Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2853 SIMON CONTRACTORS AND SUBSIDIARIES
Contract ID:6765
Estimate Number:0028
Pay Period End Date:05.04.2002
Contract Location:
HERSHEY NORTHEstimate Type:PROG
Contractor:
SIMON CONTRACTORS AND SUBSIDIARIESDate Let:01.11.2001
4819 S INDUSTRIAL SERVICE RDDate Awarded:01.25.2001
PO BOX 347Date Contract Executed:02.26.2001
Date Notice to Proceed:02.26.2001
CHEYENNE WY 82003Date Work Began:04.02.2001
Phone:Date Physical Work Completed:
(307)632-7900Date Accepted:
Escrow Agent:
Surety Co:
LIBERTY MUTUAL INSURANCE COMPANY
Counties
LINCOLN
Project Number PCT Fed State Project Number Description
60765 000  0.000 STPE-BR-1410(2)  GR BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,491,628.48$1,442,373.49$49,254.99
$1,487,204.34Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,491,628.48$1,442,373.49$49,254.99
$1,475,433.95Retainage$-14,916.28$-14,423.73$-492.55
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
100.30%Net Earnings$1,476,712.20$1,427,949.76$48,762.44
Liquidated Damages-$8,528.00-$7,216.00-$1,312.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-185.81$-185.81$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$8,713.81-$7,401.81-$1,312.00
Payment$1,467,998.39$1,420,547.95$47,450.44
Project ManagerDiv. Head/Dist. Eng.
Shaner, Kitty05.06.2002Thayer, Gary05.07.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve05.07.2002
Controller Div. Processed
Burling, Laurie05.07.2002
Detailed breakdown of stockpiled materials
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00256011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Initial Payment40,738.2896619546
Total for estimate 0012:40,738.28
Est Nbr:0015
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00256011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Initial Payment95,055.9896780345
3-A Beams
Total for estimate 0015:95,055.98
Est Nbr:0020
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00256011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-4,073.8396619546
S.P. Adjustment-4,073.8396780345
3-A Beams
Total for estimate 0020:-8,147.66
Est Nbr:0021
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00256011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-2,715.8996619546
S.P. Adjustment-2,715.8996780345
3-A Beams
Total for estimate 0021:-5,431.78
Est Nbr:0027
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00256011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Closure-33,948.5696619546
S.P. Closure-88,266.2696780345
3-A Beams
Total for estimate 0027:-122,214.82
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 224.008.0001,792.00
COVER CROP SEEDING ACRE8.0001,792.00
0.0000.00
0.0000.00

0002                          0030.10 5,438.721.0005,438.72
MOBILIZATION LS 1.0005,438.72
1.0005,438.72
0.0000.00

0003                          1000.00 62.10155.0009,625.50
LARGE TREE REMOVAL EACH155.0009,625.50
120.0007,452.00
-18.000-1,117.80

0004                          1011.00 10.0495.000953.80
WATER MGAL95.000953.80
0.0000.00
0.0000.00

0005                          1030.00 8.3713,325.000111,530.25
EARTHWORK MEASURED IN EMBANKMENT CY 13,325.000111,530.25
13,325.000111,530.25
0.0000.00

0006                          1040.00 0.4338,720.00016,649.60
SLOPE PROTECTION SY 38,720.00016,649.60
38,720.00016,649.60
38,720.00016,649.60

0007                          1040.06 95.2039.0003,712.80
SLOPE PROTECTION MULCH TON 39.0003,712.80
40.0003,808.00
40.0003,808.00

0008                          4045.00 1,176.001.0001,176.00
REMOVE STRUCTURE EACH1.0001,176.00
AT STA. 14+77 1.0001,176.00
0.0000.00

0009                          4050.01 22.409.000201.60
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS CY 9.000201.60
9.000201.60
0.0000.00

0010                          4300.36 50.40162.0008,164.80
36" CULVERT PIPE LF 162.0008,164.80
162.0008,164.80
0.0000.00

0011                          4500.42 100.8072.0007,257.60
42" ROUND EQUIVALENT REINFORCED CONCRETE PIPE LF 72.0007,257.60
75.0007,560.00
0.0000.00

4002                          2009.10 395.400.0000.00
GRAVEL EMBEDMENT STA 14.0005,535.60
14.0005,535.60
0.0000.00

90                           L001.19 2,362.500.0000.00
SEEDING, TYPE WETLAND-LOW ACRE1.0002,362.50
1.0002,362.50
1.0002,362.50

GROUP 1 GRADINGContracted166,502.67
Current174,400.77
In place169,879.07
This Estimate21,702.30

GROUP 6 BRIDGE AT STA. 25+10
0012                          0030.60 18,200.001.00018,200.00
MOBILIZATION LS 1.00018,200.00
1.00018,200.00
0.0000.00

0013                          1010.01 8.401,320.00011,088.00
EXCAVATION (ESTABLISHED QUANTITY) CY 1,320.00011,088.00
1,320.00011,088.00
0.0000.00

0014                          3050.15 256.4453.00013,591.32
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 CY 53.00013,591.32
53.00013,591.32
0.0000.00

0015                          3051.10 0.645,710.0003,654.40
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 5,710.0003,654.40
5,710.0003,654.40
0.0000.00

0016                          6000.10 5,768.001.0005,768.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,768.00
1.0005,768.00
0.0000.00

0017                          6000.11 5,768.001.0005,768.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,768.00
1.0005,768.00
0.0000.00

0018                          6000.62 18,480.001.00018,480.00
PIER NO.3 EXCAVATION LS 1.00018,480.00
1.00018,480.00
0.0000.00

0019                          6001.50 10,752.001.00010,752.00
BENT NO.1 EXCAVATION LS 1.00010,752.00
1.00010,752.00
0.0000.00

0020                          6001.51 10,752.001.00010,752.00
BENT NO.2 EXCAVATION LS 1.00010,752.00
1.00010,752.00
0.0000.00

0021                          6001.53 10,752.001.00010,752.00
BENT NO.4 EXCAVATION LS 1.00010,752.00
1.00010,752.00
0.0000.00

0022                          6005.78 840.008.0006,720.00
EXPANSION BEARING, TFE TYPE EACH8.0006,720.00
8.0006,720.00
4.0003,360.00

0023                          6010.22 298.18256.60076,512.99
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 256.60076,512.99
256.60076,512.99
0.0000.00

0024                          6010.26 317.08397.900126,166.13
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 397.900126,166.13
397.900126,166.13
0.0000.00

0025                          6011.11 188,585.601.000188,585.60
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000188,585.60
AT STA. 25+10 1.000188,585.60
0.0000.00

0026                          6040.00 40,875.521.00040,875.52
REMOVE STRUCTURE EACH1.00040,875.52
AT STA. 24+29 1.00040,875.52
0.0000.00

0027                          6080.00 1.472,320.0003,410.40
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 2,320.0003,410.40
1,300.0001,911.00
0.0000.00

0028                          6105.02 43.09114.0004,912.26
ROCK RIPRAP, TYPE B TON 114.0004,912.26
117.0005,041.53
-44.000-1,895.96

0029                          6131.50 0.6289,870.00055,719.40
EPOXY COATED REINFORCING STEEL LB 89,870.00055,719.40
89,870.00055,719.40
0.0000.00

0030                          6210.12 20.471,900.00038,893.00
HP 10"X42# STEEL PILING LF 1,900.00038,893.00
1,825.46037,367.17
0.0000.00

0031                          6251.00 1,691.204.0006,764.80
TEST PILE EACH4.0006,764.80
5.0008,456.00
0.0000.00

0032                          6610.45 117.0556.5006,613.33
STRIP SEALS LF 56.5006,613.33
56.5006,613.33
0.0000.00

0033                          8091.00 17.51103.0001,803.53
GRANULAR BACKFILL CY 103.0001,803.53
103.0001,803.53
7.000122.57

090                           6210.59 12.280.0000.00
PILE CUT-OFF LF 1.50018.42
10"X42# Pile cut-off 49.540608.35
0.0000.00

4001                          6210.59 11.350.0000.00
PILE CUT-OFF LF 94.7601,075.53
HP 8"36# Steel Piling 94.7601,075.53
0.0000.00

4003                          6960.03 750.000.0000.00
ADDITIONAL SOIL-SETUP FACTOR EACH1.000750.00
Soil set up on bent No. 1 as requested by Omar Qudus- Bridgedivision 2.0001,500.00
0.0000.00

GROUP 6 BRIDGE AT STA. 25+10Contracted665,782.68
Current667,626.62
In place667,761.80
This Estimate1,586.61

GROUP 6A BRIDGE AT STA. 40+25
0034                          0030.60 11,132.801.00011,132.80
MOBILIZATION LS 1.00011,132.80
1.00011,132.80
0.0000.00

0035                          3050.15 256.2752.90013,556.68
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 CY 52.90013,556.68
52.90013,556.68
0.0000.00

0036                          3051.10 0.645,670.0003,628.80
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 5,670.0003,628.80
5,670.0003,628.80
0.0000.00

0037                          6000.10 3,808.001.0003,808.00
ABUTMENT NO.1 EXCAVATION LS 1.0003,808.00
1.0003,808.00
0.0000.00

0038                          6000.11 3,808.001.0003,808.00
ABUTMENT NO.2 EXCAVATION LS 1.0003,808.00
1.0003,808.00
0.0000.00

0039                          6001.50 952.001.000952.00
BENT NO.1 EXCAVATION LS 1.000952.00
1.000952.00
0.0000.00

0040                          6001.51 952.001.000952.00
BENT NO.2 EXCAVATION LS 1.000952.00
1.000952.00
0.0000.00

0041                          6005.78 798.008.0006,384.00
EXPANSION BEARING, TFE TYPE EACH8.0006,384.00
8.0006,384.00
0.0000.00

0042                          6010.22 309.4787.40027,047.68
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 87.40027,047.68
87.40027,047.68
0.0000.00

0043                          6010.26 319.61169.50054,173.90
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 169.50054,173.90
169.50054,173.89
0.0000.00

0044                          6011.11 77,644.001.00077,644.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00077,644.00
AT STA. 40+25 1.00077,644.00
0.0000.00

0045                          6040.00 37,296.001.00037,296.00
REMOVE STRUCTURE EACH1.00037,296.00
AT STA. 40+55 1.00037,296.00
0.0000.00

0046                          6080.00 1.781,300.0002,314.00
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 1,300.0002,314.00
280.000498.40
0.0000.00

0047                          6105.02 51.8927.0001,401.03
ROCK RIPRAP, TYPE B TON 27.0001,401.03
27.0001,401.03
0.0000.00

0048                          6131.50 0.6537,590.00024,433.50
EPOXY COATED REINFORCING STEEL LB 37,590.00024,433.50
37,590.00024,433.50
0.0000.00

0049                          6210.12 25.30930.00023,529.00
HP 10"X42# STEEL PILING LF 930.00023,529.00
930.00023,529.00
0.0000.00

0050                          6610.45 117.0556.5006,613.33
STRIP SEALS LF 56.5006,613.33
56.5006,613.33
0.0000.00

0051                          8091.00 17.51103.0001,803.53
GRANULAR BACKFILL CY 103.0001,803.53
103.0001,803.53
0.0000.00

0088                          6210.59 6.640.0000.00
PILE CUT-OFF LF 200.0001,328.00
200.0001,328.00
0.0000.00

89                           6210.61 102.350.0000.00
PILE SPLICE EACH1.000102.35
Pile splice HP 10"X42# steel piling 1.000102.35
1.000102.35

GROUP 6A BRIDGE AT STA. 40+25Contracted300,478.24
Current301,908.59
In place300,092.99
This Estimate102.35

GROUP 6B BRIDGE AT STA. 25+10 - 70' LT.
0052                          0030.60 6,440.001.0006,440.00
MOBILIZATION LS 1.0006,440.00
1.0006,440.00
0.0000.00

0053                          6041.00 17,976.001.00017,976.00
REMOVE DETOUR BRIDGE EACH1.00017,976.00
AT STA. 25+10 - 70' LT. 1.00017,976.00
0.2003,595.20

0054                          6052.00 26,930.401.00026,930.40
ERECTING DETOUR BRIDGE EACH1.00026,930.40
AT STA. 25+10 - 70' LT. 1.00026,930.40
0.0000.00

0055                          6080.00 0.995,160.0005,108.40
STRUCTURAL STEEL FOR SUBSTRUCTURE LB 5,160.0005,108.40
5,660.0005,603.40
0.0000.00

0056                          6210.11 18.921,220.00023,082.40
HP 8"X36# STEEL PILING LF 1,220.00023,082.40
1,125.24021,289.54
0.0000.00

0057                          6310.00 11.071,760.00019,483.20
STEEL SHEET PILING SF 1,760.00019,483.20
1,560.00017,269.20
0.0000.00

GROUP 6B BRIDGE AT STA. 25+10 - 70' LT.Contracted99,020.40
Current99,020.40
In place95,508.54
This Estimate3,595.20

GROUP 7 GUARDRAIL
0058                          0030.70 1,411.201.0001,411.20
MOBILIZATION LS 1.0001,411.20
1.0001,411.20
1.0001,411.20

0059                          7020.00 1,176.008.0009,408.00
BRIDGE APPROACH SECTIONS EACH8.0009,408.00
8.0009,408.00
8.0009,408.00

0060                          7021.45 1,148.008.0009,184.00
BREAKAWAY CABLE TERMINAL EACH8.0009,184.00
8.0009,184.00
8.0009,184.00

GROUP 7 GUARDRAILContracted20,003.20
Current20,003.20
In place20,003.20
This Estimate20,003.20

GROUP 9 BITUMINOUS
0061                          0030.90 25,399.361.00025,399.36
MOBILIZATION LS 1.00025,399.36
1.00025,399.36
0.0000.00

0062                          2001.00 12.91170.0002,194.70
GRAVEL SURFACE COURSE CY 170.0002,194.70
170.0002,194.70
0.0000.00

0063                          2020.00 6.3732.000203.84
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS SY 32.000203.84
32.000203.84
0.0000.00

0064                          2021.00 113.121.000113.12
MAILBOX POST EACH1.000113.12
1.000113.12
0.0000.00

0065                          9005.00 35.56100.0003,556.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE TON 100.0003,556.00
SP2(0.5) 60.0002,133.60
0.0000.00

0066                          9005.30 24.203,130.00075,746.00
ASPHALTIC CONCRETE, TYPE SP2(0.5) TON 3,130.00075,746.00
3,298.60079,826.12
0.0000.00

0067                          9021.01 239.46174.42041,766.61
PERFORMANCE GRADED BINDER (64-22) TON 174.42041,766.61
169.26940,533.15
0.0000.00

0068                          9053.00 0.911,970.0001,792.70
TACK COAT GAL 1,970.0001,792.70
1,170.0001,064.70
0.0000.00

0069                          9110.01 64.9610.000649.60
RENTAL OF LOADER, FULLY OPERATED HOUR10.000649.60
0.0000.00
0.0000.00

0070                          9110.02 58.4610.000584.60
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000584.60
0.0000.00
0.0000.00

0071                          9110.03 46.8210.000468.20
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000468.20
0.0000.00
0.0000.00

0072                          9110.07 46.2610.000462.60
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000462.60
0.0000.00
0.0000.00

0073                          9111.00 10.06146.0001,468.76
WATER MGAL146.0001,468.76
0.0000.00
0.0000.00

0074                          9170.00 21.3993.9462,009.50
EARTH SHOULDER CONSTRUCTION STA 93.9462,009.50
93.9462,009.50
13.209282.54

0075                          9173.00 147.8910.2241,512.03
SUBGRADE PREPARATION STA 10.2241,512.03
11.1731,652.37
0.0000.00

0076                          9173.15 21.2973.5001,564.81
TRENCHED WIDENING STA 73.5001,564.81
73.5001,564.82
0.0000.00

0077                          9179.24 1,016.859.7409,904.12
COLD MILLING, CLASS 4 STA 9.7409,904.12
12.60012,812.31
0.0000.00

GROUP 9 BITUMINOUSContracted169,396.56
Current169,396.56
In place169,507.59
This Estimate282.54

GROUP 10 GENERAL ITEMS
0078                          0001.08 0.5015,168.0007,584.00
BARRICADE, TYPE II BDAY15,168.0007,584.00
27,433.00013,716.50
377.000188.50

0079                          0001.10 4.204,029.00016,921.80
BARRICADE, TYPE III BDAY4,029.00016,921.80
6,912.00029,030.40
27.000113.40

0080                          0001.30 5.601,185.0006,636.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,185.0006,636.00
773.0004,328.80
-2.000-11.20

0081                          0001.90 0.5618,765.00010,508.40
SIGN DAY EACH18,765.00010,508.40
15,722.0008,804.32
-7.000-3.92

0082                          0003.10 212.0014.0002,968.00
FLAGGING DAY 14.0002,968.00
17.0003,604.00
8.0001,696.00

0083                          0010.04 6,160.001.0006,160.00
FIELD OFFICE EACH1.0006,160.00
1.0006,160.00
0.0000.00

0084                          0030.00 3,472.001.0003,472.00
MOBILIZATION LS 1.0003,472.00
0.9303,231.20
0.0000.00

91                           0002.70 11.500.0000.00
PERMANENT PAVEMENT MARKING STA 52.000598.00
State opted not to do this work with their forces. 0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted54,250.20
Current54,848.20
In place68,875.22
This Estimate1,982.78

Totals for contractContracted1,475,433.95
Current1,487,204.34
In place1,491,628.41
This Estimate49,254.98