| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 1 GRADING | | |
|
0001 L006.00 | 224.00 | 8.000 | 1,792.00
|
COVER CROP SEEDING | ACRE | 8.000 | 1,792.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 0030.10 | 5,438.72 | 1.000 | 5,438.72
|
MOBILIZATION | LS | 1.000 | 5,438.72
|
| | 1.000 | 5,438.72
|
| | 0.000 | 0.00
|
| | |
|
0003 1000.00 | 62.10 | 155.000 | 9,625.50
|
LARGE TREE REMOVAL | EACH | 155.000 | 9,625.50
|
| | 120.000 | 7,452.00
|
| | -18.000 | -1,117.80
|
| | |
|
0004 1011.00 | 10.04 | 95.000 | 953.80
|
WATER | MGAL | 95.000 | 953.80
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0005 1030.00 | 8.37 | 13,325.000 | 111,530.25
|
EARTHWORK MEASURED IN EMBANKMENT | CY | 13,325.000 | 111,530.25
|
| | 13,325.000 | 111,530.25
|
| | 0.000 | 0.00
|
| | |
|
0006 1040.00 | 0.43 | 38,720.000 | 16,649.60
|
SLOPE PROTECTION | SY | 38,720.000 | 16,649.60
|
| | 38,720.000 | 16,649.60
|
| | 38,720.000 | 16,649.60
|
| | |
|
0007 1040.06 | 95.20 | 39.000 | 3,712.80
|
SLOPE PROTECTION MULCH | TON | 39.000 | 3,712.80
|
| | 40.000 | 3,808.00
|
| | 40.000 | 3,808.00
|
| | |
|
0008 4045.00 | 1,176.00 | 1.000 | 1,176.00
|
REMOVE STRUCTURE | EACH | 1.000 | 1,176.00
|
AT STA. 14+77 | | 1.000 | 1,176.00
|
| | 0.000 | 0.00
|
| | |
|
0009 4050.01 | 22.40 | 9.000 | 201.60
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | CY | 9.000 | 201.60
|
| | 9.000 | 201.60
|
| | 0.000 | 0.00
|
| | |
|
0010 4300.36 | 50.40 | 162.000 | 8,164.80
|
36" CULVERT PIPE | LF | 162.000 | 8,164.80
|
| | 162.000 | 8,164.80
|
| | 0.000 | 0.00
|
| | |
|
0011 4500.42 | 100.80 | 72.000 | 7,257.60
|
42" ROUND EQUIVALENT REINFORCED CONCRETE PIPE | LF | 72.000 | 7,257.60
|
| | 75.000 | 7,560.00
|
| | 0.000 | 0.00
|
| | |
|
4002 2009.10 | 395.40 | 0.000 | 0.00
|
GRAVEL EMBEDMENT | STA | 14.000 | 5,535.60
|
| | 14.000 | 5,535.60
|
| | 0.000 | 0.00
|
| | |
|
90 L001.19 | 2,362.50 | 0.000 | 0.00
|
SEEDING, TYPE WETLAND-LOW | ACRE | 1.000 | 2,362.50
|
| | 1.000 | 2,362.50
|
| | 1.000 | 2,362.50
|
| | |
|
GROUP 1 GRADING | | Contracted | 166,502.67
|
| | Current | 174,400.77
|
| | In place | 169,879.07
|
| | This Estimate | 21,702.30
|
| | |
|
GROUP 6 BRIDGE AT STA. 25+10 | | |
|
0012 0030.60 | 18,200.00 | 1.000 | 18,200.00
|
MOBILIZATION | LS | 1.000 | 18,200.00
|
| | 1.000 | 18,200.00
|
| | 0.000 | 0.00
|
| | |
|
0013 1010.01 | 8.40 | 1,320.000 | 11,088.00
|
EXCAVATION (ESTABLISHED QUANTITY) | CY | 1,320.000 | 11,088.00
|
| | 1,320.000 | 11,088.00
|
| | 0.000 | 0.00
|
| | |
|
0014 3050.15 | 256.44 | 53.000 | 13,591.32
|
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 | CY | 53.000 | 13,591.32
|
| | 53.000 | 13,591.32
|
| | 0.000 | 0.00
|
| | |
|
0015 3051.10 | 0.64 | 5,710.000 | 3,654.40
|
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | LB | 5,710.000 | 3,654.40
|
| | 5,710.000 | 3,654.40
|
| | 0.000 | 0.00
|
| | |
|
0016 6000.10 | 5,768.00 | 1.000 | 5,768.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 5,768.00
|
| | 1.000 | 5,768.00
|
| | 0.000 | 0.00
|
| | |
|
0017 6000.11 | 5,768.00 | 1.000 | 5,768.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 5,768.00
|
| | 1.000 | 5,768.00
|
| | 0.000 | 0.00
|
| | |
|
0018 6000.62 | 18,480.00 | 1.000 | 18,480.00
|
PIER NO.3 EXCAVATION | LS | 1.000 | 18,480.00
|
| | 1.000 | 18,480.00
|
| | 0.000 | 0.00
|
| | |
|
0019 6001.50 | 10,752.00 | 1.000 | 10,752.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 10,752.00
|
| | 1.000 | 10,752.00
|
| | 0.000 | 0.00
|
| | |
|
0020 6001.51 | 10,752.00 | 1.000 | 10,752.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 10,752.00
|
| | 1.000 | 10,752.00
|
| | 0.000 | 0.00
|
| | |
|
0021 6001.53 | 10,752.00 | 1.000 | 10,752.00
|
BENT NO.4 EXCAVATION | LS | 1.000 | 10,752.00
|
| | 1.000 | 10,752.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6005.78 | 840.00 | 8.000 | 6,720.00
|
EXPANSION BEARING, TFE TYPE | EACH | 8.000 | 6,720.00
|
| | 8.000 | 6,720.00
|
| | 4.000 | 3,360.00
|
| | |
|
0023 6010.22 | 298.18 | 256.600 | 76,512.99
|
CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 256.600 | 76,512.99
|
| | 256.600 | 76,512.99
|
| | 0.000 | 0.00
|
| | |
|
0024 6010.26 | 317.08 | 397.900 | 126,166.13
|
CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 397.900 | 126,166.13
|
| | 397.900 | 126,166.13
|
| | 0.000 | 0.00
|
| | |
|
0025 6011.11 | 188,585.60 | 1.000 | 188,585.60
|
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 188,585.60
|
AT STA. 25+10 | | 1.000 | 188,585.60
|
| | 0.000 | 0.00
|
| | |
|
0026 6040.00 | 40,875.52 | 1.000 | 40,875.52
|
REMOVE STRUCTURE | EACH | 1.000 | 40,875.52
|
AT STA. 24+29 | | 1.000 | 40,875.52
|
| | 0.000 | 0.00
|
| | |
|
0027 6080.00 | 1.47 | 2,320.000 | 3,410.40
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 2,320.000 | 3,410.40
|
| | 1,300.000 | 1,911.00
|
| | 0.000 | 0.00
|
| | |
|
0028 6105.02 | 43.09 | 114.000 | 4,912.26
|
ROCK RIPRAP, TYPE B | TON | 114.000 | 4,912.26
|
| | 117.000 | 5,041.53
|
| | -44.000 | -1,895.96
|
| | |
|
0029 6131.50 | 0.62 | 89,870.000 | 55,719.40
|
EPOXY COATED REINFORCING STEEL | LB | 89,870.000 | 55,719.40
|
| | 89,870.000 | 55,719.40
|
| | 0.000 | 0.00
|
| | |
|
0030 6210.12 | 20.47 | 1,900.000 | 38,893.00
|
HP 10"X42# STEEL PILING | LF | 1,900.000 | 38,893.00
|
| | 1,825.460 | 37,367.17
|
| | 0.000 | 0.00
|
| | |
|
0031 6251.00 | 1,691.20 | 4.000 | 6,764.80
|
TEST PILE | EACH | 4.000 | 6,764.80
|
| | 5.000 | 8,456.00
|
| | 0.000 | 0.00
|
| | |
|
0032 6610.45 | 117.05 | 56.500 | 6,613.33
|
STRIP SEALS | LF | 56.500 | 6,613.33
|
| | 56.500 | 6,613.33
|
| | 0.000 | 0.00
|
| | |
|
0033 8091.00 | 17.51 | 103.000 | 1,803.53
|
GRANULAR BACKFILL | CY | 103.000 | 1,803.53
|
| | 103.000 | 1,803.53
|
| | 7.000 | 122.57
|
| | |
|
090 6210.59 | 12.28 | 0.000 | 0.00
|
PILE CUT-OFF | LF | 1.500 | 18.42
|
10"X42# Pile cut-off | | 49.540 | 608.35
|
| | 0.000 | 0.00
|
| | |
|
4001 6210.59 | 11.35 | 0.000 | 0.00
|
PILE CUT-OFF | LF | 94.760 | 1,075.53
|
HP 8"36# Steel Piling | | 94.760 | 1,075.53
|
| | 0.000 | 0.00
|
| | |
|
4003 6960.03 | 750.00 | 0.000 | 0.00
|
ADDITIONAL SOIL-SETUP FACTOR | EACH | 1.000 | 750.00
|
Soil set up on bent No. 1 as requested by Omar Qudus- Bridgedivision | | 2.000 | 1,500.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 25+10 | | Contracted | 665,782.68
|
| | Current | 667,626.62
|
| | In place | 667,761.80
|
| | This Estimate | 1,586.61
|
| | |
|
GROUP 6A BRIDGE AT STA. 40+25 | | |
|
0034 0030.60 | 11,132.80 | 1.000 | 11,132.80
|
MOBILIZATION | LS | 1.000 | 11,132.80
|
| | 1.000 | 11,132.80
|
| | 0.000 | 0.00
|
| | |
|
0035 3050.15 | 256.27 | 52.900 | 13,556.68
|
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 | CY | 52.900 | 13,556.68
|
| | 52.900 | 13,556.68
|
| | 0.000 | 0.00
|
| | |
|
0036 3051.10 | 0.64 | 5,670.000 | 3,628.80
|
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES | LB | 5,670.000 | 3,628.80
|
| | 5,670.000 | 3,628.80
|
| | 0.000 | 0.00
|
| | |
|
0037 6000.10 | 3,808.00 | 1.000 | 3,808.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 3,808.00
|
| | 1.000 | 3,808.00
|
| | 0.000 | 0.00
|
| | |
|
0038 6000.11 | 3,808.00 | 1.000 | 3,808.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 3,808.00
|
| | 1.000 | 3,808.00
|
| | 0.000 | 0.00
|
| | |
|
0039 6001.50 | 952.00 | 1.000 | 952.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 952.00
|
| | 1.000 | 952.00
|
| | 0.000 | 0.00
|
| | |
|
0040 6001.51 | 952.00 | 1.000 | 952.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 952.00
|
| | 1.000 | 952.00
|
| | 0.000 | 0.00
|
| | |
|
0041 6005.78 | 798.00 | 8.000 | 6,384.00
|
EXPANSION BEARING, TFE TYPE | EACH | 8.000 | 6,384.00
|
| | 8.000 | 6,384.00
|
| | 0.000 | 0.00
|
| | |
|
0042 6010.22 | 309.47 | 87.400 | 27,047.68
|
CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 87.400 | 27,047.68
|
| | 87.400 | 27,047.68
|
| | 0.000 | 0.00
|
| | |
|
0043 6010.26 | 319.61 | 169.500 | 54,173.90
|
CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 169.500 | 54,173.90
|
| | 169.500 | 54,173.89
|
| | 0.000 | 0.00
|
| | |
|
0044 6011.11 | 77,644.00 | 1.000 | 77,644.00
|
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 77,644.00
|
AT STA. 40+25 | | 1.000 | 77,644.00
|
| | 0.000 | 0.00
|
| | |
|
0045 6040.00 | 37,296.00 | 1.000 | 37,296.00
|
REMOVE STRUCTURE | EACH | 1.000 | 37,296.00
|
AT STA. 40+55 | | 1.000 | 37,296.00
|
| | 0.000 | 0.00
|
| | |
|
0046 6080.00 | 1.78 | 1,300.000 | 2,314.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 1,300.000 | 2,314.00
|
| | 280.000 | 498.40
|
| | 0.000 | 0.00
|
| | |
|
0047 6105.02 | 51.89 | 27.000 | 1,401.03
|
ROCK RIPRAP, TYPE B | TON | 27.000 | 1,401.03
|
| | 27.000 | 1,401.03
|
| | 0.000 | 0.00
|
| | |
|
0048 6131.50 | 0.65 | 37,590.000 | 24,433.50
|
EPOXY COATED REINFORCING STEEL | LB | 37,590.000 | 24,433.50
|
| | 37,590.000 | 24,433.50
|
| | 0.000 | 0.00
|
| | |
|
0049 6210.12 | 25.30 | 930.000 | 23,529.00
|
HP 10"X42# STEEL PILING | LF | 930.000 | 23,529.00
|
| | 930.000 | 23,529.00
|
| | 0.000 | 0.00
|
| | |
|
0050 6610.45 | 117.05 | 56.500 | 6,613.33
|
STRIP SEALS | LF | 56.500 | 6,613.33
|
| | 56.500 | 6,613.33
|
| | 0.000 | 0.00
|
| | |
|
0051 8091.00 | 17.51 | 103.000 | 1,803.53
|
GRANULAR BACKFILL | CY | 103.000 | 1,803.53
|
| | 103.000 | 1,803.53
|
| | 0.000 | 0.00
|
| | |
|
0088 6210.59 | 6.64 | 0.000 | 0.00
|
PILE CUT-OFF | LF | 200.000 | 1,328.00
|
| | 200.000 | 1,328.00
|
| | 0.000 | 0.00
|
| | |
|
89 6210.61 | 102.35 | 0.000 | 0.00
|
PILE SPLICE | EACH | 1.000 | 102.35
|
Pile splice HP 10"X42# steel piling | | 1.000 | 102.35
|
| | 1.000 | 102.35
|
| | |
|
GROUP 6A BRIDGE AT STA. 40+25 | | Contracted | 300,478.24
|
| | Current | 301,908.59
|
| | In place | 300,092.99
|
| | This Estimate | 102.35
|
| | |
|
GROUP 6B BRIDGE AT STA. 25+10 - 70' LT. | | |
|
0052 0030.60 | 6,440.00 | 1.000 | 6,440.00
|
MOBILIZATION | LS | 1.000 | 6,440.00
|
| | 1.000 | 6,440.00
|
| | 0.000 | 0.00
|
| | |
|
0053 6041.00 | 17,976.00 | 1.000 | 17,976.00
|
REMOVE DETOUR BRIDGE | EACH | 1.000 | 17,976.00
|
AT STA. 25+10 - 70' LT. | | 1.000 | 17,976.00
|
| | 0.200 | 3,595.20
|
| | |
|
0054 6052.00 | 26,930.40 | 1.000 | 26,930.40
|
ERECTING DETOUR BRIDGE | EACH | 1.000 | 26,930.40
|
AT STA. 25+10 - 70' LT. | | 1.000 | 26,930.40
|
| | 0.000 | 0.00
|
| | |
|
0055 6080.00 | 0.99 | 5,160.000 | 5,108.40
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 5,160.000 | 5,108.40
|
| | 5,660.000 | 5,603.40
|
| | 0.000 | 0.00
|
| | |
|
0056 6210.11 | 18.92 | 1,220.000 | 23,082.40
|
HP 8"X36# STEEL PILING | LF | 1,220.000 | 23,082.40
|
| | 1,125.240 | 21,289.54
|
| | 0.000 | 0.00
|
| | |
|
0057 6310.00 | 11.07 | 1,760.000 | 19,483.20
|
STEEL SHEET PILING | SF | 1,760.000 | 19,483.20
|
| | 1,560.000 | 17,269.20
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6B BRIDGE AT STA. 25+10 - 70' LT. | | Contracted | 99,020.40
|
| | Current | 99,020.40
|
| | In place | 95,508.54
|
| | This Estimate | 3,595.20
|
| | |
|
GROUP 7 GUARDRAIL | | |
|
0058 0030.70 | 1,411.20 | 1.000 | 1,411.20
|
MOBILIZATION | LS | 1.000 | 1,411.20
|
| | 1.000 | 1,411.20
|
| | 1.000 | 1,411.20
|
| | |
|
0059 7020.00 | 1,176.00 | 8.000 | 9,408.00
|
BRIDGE APPROACH SECTIONS | EACH | 8.000 | 9,408.00
|
| | 8.000 | 9,408.00
|
| | 8.000 | 9,408.00
|
| | |
|
0060 7021.45 | 1,148.00 | 8.000 | 9,184.00
|
BREAKAWAY CABLE TERMINAL | EACH | 8.000 | 9,184.00
|
| | 8.000 | 9,184.00
|
| | 8.000 | 9,184.00
|
| | |
|
GROUP 7 GUARDRAIL | | Contracted | 20,003.20
|
| | Current | 20,003.20
|
| | In place | 20,003.20
|
| | This Estimate | 20,003.20
|
| | |
|
GROUP 9 BITUMINOUS | | |
|
0061 0030.90 | 25,399.36 | 1.000 | 25,399.36
|
MOBILIZATION | LS | 1.000 | 25,399.36
|
| | 1.000 | 25,399.36
|
| | 0.000 | 0.00
|
| | |
|
0062 2001.00 | 12.91 | 170.000 | 2,194.70
|
GRAVEL SURFACE COURSE | CY | 170.000 | 2,194.70
|
| | 170.000 | 2,194.70
|
| | 0.000 | 0.00
|
| | |
|
0063 2020.00 | 6.37 | 32.000 | 203.84
|
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS | SY | 32.000 | 203.84
|
| | 32.000 | 203.84
|
| | 0.000 | 0.00
|
| | |
|
0064 2021.00 | 113.12 | 1.000 | 113.12
|
MAILBOX POST | EACH | 1.000 | 113.12
|
| | 1.000 | 113.12
|
| | 0.000 | 0.00
|
| | |
|
0065 9005.00 | 35.56 | 100.000 | 3,556.00
|
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 100.000 | 3,556.00
|
SP2(0.5) | | 60.000 | 2,133.60
|
| | 0.000 | 0.00
|
| | |
|
0066 9005.30 | 24.20 | 3,130.000 | 75,746.00
|
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 3,130.000 | 75,746.00
|
| | 3,298.600 | 79,826.12
|
| | 0.000 | 0.00
|
| | |
|
0067 9021.01 | 239.46 | 174.420 | 41,766.61
|
PERFORMANCE GRADED BINDER (64-22) | TON | 174.420 | 41,766.61
|
| | 169.269 | 40,533.15
|
| | 0.000 | 0.00
|
| | |
|
0068 9053.00 | 0.91 | 1,970.000 | 1,792.70
|
TACK COAT | GAL | 1,970.000 | 1,792.70
|
| | 1,170.000 | 1,064.70
|
| | 0.000 | 0.00
|
| | |
|
0069 9110.01 | 64.96 | 10.000 | 649.60
|
RENTAL OF LOADER, FULLY OPERATED | HOUR | 10.000 | 649.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0070 9110.02 | 58.46 | 10.000 | 584.60
|
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 10.000 | 584.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0071 9110.03 | 46.82 | 10.000 | 468.20
|
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 10.000 | 468.20
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0072 9110.07 | 46.26 | 10.000 | 462.60
|
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 10.000 | 462.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0073 9111.00 | 10.06 | 146.000 | 1,468.76
|
WATER | MGAL | 146.000 | 1,468.76
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0074 9170.00 | 21.39 | 93.946 | 2,009.50
|
EARTH SHOULDER CONSTRUCTION | STA | 93.946 | 2,009.50
|
| | 93.946 | 2,009.50
|
| | 13.209 | 282.54
|
| | |
|
0075 9173.00 | 147.89 | 10.224 | 1,512.03
|
SUBGRADE PREPARATION | STA | 10.224 | 1,512.03
|
| | 11.173 | 1,652.37
|
| | 0.000 | 0.00
|
| | |
|
0076 9173.15 | 21.29 | 73.500 | 1,564.81
|
TRENCHED WIDENING | STA | 73.500 | 1,564.81
|
| | 73.500 | 1,564.82
|
| | 0.000 | 0.00
|
| | |
|
0077 9179.24 | 1,016.85 | 9.740 | 9,904.12
|
COLD MILLING, CLASS 4 | STA | 9.740 | 9,904.12
|
| | 12.600 | 12,812.31
|
| | 0.000 | 0.00
|
| | |
|
GROUP 9 BITUMINOUS | | Contracted | 169,396.56
|
| | Current | 169,396.56
|
| | In place | 169,507.59
|
| | This Estimate | 282.54
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0078 0001.08 | 0.50 | 15,168.000 | 7,584.00
|
BARRICADE, TYPE II | BDAY | 15,168.000 | 7,584.00
|
| | 27,433.000 | 13,716.50
|
| | 377.000 | 188.50
|
| | |
|
0079 0001.10 | 4.20 | 4,029.000 | 16,921.80
|
BARRICADE, TYPE III | BDAY | 4,029.000 | 16,921.80
|
| | 6,912.000 | 29,030.40
|
| | 27.000 | 113.40
|
| | |
|
0080 0001.30 | 5.60 | 1,185.000 | 6,636.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 1,185.000 | 6,636.00
|
| | 773.000 | 4,328.80
|
| | -2.000 | -11.20
|
| | |
|
0081 0001.90 | 0.56 | 18,765.000 | 10,508.40
|
SIGN DAY | EACH | 18,765.000 | 10,508.40
|
| | 15,722.000 | 8,804.32
|
| | -7.000 | -3.92
|
| | |
|
0082 0003.10 | 212.00 | 14.000 | 2,968.00
|
FLAGGING | DAY | 14.000 | 2,968.00
|
| | 17.000 | 3,604.00
|
| | 8.000 | 1,696.00
|
| | |
|
0083 0010.04 | 6,160.00 | 1.000 | 6,160.00
|
FIELD OFFICE | EACH | 1.000 | 6,160.00
|
| | 1.000 | 6,160.00
|
| | 0.000 | 0.00
|
| | |
|
0084 0030.00 | 3,472.00 | 1.000 | 3,472.00
|
MOBILIZATION | LS | 1.000 | 3,472.00
|
| | 0.930 | 3,231.20
|
| | 0.000 | 0.00
|
| | |
|
91 0002.70 | 11.50 | 0.000 | 0.00
|
PERMANENT PAVEMENT MARKING | STA | 52.000 | 598.00
|
State opted not to do this work with their forces. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 54,250.20
|
| | Current | 54,848.20
|
| | In place | 68,875.22
|
| | This Estimate | 1,982.78
|
| | |
|
Totals for contract | | Contracted | 1,475,433.95
|
---|
| | Current | 1,487,204.34
|
---|
| | In place | 1,491,628.41
|
---|
| | This Estimate | 49,254.98
|
---|