Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2283 PERRETT CONSTRUCTION LTD.
Contract ID:5862
Estimate Number:0003
Pay Period End Date:09.20.2003
Contract Location:
MARSLAND NORTHEstimate Type:PROG
Contractor:
PERRETT CONSTRUCTION LTD.Date Let:06.26.2003
120 S MACOMB STDate Awarded:07.03.2003
PO BOX 32Date Contract Executed:07.16.2003
Date Notice to Proceed:07.16.2003
VALENTINE NE 69201Date Work Began:
Phone:Date Physical Work Completed:
(402)376-3797Date Accepted:
Escrow Agent:
Surety Co:
UNITED STATES FIDELITY AND GUARANTY COMPANY
Counties
BOX BUTTE
DAWES
Project Number PCT Fed State Project Number Description
50862 000  0.000 EACSTPD-71-4(114)  GRAD CULV BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$136,682.95$85,291.80$51,391.15
$4,347,919.63Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$136,682.95$85,291.80$51,391.15
$4,347,919.63Retainage$-1,366.83$-852.92$-513.91
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
3.14%Net Earnings$135,316.12$84,438.88$50,877.24
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$135,316.12$84,438.88$50,877.24
Project ManagerDiv. Head/Dist. Eng.
Gardner, Jerrold09.22.2003Hoevet, Doug09.22.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve09.22.2003
Controller Div. Processed
Burling, Laurie09.23.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 50,000.001.00050,000.00
MOBILIZATION LS 1.00050,000.00
0.57028,500.00
0.0000.00

0002                          1000.00 350.005.0001,750.00
LARGE TREE REMOVAL EACH5.0001,750.00
0.0000.00
0.0000.00

0003                          1009.00 15,000.001.00015,000.00
GENERAL CLEARING AND GRUBBING LS 1.00015,000.00
0.0000.00
0.0000.00

0004                          1010.00 1.67496,931.000829,874.77
EXCAVATION m3 496,931.000829,874.77
0.0000.00
0.0000.00

0005                          1011.00 2.0031,479.00062,958.00
WATER kL 31,479.00062,958.00
0.0000.00
0.0000.00

0006                          1012.00 65.00170.00011,050.00
RIGHT-OF-WAY MARKERS EACH170.00011,050.00
0.0000.00
0.0000.00

0007                          1040.05 1.006,000.0006,000.00
TEMPORARY SLOPE PROTECTION m2 6,000.0006,000.00
0.0000.00
0.0000.00

0008                          1041.00 0.606,000.0003,600.00
SALVAGING AND PLACING TOPSOIL m2 6,000.0003,600.00
0.0000.00
0.0000.00

0009                          1102.00 4.002,548.00010,192.00
REMOVE ASPHALT SURFACE m2 2,548.00010,192.00
0.0000.00
0.0000.00

0010                          1137.00 1,500.001.0001,500.00
REMOVE AND RESET HISTORICAL MARKER EACH1.0001,500.00
0.0000.00
0.0000.00

0011                          1701.24 56.00247.00013,832.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 247.00013,832.00
0.0000.00
0.0000.00

0012                          7017.00 7.001,496.00010,472.00
REMOVE GUARDRAIL m 1,496.00010,472.00
0.0000.00
0.0000.00

0013                          7151.65 1,500.001.0001,500.00
REMOVE AND RESET CATTLE GUARD EACH1.0001,500.00
0.0000.00
0.0000.00

0014                          L006.00 272.0043.60011,859.20
COVER CROP SEEDING ha 43.60011,859.20
0.0000.00
0.0000.00

0015                          L020.01 5.7038,811.000221,222.70
EROSION CONTROL, TYPE A m2 38,811.000221,222.70
0.0000.00
0.0000.00

0016                          L020.03 2.002,176.0004,352.00
EROSION CONTROL, TYPE C m2 2,176.0004,352.00
0.0000.00
0.0000.00

0017                          L020.08 6.0018,206.000109,236.00
EROSION CONTROL, TYPE AA m2 18,206.000109,236.00
0.0000.00
0.0000.00

0018                          L020.10 1.5013,461.00020,191.50
EROSION CONTROL, TYPE HV m2 13,461.00020,191.50
0.0000.00
0.0000.00

0019                          L021.01 25.001,238.00030,950.00
EROSION CHECKS, TYPE A BALE1,238.00030,950.00
0.0000.00
0.0000.00

0020                          L021.03 23.0086.0001,978.00
EROSION CHECKS, TYPE C BALE86.0001,978.00
0.0000.00
0.0000.00

0021                          L021.06 22.001,258.00027,676.00
EROSION CHECKS, TYPE HV BALE1,258.00027,676.00
0.0000.00
0.0000.00

0022                          L021.11 30.0088.0002,640.00
EROSION CHECKS, TYPE ST-A BALE88.0002,640.00
0.0000.00
0.0000.00

0023                          L021.13 31.00262.0008,122.00
EROSION CHECKS, TYPE ST-AA BALE262.0008,122.00
0.0000.00
0.0000.00

0024                          L021.15 25.00102.0002,550.00
EROSION CHECKS, TYPE ST-HV BALE102.0002,550.00
0.0000.00
0.0000.00

0025                          L021.21 26.00702.00018,252.00
EROSION CHECKS, TYPE AA BALE702.00018,252.00
0.0000.00
0.0000.00

0026                          L022.25 8.507,710.00065,535.00
FABRIC SILT FENCE, TYPE COIR FIBER m 7,710.00065,535.00
1,899.00016,141.50
0.0000.00

0027                          L022.75 10.00518.0005,180.00
TEMPORARY SILT CHECK m 518.0005,180.00
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted1,547,473.17
Current1,547,473.17
In place44,641.50
This Estimate0.00

GROUP 4 CULVERTS
0028                          0030.40 35,000.001.00035,000.00
MOBILIZATION LS 1.00035,000.00
0.0000.00
0.0000.00

0029                          1043.50 2.00562.0001,124.00
RIPRAP FILTER FABRIC m2 562.0001,124.00
0.0000.00
0.0000.00

0030                          4040.00 100.0053.0005,300.00
REMOVE HEADWALLS FROM CULVERTS EACH53.0005,300.00
1.000100.00
0.0000.00

0031                          4044.00 1,500.001.0001,500.00
PREPARATION OF STRUCTURE EACH1.0001,500.00
STA 119+48.30 0.0000.00
0.0000.00

0032                          4044.01 1,500.001.0001,500.00
PREPARATION OF STRUCTURE EACH1.0001,500.00
STA 122+49.80 0.0000.00
0.0000.00

0033                          4044.02 1,500.001.0001,500.00
PREPARATION OF STRUCTURE EACH1.0001,500.00
AT STA 149+64.9 0.0000.00
0.0000.00

0034                          4044.03 1,500.001.0001,500.00
PREPARATION OF STRUCTURE EACH1.0001,500.00
AT STA 154+90.90 0.0000.00
0.0000.00

0035                          4044.04 1,500.001.0001,500.00
PREPARATION OF STRUCTURE EACH1.0001,500.00
AT STA 179+08.80 0.0000.00
0.0000.00

0036                          4050.01 10.006,227.00062,270.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 6,227.00062,270.00
2.00020.00
0.0000.00

0037                          4051.01 10.003,960.00039,600.00
EXCAVATION FOR BOX CULVERTS m3 3,960.00039,600.00
18.000180.00
0.0000.00

0038                          4101.06 350.00698.160244,356.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 698.160244,356.00
26.5359,287.25
0.0000.00

0039                          4151.00 1.4536,880.00053,476.00
REINFORCING STEEL FOR BOX CULVERT kg 36,880.00053,476.00
1,754.4402,543.94
0.0000.00

0040                          4310.24 200.0017.0003,400.00
600 mm FLARED-END SECTION EACH17.0003,400.00
0.0000.00
0.0000.00

0041                          4310.30 300.0029.0008,700.00
750 mm FLARED-END SECTION EACH29.0008,700.00
1.000300.00
0.0000.00

0042                          4310.36 400.0012.0004,800.00
900 mm FLARED-END SECTION EACH12.0004,800.00
0.0000.00
0.0000.00

0043                          4310.42 950.006.0005,700.00
1050 mm FLARED-END SECTION EACH6.0005,700.00
0.0000.00
0.0000.00

0044                          4310.54 1,200.002.0002,400.00
1350 mm FLARED-END SECTION EACH2.0002,400.00
0.0000.00
0.0000.00

0045                          4670.05 95.0028.0002,660.00
CULVERT SANDFILL m3 28.0002,660.00
0.0000.00
0.0000.00

0046                          4880.42 1,400.0015.00021,000.00
JACKING 1050 mm CULVERT PIPE, TYPE 2 CLASS IV m 15.00021,000.00
0.0000.00
0.0000.00

0047                          6105.01 40.00151.5006,060.00
ROCK RIPRAP, TYPE A Mg 151.5006,060.00
0.0000.00
0.0000.00

0048                          6105.02 40.0080.0003,200.00
ROCK RIPRAP, TYPE B Mg 80.0003,200.00
0.0000.00
0.0000.00

0049                          6105.03 40.00384.70015,388.00
ROCK RIPRAP, TYPE C Mg 384.70015,388.00
0.0000.00
0.0000.00

0050                          P120.24 150.009.0001,350.00
600 mm CULVERT PIPE, TYPE 2 m 9.0001,350.00
0.0000.00
0.0000.00

0051                          P120.30 220.0022.5004,950.00
750 mm CULVERT PIPE, TYPE 2 m 22.5004,950.00
0.0000.00
0.0000.00

0052                          P128.42 700.0015.00010,500.00
1050 mm CULVERT PIPE, TYPE 2 CLASS IV m 15.00010,500.00
0.0000.00
0.0000.00

0053                          P255.30 115.0056.5006,497.50
750 mm CULVERT PIPE, TYPE 4 OR 5 m 56.5006,497.50
0.0000.00
0.0000.00

0054                          P255.36 150.00108.90016,335.00
900 mm CULVERT PIPE, TYPE 4 OR 5 m 108.90016,335.00
0.0000.00
0.0000.00

0055                          P255.42 225.0096.80021,780.00
1050 mm CULVERT PIPE, TYPE 4 OR 5 m 96.80021,780.00
0.0000.00
0.0000.00

0056                          P255.54 270.0051.00013,770.00
1350 mm CULVERT PIPE, TYPE 4 OR 5 m 51.00013,770.00
0.0000.00
0.0000.00

0057                          P300.24 60.00154.1009,246.00
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 154.1009,246.00
0.0000.00
0.0000.00

0058                          P300.30 90.00151.30013,617.00
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 151.30013,617.00
4.500405.00
0.0000.00

0059                          P300.36 100.0042.2004,220.00
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 42.2004,220.00
0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted624,199.50
Current624,199.50
In place12,836.19
This Estimate0.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 139+41
0060                          0030.40 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
1.00015,000.00

0061                          4044.00 4,000.001.0004,000.00
PREPARATION OF STRUCTURE EACH1.0004,000.00
AT STA. 139+41 0.0000.00
0.0000.00

0062                          4051.01 10.00218.0002,180.00
EXCAVATION FOR BOX CULVERTS m3 218.0002,180.00
109.0001,090.00
0.0000.00

0063                          4101.06 350.00295.980103,593.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 295.980103,593.00
136.41347,744.55
77.35127,072.85

0064                          4151.00 1.4519,834.00028,759.30
REINFORCING STEEL FOR BOX CULVERT kg 19,834.00028,759.30
9,520.32013,804.46
6,000.0008,700.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 139+41Contracted153,532.30
Current153,532.30
In place77,639.01
This Estimate50,772.85

GROUP 9 BITUMINOUS
0065                          0002.55 22.50401.5009,033.75
OVERLAY BROKEN LINES StaM401.5009,033.75
0.0000.00
0.0000.00

0066                          0002.60 22.50803.00018,067.50
OVERLAY SOLID LINES StaM803.00018,067.50
0.0000.00
0.0000.00

0067                          0030.90 52,000.001.00052,000.00
MOBILIZATION LS 1.00052,000.00
0.0000.00
0.0000.00

0068                          1020.03 8.0083.000664.00
DELINEATOR, TYPE III EACH83.000664.00
0.0000.00
0.0000.00

0069                          1020.20 10.0040.000400.00
INSTALL CHEVRONS EACH40.000400.00
0.0000.00
0.0000.00

0070                          2001.00 16.001,750.00028,000.00
GRAVEL SURFACE COURSE m3 1,750.00028,000.00
0.0000.00
0.0000.00

0071                          2009.10 150.0025.4213,813.15
GRAVEL EMBEDMENT StaM25.4213,813.15
0.0000.00
0.0000.00

0072                          2020.00 5.75455.0002,616.25
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 455.0002,616.25
0.0000.00
0.0000.00

0073                          2021.00 40.007.000280.00
MAILBOX POST EACH7.000280.00
0.0000.00
0.0000.00

0074                          9000.75 17.25200.0003,450.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 200.0003,450.00
SP2(12.5) 0.0000.00
0.0000.00

0075                          9005.00 22.50300.0006,750.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 300.0006,750.00
SP2(12.5) 0.0000.00
0.0000.00

0076                          9005.30 20.0046,100.000922,000.00
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 46,100.000922,000.00
0.0000.00
0.0000.00

0077                          9009.00 4.002,742.00010,968.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 2,742.00010,968.00
0.0000.00
0.0000.00

0078                          9009.75 20.355,990.000121,896.50
TEMPORARY SURFACING m2 5,990.000121,896.50
0.0000.00
0.0000.00

0079                          9020.91 185.0010.8001,998.00
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 10.8001,998.00
0.0000.00
0.0000.00

0080                          9021.01 185.002,505.600463,536.00
PERFORMANCE GRADED BINDER (64-22) Mg 2,505.600463,536.00
0.0000.00
0.0000.00

0081                          9034.00 2.402,742.0006,580.80
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 2,742.0006,580.80
0.0000.00
0.0000.00

0082                          9053.00 0.3886,860.00033,006.80
TACK COAT L 86,860.00033,006.80
0.0000.00
0.0000.00

0083                          9111.00 2.401,448.0003,475.20
WATER kL 1,448.0003,475.20
0.0000.00
0.0000.00

0084                          9170.00 95.00295.59928,081.91
EARTH SHOULDER CONSTRUCTION StaM295.59928,081.91
0.0000.00
0.0000.00

0085                          9173.00 450.0046.05020,722.50
SUBGRADE PREPARATION StaM46.05020,722.50
0.0000.00
0.0000.00

0086                          9173.15 70.00153.50010,745.00
TRENCHED WIDENING StaM153.50010,745.00
0.0000.00
0.0000.00

0087                          9179.23 325.00101.75033,068.75
COLD MILLING, CLASS 3 StaM101.75033,068.75
0.0000.00
0.0000.00

0088                          9179.34 2.2520,267.00045,600.75
COLD MILLING, CLASS 4 m2 20,267.00045,600.75
0.0000.00
0.0000.00

0089                          9300.52 4,500.001.0004,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0004,500.00
0.0000.00
0.0000.00

0090                          L001.01 1,100.0033.00036,300.00
SEEDING, TYPE A ha 33.00036,300.00
0.0000.00
0.0000.00

0091                          L001.02 1,050.0010.00010,500.00
SEEDING, TYPE B ha 10.00010,500.00
0.0000.00
0.0000.00

0092                          L032.75 110.00215.00023,650.00
MULCH Mg 215.00023,650.00
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted1,901,704.86
Current1,901,704.86
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0093                          0001.08 0.5027,020.00013,510.00
BARRICADE, TYPE II BDAY27,020.00013,510.00
187.00093.50
66.00033.00

0094                          0001.10 1.5014,040.00021,060.00
BARRICADE, TYPE III BDAY14,040.00021,060.00
431.000646.50
108.000162.00

0095                          0001.75 2.00720.0001,440.00
TEMPORARY SIGN DAY EACH720.0001,440.00
0.0000.00
0.0000.00

0096                          0001.90 0.3521,228.0007,429.80
SIGN DAY EACH21,228.0007,429.80
575.000201.25
138.00048.30

0097                          0001.99 1.00720.000720.00
CONTRACTOR FURNISHED SIGN DAY EACH720.000720.00
0.0000.00
0.0000.00

0098                          0002.30 2.501,500.0003,750.00
PAVEMENT MARKING REMOVAL m 1,500.0003,750.00
0.0000.00
0.0000.00

0099                          0002.39 2.252,000.0004,500.00
TEMPORARY PAVEMENT MARKING, TYPE II m 2,000.0004,500.00
0.0000.00
0.0000.00

0100                          0002.47 1.002,000.0002,000.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 2,000.0002,000.00
0.0000.00
0.0000.00

0101                          0003.10 250.0080.00020,000.00
FLAGGING DAY 80.00020,000.00
2.500625.00
1.500375.00

0102                          0003.20 250.0040.00010,000.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 40.00010,000.00
0.0000.00
0.0000.00

0103                          0010.04 4,500.001.0004,500.00
FIELD OFFICE EACH1.0004,500.00
0.0000.00
0.0000.00

0104                          0030.00 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
0.0000.00
0.0000.00

0105                          9110.01 85.00120.00010,200.00
RENTAL OF LOADER, FULLY OPERATED HOUR120.00010,200.00
0.0000.00
0.0000.00

0106                          9110.02 75.0040.0003,000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR40.0003,000.00
0.0000.00
0.0000.00

0107                          9110.03 55.00120.0006,600.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR120.0006,600.00
0.0000.00
0.0000.00

0108                          9110.06 55.0080.0004,400.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR80.0004,400.00
0.0000.00
0.0000.00

0109                          9110.07 45.00120.0005,400.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR120.0005,400.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted121,009.80
Current121,009.80
In place1,566.25
This Estimate618.30

Totals for contractContracted4,347,919.62
Current4,347,919.62
In place136,682.95
This Estimate51,391.15