Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0477 WESTERN ENGINEERING COMPANY, INC.
Contract ID:6860
Estimate Number:0024
Pay Period End Date:08.30.2003
Contract Location:
MAXWELL - BRADYEstimate Type:PROG
Contractor:
WESTERN ENGINEERING COMPANY, INC.Date Let:09.20.2001
1149 WEST HIGHWAY 44Date Awarded:09.27.2001
PO BOX 350Date Contract Executed:10.17.2001
Date Notice to Proceed:10.17.2001
HARLAN IA 51537Date Work Began:02.18.2002
Phone:Date Physical Work Completed:
(712)755-5191Date Accepted:
Escrow Agent:
Surety Co:
HARTFORD FIRE INSURANCE COMPANY
Counties
LINCOLN
Project Number PCT Fed State Project Number Description
60860 000  0.000 F-30-2(1018)  GR CULV SEED BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$3,583,683.98$3,575,475.00$8,208.98
$3,645,377.51Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$3,583,683.98$3,575,475.00$8,208.98
$3,389,572.84Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
98.31%Net Earnings$3,558,683.98$3,550,475.00$8,208.98
Liquidated Damages$.00-$30,120.00$30,120.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-1,995.53$-1,995.53$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$1,995.53-$32,115.53$30,120.00
Payment$3,556,688.45$3,518,359.47$38,328.98
Project ManagerDiv. Head/Dist. Eng.
Brinker, Gary09.02.2003Thayer, Gary09.02.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.03.2003
Controller Div. Processed
Burling, Laurie09.03.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 200.0022.0004,400.00
COVER CROP SEEDING ha 23.0004,600.00
0.0000.00
0.0000.00

0002                          L020.00 3.501,710.0005,985.00
EROSION CONTROL m2 1,710.0005,985.00
1,771.6506,200.78
0.0000.00

0003                          L022.25 20.001,037.00020,740.00
FABRIC SILT FENCE, TYPE COIR FIBER m 1,037.00020,740.00
0.0000.00
0.0000.00

0004                          0030.10 10,700.001.00010,700.00
MOBILIZATION LS 1.00010,700.00
1.00010,700.00
0.0000.00

0005                          1000.00 625.009.0005,625.00
LARGE TREE REMOVAL EACH9.0005,625.00
15.0009,375.00
0.0000.00

0006                          1009.00 7,000.001.0007,000.00
GENERAL CLEARING AND GRUBBING LS 1.0007,000.00
1.0007,000.00
0.0000.00

0007                          1010.00 3.1558,956.000185,711.40
EXCAVATION m3 71,881.000226,425.15
71,871.690226,395.82
0.0000.00

0008                          1010.10 7.5042,359.000317,692.50
EXCAVATION, BORROW m3 42,359.001317,692.51
42,359.000317,692.50
0.0000.00

0009                          1011.00 2.007,599.00015,198.00
WATER kL 7,599.00015,198.00
0.0000.00
0.0000.00

0010                          1021.10 2.5011.00027.50
REMOVE DELINEATOR UNITS EACH11.00027.50
0.0000.00
0.0000.00

0011                          1041.00 0.5551,300.00028,215.00
SALVAGING AND PLACING TOPSOIL m2 51,300.00028,215.00
53,376.00029,356.80
0.0000.00

0012                          1042.00 0.859,955.0008,461.75
SALVAGING AND PLACING HYDRIC SOIL m2 9,955.0008,461.75
9,828.8608,354.53
0.0000.00

0013                          1043.50 2.302,621.0006,028.30
RIPRAP FILTER FABRIC m2 2,621.0006,028.30
1,825.0604,197.64
0.0000.00

0014                          1101.00 3.502,545.0008,907.50
REMOVE PAVEMENT m2 1,405.0004,917.50
1,199.0004,196.50
0.0000.00

0015                          1102.00 3.5010,527.00036,844.50
REMOVE ASPHALT SURFACE m2 10,527.00036,844.50
10,851.04437,978.66
0.0000.00

0016                          1106.00 3.502,691.0009,418.50
REMOVE DRIVEWAY m2 2,691.0009,418.50
3,021.49210,575.23
0.0000.00

0017                          1107.00 2.00533.0001,066.00
REMOVE WALK m2 533.0001,066.00
494.317988.63
0.1200.24

0018                          1705.42 190.0030.0005,700.00
1050 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE, TYPE 2,3,4OR 5 m 30.0005,700.00
43.9008,341.00
0.0000.00

0019                          6104.00 9.6568.000656.20
BROKEN CONCRETE RIPRAP Mg 68.000656.20
266.5402,572.11
0.0000.00

0020                          6105.02 49.001,845.00090,405.00
ROCK RIPRAP, TYPE B Mg 0.0000.00
0.0000.00
0.0000.00

0021                          7017.00 11.0031.400345.40
REMOVE GUARDRAIL m 31.400345.40
30.700337.70
0.0000.00

0022                          9110.09 70.0015.0001,050.00
RENTAL OF TRACTOR AND SCRAPER, FULLY OPERATED HOUR15.0001,050.00
15.0001,050.00
0.0000.00

4002                          1012.00 66.150.0000.00
RIGHT-OF-WAY MARKER EACH163.00010,782.45
159.00010,517.85
0.0000.00

4003                          1013.00 49.350.0000.00
RESET RIGHT-OF-WAY MARKER EACH10.000493.50
2.00098.70
0.0000.00

4010                          1305.24 78.750.0000.00
600 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE m 28.0002,205.00
42.6703,360.26
0.0000.00

4011                          1300.30 103.950.0000.00
750 mm DRIVEWAY CULVERT PIPE m 57.0005,925.15
56.6105,884.61
0.0000.00

4012                          1300.48 229.950.0000.00
1200 mm DRIVEWAY CULVERT PIPE m 14.6003,357.27
14.6303,364.17
0.0000.00

4025                          6104.00 22.300.0000.00
BROKEN CONCRETE RIPRAP Mg 1,845.00041,143.50
BROKEN CONCRETE RIPRAP HAULED FROM NORTH PLATTE STOCKPILE SITE 1,506.06333,585.20
0.0000.00

GROUP 1 GRADINGContracted770,177.55
Current780,603.18
In place742,123.69
This Estimate0.24

GROUP 4 CULVERTS
0023                          P300.36 99.0034.8003,445.20
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 51.5005,098.50
33.1403,280.86
0.0000.00

0024                          P372.36 116.0069.5008,062.00
900 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2,4 OR 5 m 53.7006,229.20
48.1405,584.24
0.0000.00

0025                          P500.24 67.0014.500971.50
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 14.500971.50
14.640980.88
0.0000.00

0026                          P500.36 99.0043.3004,286.70
900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 43.3004,286.70
40.8704,046.13
0.0000.00

0027                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0028                          4035.00 100.002.000200.00
REMOVE FLARED-END SECTION EACH2.000200.00
1.000100.00
0.0000.00

0029                          4040.00 100.005.000500.00
REMOVE HEADWALLS FROM CULVERTS EACH6.000600.00
7.000700.00
0.0000.00

0030                          4044.00 1,525.001.0001,525.00
PREPARATION OF STRUCTURE EACH1.0001,525.00
AT STA. 23+74.65 1.0001,525.00
0.0000.00

0031                          4044.01 2,525.001.0002,525.00
PREPARATION OF STRUCTURE EACH1.0002,525.00
AT STA. 68+22.8 1.0002,525.00
0.0000.00

0032                          4044.02 2,525.001.0002,525.00
PREPARATION OF STRUCTURE EACH1.0002,525.00
AT STA. 94+21.7 1.0002,525.00
0.0000.00

0033                          4045.00 3,025.001.0003,025.00
REMOVE STRUCTURE EACH1.0003,025.00
AT STA. 16+38.2-10.4 m RT. 1.0003,025.00
0.0000.00

0034                          4045.01 3,025.001.0003,025.00
REMOVE STRUCTURE EACH1.0003,025.00
AT STA. 57+64.5-14.1 m LT. 1.0003,025.00
0.0000.00

0035                          4045.02 3,025.001.0003,025.00
REMOVE STRUCTURE EACH1.0003,025.00
AT STA. 74+70.18 1.0003,025.00
0.0000.00

0036                          4045.03 3,025.001.0003,025.00
REMOVE STRUCTURE EACH1.0003,025.00
AT STA. 92+21.3 1.0003,025.00
0.0000.00

0037                          4050.01 20.00455.0009,100.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 430.0008,600.00
429.8108,596.20
0.0000.00

0038                          4051.01 20.00205.0004,100.00
EXCAVATION FOR BOX CULVERTS m3 355.0007,100.00
636.67412,733.48
123.7002,474.00

0039                          4101.06 330.00200.94066,310.20
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 230.15075,949.50
239.24878,951.84
0.0000.00

0040                          4151.00 1.6511,578.00019,103.70
REINFORCING STEEL FOR BOX CULVERT kg 13,167.00021,725.55
14,340.53923,661.90
0.0000.00

0041                          4310.24 180.002.000360.00
600 mm FLARED-END SECTION EACH5.000900.00
2.000360.00
0.0000.00

0042                          4310.36 255.006.0001,530.00
900 mm FLARED-END SECTION EACH6.0001,530.00
6.0001,530.00
0.0000.00

0043                          4320.36 255.008.0002,040.00
900 mm ROUND EQUIVALENT FLARED-END SECTION EACH4.0001,020.00
4.0001,020.00
0.0000.00

4013                          4450.24 199.500.0000.00
600 mm REINFORCED CONCRETE PIPE m 7.0001,396.50
7.0001,396.50
0.0000.00

4014                          4460.24 577.500.0000.00
600 mm CONCRETE FLARED END SECTION EACH1.000577.50
1.000577.50
0.0000.00

4015                          4305.24 78.750.0000.00
600 mm ROUND EQUIVALENT CULVERT PIPE m 33.5002,638.13
33.5202,639.70
0.0000.00

4016                          4320.24 262.500.0000.00
600 mm ROUND EQUIVALENT FLARED END SECTION EACH2.000525.00
2.000525.00
0.0000.00

4017                          0095.00 320.250.0000.00
ADDITIONAL FREIGHT COSTS LS 1.000320.25
FREIGHT COSTS FOR REINFORCED CONCRETE CULVERT AND F.E.S. 1.000320.25
0.0000.00

4031                          4976.05 843.380.0000.00
ADDITIONAL WORK LS 1.000843.38
1.000843.38
0.0000.00

GROUP 4 CULVERTSContracted141,184.30
Current161,686.70
In place169,022.86
This Estimate2,474.00

GROUP 4A CULVERT AT STA. 129+56.4
0044                          0030.40 5,250.001.0005,250.00
MOBILIZATION LS 1.0005,250.00
1.0005,250.00
0.140735.00

0045                          4044.03 4,500.001.0004,500.00
PREPARATION OF STRUCTURE EACH1.0004,500.00
AT STA. 129+56.4 1.0004,500.00
0.0000.00

0046                          4051.01 20.0037.000740.00
EXCAVATION FOR BOX CULVERTS m3 37.000740.00
117.6302,352.60
0.0000.00

0047                          4101.06 330.0080.70026,631.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 80.70026,631.00
83.75627,639.48
0.0000.00

0048                          4151.00 1.505,420.0008,130.00
REINFORCING STEEL FOR BOX CULVERT kg 5,420.0008,130.00
5,648.2508,472.38
0.0000.00

4030                          4976.05 12,695.030.0000.00
ADDITIONAL WORK LS 1.00012,695.03
REPAIR OF BOX CULVERT 129+56 1.00012,695.03
0.0000.00

GROUP 4A CULVERT AT STA. 129+56.4Contracted45,251.00
Current57,946.03
In place60,909.49
This Estimate735.00

GROUP 5 SEEDING
0049                          L001.01 1,300.009.00011,700.00
SEEDING, TYPE A ha 22.65429,450.20
22.65429,450.20
0.0000.00

0050                          L001.02 1,000.0013.00013,000.00
SEEDING, TYPE B ha 13.00013,000.00
8.9908,990.00
0.0000.00

0051                          L001.18 1,450.002.0402,958.00
SEEDING, TYPE WETLAND-HIGH ha 2.0402,958.00
2.6123,787.40
0.0000.00

0052                          L001.19 2,035.003.1006,308.50
SEEDING, TYPE WETLAND-LOW ha 3.1006,308.50
2.7255,545.37
0.0000.00

0053                          L032.75 85.0099.0008,415.00
MULCH Mg 142.39812,103.83
142.39812,103.83
0.0000.00

0054                          0030.50 1,600.001.0001,600.00
MOBILIZATION LS 1.0001,600.00
1.0001,600.00
0.0000.00

4029                          1905.00 3,311.230.0000.00
MATERIAL DELIVERED NOT INCORPORATED LS 1.0003,311.23
TYPE "A" SEED TAKEN INTO STATE INVENTORY 1.0003,311.23
0.0000.00

GROUP 5 SEEDINGContracted43,981.50
Current68,731.76
In place64,788.03
This Estimate0.00

GROUP 9 BITUMINOUS
0055                          L010.00 6.105,683.00034,666.30
SODDING m2 5,683.00034,666.30
3,626.91322,124.17
726.9134,434.17

0056                          W600.03 230.009.0002,070.00
ADJUST VALVE BOX TO GRADE EACH9.0002,070.00
10.0002,300.00
0.0000.00

0057                          W600.16 250.0011.0002,750.00
ADJUST METER PIT TO GRADE EACH11.0002,750.00
13.0003,250.00
3.000750.00

0058                          W600.21 1,200.002.0002,400.00
ADJUST FIRE HYDRANT TO GRADE EACH2.0002,400.00
0.0000.00
0.0000.00

0059                          0030.90 40,000.001.00040,000.00
MOBILIZATION LS 1.00040,000.00
1.00040,000.00
0.0000.00

0060                          2001.00 12.00365.0004,380.00
GRAVEL SURFACE COURSE m3 365.0004,380.00
208.3302,499.96
0.0000.00

0061                          2021.00 50.004.000200.00
MAILBOX POST EACH4.000200.00
8.000400.00
0.0000.00

0062                          3008.05 35.0024.000840.00
TIE BARS EACH24.000840.00
17.000595.00
0.0000.00

0063                          3013.07 75.50383.60028,961.80
CONCRETE CLASS 47B-25 BARRIER CURB, TYPE I m 383.60028,961.80
425.60532,133.19
0.0000.00

0064                          3016.21 31.25540.00016,875.00
CONCRETE CLASS 47B-20 SIDEWALKS m2 540.00016,875.00
546.51317,078.54
0.1203.75

0065                          3031.14 152.00141.00021,432.00
205 mm CONCRETE BASE COURSE m2 141.00021,432.00
CLASS PR-25 141.00021,432.00
0.0000.00

0066                          3040.11 152.003.600547.20
CONCRETE PAVEMENT REPAIR, TYPE A, FULL DEPTH m2 3.600547.20
11.1301,691.76
0.0000.00

0067                          3040.12 152.0034.5005,244.00
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH m2 34.5005,244.00
34.0405,174.08
0.0000.00

0068                          3040.13 152.0034.0005,168.00
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH m2 34.0005,168.00
17.3902,643.28
0.0000.00

0069                          3221.05 152.00147.40022,404.80
CONCRETE PAVEMENT, CLASS PR-25 m2 147.40022,404.80
JOINT REPAIR 230.15034,982.80
0.0000.00

0070                          4015.00 500.005.0002,500.00
ADJUST MANHOLE TO GRADE EACH5.0002,500.00
4.0002,000.00
0.0000.00

0071                          8029.85 2.2575,749.000170,435.25
BITUMINOUS FOUNDATION COURSE 125 mm m2 75,749.000170,435.25
75,739.200170,413.20
0.0000.00

0072                          8111.00 350.00315.620110,467.00
SHOULDER SUBGRADE PREPARATION StaM315.620110,467.00
315.580110,453.00
0.0000.00

0073                          9000.01 40.00254.00010,160.00
ASPHALTIC CONCRETE Mg 0.0000.00
0.0000.00
0.0000.00

0074                          9005.00 24.00100.0002,400.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0002,400.00
SP4(12.5) 8.000192.00
0.0000.00

0075                          9005.23 12.6023,925.000301,455.00
ASPHALTIC CONCRETE, TYPE SPS Mg 23,900.000301,140.00
24,169.880304,540.49
0.0000.00

0076                          9005.45 20.9030,440.000636,196.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 22,740.000475,266.00
22,932.430479,287.79
0.0000.00

0077                          9009.00 4.358,959.00038,971.65
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 8,879.00038,623.65
8,991.78439,114.26
0.0000.00

0078                          9021.01 182.501,649.160300,971.70
PERFORMANCE GRADED BINDER (64-22) Mg 1,649.160300,971.70
1,488.662271,680.81
0.0000.00

0079                          9021.03 182.501,300.000237,250.00
PERFORMANCE GRADED BINDER (58-28) Mg 1,299.000237,067.50
883.010161,149.32
0.0000.00

0080                          9030.00 14.00491.0006,874.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 0.0000.00
0.0000.00
0.0000.00

0081                          9034.00 1.118,959.0009,944.49
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 8,879.0009,855.69
7,877.7848,744.34
0.0000.00

0082                          9053.00 0.28121,960.00034,148.80
TACK COAT L 121,960.00034,148.80
176,401.00049,392.28
0.0000.00

0083                          9111.00 2.501,894.0004,735.00
WATER kL 1,894.0004,735.00
2,279.7405,699.35
0.0000.00

0084                          9179.24 1,330.00158.410210,685.30
COLD MILLING, CLASS 4 StaM158.410210,685.30
157.820209,900.60
0.0000.00

0085                          9300.50 4,500.001.0004,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0004,500.00
1.0004,500.00
0.0000.00

4004                          3017.39 38.850.0000.00
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 1,086.00042,191.10
1,092.18442,431.35
0.0000.00

4005                          3012.05 73.500.0000.00
CONCRETE CLASS 47B-20 MEDIAN CURB m 491.00036,088.50
491.86036,151.71
0.0000.00

4006                          9179.33 1.330.0000.00
COLD MILLING, CLASS 3 m2 1,140.0001,516.20
Class 3 Cold Milling of Intersections 1,114.0001,481.62
0.0000.00

4007                          3900.22 217.0270.0000.00
ADDITIONAL COST m3 45.0009,766.22
Additional Concrete for Median Surfacing 40.8078,856.22
0.0000.00

4008                          6960.06 2.070.0000.00
ADDITIONAL WORK m 400.000828.00
Additional 1"x4" Expansion Material for Median Surfacing 491.8601,018.15
0.0000.00

4009                          3041.25 272.160.0000.00
BITUMINOUS PATCHING Mg 11.0002,993.76
7.2581,975.34
0.0000.00

4018                          3900.22 50.200.0000.00
ADDITIONAL COST m3 20.0001,004.00
ADD. CONC. FOR 205MM CONCRETE BASE COURSE PR-25 19.060956.81
0.0000.00

4019                          9005.45 18.28750.0000.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 900.00016,458.75
TEST STRIP DEDUCTION HIGH AIR VOID 900.00016,458.75
0.0000.00

4020                          9005.45 18.810.0000.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 680.00012,790.80
90% PAY 680.00012,790.80
0.0000.00

4021                          9005.45 18.8620.0000.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 680.00012,826.16
90.25% PAY 680.00012,826.16
0.0000.00

4022                          9005.45 19.8550.0000.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 4,080.00081,008.40
95% PAY 4,080.00081,008.40
0.0000.00

4023                          9005.45 20.2520.0000.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 1,360.00027,542.72
96.90% PAY 1,360.00027,542.72
0.0000.00

4024                          3016.02 53.320.0000.00
CONCRETE SIDEWALK 155 MM m2 80.0004,265.60
58.6443,126.90
0.0000.00

4026                          9300.60 0.93840.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 13,701.54012,857.53
14,215.50013,339.83
0.0000.00

4027                          9300.77 8.190.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 718.4295,883.93
PG BINDER 64-22 745.3786,104.64
0.0000.00

4028                          9300.56 0.45770.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 22,932.43010,496.17
22,932.43010,496.17
0.0000.00

GROUP 9 BITUMINOUSContracted2,269,633.29
Current2,369,252.83
In place2,279,937.79
This Estimate5,187.92

GROUP 10 GENERAL ITEMS
0086                          0001.08 0.5040,080.00020,040.00
BARRICADE, TYPE II BDAY40,080.00020,040.00
7,587.0003,793.50
0.0000.00

0087                          0001.10 4.002,472.0009,888.00
BARRICADE, TYPE III BDAY2,472.0009,888.00
4,256.00017,024.00
0.0000.00

0088                          0001.30 4.00504.0002,016.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY504.0002,016.00
309.0001,236.00
0.0000.00

0089                          0001.75 7.00700.0004,900.00
TEMPORARY SIGN DAY EACH700.0004,900.00
1,472.00010,304.00
0.0000.00

0090                          0001.90 0.8018,016.00014,412.80
SIGN DAY EACH18,016.00014,412.80
21,905.00017,524.00
0.0000.00

0091                          0002.55 20.00315.6406,312.80
OVERLAY BROKEN LINES StaM315.6406,312.80
515.16510,303.30
0.0000.00

0092                          0002.60 20.00631.28012,625.60
OVERLAY SOLID LINES StaM631.28012,625.60
1,296.40025,928.00
0.0000.00

0093                          0003.10 200.00116.00023,200.00
FLAGGING DAY 116.00023,200.00
381.00076,200.00
0.0000.00

0094                          0010.04 4,000.001.0004,000.00
FIELD OFFICE EACH1.0004,000.00
1.0004,000.00
0.0000.00

0095                          0030.00 8,000.001.0008,000.00
MOBILIZATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0096                          9110.01 55.0080.0004,400.00
RENTAL OF LOADER, FULLY OPERATED HOUR80.0004,400.00
39.0002,145.00
0.0000.00

0097                          9110.02 55.0050.0002,750.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR50.0002,750.00
0.0000.00
0.0000.00

0098                          9110.03 45.0080.0003,600.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR80.0003,600.00
58.5002,632.50
0.0000.00

0099                          9110.07 40.0080.0003,200.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR80.0003,200.00
0.0000.00
0.0000.00

4001                          1017.50 88,000.000.0000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00088,000.00
1.00088,000.00
0.0000.00

4032                          3300.03 -188.180.0000.00
DEDUCTION LS 1.000-188.18
1.000-188.18
1.000-188.18

GROUP 10 GENERAL ITEMSContracted119,345.20
Current207,157.02
In place266,902.12
This Estimate-188.18

Totals for contractContracted3,389,572.84
Current3,645,377.52
In place3,583,683.98
This Estimate8,208.98