| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 6 BRIDGE AT STA. 63+90 | | |
|
| 0001 0030.60 | 3,500.00 | 1.000 | 3,500.00
|
| MOBILIZATION | LS | 1.000 | 3,500.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 6010.26 | 300.00 | 23.100 | 6,930.00
|
| CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 23.100 | 6,930.00
|
| | | 11.550 | 3,465.00
|
| | 11.550 | 3,465.00
|
| | |
|
| 0003 6020.00 | 1.00 | 2,445.000 | 2,445.00
|
| REINFORCING STEEL FOR BRIDGE | LB | 2,445.000 | 2,445.00
|
| | | 1,222.500 | 1,222.50
|
| | 1,222.500 | 1,222.50
|
| | |
|
| 0004 6030.00 | 5,000.00 | 1.000 | 5,000.00
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 5,000.00
|
| AT STA. 63+90 | | 1.000 | 5,000.00
|
| | 1.000 | 5,000.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 63+90 | | Contracted | 17,875.00
|
| | Current | 17,875.00
|
| | In place | 9,687.50
|
| | This Estimate | 9,687.50
|
| | |
|
| GROUP 6A BRIDGE AT STA. 150+88 | | |
|
| 0005 0030.60 | 3,500.00 | 1.000 | 3,500.00
|
| MOBILIZATION | LS | 1.000 | 3,500.00
|
| | | 1.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 6010.26 | 310.00 | 18.500 | 5,735.00
|
| CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 18.500 | 5,735.00
|
| | | 18.500 | 5,735.00
|
| | 0.000 | 0.00
|
| | |
|
| 0007 6020.00 | 1.00 | 2,060.000 | 2,060.00
|
| REINFORCING STEEL FOR BRIDGE | LB | 2,060.000 | 2,060.00
|
| | | 2,060.000 | 2,060.00
|
| | 0.000 | 0.00
|
| | |
|
| 0008 6030.00 | 5,000.00 | 1.000 | 5,000.00
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 5,000.00
|
| AT STA. 150+88 | | 1.000 | 5,000.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6A BRIDGE AT STA. 150+88 | | Contracted | 16,295.00
|
| | Current | 16,295.00
|
| | In place | 16,295.00
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 6B BRIDGE AT STA. 530+30 | | |
|
| 0009 0030.60 | 3,500.00 | 1.000 | 3,500.00
|
| MOBILIZATION | LS | 1.000 | 3,500.00
|
| | | 1.000 | 3,500.00
|
| | 1.000 | 3,500.00
|
| | |
|
| 0010 6010.26 | 300.00 | 27.400 | 8,220.00
|
| CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 27.400 | 8,220.00
|
| | | 27.400 | 8,220.00
|
| | 27.400 | 8,220.00
|
| | |
|
| 0011 6020.00 | 1.00 | 2,875.000 | 2,875.00
|
| REINFORCING STEEL FOR BRIDGE | LB | 2,875.000 | 2,875.00
|
| | | 2,875.000 | 2,875.00
|
| | 2,875.000 | 2,875.00
|
| | |
|
| 0012 6030.00 | 6,000.00 | 1.000 | 6,000.00
|
| PREPARATION OF BRIDGE | EACH | 1.000 | 6,000.00
|
| AT STA. 530+30 | | 1.000 | 6,000.00
|
| | 0.500 | 3,000.00
|
| | |
|
| GROUP 6B BRIDGE AT STA. 530+30 | | Contracted | 20,595.00
|
| | Current | 20,595.00
|
| | In place | 20,595.00
|
| | This Estimate | 17,595.00
|
| | |
|
| GROUP 7 GUARDRAIL | | |
|
| 0013 0030.70 | 6,900.00 | 1.000 | 6,900.00
|
| MOBILIZATION | LS | 1.000 | 6,900.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0014 1033.00 | 300.00 | 13.060 | 3,918.00
|
| ROADWAY GRADING | STA | 13.060 | 3,918.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 7011.20 | 14.00 | 412.500 | 5,775.00
|
| W-BEAM GUARDRAIL | LF | 412.500 | 5,775.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 7017.00 | 5.00 | 887.000 | 4,435.00
|
| REMOVE GUARDRAIL | LF | 887.000 | 4,435.00
|
| | | 888.000 | 4,440.00
|
| | 468.000 | 2,340.00
|
| | |
|
| 0017 7020.00 | 2,500.00 | 12.000 | 30,000.00
|
| BRIDGE APPROACH SECTIONS | EACH | 12.000 | 30,000.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 7024.27 | 1,425.00 | 12.000 | 17,100.00
|
| GUARDRAIL END TREATMENT, TYPE II | EACH | 12.000 | 17,100.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 9188.50 | 35.00 | 679.000 | 23,765.00
|
| SURFACING UNDER GUARDRAIL | SY | 679.000 | 23,765.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 L020.00 | 2.14 | 3,510.000 | 7,511.40
|
| EROSION CONTROL | SY | 3,510.000 | 7,511.40
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | Contracted | 99,404.40
|
| | Current | 99,404.40
|
| | In place | 4,440.00
|
| | This Estimate | 2,340.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | |
|
| 0021 0001.08 | 0.50 | 2,895.000 | 1,447.50
|
| BARRICADE, TYPE II | BDAY | 2,895.000 | 1,447.50
|
| | | 2,796.000 | 1,398.00
|
| | 1,656.000 | 828.00
|
| | |
|
| 0022 0001.10 | 2.00 | 1,068.000 | 2,136.00
|
| BARRICADE, TYPE III | BDAY | 1,068.000 | 2,136.00
|
| | | 1,091.000 | 2,182.00
|
| | 629.000 | 1,258.00
|
| | |
|
| 0023 0001.90 | 0.85 | 1,602.000 | 1,361.70
|
| SIGN DAY | EACH | 1,602.000 | 1,361.70
|
| | | 2,585.000 | 2,197.25
|
| | 1,473.000 | 1,252.05
|
| | |
|
| 0024 0003.10 | 180.00 | 90.000 | 16,200.00
|
| FLAGGING | DAY | 90.000 | 16,200.00
|
| | | 61.000 | 10,980.00
|
| | 22.000 | 3,960.00
|
| | |
|
| 0025 0030.70 | 3,000.00 | 1.000 | 3,000.00
|
| MOBILIZATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | Contracted | 24,145.20
|
| | Current | 24,145.20
|
| | In place | 19,757.25
|
| | This Estimate | 7,298.05
|
| | |
|
| Totals for contract | | Contracted | 178,314.60
|
|---|
| | Current | 178,314.60
|
|---|
| | In place | 70,774.75
|
|---|
| | This Estimate | 36,920.55
|
|---|