Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1342 MONARCH OIL, INC.
Contract ID:5903B
Estimate Number:0003
Pay Period End Date:07.29.2003
Contract Location:
OSHKOSH - LEWELLENEstimate Type:FINL
Contractor:
MONARCH OIL, INC.Date Let:05.23.2002
2200 AVE H EASTDate Awarded:05.30.2002
PO BOX 3189Date Contract Executed:06.25.2002
Date Notice to Proceed:06.25.2002
OMAHA NE 68103Date Work Began:10.14.2002
Phone:Date Physical Work Completed:
(402)341-5254Date Accepted:06.11.2003
Escrow Agent:
Surety Co:
UNION INSURANCE COMPANY
Counties
GARDEN
Project Number PCT Fed State Project Number Description
59903B 000  0.000 PM-26-1(1054)  BITUMINOUS
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$401,893.80$401,893.80$.00
$395,325.74Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$401,893.80$401,893.80$.00
$395,325.74Retainage$.00$-4,018.94$4,018.94
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
101.66%Net Earnings$401,893.80$397,874.86$4,018.94
Liquidated Damages-$4,743.00-$7,905.00$3,162.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$4,743.00-$7,905.00$3,162.00
Payment$397,150.80$389,969.86$7,180.94
Project ManagerDiv. Head/Dist. Eng.
Smith, Don07.29.2003Lind, Craig07.29.2003
Constr. Estimate Eng.Materials Eng.
Davis, Carl07.30.2003Hall, David07.30.2003
Controller Div. Processed
Harring, Joyce09.08.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 9 BITUMINOUS
0001                          0001.10 4.00108.000432.00
BARRICADE, TYPE III BDAY108.000432.00
135.000540.00
0.0000.00

0002                          0001.30 6.0054.000324.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY54.000324.00
0.0000.00
0.0000.00

0003                          0001.75 6.00120.000720.00
TEMPORARY SIGN DAY EACH120.000720.00
88.000528.00
0.0000.00

0004                          0001.90 2.002,430.0004,860.00
SIGN DAY EACH2,430.0004,860.00
1,416.0002,832.00
0.0000.00

0005                          0002.45 7.00662.6404,638.48
TEMPORARY BROKEN LINES STA 662.6404,638.48
715.5005,008.50
0.0000.00

0006                          0003.10 170.0030.0005,100.00
FLAGGING DAY 30.0005,100.00
58.0009,860.00
0.0000.00

0007                          0003.20 250.0015.0003,750.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 15.0003,750.00
21.5005,375.00
0.0000.00

0008                          0030.90 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0009                          8008.50 14.003,765.00052,710.00
AGGREGATE FOR MICROSURFACING TON 3,765.00052,710.00
3,561.40549,859.67
0.0000.00

0010                          8070.05 10.0075.300753.00
MINERAL FILLER FOR MICROSURFACING TON 75.300753.00
31.584315.84
0.0000.00

0011                          9009.15 324.21662.640214,834.51
MICROSURFACING PLACEMENT STA 662.640214,834.51
699.721226,856.54
0.0000.00

0012                          9052.10 0.85108,475.00092,203.75
EMULSIFIED ASPHALT FOR MICROSURFACING GAL 108,475.00092,203.75
100,845.00085,718.25
0.0000.00

GROUP 9 BITUMINOUSContracted395,325.74
Current395,325.74
In place401,893.80
This Estimate0.00

Totals for contractContracted395,325.74
Current395,325.74
In place401,893.80
This Estimate0.00