Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2400 ADAMS CONSTRUCTION CO. & ADAMS LAND IMP |
Contract ID: | 63471 |
Estimate Number: | 0003 |
Pay Period End Date: | 07.05.2003 |
Contract Location: | ||
Big Springs | Estimate Type: | PROG |
Reference Post104.27 | ||
Contractor: | ||
ADAMS CONSTRUCTION CO. & ADAMS LAND IMP | Date Let: | |
712 OAK ST | Date Awarded: | |
PO BOX 657 | Date Contract Executed: | 06.03.2003 |
Date Notice to Proceed: | 06.03.2003 | |
ARAPAHOE NE 68922-0657 | Date Work Began: | 06.09.2003 |
Phone: | Date Physical Work Completed: | |
(308)962-7918 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
UNIVERSAL SURETY COMPANY |
Counties |
---|
DEUEL |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
6347 001 |   | 0.000 |   | ER-80-3(131) |   | Temporary Road - Big Springs |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $209,973.85 | $172,538.75 | $37,435.10 |
$305,251.00 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $209,973.85 | $172,538.75 | $37,435.10 |
$305,251.00 | Retainage | $.00 | $.00 | $.00 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
68.79% | Net Earnings | $209,973.85 | $172,538.75 | $37,435.10 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $209,973.85 | $172,538.75 | $37,435.10 | |
Project Manager | Div. Head/Dist. Eng. | |||
Thomsen, Toby | 07.07.2003 | O'Donnell, Les | 07.08.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 07.08.2003 | |||
Controller Div. Processed | ||||
Burling, Laurie | 07.08.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
Temporary Road for Bridge @ 104.27 | |||
0001 2001.00 | 8.50 | 2,040.000 | 17,340.00 |
GRAVEL SURFACE COURSE | CY | 2,040.000 | 17,340.00 |
3" Gravel Surface Course | 2,137.500 | 18,168.75 | |
1,747.500 | 14,853.75 | ||
0002 2009.10 | 125.00 | 110.000 | 13,750.00 |
GRAVEL EMBEDMENT | STA | 110.000 | 13,750.00 |
114.000 | 14,250.00 | ||
114.000 | 14,250.00 | ||
0003 1030.00 | 6.95 | 19,150.000 | 133,092.50 |
EARTHWORK MEASURED IN EMBANKMENT | CY | 19,150.000 | 133,092.50 |
19,150.000 | 133,092.50 | ||
0.000 | 0.00 | ||
0004 4350.48 | 20.00 | 204.000 | 4,080.00 |
48" CORRUGATED METAL PIPE | LF | 204.000 | 4,080.00 |
136.000 | 2,720.00 | ||
136.000 | 2,720.00 | ||
0005 1010.01 | 3.95 | 19,150.000 | 75,642.50 |
EXCAVATION (ESTABLISHED QUANTITY) | CY | 19,150.000 | 75,642.50 |
Temporary Road Removal | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0006 0030.60 | 25,000.00 | 1.000 | 25,000.00 |
MOBILIZATION | LS | 1.000 | 25,000.00 |
1.000 | 25,000.00 | ||
0.000 | 0.00 | ||
0007 9111.00 | 12.00 | 480.000 | 5,760.00 |
WATER | MGAL | 480.000 | 5,760.00 |
Water Applied | 258.300 | 3,099.60 | |
86.100 | 1,033.20 | ||
0008 1041.00 | 0.33 | 34,200.000 | 11,286.00 |
SALVAGING AND PLACING TOPSOIL | SY | 34,200.000 | 11,286.00 |
17,100.000 | 5,643.00 | ||
2,055.000 | 678.15 | ||
0009 L006.50 | 650.00 | 6.000 | 3,900.00 |
TEMPORARY SEEDING | ACRE | 6.000 | 3,900.00 |
6.000 | 3,900.00 | ||
6.000 | 3,900.00 | ||
0010 L001.01 | 650.00 | 13.000 | 8,450.00 |
SEEDING, TYPE A | ACRE | 13.000 | 8,450.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0011 L032.75 | 85.00 | 30.000 | 2,550.00 |
MULCH | TON | 30.000 | 2,550.00 |
Mulch (Hay or Straw) | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0012 1009.00 | 3,500.00 | 1.000 | 3,500.00 |
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 3,500.00 |
1.000 | 3,500.00 | ||
0.000 | 0.00 | ||
0013 1000.00 | 150.00 | 6.000 | 900.00 |
LARGE TREE REMOVAL | EACH | 6.000 | 900.00 |
4.000 | 600.00 | ||
0.000 | 0.00 | ||
Temporary Road for Bridge @ 104.27 | Contracted | 305,251.00 | |
Current | 305,251.00 | ||
In place | 209,973.85 | ||
This Estimate | 37,435.10 | ||
Totals for contract | Contracted | 305,251.00 | |
Current | 305,251.00 | ||
In place | 209,973.85 | ||
This Estimate | 37,435.10 |