | 0.000 | 0.00
|
| | |
|
| 4019 9005.45 | 18.2875 | 0.000 | 0.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 900.000 | 16,458.75
|
| TEST STRIP DEDUCTION HIGH AIR VOID | | 900.000 | 16,458.75
|
| | 0.000 | 0.00
|
| | |
|
| 4020 9005.45 | 18.81 | 0.000 | 0.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 680.000 | 12,790.80
|
| 90% PAY | | 680.000 | 12,790.80
|
| | 0.000 | 0.00
|
| | |
|
| 4021 9005.45 | 18.862 | 0.000 | 0.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 680.000 | 12,826.16
|
| 90.25% PAY | | 680.000 | 12,826.16
|
| | 0.000 | 0.00
|
| | |
|
| 4022 9005.45 | 19.855 | 0.000 | 0.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 4,080.000 | 81,008.40
|
| 95% PAY | | 4,080.000 | 81,008.40
|
| | 0.000 | 0.00
|
| | |
|
| 4023 9005.45 | 20.252 | 0.000 | 0.00
|
| ASPHALTIC CONCRETE, TYPE SP4(12.5) | Mg | 1,360.000 | 27,542.72
|
| 96.90% PAY | | 1,360.000 | 27,542.72
|
| | 0.000 | 0.00
|
| | |
|
| 4024 3016.02 | 53.32 | 0.000 | 0.00
|
| CONCRETE SIDEWALK 155 MM | m2 | 80.000 | 4,265.60
|
| | | 58.644 | 3,126.90
|
| | 0.000 | 0.00
|
| | |
|
| 4026 9300.60 | 0.9384 | 0.000 | 0.00
|
| SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE | Mg | 13,701.540 | 12,857.53
|
| | | 14,215.500 | 13,339.83
|
| | 0.000 | 0.00
|
| | |
|
| 4027 9300.77 | 8.19 | 0.000 | 0.00
|
| SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER | Mg | 718.429 | 5,883.93
|
| PG BINDER 64-22 | | 745.378 | 6,104.64
|
| | 0.000 | 0.00
|
| | |
|
| 4028 9300.56 | 0.4577 | 0.000 | 0.00
|
| SUPERPAVE QUALITY INCENTIVE | Mg | 22,932.430 | 10,496.17
|
| | | 22,932.430 | 10,496.17
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 9 BITUMINOUS | | Contracted | 2,269,633.29
|
| | Current | 2,369,252.83
|
| | In place | 2,279,937.79
|
| | This Estimate | 5,187.92
|
| | |
|
| GROUP 10 GENERAL ITEMS | | |
|
| 0086 0001.08 | 0.50 | 40,080.000 | 20,040.00
|
| BARRICADE, TYPE II | BDAY | 40,080.000 | 20,040.00
|
| | | 7,587.000 | 3,793.50
|
| | 0.000 | 0.00
|
| | |
|
| 0087 0001.10 | 4.00 | 2,472.000 | 9,888.00
|
| BARRICADE, TYPE III | BDAY | 2,472.000 | 9,888.00
|
| | | 4,256.000 | 17,024.00
|
| | 0.000 | 0.00
|
| | |
|
| 0088 0001.30 | 4.00 | 504.000 | 2,016.00
|
| TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 504.000 | 2,016.00
|
| | | 309.000 | 1,236.00
|
| | 0.000 | 0.00
|
| | |
|
| 0089 0001.75 | 7.00 | 700.000 | 4,900.00
|
| TEMPORARY SIGN DAY | EACH | 700.000 | 4,900.00
|
| | | 1,472.000 | 10,304.00
|
| | 0.000 | 0.00
|
| | |
|
| 0090 0001.90 | 0.80 | 18,016.000 | 14,412.80
|
| SIGN DAY | EACH | 18,016.000 | 14,412.80
|
| | | 21,905.000 | 17,524.00
|
| | 0.000 | 0.00
|
| | |
|
| 0091 0002.55 | 20.00 | 315.640 | 6,312.80
|
| OVERLAY BROKEN LINES | StaM | 315.640 | 6,312.80
|
| | | 515.165 | 10,303.30
|
| | 0.000 | 0.00
|
| | |
|
| 0092 0002.60 | 20.00 | 631.280 | 12,625.60
|
| OVERLAY SOLID LINES | StaM | 631.280 | 12,625.60
|
| | | 1,296.400 | 25,928.00
|
| | 0.000 | 0.00
|
| | |
|
| 0093 0003.10 | 200.00 | 116.000 | 23,200.00
|
| FLAGGING | DAY | 116.000 | 23,200.00
|
| | | 381.000 | 76,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0094 0010.04 | 4,000.00 | 1.000 | 4,000.00
|
| FIELD OFFICE | EACH | 1.000 | 4,000.00
|
| | | 1.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0095 0030.00 | 8,000.00 | 1.000 | 8,000.00
|
| MOBILIZATION | LS | 1.000 | 8,000.00
|
| | | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0096 9110.01 | 55.00 | 80.000 | 4,400.00
|
| RENTAL OF LOADER, FULLY OPERATED | HOUR | 80.000 | 4,400.00
|
| | | 39.000 | 2,145.00
|
| | 0.000 | 0.00
|
| | |
|
| 0097 9110.02 | 55.00 | 50.000 | 2,750.00
|
| RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 50.000 | 2,750.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0098 9110.03 | 45.00 | 80.000 | 3,600.00
|
| RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 80.000 | 3,600.00
|
| | | 58.500 | 2,632.50
|
| | 0.000 | 0.00
|
| | |
|
| 0099 9110.07 | 40.00 | 80.000 | 3,200.00
|
| RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 80.000 | 3,200.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 4001 1017.50 | 88,000.00 | 0.000 | 0.00
|
| CONSTRUCTION STAKING AND SURVEYING | LS | 1.000 | 88,000.00
|
| | | 1.000 | 88,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 4032 3300.03 | -188.18 | 0.000 | 0.00
|
| DEDUCTION | LS | 1.000 | -188.18
|
| | | 1.000 | -188.18
|
| | 1.000 | -188.18
|
| | |
|
| GROUP 10 GENERAL ITEMS | | Contracted | 119,345.20
|
| | Current | 207,157.02
|
| | In place | 266,902.12
|
| | This Estimate | -188.18
|
| | |
|
| Totals for contract | | Contracted | 3,389,572.84
|
|---|
| | Current | 3,645,377.52
|
|---|
| | In place | 3,583,683.98
|
|---|
| | This Estimate | 8,208.98
|
|---|