| | Detailed breakdown of stockpiled materials | |
|
---|
Est Nbr: | 0004 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Initial Payment | 4,839.50 | 210350
|
| | ROCK | |
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Initial Payment | 4,431.68 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Initial Payment | 29,564.67 | 210350
|
| | ROCK | |
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Initial Payment | 41,853.52 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Initial Payment | 4,932.30 | 0157615
|
| | Stored | |
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Initial Payment | 893.82 | 0157615
|
| | Stored | |
|
0062 | W205.10 | 250 mm WATER MAIN PIPE | |
|
| | S.P. Initial Payment | 9,702.00 | 0157615
|
| | Stored | |
|
0063 | W219.66 | 150 mm GATE VALVE AND BOX | |
|
| | S.P. Initial Payment | 902.67 | 0157615
|
| | Stored | |
|
0065 | W219.70 | 250 mm GATE VALVE AND BOX | |
|
| | S.P. Initial Payment | 5,855.67 | 0157615
|
| | Stored | |
|
0066 | W222.06 | 150 mm FIRE HYDRANT | |
|
| | S.P. Initial Payment | 2,565.15 | 0157615
|
| | Stored | |
|
0070 | W356.18 | 250 mm X 150 mm TEE | |
|
| | S.P. Initial Payment | 779.46 | 0157615
|
| | Stored | |
|
0073 | W357.16 | 150 mm- 45 DEGREE BEND | |
|
| | S.P. Initial Payment | 329.84 | 0157615
|
| | Stored | |
|
0075 | W357.43 | 250 mm - 45 DEGREE BEND | |
|
| | S.P. Initial Payment | 411.72 | 0157615
|
| | Stored | |
|
| | S.P. Adjustment | -274.48 | 0157615
|
| | Stored | |
|
0087 | 4764.80 | 250 mm P.V.C. SEWER PIPE | |
|
| | S.P. Initial Payment | 331.38 | 0157615
|
| | Stored | |
|
0089 | 4796.00 | 150 mm PLUG | |
|
| | S.P. Initial Payment | 205.83 | 0157615
|
| | Stored | |
|
| | Total for estimate 0004: | 107,324.73 |
|
Est Nbr: | 0005 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -50.67 | 0157615
|
| | Stored | |
|
0062 | W205.10 | 250 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -3,591.00 | 0157615
|
| | Stored | |
|
0065 | W219.70 | 250 mm GATE VALVE AND BOX | |
|
| | S.P. Adjustment | -2,602.52 | 0157615
|
| | Stored | |
|
0066 | W222.06 | 150 mm FIRE HYDRANT | |
|
| | S.P. Adjustment | -855.05 | 0157615
|
| | Stored | |
|
0070 | W356.18 | 250 mm X 150 mm TEE | |
|
| | S.P. Adjustment | -129.91 | 0157615
|
| | Stored | |
|
| | Total for estimate 0005: | -7,229.15 |
|
Est Nbr: | 0006 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | -1,065.57 | 0157615
|
| | Stored | |
|
0062 | W205.10 | 250 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -2,935.49 | 0157615
|
| | Stored | |
|
| | Total for estimate 0006: | -4,001.06 |
|
Est Nbr: | 0009 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -7,518.52 | 210350
|
| | ROCK | |
|
0062 | W205.10 | 250 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -305.55 | 0157615
|
| | Stored | |
|
0075 | W357.43 | 250 mm - 45 DEGREE BEND | |
|
| | S.P. Adjustment | -137.24 | 0157615
|
| | Stored | |
|
| | Total for estimate 0009: | -7,961.31 |
|
Est Nbr: | 0010 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -3,113.68 | 210350
|
| | ROCK | |
|
| | Total for estimate 0010: | -3,113.68 |
|
Est Nbr: | 0011 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -63.56 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -637.23 | 210350
|
| | ROCK | |
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -865.22 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | -1,897.95 | 0157615
|
| | Stored | |
|
| | Total for estimate 0011: | -3,463.96 |
|
Est Nbr: | 0012 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -4,249.81 | 210350
|
| | ROCK | |
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -7,534.99 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | -73.98 | 0157615
|
| | Stored | |
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -242.04 | 0157615
|
| | Stored | |
|
0062 | W205.10 | 250 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -2,869.97 | 0157615
|
| | Stored | |
|
0063 | W219.66 | 150 mm GATE VALVE AND BOX | |
|
| | S.P. Adjustment | -601.78 | 0157615
|
| | Stored | |
|
0065 | W219.70 | 250 mm GATE VALVE AND BOX | |
|
| | S.P. Adjustment | -3,253.15 | 0157615
|
| | Stored | |
|
0066 | W222.06 | 150 mm FIRE HYDRANT | |
|
| | S.P. Adjustment | -855.05 | 0157615
|
| | Stored | |
|
0070 | W356.18 | 250 mm X 150 mm TEE | |
|
| | S.P. Adjustment | -389.73 | 0157615
|
| | Stored | |
|
0073 | W357.16 | 150 mm- 45 DEGREE BEND | |
|
| | S.P. Adjustment | -141.36 | 0157615
|
| | Stored | |
|
0087 | 4764.80 | 250 mm P.V.C. SEWER PIPE | |
|
| | S.P. Adjustment | -244.59 | 0157615
|
| | Stored | |
|
0093 | A001.12 | PULL BOX, TYPE PB-5 | |
|
| | S.P. Initial Payment | 2,901.60 | 01906254
|
| | | |
|
0094 | A009.09 | STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 | |
|
| | S.P. Initial Payment | 29,987.40 | 053202145
|
| | | |
|
0095 | A009.10 | STREET LIGHTING UNIT, TYPE SL-A-12.2-3-0.25 | |
|
| | S.P. Initial Payment | 4,121.52 | 053202145
|
| | | |
|
0096 | A009.11 | STREET LIGHTING UNIT, TYPE SL-A-12.2-3.7-0.25 | |
|
| | S.P. Initial Payment | 3,155.34 | 053202145
|
| | | |
|
0097 | A009.14 | STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 | |
|
| | S.P. Initial Payment | 1,149.67 | 053202145
|
| | | |
|
0098 | A020.30 | LIGHTING CONTROL CENTER, TYPE R | |
|
| | S.P. Initial Payment | 1,848.00 | 40011974
|
| | | |
|
| | Total for estimate 0012: | 22,707.08 |
|
Est Nbr: | 0013 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -2,642.66 | 210350
|
| | ROCK | |
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -807.02 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | -1,071.30 | 0157615
|
| | Stored | |
|
0073 | W357.16 | 150 mm- 45 DEGREE BEND | |
|
| | S.P. Adjustment | -47.12 | 0157615
|
| | Stored | |
|
| | Total for estimate 0013: | -4,568.10 |
|
Est Nbr: | 0014 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -121.94 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -1,453.19 | 210350
|
| | ROCK | |
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -1,101.22 | 210350
|
| | ROCK | |
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -129.54 | 0157615
|
| | Stored | |
|
0070 | W356.18 | 250 mm X 150 mm TEE | |
|
| | S.P. Adjustment | -129.91 | 0157615
|
| | Stored | |
|
0073 | W357.16 | 150 mm- 45 DEGREE BEND | |
|
| | S.P. Adjustment | -141.36 | 0157615
|
| | Stored | |
|
0089 | 4796.00 | 150 mm PLUG | |
|
| | S.P. Adjustment | -22.87 | 0157615
|
| | Stored | |
|
| | Total for estimate 0014: | -3,100.03 |
|
Est Nbr: | 0015 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -348.30 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Closure | -26.97 | 210350
|
| | ROCK | |
|
| | S.P. Adjustment | -2,154.18 | 210350
|
| | ROCK | |
|
0020 | 3075.45 | 230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Closure | -23,984.75 | 210350
|
| | ROCK | |
|
| | S.P. Adjustment | -41.80 | 210350
|
| | ROCK | |
|
0093 | A001.12 | PULL BOX, TYPE PB-5 | |
|
| | S.P. Adjustment | -763.59 | 01906254
|
| | | |
|
0094 | A009.09 | STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 | |
|
| | S.P. Adjustment | -1,199.49 | 053202145
|
| | | |
|
0097 | A009.14 | STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 | |
|
| | S.P. Adjustment | -114.97 | 053202145
|
| | | |
|
| | Total for estimate 0015: | -28,634.05 |
|
Est Nbr: | 0016 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -123.10 | 210350
|
| | ROCK | |
|
0093 | A001.12 | PULL BOX, TYPE PB-5 | |
|
| | S.P. Adjustment | -30.54 | 01906254
|
| | | |
|
0094 | A009.09 | STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 | |
|
| | S.P. Adjustment | -599.75 | 053202145
|
| | | |
|
| | Total for estimate 0016: | -753.39 |
|
Est Nbr: | 0017 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -2,301.38 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | 171.64 | 0157615
|
| | Stored | |
|
0093 | A001.12 | PULL BOX, TYPE PB-5 | |
|
| | S.P. Adjustment | -733.04 | 01906254
|
| | | |
|
0094 | A009.09 | STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 | |
|
| | S.P. Adjustment | -17,192.78 | 053202145
|
| | | |
|
0097 | A009.14 | STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 | |
|
| | S.P. Adjustment | -1,034.70 | 053202145
|
| | | |
|
0098 | A020.30 | LIGHTING CONTROL CENTER, TYPE R | |
|
| | S.P. Adjustment | -1,232.00 | 40011974
|
| | | |
|
| | Total for estimate 0017: | -22,322.26 |
|
Est Nbr: | 0018 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -735.03 | 210350
|
| | ROCK | |
|
0066 | W222.06 | 150 mm FIRE HYDRANT | |
|
| | S.P. Adjustment | -855.05 | 0157615
|
| | Stored | |
|
0093 | A001.12 | PULL BOX, TYPE PB-5 | |
|
| | S.P. Adjustment | -610.86 | 01906254
|
| | | |
|
0094 | A009.09 | STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 | |
|
| | S.P. Adjustment | -7,996.64 | 053202145
|
| | | |
|
0098 | A020.30 | LIGHTING CONTROL CENTER, TYPE R | |
|
| | S.P. Adjustment | -616.00 | 40011974
|
| | | |
|
| | Total for estimate 0018: | -10,813.58 |
|
Est Nbr: | 0019 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0063 | W219.66 | 150 mm GATE VALVE AND BOX | |
|
| | S.P. Adjustment | 601.78 | 0157615
|
| | Stored | |
|
0070 | W356.18 | 250 mm X 150 mm TEE | |
|
| | S.P. Adjustment | 129.91 | 0157615
|
| | Stored | |
|
0089 | 4796.00 | 150 mm PLUG | |
|
| | S.P. Adjustment | 22.87 | 0157615
|
| | Stored | |
|
| | Total for estimate 0019: | 754.56 |
|
Est Nbr: | 0020 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -445.42 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | 261.91 | 0157615
|
| | Stored | |
|
| | Total for estimate 0020: | -183.51 |
|
Est Nbr: | 0021 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -98.50 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | 516.38 | 210350
|
| | ROCK | |
|
| | Total for estimate 0021: | 417.88 |
|
Est Nbr: | 0022 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Adjustment | -151.62 | 210350
|
| | ROCK | |
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -1,384.35 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -479.77 | 210350
|
| | ROCK | |
|
| | Total for estimate 0022: | -2,015.74 |
|
Est Nbr: | 0023 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Closure | -129.61 | 210350
|
| | ROCK | |
|
| | S.P. Adjustment | -935.99 | 210350
|
| | ROCK | |
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Closure | -176.84 | 210350
|
| | ROCK | |
|
| | S.P. Adjustment | -291.97 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -407.27 | 210350
|
| | ROCK | |
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -322.80 | 0157615
|
| | Stored | |
|
0063 | W219.66 | 150 mm GATE VALVE AND BOX | |
|
| | S.P. Adjustment | -601.78 | 0157615
|
| | Stored | |
|
0070 | W356.18 | 250 mm X 150 mm TEE | |
|
| | S.P. Adjustment | -259.82 | 0157615
|
| | Stored | |
|
0089 | 4796.00 | 150 mm PLUG | |
|
| | S.P. Adjustment | -45.74 | 0157615
|
| | Stored | |
|
| | Total for estimate 0023: | -3,171.82 |
|
Est Nbr: | 0024 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Adjustment | -1,080.22 | 210350
|
| | ROCK | |
|
| | Total for estimate 0024: | -1,080.22 |
|
Est Nbr: | 0025 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Adjustment | -614.47 | 210350
|
| | ROCK | |
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -239.45 | 210350
|
| | ROCK | |
|
0058 | W176.26 | 25 mm WATER SERVICE | |
|
| | S.P. Adjustment | -1,257.05 | 0157615
|
| | Stored | |
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -95.42 | 0157615
|
| | Stored | |
|
0089 | 4796.00 | 150 mm PLUG | |
|
| | S.P. Adjustment | -45.74 | 0157615
|
| | Stored | |
|
| | Total for estimate 0025: | -2,252.13 |
|
Est Nbr: | 0026 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Adjustment | -105.50 | 210350
|
| | ROCK | |
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -361.90 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -5,021.29 | 210350
|
| | ROCK | |
|
0060 | W205.06 | 150 mm WATER MAIN PIPE | |
|
| | S.P. Adjustment | -53.35 | 0157615
|
| | Stored | |
|
0063 | W219.66 | 150 mm GATE VALVE AND BOX | |
|
| | S.P. Adjustment | -300.89 | 0157615
|
| | Stored | |
|
0089 | 4796.00 | 150 mm PLUG | |
|
| | S.P. Adjustment | -22.87 | 0157615
|
| | Stored | |
|
| | Total for estimate 0026: | -5,865.80 |
|
Est Nbr: | 0027 | | |
|
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr
|
0017 | 3016.21 | CONCRETE CLASS 47B-20 SIDEWALKS | |
|
| | S.P. Adjustment | -207.34 | 210350
|
| | ROCK | |
|
0018 | 3020.26 | CONCRETE CLASS 47B-25 DRIVEWAY | |
|
| | S.P. Adjustment | -103.75 | 210350
|
| | ROCK | |
|
0019 | 3075.41 | 230 mm CONCRETE PAVEMENT, CLASS 47B-25 | |
|
| | S.P. Adjustment | -3,140.32 | 210350
|
| | ROCK | |
|
0087 | 4764.80 | 250 mm P.V.C. SEWER PIPE | |
|
| | S.P. Adjustment | -86.79 | 0157615
|
| | Stored | |
|
| | Total for estimate 0027: | -3,538.20 |
|
| | Total remaining for contract: | 17,136.26 |
|
---|
| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 4 CULVERTS | | |
|
4039 6960.02 | 564.89 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 564.89
|
ADJUST INLETS TO GRADE | | 1.000 | 564.89
|
| | 0.000 | 0.00
|
| | |
|
4048 4012.29 | 926.00 | 0.000 | 0.00
|
RECONSTRUCT CURB INLET | EACH | 1.000 | 926.00
|
NO. 37 | | 1.000 | 926.00
|
| | 1.000 | 926.00
|
| | |
|
GROUP 4 CULVERTS | | Contracted | 0.00
|
| | Current | 1,490.89
|
| | In place | 1,490.89
|
| | This Estimate | 926.00
|
| | |
|
GROUP 8B ELECTRICAL | | |
|
4051 A700.75 | 1,305.38 | 0.000 | 0.00
|
RELOCATE LIGHT POLE | EACH | 1.000 | 1,305.38
|
NO. 11 | | 1.000 | 1,305.38
|
| | 1.000 | 1,305.38
|
| | |
|
GROUP 8B ELECTRICAL | | Contracted | 0.00
|
| | Current | 1,305.38
|
| | In place | 1,305.38
|
| | This Estimate | 1,305.38
|
| | |
|
GROUP 1 GRADING | | |
|
0001 L020.09 | 25.00 | 12.000 | 300.00
|
EROSION CONTROL, TYPE AAA | m2 | 12.000 | 300.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 0030.10 | 8,000.00 | 1.000 | 8,000.00
|
MOBILIZATION | LS | 1.000 | 8,000.00
|
| | 1.000 | 8,000.00
|
| | 0.000 | 0.00
|
| | |
|
0003 1009.00 | 8,000.00 | 1.000 | 8,000.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 8,000.00
|
| | 0.715 | 5,720.00
|
| | 0.000 | 0.00
|
| | |
|
0004 1010.01 | 4.38 | 19,409.000 | 85,011.42
|
EXCAVATION (ESTABLISHED QUANTITY) | m3 | 19,409.000 | 85,011.42
|
| | 38,779.780 | 169,855.45
|
| | 0.000 | 0.00
|
| | |
|
0005 1011.00 | 2.15 | 22.000 | 47.30
|
WATER | kL | 22.000 | 47.30
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0006 1016.00 | 157.50 | 212.000 | 33,390.00
|
RE-ESTABLISH PROPERTY CORNER | EACH | 212.000 | 33,390.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0007 1101.00 | 2.98 | 10,284.000 | 30,646.32
|
REMOVE PAVEMENT | m2 | 10,284.000 | 30,646.32
|
| | 9,973.833 | 29,722.03
|
| | 0.000 | 0.00
|
| | |
|
0008 1106.00 | 3.26 | 566.000 | 1,845.16
|
REMOVE DRIVEWAY | m2 | 566.000 | 1,845.16
|
| | 612.737 | 1,997.53
|
| | 0.000 | 0.00
|
| | |
|
0009 1107.00 | 2.15 | 1,568.000 | 3,371.20
|
REMOVE WALK | m2 | 1,568.000 | 3,371.20
|
| | 1,582.342 | 3,402.04
|
| | 0.000 | 0.00
|
| | |
|
0010 1109.00 | 6.55 | 44.000 | 288.20
|
REMOVE CURB | m | 44.000 | 288.20
|
| | 49.370 | 323.37
|
| | 0.000 | 0.00
|
| | |
|
0011 1114.10 | 9.86 | 43.500 | 428.91
|
REMOVE RETAINING WALL | m | 43.500 | 428.91
|
| | 39.300 | 387.50
|
| | 0.000 | 0.00
|
| | |
|
0012 1701.18 | 48.10 | 10.000 | 481.00
|
450 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 | m | 10.000 | 481.00
|
| | 10.000 | 481.00
|
| | 0.000 | 0.00
|
| | |
|
4007 L999.10 | 315.00 | 0.000 | 0.00
|
TREE | EACH | 1.000 | 315.00
|
REMOVAL AT STA. 103+97, 13.8m RT. | | 1.000 | 315.00
|
| | 0.000 | 0.00
|
| | |
|
4036 9110.10 | 65.76 | 0.000 | 0.00
|
RENTAL OF EXCAVATOR, FULLY OPERATED | HOUR | 17.000 | 1,117.92
|
| | 17.000 | 1,117.92
|
| | 0.000 | 0.00
|
| | |
|
GROUP 1 GRADING | | Contracted | 171,809.51
|
| | Current | 173,242.43
|
| | In place | 221,321.84
|
| | This Estimate | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | |
|
0013 L001.02 | 1,457.00 | 0.590 | 859.63
|
SEEDING, TYPE B | ha | 0.590 | 859.63
|
| | 1.241 | 1,808.13
|
| | 0.000 | 0.00
|
| | |
|
0014 L010.00 | 3.23 | 9,106.000 | 29,412.38
|
SODDING | m2 | 9,106.000 | 29,412.38
|
| | 5,594.185 | 18,069.22
|
| | 0.000 | 0.00
|
| | |
|
0015 L032.75 | 385.00 | 3.000 | 1,155.00
|
MULCH | Mg | 3.000 | 1,155.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0016 0030.30 | 18,000.00 | 1.000 | 18,000.00
|
MOBILIZATION | LS | 1.000 | 18,000.00
|
| | 1.000 | 18,000.00
|
| | 0.000 | 0.00
|
| | |
|
0017 3016.21 | 24.00 | 4,361.100 | 104,666.40
|
CONCRETE CLASS 47B-20 SIDEWALKS | m2 | 4,361.100 | 104,666.40
|
| | 2,905.959 | 69,743.02
|
| | 287.753 | 6,906.08
|
| | |
|
0018 3020.26 | 28.70 | 2,662.000 | 76,399.40
|
CONCRETE CLASS 47B-25 DRIVEWAY | m2 | 2,662.000 | 76,399.40
|
| | 1,852.871 | 53,177.40
|
| | 62.322 | 1,788.64
|
| | |
|
0019 3075.41 | 27.85 | 11,584.000 | 322,614.40
|
230 mm CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 11,584.000 | 322,614.40
|
| | 10,372.389 | 288,871.03
|
| | 1,263.525 | 35,189.17
|
| | |
|
0020 3075.45 | 30.71 | 16,399.000 | 503,613.29
|
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 | m2 | 16,399.000 | 503,613.29
|
| | 13,474.698 | 413,807.99
|
| | 1,614.187 | 49,571.68
|
| | |
|
0021 4103.06 | 2,000.00 | 0.550 | 1,100.00
|
CLASS 47B-20 CONCRETE FOR STEP | m3 | 0.550 | 1,100.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0022 8029.75 | 3.90 | 27,983.000 | 109,133.70
|
BITUMINOUS FOUNDATION COURSE | m2 | 27,983.000 | 109,133.70
|
| | 23,700.809 | 92,433.15
|
| | 2,876.865 | 11,219.77
|
| | |
|
0023 9111.00 | 2.15 | 493.000 | 1,059.95
|
WATER | kL | 493.000 | 1,059.95
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0024 9170.00 | 325.00 | 37.248 | 12,105.60
|
EARTH SHOULDER CONSTRUCTION | StaM | 37.248 | 12,105.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0025 9173.20 | 1.00 | 30,645.000 | 30,645.00
|
SUBGRADE PREPARATION | m2 | 30,645.000 | 30,645.00
|
| | 25,598.964 | 25,598.98
|
| | 2,955.954 | 2,955.96
|
| | |
|
4002 0025.01 | 641.24 | 0.000 | 0.00
|
PARTNERING WORKSHOP | LS | 1.000 | 641.24
|
| | 1.000 | 641.24
|
| | 0.000 | 0.00
|
| | |
|
4035 9000.50 | 57.19 | 0.000 | 0.00
|
ASPHALTIC CONCRETE FOR TEMPORARY SURFACING | Mg | 250.000 | 14,297.50
|
| | 155.572 | 8,897.17
|
| | 0.000 | 0.00
|
| | |
|
4041 2001.00 | 14.00 | 0.000 | 0.00
|
GRAVEL SURFACE COURSE | m3 | 40.000 | 560.00
|
| | 85.887 | 1,202.41
|
| | 0.000 | 0.00
|
| | |
|
4047 3014.12 | 43.50 | 0.000 | 0.00
|
COMBINATION CONCRETE CLASS 47B-25 CURB AND GUTTER | m | 13.690 | 595.52
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 3 CONCRETE PAVEMENT | | Contracted | 1,210,764.75
|
| | Current | 1,226,859.00
|
| | In place | 992,249.74
|
| | This Estimate | 107,631.30
|
| | |
|
GROUP 4 CULVERTS | | |
|
0026 P700.15 | 48.33 | 304.500 | 14,716.48
|
375 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 179.519 | 8,676.15
|
| | 162.792 | 7,867.75
|
| | 28.891 | 1,396.30
|
| | |
|
0027 P700.18 | 56.07 | 1,130.500 | 63,387.14
|
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 1,016.612 | 57,001.43
|
| | 1,089.324 | 61,078.40
|
| | 104.735 | 5,872.49
|
| | |
|
0028 P700.24 | 78.64 | 667.500 | 52,492.20
|
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 450.068 | 35,393.35
|
| | 389.098 | 30,598.66
|
| | 0.000 | 0.00
|
| | |
|
0029 P700.30 | 105.85 | 344.500 | 36,465.32
|
750 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 344.500 | 36,465.32
|
| | 346.250 | 36,650.56
|
| | 0.000 | 0.00
|
| | |
|
0030 P700.36 | 137.84 | 196.500 | 27,085.56
|
900 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 196.500 | 27,085.56
|
| | 199.739 | 27,532.02
|
| | 0.000 | 0.00
|
| | |
|
0031 P700.42 | 176.21 | 645.000 | 113,655.45
|
1050 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 645.000 | 113,655.45
|
| | 647.011 | 114,009.82
|
| | 0.000 | 0.00
|
| | |
|
0032 P775.24 | 153.82 | 20.000 | 3,076.40
|
600 mm ROUND EQUIVALENT STORM SEWER PIPE, TYPE 1 | m | 9.000 | 1,384.38
|
| | 79.023 | 12,155.31
|
| | 0.000 | 0.00
|
| | |
|
0033 P775.30 | 221.61 | 7.000 | 1,551.27
|
750 mm ROUND EQUIVALENT STORM SEWER PIPE, TYPE 1 | m | 7.000 | 1,551.27
|
| | 7.810 | 1,730.77
|
| | 0.000 | 0.00
|
| | |
|
0034 0030.40 | 7,500.00 | 1.000 | 7,500.00
|
MOBILIZATION | LS | 1.000 | 7,500.00
|
| | 1.000 | 7,500.00
|
| | 0.000 | 0.00
|
| | |
|
0035 1043.50 | 4.42 | 142.000 | 627.64
|
RIPRAP FILTER FABRIC | m2 | 142.000 | 627.64
|
| | 192.300 | 849.97
|
| | 0.000 | 0.00
|
| | |
|
0036 1117.00 | 300.00 | 2.000 | 600.00
|
REMOVE MANHOLE | EACH | 2.000 | 600.00
|
| | 7.000 | 2,100.00
|
| | 0.000 | 0.00
|
| | |
|
0037 1119.00 | 150.00 | 45.000 | 6,750.00
|
REMOVE INLET | EACH | 45.000 | 6,750.00
|
| | 40.000 | 6,000.00
|
| | 0.000 | 0.00
|
| | |
|
0038 4002.00 | 2.25 | 6,889.000 | 15,500.25
|
CAST IRON COVER AND FRAME | kg | 6,889.000 | 15,500.25
|
| | 5,124.000 | 11,529.00
|
| | 741.000 | 1,667.25
|
| | |
|
0039 4003.00 | 2.10 | 526.000 | 1,104.60
|
CAST IRON COVER, FRAME, AND FLANGE | kg | 526.000 | 1,104.60
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0040 4004.50 | 2.00 | 676.000 | 1,352.00
|
CAST IRON GRATE AND FRAME | kg | 676.000 | 1,352.00
|
| | 676.000 | 1,352.00
|
| | 0.000 | 0.00
|
| | |
|
0041 4016.00 | 1,750.00 | 1.000 | 1,750.00
|
MANHOLE | EACH | 1.000 | 1,750.00
|
AT STA. 101+08.3 LT. | | 0.330 | 577.50
|
| | 0.330 | 577.50
|
| | |
|
0042 4016.01 | 1,750.00 | 1.000 | 1,750.00
|
MANHOLE | EACH | 1.000 | 1,750.00
|
AT STA. 101+08.3 RT. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0043 4016.02 | 1,200.00 | 1.000 | 1,200.00
|
MANHOLE | EACH | 1.000 | 1,200.00
|
AT STA. 105+34.2 RT. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0044 4016.03 | 1,950.00 | 1.000 | 1,950.00
|
MANHOLE | EACH | 1.000 | 1,950.00
|
AT STA. 106+31.8 LT. | | 1.000 | 1,950.00
|
| | 0.000 | 0.00
|
| | |
|
0045 4016.04 | 2,000.00 | 1.000 | 2,000.00
|
MANHOLE | EACH | 1.000 | 2,000.00
|
AT STA. 106+31.8 RT. | | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0046 4016.05 | 1,200.00 | 1.000 | 1,200.00
|
MANHOLE | EACH | 1.000 | 1,200.00
|
AT STA. 107+42.4 RT. | | 1.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | |
|
0047 4016.06 | 1,200.00 | 1.000 | 1,200.00
|
MANHOLE | EACH | 1.000 | 1,200.00
|
AT STA. 108+47.1 RT. | | 1.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | |
|
0048 4016.07 | 1,500.00 | 1.000 | 1,500.00
|
MANHOLE | EACH | 1.000 | 1,500.00
|
AT STA. 110+56.7 LT. | | 1.000 | 1,500.00
|
| | 0.000 | 0.00
|
| | |
|
0049 4016.08 | 2,100.00 | 1.000 | 2,100.00
|
MANHOLE | EACH | 1.000 | 2,100.00
|
AT STA. 114+67.8 LT. | | 1.000 | 2,100.00
|
| | 0.000 | 0.00
|
| | |
|
0050 4016.09 | 2,100.00 | 1.000 | 2,100.00
|
MANHOLE | EACH | 1.000 | 2,100.00
|
AT STA. 114+67.8 RT. | | 1.000 | 2,100.00
|
| | 0.000 | 0.00
|
| | |
|
0051 4043.50 | 3.30 | 1,468.300 | 4,845.39
|
REMOVE SEWER PIPE | m | 1,468.300 | 4,845.39
|
| | 1,543.100 | 5,092.23
|
| | 122.500 | 404.25
|
| | |
|
0052 4050.01 | 19.61 | 126.000 | 2,470.86
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 126.000 | 2,470.86
|
| | 126.000 | 2,470.86
|
| | 0.000 | 0.00
|
| | |
|
0053 4105.59 | 506.64 | 260.540 | 131,999.99
|
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX | m3 | 307.503 | 155,793.32
|
| | 272.223 | 137,919.06
|
| | 12.227 | 6,194.69
|
| | |
|
0054 4107.07 | 300.00 | 2.700 | 810.00
|
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS | m3 | 2.700 | 810.00
|
| | 2.500 | 750.00
|
| | 0.400 | 120.00
|
| | |
|
0055 4155.50 | 1.90 | 8,309.000 | 15,787.10
|
REINFORCING STEEL FOR INLET AND JUNCTION BOX | kg | 8,309.000 | 15,787.10
|
| | 6,323.300 | 12,014.27
|
| | 1,134.400 | 2,155.36
|
| | |
|
0056 4910.25 | 26.33 | 3,326.400 | 87,584.11
|
DEWATERING | m | 3,326.400 | 87,584.11
|
| | 2,546.608 | 67,052.19
|
| | 0.000 | 0.00
|
| | |
|
0057 6104.00 | 38.57 | 115.000 | 4,435.55
|
BROKEN CONCRETE RIPRAP | Mg | 115.000 | 4,435.55
|
| | 184.608 | 7,120.33
|
| | 0.000 | 0.00
|
| | |
|
4000 4310.42 | 734.00 | 0.000 | 0.00
|
1050 mm FLARED-END SECTION | EACH | 1.000 | 734.00
|
| | 1.000 | 734.00
|
| | 0.000 | 0.00
|
| | |
|
4001 4310.18 | 317.00 | 0.000 | 0.00
|
450 mm FLARED-END SECTION | EACH | 1.000 | 317.00
|
| | 2.000 | 634.00
|
| | 0.000 | 0.00
|
| | |
|
4003 4050.01 | 19.61 | 0.000 | 0.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 10.000 | 196.10
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4008 1119.00 | 350.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 350.00
|
STA. 116+50, 7.5 M RT. | | 1.000 | 350.00
|
| | 0.000 | 0.00
|
| | |
|
4009 1119.00 | 350.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 350.00
|
STA. 116+50, 13.0 M RT. | | 1.000 | 350.00
|
| | 0.000 | 0.00
|
| | |
|
4010 1119.00 | 350.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 350.00
|
STA. 115+79, RT. | | 1.000 | 350.00
|
| | 0.000 | 0.00
|
| | |
|
4011 1119.00 | 350.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 350.00
|
STA. 113+62, RT. | | 1.000 | 350.00
|
| | 0.000 | 0.00
|
| | |
|
4012 1119.00 | 350.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 350.00
|
STA. 112+66, RT. | | 1.000 | 350.00
|
| | 0.000 | 0.00
|
| | |
|
4013 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 116+50, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4014 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 115+70, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4015 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 114+88, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4016 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 114+56, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4017 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 113+94, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4018 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 113+30, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4019 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 112+75, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4020 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 112+45, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4021 1119.00 | 700.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 700.00
|
STA. 111+37, LT. | | 1.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
4022 4039.10 | 170.00 | 0.000 | 0.00
|
REMOVE AND RELAY REINFORCED CONCRETE SEWER PIPE | m | 560.000 | 95,200.00
|
(1050 mm) | | 596.930 | 101,478.10
|
| | 0.000 | 0.00
|
| | |
|
4023 P700.42 | 225.00 | 0.000 | 0.00
|
1050 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 61.000 | 13,725.00
|
(REVISED) | | 16.850 | 3,791.25
|
| | 0.000 | 0.00
|
| | |
|
4024 6603.00 | 14,497.74 | 0.000 | 0.00
|
DEWATERING | LS | 1.000 | 14,497.74
|
ROOSEVELT EAST (STA. 114+56) | | 1.000 | 14,497.74
|
| | 0.000 | 0.00
|
| | |
|
4025 6603.00 | 13,440.00 | 0.000 | 0.00
|
DEWATERING | LS | 1.000 | 13,440.00
|
(REVISED, ROOSEVELT TO BRYAN AVE.) | | 1.000 | 13,440.00
|
| | 0.000 | 0.00
|
| | |
|
4026 6603.00 | 3,458.00 | 0.000 | 0.00
|
DEWATERING | LS | 1.000 | 3,458.00
|
MAINTENANCE DURING SHUT DOWN PERIOD (13DAY*266) | | 1.000 | 3,458.00
|
| | 0.000 | 0.00
|
| | |
|
4027 1117.00 | 1,200.00 | 0.000 | 0.00
|
REMOVE MANHOLE | EACH | 1.000 | 1,200.00
|
AT STA. 114+67, LT. | | 1.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | |
|
4028 4039.10 | 72.00 | 0.000 | 0.00
|
REMOVE AND RELAY REINFORCED CONCRETE SEWER PIPE | m | 349.300 | 25,149.60
|
(375 mm & 450 mm) | | 285.899 | 20,584.73
|
| | 0.000 | 0.00
|
| | |
|
4029 1119.00 | 200.00 | 0.000 | 0.00
|
REMOVE INLET | EACH | 1.000 | 200.00
|
BASE AT STA. 110+87, LT. | | 1.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
4030 1136.10 | 1,214.26 | 0.000 | 0.00
|
REMOVE | LS | 1.000 | 1,214.26
|
FORMS INLET AT STA. 110+87, LT. | | 1.000 | 1,214.26
|
| | 0.000 | 0.00
|
| | |
|
4031 6960.02 | 5,597.43 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 5,597.43
|
LOWER WATERMAIN @ ROOSEVELT AND MEYER | | 1.000 | 5,597.43
|
| | 0.000 | 0.00
|
| | |
|
4032 W600.15 | 210.00 | 0.000 | 0.00
|
ADJUST WATER SERVICE | EACH | 11.000 | 2,310.00
|
LEFT | | 11.000 | 2,310.00
|
| | 0.000 | 0.00
|
| | |
|
4033 W600.15 | 214.76 | 0.000 | 0.00
|
ADJUST WATER SERVICE | EACH | 1.000 | 214.76
|
2" RIGHT | | 1.000 | 214.76
|
| | 0.000 | 0.00
|
| | |
|
4034 P702.18 | 174.00 | 0.000 | 0.00
|
450 mm STORM SEWER PIPE, TYPE 1 | m | 282.214 | 49,105.24
|
ARCH | | 282.222 | 49,106.63
|
| | 32.535 | 5,661.09
|
| | |
|
4042 P700.18 | 168.00 | 0.000 | 0.00
|
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 233.927 | 39,299.74
|
ARCH (SINGLE RUN) | | 221.494 | 37,210.98
|
| | 148.655 | 24,974.04
|
| | |
|
4043 P700.24 | 185.55 | 0.000 | 0.00
|
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 | m | 79.023 | 14,662.72
|
ARCH | | 68.742 | 12,755.08
|
| | 68.742 | 12,755.08
|
| | |
|
4044 4680.15 | 309.54 | 0.000 | 0.00
|
375 mm CORRUGATED METAL SLOTTED PIPE | m | 12.987 | 4,020.00
|
| | 12.987 | 4,020.00
|
| | 0.000 | 0.00
|
| | |
|
4045 4037.00 | 350.00 | 0.000 | 0.00
|
REMOVE AND REINSTALL CONCRETE FLARED END SECTIONS | EACH | 1.000 | 350.00
|
1050 mm | | 1.000 | 350.00
|
| | 0.000 | 0.00
|
| | |
|
4046 4015.50 | 2,100.00 | 0.000 | 0.00
|
RECONSTRUCT MANHOLE | EACH | 1.000 | 2,100.00
|
AT STA. 114+67.8, LT. | | 1.000 | 2,100.00
|
| | 0.000 | 0.00
|
| | |
|
4050 B003.00 | 283.43 | 0.000 | 0.00
|
UTILITIES | LS | 1.000 | 283.43
|
WINTER MONTHS | | 1.000 | 283.43
|
| | 1.000 | 283.43
|
| | |
|
GROUP 4 CULVERTS | | Contracted | 610,547.31
|
| | Current | 898,448.75
|
| | In place | 849,231.09
|
| | This Estimate | 62,061.48
|
| | |
|
GROUP 4A CULVERTS | | |
|
0058 W176.26 | 36.85 | 1,100.820 | 40,565.22
|
25 mm WATER SERVICE | m | 1,100.820 | 40,565.22
|
| | 1,040.670 | 38,348.70
|
| | 76.400 | 2,815.34
|
| | |
|
0059 W176.30 | 48.17 | 21.320 | 1,026.98
|
50 mm WATER SERVICE | m | 21.320 | 1,026.98
|
| | 22.500 | 1,083.83
|
| | 0.000 | 0.00
|
| | |
|
0060 W205.06 | 38.29 | 206.300 | 7,899.23
|
150 mm WATER MAIN PIPE | m | 206.300 | 7,899.23
|
| | 184.877 | 7,078.93
|
| | 0.000 | 0.00
|
| | |
|
0061 W205.08 | 50.18 | 73.530 | 3,689.74
|
200 mm WATER MAIN PIPE | m | 73.530 | 3,689.74
|
| | 71.914 | 3,608.65
|
| | 0.000 | 0.00
|
| | |
|
0062 W205.10 | 56.30 | 1,566.570 | 88,197.89
|
250 mm WATER MAIN PIPE | m | 1,566.570 | 88,197.89
|
| | 1,473.840 | 82,977.19
|
| | 0.000 | 0.00
|
| | |
|
0063 W219.66 | 525.89 | 5.000 | 2,629.45
|
150 mm GATE VALVE AND BOX | EACH | 5.000 | 2,629.45
|
| | 4.000 | 2,103.56
|
| | 0.000 | 0.00
|
| | |
|
0064 W219.68 | 712.99 | 3.000 | 2,138.97
|
200 mm GATE VALVE AND BOX | EACH | 3.000 | 2,138.97
|
| | 3.000 | 2,138.97
|
| | 0.000 | 0.00
|
| | |
|
0065 W219.70 | 1,050.63 | 23.000 | 24,164.49
|
250 mm GATE VALVE AND BOX | EACH | 23.000 | 24,164.49
|
| | 23.000 | 24,164.49
|
| | 1.000 | 1,050.63
|
| | |
|
0066 W222.06 | 1,860.50 | 8.000 | 14,884.00
|
150 mm FIRE HYDRANT | EACH | 8.000 | 14,884.00
|
| | 8.000 | 14,884.00
|
| | 0.000 | 0.00
|
| | |
|
0067 W355.06 | 100.32 | 1.000 | 100.32
|
150 mm SLEEVE | EACH | 1.000 | 100.32
|
| | 3.000 | 300.96
|
| | 0.000 | 0.00
|
| | |
|
0068 W355.10 | 157.80 | 1.000 | 157.80
|
250 mm SLEEVE | EACH | 1.000 | 157.80
|
| | 3.000 | 473.40
|
| | 1.000 | 157.80
|
| | |
|
0069 W356.15 | 334.49 | 1.000 | 334.49
|
250 mm X 200 mm TEE | EACH | 1.000 | 334.49
|
| | 1.000 | 334.49
|
| | 0.000 | 0.00
|
| | |
|
0070 W356.18 | 329.91 | 13.000 | 4,288.83
|
250 mm X 150 mm TEE | EACH | 13.000 | 4,288.83
|
| | 12.000 | 3,958.92
|
| | 0.000 | 0.00
|
| | |
|
0071 W356.50 | 431.61 | 2.000 | 863.22
|
CROSS | EACH | 2.000 | 863.22
|
250 X 200 | | 1.000 | 431.61
|
| | 0.000 | 0.00
|
| | |
|
0072 W356.51 | 462.71 | 1.000 | 462.71
|
CROSS | EACH | 1.000 | 462.71
|
250 X 250 | | 1.000 | 462.71
|
| | 0.000 | 0.00
|
| | |
|
0073 W357.16 | 147.12 | 9.000 | 1,324.08
|
150 mm- 45 DEGREE BEND | EACH | 9.000 | 1,324.08
|
| | 19.000 | 2,795.28
|
| | 0.000 | 0.00
|
| | |
|
0074 W357.40 | 218.62 | 12.000 | 2,623.44
|
200 mm - 45 DEGREE BEND | EACH | 12.000 | 2,623.44
|
| | 6.000 | 1,311.72
|
| | 0.000 | 0.00
|
| | |
|
0075 W357.43 | 293.32 | 12.000 | 3,519.84
|
250 mm - 45 DEGREE BEND | EACH | 12.000 | 3,519.84
|
| | 25.000 | 7,333.00
|
| | 0.000 | 0.00
|
| | |
|
0076 W800.05 | 100.00 | 7.000 | 700.00
|
REMOVE GATE VALVE AND BOX | EACH | 7.000 | 700.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0077 W800.12 | 100.00 | 4.000 | 400.00
|
REMOVE TEE | EACH | 4.000 | 400.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0078 W800.14 | 100.00 | 2.000 | 200.00
|
REMOVE REDUCER | EACH | 2.000 | 200.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0079 W800.20 | 150.00 | 1.000 | 150.00
|
REMOVE CROSS | EACH | 1.000 | 150.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0080 W800.21 | 27.00 | 151.660 | 4,094.82
|
REMOVE WATER MAIN PIPE | m | 151.660 | 4,094.82
|
| | 20.370 | 549.99
|
| | 0.000 | 0.00
|
| | |
|
0081 W800.33 | 400.00 | 8.000 | 3,200.00
|
REMOVE HYDRANT | EACH | 8.000 | 3,200.00
|
| | 6.000 | 2,400.00
|
| | 0.000 | 0.00
|
| | |
|
0082 0030.40 | 15,000.00 | 1.000 | 15,000.00
|
MOBILIZATION | LS | 1.000 | 15,000.00
|
| | 1.000 | 15,000.00
|
| | 0.000 | 0.00
|
| | |
|
0083 1117.00 | 250.00 | 2.000 | 500.00
|
REMOVE MANHOLE | EACH | 2.000 | 500.00
|
| | 2.000 | 500.00
|
| | 0.000 | 0.00
|
| | |
|
0084 4015.50 | 1,950.00 | 1.000 | 1,950.00
|
RECONSTRUCT MANHOLE | EACH | 1.000 | 1,950.00
|
| | 1.000 | 1,950.00
|
| | 0.000 | 0.00
|
| | |
|
0085 4043.50 | 18.00 | 258.400 | 4,651.20
|
REMOVE SEWER PIPE | m | 258.400 | 4,651.20
|
| | 240.828 | 4,334.90
|
| | 0.000 | 0.00
|
| | |
|
0086 4764.78 | 50.10 | 42.000 | 2,104.20
|
200 mm P.V.C. SEWER PIPE | m | 42.000 | 2,104.20
|
| | 20.800 | 1,042.08
|
| | 0.000 | 0.00
|
| | |
|
0087 4764.80 | 53.11 | 31.000 | 1,646.41
|
250 mm P.V.C. SEWER PIPE | m | 31.000 | 1,646.41
|
| | 89.790 | 4,768.75
|
| | 42.090 | 2,235.40
|
| | |
|
0088 4764.85 | 67.40 | 45.500 | 3,066.70
|
375 mm P.V.C. SEWER PIPE | m | 45.500 | 3,066.70
|
| | 45.528 | 3,068.59
|
| | 0.000 | 0.00
|
| | |
|
0089 4796.00 | 65.85 | 18.000 | 1,185.30
|
150 mm PLUG | EACH | 18.000 | 1,185.30
|
| | 6.000 | 395.10
|
| | 0.000 | 0.00
|
| | |
|
0090 4796.01 | 80.97 | 3.000 | 242.91
|
200 mm PLUG | EACH | 3.000 | 242.91
|
| | 2.000 | 161.94
|
| | 0.000 | 0.00
|
| | |
|
0091 4796.02 | 105.13 | 3.000 | 315.39
|
250 mm PLUG | EACH | 3.000 | 315.39
|
| | 1.000 | 105.13
|
| | 0.000 | 0.00
|
| | |
|
0092 4910.25 | 26.33 | 1,927.990 | 50,763.98
|
DEWATERING | m | 1,927.990 | 50,763.98
|
| | 2,447.742 | 64,449.05
|
| | 0.000 | 0.00
|
| | |
|
4006 W750.00 | 600.00 | 0.000 | 0.00
|
RELOCATE WATER METER | EACH | 34.000 | 20,400.00
|
| | 32.000 | 19,200.00
|
| | 0.000 | 0.00
|
| | |
|
4040 6960.02 | 1,910.52 | 0.000 | 0.00
|
ADDITIONAL WORK | LS | 1.000 | 1,910.52
|
LOWER WATERMAIN AT BRYAN AVE. | | 1.000 | 1,910.52
|
| | 0.000 | 0.00
|
| | |
|
4049 W600.27 | 150.00 | 0.000 | 0.00
|
ADJUST WATER METER | EACH | 4.000 | 600.00
|
PIT TO GRADE | | 4.000 | 600.00
|
| | 4.000 | 600.00
|
| | |
|
GROUP 4A CULVERTS | | Contracted | 289,041.60
|
| | Current | 311,952.12
|
| | In place | 314,226.46
|
| | This Estimate | 6,859.17
|
| | |
|
GROUP 8B ELECTRICAL | | |
|
0093 A001.12 | 250.00 | 19.000 | 4,750.00
|
PULL BOX, TYPE PB-5 | EACH | 19.000 | 4,750.00
|
| | 14.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | |
|
0094 A009.09 | 1,325.00 | 30.000 | 39,750.00
|
STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 | EACH | 30.000 | 39,750.00
|
| | 27.000 | 35,775.00
|
| | 0.000 | 0.00
|
| | |
|
0095 A009.10 | 1,500.00 | 4.000 | 6,000.00
|
STREET LIGHTING UNIT, TYPE SL-A-12.2-3-0.25 | EACH | 4.000 | 6,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0096 A009.11 | 1,600.00 | 3.000 | 4,800.00
|
STREET LIGHTING UNIT, TYPE SL-A-12.2-3.7-0.25 | EACH | 3.000 | 4,800.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0097 A009.14 | 1,800.00 | 1.000 | 1,800.00
|
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 | EACH | 1.000 | 1,800.00
|
| | 1.000 | 1,800.00
|
| | 0.000 | 0.00
|
| | |
|
0098 A020.30 | 1,500.00 | 3.000 | 4,500.00
|
LIGHTING CONTROL CENTER, TYPE R | EACH | 3.000 | 4,500.00
|
| | 3.000 | 4,500.00
|
| | 0.000 | 0.00
|
| | |
|
0099 A070.10 | 5.00 | 1,725.000 | 8,625.00
|
38 mm CONDUIT IN TRENCH | m | 2,089.000 | 10,445.00
|
| | 1,852.400 | 9,262.00
|
| | 0.000 | 0.00
|
| | |
|
0100 A072.10 | 5.00 | 654.000 | 3,270.00
|
38 mm CONDUIT UNDER ROADWAY | m | 823.000 | 4,115.00
|
| | 519.000 | 2,595.00
|
| | 29.000 | 145.00
|
| | |
|
0101 A080.10 | 2.25 | 166.000 | 373.50
|
STREET LIGHTING CABLE, NO. 2 USE | m | 166.000 | 373.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0102 A080.11 | 1.50 | 83.000 | 124.50
|
STREET LIGHTING CABLE, NO. 2 BARE | m | 83.000 | 124.50
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0103 A080.22 | 1.00 | 2,296.000 | 2,296.00
|
STREET LIGHTING CABLE, NO. 6 BARE | m | 2,296.000 | 2,296.00
|
| | 1,493.400 | 1,493.40
|
| | 0.000 | 0.00
|
| | |
|
0104 A080.24 | 1.65 | 4,592.000 | 7,576.80
|
STREET LIGHTING CABLE, NO. 6 USE | m | 4,592.000 | 7,576.80
|
| | 2,986.800 | 4,928.22
|
| | 0.000 | 0.00
|
| | |
|
0105 0030.81 | 4,000.00 | 1.000 | 4,000.00
|
MOBILIZATION | LS | 1.000 | 4,000.00
|
| | 1.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
0106 7500.23 | 265.00 | 16.000 | 4,240.00
|
LEFT ARROW, PREFORMED PAVEMENT MARKING, TYPE 3 | EACH | 16.000 | 4,240.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0107 7550.03 | 2.15 | 4,400.000 | 9,460.00
|
100 mm YELLOW EPOXY PAVEMENT MARKING | m | 4,400.000 | 9,460.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
4037 7200.00 | 327.915 | 0.000 | 0.00
|
BREAKAWAY DEVICE FOR ANCHOR BASE POLE | EACH | 28.000 | 9,181.62
|
| | 18.000 | 5,902.47
|
| | 0.000 | 0.00
|
| | |
|
4038 7200.00 | 327.915 | 0.000 | 0.00
|
BREAKAWAY DEVICE FOR ANCHOR BASE POLE | EACH | 9.000 | 2,951.24
|
| | 9.000 | 2,951.24
|
| | 0.000 | 0.00
|
| | |
|
GROUP 8B ELECTRICAL | | Contracted | 101,565.80
|
| | Current | 116,363.66
|
| | In place | 76,707.33
|
| | This Estimate | 145.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0108 0001.10 | 1.25 | 11,376.000 | 14,220.00
|
BARRICADE, TYPE III | BDAY | 11,376.000 | 14,220.00
|
| | 29,117.000 | 36,396.25
|
| | 1,204.000 | 1,505.00
|
| | |
|
0109 0001.30 | 2.25 | 237.000 | 533.25
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 237.000 | 533.25
|
| | 436.000 | 981.00
|
| | 14.000 | 31.50
|
| | |
|
0110 0001.90 | 0.25 | 14,457.000 | 3,614.25
|
SIGN DAY | EACH | 14,457.000 | 3,614.25
|
| | 17,127.000 | 4,281.75
|
| | 682.000 | 170.50
|
| | |
|
0111 0003.10 | 150.00 | 20.000 | 3,000.00
|
FLAGGING | DAY | 20.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0112 0010.04 | 2,500.00 | 1.000 | 2,500.00
|
FIELD OFFICE | EACH | 1.000 | 2,500.00
|
| | 1.000 | 2,500.00
|
| | 0.000 | 0.00
|
| | |
|
0113 0030.10 | 4,000.00 | 1.000 | 4,000.00
|
MOBILIZATION | LS | 1.000 | 4,000.00
|
| | 0.694 | 2,777.88
|
| | 0.000 | 0.00
|
| | |
|
4004 0001.08 | 0.50 | 0.000 | 0.00
|
BARRICADE, TYPE II | BDAY | 4,000.000 | 2,000.00
|
| | 19,364.000 | 9,682.00
|
| | 0.000 | 0.00
|
| | |
|
4005 0001.08 | 0.50 | 0.000 | 0.00
|
BARRICADE, TYPE II | BDAY | 1,000.000 | 500.00
|
| | 8,711.000 | 4,355.50
|
| | 256.000 | 128.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 27,867.50
|
| | Current | 30,367.50
|
| | In place | 60,974.38
|
| | This Estimate | 1,835.00
|
| | |
|
Totals for contract | | Contracted | 2,411,596.47
|
---|
| | Current | 2,760,029.73
|
---|
| | In place | 2,517,507.11
|
---|
| | This Estimate | 180,763.33
|
---|