Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1730 WILKE CONTRACTING CORPORATION
Contract ID:6197
Estimate Number:0006
Pay Period End Date:09.06.2003
Contract Location:
GOTHENBURG SOUTHEstimate Type:PROG
Contractor:
WILKE CONTRACTING CORPORATIONDate Let:09.05.2002
27705 115TH RDDate Awarded:09.12.2002
PO BOX 1205Date Contract Executed:09.26.2002
Date Notice to Proceed:09.26.2002
KEARNEY NE 68848Date Work Began:
Phone:Date Physical Work Completed:
(308)236-9014Date Accepted:
Escrow Agent:
Surety Co:
AMERICAN CASUALTY COMPANY OF READING, PENNSYLVANIA
Counties
DAWSON
Project Number PCT Fed State Project Number Description
61197 000  0.000 EACSTPD-47-2(108)  BRIDGE
61292 000  0.000 STPP-47-2(109)  BRIDGE
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$204,196.32$144,512.44$59,683.88
$406,354.95Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$204,196.32$144,512.44$59,683.88
$401,809.95Retainage$-2,041.96$-1,445.12$-596.84
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
50.25%Net Earnings$202,154.36$143,067.32$59,087.04
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$4.09$.00$4.09
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$4.09$.00$4.09
Payment$202,158.45$143,067.32$59,091.13
Project ManagerDiv. Head/Dist. Eng.
Brinker, Gary09.08.2003O'Donnell, Les09.09.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.09.2003
Controller Div. Processed
Burling, Laurie09.09.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 6 BRIDGE AT STA. 1020+36.45
0001                          L020.10 2.002,188.0004,376.00
EROSION CONTROL, TYPE HV SY 2,188.0004,376.00
0.0000.00
0.0000.00

0002                          L022.11 5.50200.0001,100.00
FABRIC SILT FENCE-LOW POROSITY LF 200.0001,100.00
0.0000.00
0.0000.00

0003                          0001.08 0.50684.000342.00
BARRICADE, TYPE II BDAY684.000342.00
562.000281.00
148.00074.00

0004                          0001.10 2.80456.0001,276.80
BARRICADE, TYPE III BDAY456.0001,276.80
344.000963.20
80.000224.00

0005                          0001.90 0.603,876.0002,325.60
SIGN DAY EACH3,876.0002,325.60
3,301.0001,980.60
760.000456.00

0006                          0002.30 0.80155.000124.00
PAVEMENT MARKING REMOVAL LF 155.000124.00
562.000449.60
207.000165.60

0007                          0002.39 1.702,000.0003,400.00
TEMPORARY PAVEMENT MARKING, TYPE II LF 2,000.0003,400.00
5,511.0009,368.70
932.0001,584.40

0008                          0002.47 2.101,000.0002,100.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION LF 1,000.0002,100.00
0.0000.00
0.0000.00

0009                          0003.51 14.00470.0006,580.00
INSTALL CONCRETE PROTECTION BARRIER LF 470.0006,580.00
460.0006,440.00
0.0000.00

0010                          0003.56 4.00470.0001,880.00
RELOCATE CONCRETE PROTECTION BARRIER LF 470.0001,880.00
450.0001,800.00
450.0001,800.00

0011                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
0.0000.00
0.0000.00

0012                          0030.60 7,800.001.0007,800.00
MOBILIZATION LS 1.0007,800.00
1.0007,800.00
0.0000.00

0013                          1009.00 1,150.001.0001,150.00
GENERAL CLEARING AND GRUBBING LS 1.0001,150.00
0.500575.00
0.0000.00

0014                          1010.01 18.00225.0004,050.00
EXCAVATION (ESTABLISHED QUANTITY) CY 225.0004,050.00
56.2501,012.50
56.2501,012.50

0015                          1011.00 18.0012.000216.00
WATER MGAL12.000216.00
0.0000.00
0.0000.00

0016                          1030.00 9.60517.0004,963.20
EARTHWORK MEASURED IN EMBANKMENT CY 517.0004,963.20
258.5002,481.60
258.5002,481.60

0017                          1043.50 1.8580.000148.00
RIPRAP FILTER FABRIC SY 80.000148.00
72.500134.13
0.0000.00

0018                          1101.00 7.70551.0004,242.70
REMOVE PAVEMENT SY 551.0004,242.70
358.3502,759.30
0.0000.00

0019                          3050.15 292.00191.70055,976.40
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-4000 CY 191.70055,976.40
80.32023,453.44
0.0000.00

0020                          3051.10 0.6021,470.00012,882.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES LB 21,470.00012,882.00
9,196.3005,517.78
0.0000.00

0021                          6000.10 1,500.001.0001,500.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0022                          6000.11 1,500.001.0001,500.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0023                          6005.35 52.00107.0005,564.00
PRECOMPRESSED POLYURETHANE FOAM JOINT LF 107.0005,564.00
38.0001,976.00
38.0001,976.00

0024                          6005.78 544.006.0003,264.00
EXPANSION BEARING, TFE TYPE EACH6.0003,264.00
3.0001,632.00
0.0000.00

0025                          6005.83 324.006.0001,944.00
FIXED BEARING EACH6.0001,944.00
3.000972.00
0.0000.00

0026                          6010.22 426.0054.00023,004.00
CLASS 47B-3000 CONCRETE FOR BRIDGE CY 54.00023,004.00
25.92011,041.92
0.0000.00

0027                          6010.26 426.0087.60037,317.60
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 87.60037,317.60
37.72016,068.72
0.0000.00

0028                          6030.00 11,400.001.00011,400.00
PREPARATION OF BRIDGE EACH1.00011,400.00
AT STA. 1020+36.45 0.5005,700.00
0.0000.00

0029                          6071.12 38,270.001.00038,270.00
STEEL SUPERSTRUCTURE LS 1.00038,270.00
AT STA. 1020+36.45 0.50019,135.00
0.0000.00

0030                          6105.01 47.0025.0001,175.00
ROCK RIPRAP, TYPE A TON 25.0001,175.00
0.0000.00
0.0000.00

0031                          6105.02 36.00205.0007,380.00
ROCK RIPRAP, TYPE B TON 205.0007,380.00
88.9003,200.40
0.0000.00

0032                          6131.50 0.6920,625.00014,231.25
EPOXY COATED REINFORCING STEEL LB 20,625.00014,231.25
8,245.8705,689.65
0.0000.00

0033                          6210.12 26.001,040.00027,040.00
HP 10"X42# STEEL PILING LF 1,040.00027,040.00
520.00013,520.00
0.0000.00

0034                          6510.55 3,600.001.0003,600.00
TEMPORARY BRIDGE SHORING LS 1.0003,600.00
0.0000.00
0.0000.00

0035                          7011.20 18.00100.0001,800.00
W-BEAM GUARDRAIL LF 100.0001,800.00
37.500675.00
37.500675.00

0036                          7017.00 3.00281.000843.00
REMOVE GUARDRAIL LF 281.000843.00
144.000432.00
0.0000.00

0037                          7020.00 1,260.004.0005,040.00
BRIDGE APPROACH SECTIONS EACH4.0005,040.00
2.0002,520.00
2.0002,520.00

0038                          7024.27 1,750.004.0007,000.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0007,000.00
2.0003,500.00
2.0003,500.00

0039                          7503.04 4.10200.000820.00
4" YELLOW PREFORMED PAVEMENT MARKING, TYPE 4 LF 200.000820.00
0.0000.00
0.0000.00

0040                          8091.00 11.0085.000935.00
GRANULAR BACKFILL CY 85.000935.00
0.0000.00
0.0000.00

0041                          9005.30 80.00180.00014,400.00
ASPHALTIC CONCRETE, TYPE SP2(0.5) TON 180.00014,400.00
110.1608,812.80
110.1608,812.80

0042                          9009.75 40.0051.0002,040.00
TEMPORARY SURFACING SY 51.0002,040.00
135.8005,432.00
0.0000.00

0043                          9021.01 340.009.7203,304.80
PERFORMANCE GRADED BINDER (64-22) TON 9.7203,304.80
0.0000.00
0.0000.00

0044                          9110.01 50.0010.000500.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000500.00
0.0000.00
0.0000.00

0045                          9110.03 50.0010.000500.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000500.00
0.0000.00
0.0000.00

0046                          9110.06 40.0010.000400.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR10.000400.00
0.0000.00
0.0000.00

0047                          9110.07 30.0010.000300.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000300.00
0.0000.00
0.0000.00

0048                          9188.50 42.0094.0003,948.00
SURFACING UNDER GUARDRAIL SY 94.0003,948.00
169.8907,135.38
169.8907,135.38

4001                          0003.10 208.000.0000.00
FLAGGING DAY 10.0002,080.00
6.0001,248.00
1.000208.00

4003                          0001.75 2.000.0000.00
TEMPORARY SIGN DAY EACH40.00080.00
0.0000.00
0.0000.00

4005                          1101.25 2.500.0000.00
SAWING PAVEMENT LF 90.000225.00
172.000430.00
0.0000.00

GROUP 6 BRIDGE AT STA. 1020+36.45Contracted335,453.35
Current337,838.35
In place177,137.72
This Estimate32,625.28

GROUP 6A BRIDGE AT STA. 175+57
0049                          L020.00 3.30847.0002,795.10
EROSION CONTROL SY 847.0002,795.10
0.0000.00
0.0000.00

0050                          0001.08 0.50186.00093.00
BARRICADE, TYPE II BDAY186.00093.00
198.00099.00
198.00099.00

0051                          0001.10 2.80124.000347.20
BARRICADE, TYPE III BDAY124.000347.20
68.000190.40
68.000190.40

0052                          0001.90 0.601,054.000632.40
SIGN DAY EACH1,054.000632.40
646.000387.60
646.000387.60

0053                          0002.30 0.802,000.0001,600.00
PAVEMENT MARKING REMOVAL LF 2,000.0001,600.00
560.000448.00
560.000448.00

0054                          0002.31 0.601,250.000750.00
TEMPORARY PAVEMENT MARKING LF 1,250.000750.00
3,602.0002,161.20
3,602.0002,161.20

0055                          0002.47 2.20750.0001,650.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION LF 750.0001,650.00
0.0000.00
0.0000.00

0056                          0003.56 10.00800.0008,000.00
RELOCATE CONCRETE PROTECTION BARRIER LF 800.0008,000.00
830.0008,300.00
830.0008,300.00

0057                          0030.60 2,600.001.0002,600.00
MOBILIZATION LS 1.0002,600.00
0.0000.00
0.0000.00

0058                          1009.00 800.001.000800.00
GENERAL CLEARING AND GRUBBING LS 1.000800.00
0.0000.00
0.0000.00

0059                          1033.00 2,950.002.7107,994.50
ROADWAY GRADING STA 2.7107,994.50
0.0000.00
0.0000.00

0060                          1102.00 5.00262.0001,310.00
REMOVE ASPHALT SURFACE SY 262.0001,310.00
0.0000.00
0.0000.00

0061                          6010.26 550.0023.90013,145.00
CLASS 47BD-4000 CONCRETE FOR BRIDGE CY 23.90013,145.00
23.90013,145.00
23.90013,145.00

0062                          6020.00 0.762,515.0001,911.40
REINFORCING STEEL FOR BRIDGE LB 2,515.0001,911.40
2,515.0001,911.40
2,515.0001,911.40

0063                          7011.20 20.0068.7501,375.00
W-BEAM GUARDRAIL LF 68.7501,375.00
0.0000.00
0.0000.00

0064                          7017.00 3.00400.0001,200.00
REMOVE GUARDRAIL LF 400.0001,200.00
0.0000.00
0.0000.00

0065                          7020.00 1,250.004.0005,000.00
BRIDGE APPROACH SECTIONS EACH4.0005,000.00
0.0000.00
0.0000.00

0066                          7024.27 1,800.004.0007,200.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0007,200.00
0.0000.00
0.0000.00

0067                          9188.50 33.00241.0007,953.00
SURFACING UNDER GUARDRAIL SY 241.0007,953.00
0.0000.00
0.0000.00

4002                          0003.10 208.000.0000.00
FLAGGING DAY 10.0002,080.00
2.000416.00
2.000416.00

4004                          0001.75 2.000.0000.00
TEMPORARY SIGN DAY EACH40.00080.00
0.0000.00
0.0000.00

GROUP 6A BRIDGE AT STA. 175+57Contracted66,356.60
Current68,516.60
In place27,058.60
This Estimate27,058.60

Totals for contractContracted401,809.95
Current406,354.95
In place204,196.32
This Estimate59,683.88