Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0477 WESTERN ENGINEERING COMPANY, INC.
Contract ID:5826
Estimate Number:0008
Pay Period End Date:08.09.2003
Contract Location:
SCOTTSBLUFF - MINATAREEstimate Type:PROG
Contractor:
WESTERN ENGINEERING COMPANY, INC.Date Let:11.14.2002
1149 WEST HIGHWAY 44Date Awarded:11.21.2002
PO BOX 350Date Contract Executed:12.06.2002
Date Notice to Proceed:12.06.2002
HARLAN IA 51537Date Work Began:
Phone:Date Physical Work Completed:
(712)755-5191Date Accepted:
Escrow Agent:
Surety Co:
HARTFORD FIRE INSURANCE COMPANY
Counties
SCOTTS BLUFF
Project Number PCT Fed State Project Number Description
50826 000  0.000 EACNH-26-1(146)  GR CONC PAVE CULV SEED ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,878,403.56$1,844,329.50$34,074.06
$8,557,825.23Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,878,403.56$1,844,329.50$34,074.06
$8,552,774.73Retainage$-18,784.04$-18,443.30$-340.74
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
21.95%Net Earnings$1,859,619.52$1,825,886.20$33,733.32
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$4,195.58$4,195.58$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$4,195.58$4,195.58$.00
Payment$1,863,815.10$1,830,081.78$33,733.32
Project ManagerDiv. Head/Dist. Eng.
Fast, Dean08.12.2003Hoevet, Doug08.15.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve08.15.2003
Controller Div. Processed
Burling, Laurie08.18.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 55,000.001.00055,000.00
MOBILIZATION LS 1.00055,000.00
1.00055,000.00
0.0000.00

0002                          1009.00 25,000.001.00025,000.00
GENERAL CLEARING AND GRUBBING LS 1.00025,000.00
1.00025,000.00
0.0000.00

0003                          1010.00 3.35393,624.0001,318,640.40
EXCAVATION m3 393,624.0001,318,640.40
362,111.2551,213,072.71
0.0000.00

0004                          1011.00 2.901,190.0003,451.00
WATER kL 1,190.0003,451.00
2,970.2238,613.65
0.0000.00

0005                          1042.00 1.00214,650.000214,650.00
SALVAGING AND PLACING HYDRIC SOIL m2 214,650.000214,650.00
193,185.000193,185.00
0.0000.00

0006                          1101.00 3.1037,445.000116,079.50
REMOVE PAVEMENT m2 37,445.000116,079.50
848.3532,629.89
0.0000.00

0007                          1101.25 8.25490.0004,042.50
SAWING PAVEMENT m 490.0004,042.50
0.0000.00
0.0000.00

0008                          1102.00 2.502,339.0005,847.50
REMOVE ASPHALT SURFACE m2 2,339.0005,847.50
0.0000.00
0.0000.00

0009                          1106.00 5.10100.000510.00
REMOVE DRIVEWAY m2 100.000510.00
0.0000.00
0.0000.00

0010                          1107.00 5.10104.000530.40
REMOVE WALK m2 104.000530.40
0.0000.00
0.0000.00

0011                          1109.00 5.102,267.00011,561.70
REMOVE CURB m 2,267.00011,561.70
0.0000.00
0.0000.00

0012                          1122.01 3.10997.0003,090.70
REMOVE CONCRETE MEDIAN SURFACING m2 997.0003,090.70
0.0000.00
0.0000.00

0013                          1701.24 66.50143.4009,536.10
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 143.4009,536.10
174.60011,610.90
0.0000.00

0014                          4004.50 3.102,040.0006,324.00
CAST IRON GRATE AND FRAME kg 2,040.0006,324.00
0.0000.00
0.0000.00

0015                          4035.00 90.004.000360.00
REMOVE FLARED-END SECTION EACH4.000360.00
4.000360.00
0.0000.00

0016                          4040.00 290.002.000580.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000580.00
1.000290.00
0.0000.00

0017                          4105.59 1,340.006.4908,696.60
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 6.4908,696.60
0.0000.00
0.0000.00

0018                          4155.50 1.50264.000396.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 264.000396.00
0.0000.00
0.0000.00

0019                          4310.18 135.0052.0007,020.00
450 mm FLARED-END SECTION EACH52.0007,020.00
49.0006,615.00
0.0000.00

0020                          7017.00 30.0017.000510.00
REMOVE GUARDRAIL m 17.000510.00
0.0000.00
0.0000.00

0021                          L006.00 350.0030.00010,500.00
COVER CROP SEEDING ha 30.00010,500.00
0.0000.00
0.0000.00

0022                          L020.01 7.40396.0002,930.40
EROSION CONTROL, TYPE A m2 396.0002,930.40
0.0000.00
0.0000.00

0023                          L020.10 1.813,540.0006,407.40
EROSION CONTROL, TYPE HV m2 3,540.0006,407.40
0.0000.00
0.0000.00

0024                          L021.01 24.006.000144.00
EROSION CHECKS, TYPE A BALE6.000144.00
0.0000.00
0.0000.00

0025                          L021.06 18.00414.0007,452.00
EROSION CHECKS, TYPE HV BALE414.0007,452.00
0.0000.00
0.0000.00

0026                          L022.75 15.00260.0003,900.00
TEMPORARY SILT CHECK m 260.0003,900.00
0.0000.00
0.0000.00

0027                          P400.18 90.00484.80043,632.00
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 484.80043,632.00
443.60039,924.00
0.0000.00

4001                          7390.10 388.500.0000.00
REMOVE SIGN, POST, AND FOOTING EACH13.0005,050.50
Remove 13 Billboard Signs 12.0004,662.00
0.0000.00

GROUP 1 GRADINGContracted1,866,792.20
Current1,871,842.70
In place1,560,963.15
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0028                          0002.55 21.50103.2802,220.52
OVERLAY BROKEN LINES StaM103.2802,220.52
0.0000.00
0.0000.00

0029                          0002.60 21.50206.5604,441.04
OVERLAY SOLID LINES StaM206.5604,441.04
0.0000.00
0.0000.00

0030                          0002.61 19.601,000.00019,600.00
PLOWABLE PAVEMENT MARKER EACH1,000.00019,600.00
0.0000.00
0.0000.00

0031                          0030.30 145,000.001.000145,000.00
MOBILIZATION LS 1.000145,000.00
0.0000.00
0.0000.00

0032                          2001.00 13.50128.0001,728.00
GRAVEL SURFACE COURSE m3 128.0001,728.00
0.0000.00
0.0000.00

0033                          3011.23 54.0081.0004,374.00
CONCRETE CLASS 47B-25 CURB, TYPE 1 m 81.0004,374.00
0.0000.00
0.0000.00

0034                          3012.08 36.401,309.00047,647.60
CONCRETE CLASS 47B-25 MEDIAN LIP CURB m 1,309.00047,647.60
0.0000.00
0.0000.00

0035                          3016.21 21.00102.0002,142.00
CONCRETE CLASS 47B-20 SIDEWALKS m2 102.0002,142.00
0.0000.00
0.0000.00

0036                          3017.40 15.0015,625.800234,387.00
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 15,625.800234,387.00
0.0000.00
0.0000.00

0037                          3020.24 20.0058.5001,170.00
CONCRETE CLASS 47B-25 DRIVEWAY m2 58.5001,170.00
0.0000.00
0.0000.00

0038                          3075.22 20.001,495.00029,900.00
180 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 1,495.00029,900.00
0.0000.00
0.0000.00

0039                          3075.42 21.6012,009.000259,394.40
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 12,009.000259,394.40
0.0000.00
0.0000.00

0040                          3075.46 25.57121,471.0003,106,013.47
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 121,471.0003,106,013.47
0.0000.00
0.0000.00

0041                          3089.25 17.00908.00015,436.00
TEMPORARY SURFACING m2 908.00015,436.00
0.0000.00
0.0000.00

0042                          3300.50 4,500.001.0004,500.00
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.0004,500.00
0.0000.00
0.0000.00

0043                          3300.65 100.0068.0006,800.00
CONCRETE PAVEMENT THICKNESS CORE EACH68.0006,800.00
0.0000.00
0.0000.00

0044                          4024.55 54.0021.0001,134.00
FLUME SPILLWAY m 21.0001,134.00
0.0000.00
0.0000.00

0045                          4024.71 2,000.001.0002,000.00
CONCRETE FLUME, TYPE II EACH1.0002,000.00
0.0000.00
0.0000.00

0046                          7502.14 6.5031,000.000201,500.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 31,000.000201,500.00
0.0000.00
0.0000.00

0047                          7503.14 6.5019,000.000123,500.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 19,000.000123,500.00
0.0000.00
0.0000.00

0048                          7508.14 21.35250.0005,337.50
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 250.0005,337.50
0.0000.00
0.0000.00

0049                          8029.10 2.60154,963.000402,903.80
AGGREGATE FOUNDATION COURSE-D 100 mm m2 154,963.000402,903.80
0.0000.00
0.0000.00

0050                          9000.75 19.60300.0005,880.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 300.0005,880.00
SP5(12.5) 0.0000.00
0.0000.00

0051                          9005.00 27.50100.0002,750.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0002,750.00
SP5(12.5) 0.0000.00
0.0000.00

0052                          9005.23 18.604,860.00090,396.00
ASPHALTIC CONCRETE, TYPE SPS Mg 4,860.00090,396.00
0.0000.00
0.0000.00

0053                          9005.55 22.308,950.000199,585.00
ASPHALTIC CONCRETE, TYPE SP5(12.5) Mg 8,950.000199,585.00
0.0000.00
0.0000.00

0054                          9009.86 11.4522,957.000262,857.65
SURFACING 150mm m2 22,957.000262,857.65
0.0000.00
0.0000.00

0055                          9009.87 21.107,755.000163,630.50
SURFACING 200mm m2 7,755.000163,630.50
0.0000.00
0.0000.00

0056                          9020.96 258.0016.2004,179.60
PERFORMANCE GRADED BINDER (70-28) FOR STATE MAINTENANCEPATCHING Mg 16.2004,179.60
0.0000.00
0.0000.00

0057                          9021.03 185.00262.50048,562.50
PERFORMANCE GRADED BINDER (58-28) Mg 262.50048,562.50
0.0000.00
0.0000.00

0058                          9021.04 258.00526.500135,837.00
PERFORMANCE GRADED BINDER (70-28) Mg 526.500135,837.00
0.0000.00
0.0000.00

0059                          9053.00 0.3781,330.00030,092.10
TACK COAT L 81,330.00030,092.10
0.0000.00
0.0000.00

0060                          9111.00 2.402,945.0007,068.00
WATER kL 2,945.0007,068.00
694.5651,666.96
694.5651,666.96

0061                          9140.00 118.00137.00016,166.00
JOINT SEALING - ASPHALT TO CONCRETE StaM137.00016,166.00
0.0000.00
0.0000.00

0062                          9170.00 200.00230.96746,193.40
EARTH SHOULDER CONSTRUCTION StaM230.96746,193.40
0.0000.00
0.0000.00

0063                          9173.20 0.40165,520.00066,208.00
SUBGRADE PREPARATION m2 165,520.00066,208.00
0.0000.00
0.0000.00

0064                          9179.33 0.85119,597.000101,657.45
COLD MILLING, CLASS 3 m2 119,597.000101,657.45
0.0000.00
0.0000.00

0065                          9300.50 2,700.001.0002,700.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0002,700.00
0.0000.00
0.0000.00

0066                          L010.00 10.00226.0002,260.00
SODDING m2 226.0002,260.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted5,807,152.53
Current5,807,152.53
In place1,666.96
This Estimate1,666.96

GROUP 4 CULVERTS
0067                          0030.40 9,200.001.0009,200.00
MOBILIZATION LS 1.0009,200.00
1.0009,200.00
0.0000.00

0068                          1119.00 280.003.000840.00
REMOVE INLET EACH3.000840.00
0.0000.00
0.0000.00

0069                          4035.00 90.006.000540.00
REMOVE FLARED-END SECTION EACH6.000540.00
0.0000.00
0.0000.00

0070                          4035.25 113.0011.0001,243.00
REMOVE AND SALVAGE FLARED-END SECTION EACH11.0001,243.00
11.0001,243.00
0.0000.00

0071                          4040.00 143.0012.0001,716.00
REMOVE HEADWALLS FROM CULVERTS EACH12.0001,716.00
5.000715.00
0.0000.00

0072                          4041.00 2,048.001.0002,048.00
CULVERT CLEANOUT EACH1.0002,048.00
AT STA. 105+53 1.0002,048.00
0.0000.00

0073                          4043.50 24.4028.000683.20
REMOVE SEWER PIPE m 28.000683.20
0.0000.00
0.0000.00

0074                          4044.00 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 93+70.83 1.0002,000.00
0.0000.00

0075                          4050.01 10.80847.8009,156.24
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 847.8009,156.24
644.7256,963.03
0.0000.00

0076                          4051.01 15.0067.0001,005.00
EXCAVATION FOR BOX CULVERTS m3 67.0001,005.00
67.0001,005.00
0.0000.00

0077                          4101.06 350.0037.85013,247.50
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 37.85013,247.50
42.29614,803.60
0.0000.00

0078                          4107.07 580.0015.4008,932.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 15.4008,932.00
9.8205,695.60
0.0000.00

0079                          4151.00 2.002,639.0005,278.00
REINFORCING STEEL FOR BOX CULVERT kg 2,639.0005,278.00
2,940.8625,881.72
0.0000.00

0080                          4157.00 2.30113.000259.90
REINFORCING STEEL FOR COLLARS kg 113.000259.90
92.000211.60
0.0000.00

0081                          4310.18 139.001.000139.00
450 mm FLARED-END SECTION EACH1.000139.00
1.000139.00
0.0000.00

0082                          4310.24 162.004.000648.00
600 mm FLARED-END SECTION EACH4.000648.00
4.000648.00
0.0000.00

0083                          4310.48 1,134.002.0002,268.00
1200 mm FLARED-END SECTION EACH2.0002,268.00
2.0002,268.00
0.0000.00

0084                          4320.24 182.004.000728.00
600 mm ROUND EQUIVALENT FLARED-END SECTION EACH4.000728.00
4.000728.00
0.0000.00

0085                          4461.24 90.002.000180.00
INSTALL 600 mm CONCRETE FLARED-END SECTION EACH2.000180.00
2.000180.00
0.0000.00

0086                          4461.36 100.002.000200.00
INSTALL 900 mm CONCRETE FLARED-END SECTION EACH2.000200.00
4.000400.00
0.0000.00

0087                          4461.42 120.001.000120.00
INSTALL 1050 mm CONCRETE FLARED-END SECTION EACH1.000120.00
1.000120.00
0.0000.00

0088                          4465.36 115.002.000230.00
INSTALL 900 mm ROUND EQUIVALENT CONCRETE FLARED-END SECTION EACH2.000230.00
2.000230.00
0.0000.00

0089                          4465.42 140.002.000280.00
INSTALL 1050 mm ROUND EQUIVALENT CONCRETE FLARED-END SECTION EACH2.000280.00
0.0000.00
0.0000.00

0090                          4465.48 180.001.000180.00
INSTALL 1200 mm ROUND EQUIVALENT CONCRETE FLARED-END SECTION EACH1.000180.00
1.000180.00
0.0000.00

0091                          4465.54 200.001.000200.00
INSTALL 1350 mm ROUND EQUIVALENT CONCRETE FLARED-END SECTION EACH1.000200.00
1.000200.00
0.0000.00

0092                          P070.18 75.008.000600.00
450 mm CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 8.000600.00
8.000600.00
0.0000.00

0093                          P120.24 118.0042.8005,050.40
600 mm CULVERT PIPE, TYPE 2 m 42.8005,050.40
48.7005,746.60
0.0000.00

0094                          P120.36 208.0035.5007,384.00
900 mm CULVERT PIPE, TYPE 2 m 35.5007,384.00
60.60012,604.80
0.0000.00

0095                          P120.42 261.0018.0004,698.00
1050 mm CULVERT PIPE TYPE 2 m 18.0004,698.00
18.7004,880.70
0.0000.00

0096                          P127.36 284.0037.20010,564.80
900 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 37.20010,564.80
36.60010,394.40
0.0000.00

0097                          P127.42 328.0028.4009,315.20
1050 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 28.4009,315.20
0.0000.00
0.0000.00

0098                          P127.48 387.0037.50014,512.50
1200 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 37.50014,512.50
37.00014,319.00
0.0000.00

0099                          P127.54 426.0020.0008,520.00
1350 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 20.0008,520.00
37.80016,102.80
0.0000.00

0100                          P420.24 85.0040.3003,425.50
600 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2,3,4 OR 5 m 40.3003,425.50
40.0003,400.00
0.0000.00

0101                          P600.24 81.2545.8003,721.25
600 mm CULVERT PIPE, TYPE 2,3,4,5,7 OR 8 m 45.8003,721.25
46.0003,737.51
0.0000.00

GROUP 4 CULVERTSContracted129,113.49
Current129,113.49
In place126,645.36
This Estimate0.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 79+27.056
0102                          0030.40 25,000.001.00025,000.00
MOBILIZATION LS 1.00025,000.00
1.00025,000.00
0.50012,500.00

0103                          1043.50 2.80205.000574.00
RIPRAP FILTER FABRIC m2 205.000574.00
0.0000.00
0.0000.00

0104                          4051.01 18.00687.00012,366.00
EXCAVATION FOR BOX CULVERTS m3 687.00012,366.00
546.1009,829.80
340.0006,120.00

0105                          4101.06 324.00814.790263,991.96
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 814.790263,991.96
259.58184,104.25
0.0000.00

0106                          4151.00 1.2557,605.00072,006.25
REINFORCING STEEL FOR BOX CULVERT kg 57,605.00072,006.25
18,138.19522,672.74
0.0000.00

0107                          6040.00 25,000.001.00025,000.00
REMOVE STRUCTURE EACH1.00025,000.00
AT STA. 79+27.056 0.0000.00
0.0000.00

0108                          6105.02 45.00269.00012,105.00
ROCK RIPRAP, TYPE B Mg 269.00012,105.00
0.0000.00
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 79+27.056Contracted411,043.21
Current411,043.21
In place141,606.79
This Estimate18,620.00

GROUP 5 SEEDING
0109                          0030.50 1,550.001.0001,550.00
MOBILIZATION LS 1.0001,550.00
0.0000.00
0.0000.00

0110                          L001.01 1,425.0018.00025,650.00
SEEDING, TYPE A ha 18.00025,650.00
0.0000.00
0.0000.00

0111                          L001.02 1,180.0012.00014,160.00
SEEDING, TYPE B ha 12.00014,160.00
0.0000.00
0.0000.00

0112                          L032.75 85.00150.00012,750.00
MULCH Mg 150.00012,750.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted54,110.00
Current54,110.00
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0113                          0030.81 3,600.001.0003,600.00
MOBILIZATION LS 1.0003,600.00
0.5001,800.00
0.5001,800.00

0114                          A001.01 450.006.0002,700.00
PULL BOX, TYPE PB-1 EACH6.0002,700.00
0.0000.00
0.0000.00

0115                          A001.02 350.001.000350.00
PULL BOX, TYPE PB-1A EACH1.000350.00
0.0000.00
0.0000.00

0116                          A001.12 350.001.000350.00
PULL BOX, TYPE PB-5 EACH1.000350.00
0.0000.00
0.0000.00

0117                          A001.16 400.001.000400.00
PULL BOX, TYPE PB-6 EACH1.000400.00
0.0000.00
0.0000.00

0118                          A006.98 200.004.000800.00
VEHICLE DETECTOR, TYPE A PREFORMED EACH4.000800.00
0.0000.00
0.0000.00

0119                          A007.00 250.008.0002,000.00
VEHICLE DETECTOR, TYPE B PREFORMED EACH8.0002,000.00
0.0000.00
0.0000.00

0120                          A009.14 1,500.001.0001,500.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH1.0001,500.00
0.0000.00
0.0000.00

0121                          A009.57 1,700.001.0001,700.00
STREET LIGHTING UNIT, TYPE SL-BT-13.7-3.7-0.25 EACH1.0001,700.00
0.0000.00
0.0000.00

0122                          A070.10 6.501,370.0008,905.00
38 mm CONDUIT IN TRENCH m 1,370.0008,905.00
0.0000.00
0.0000.00

0123                          A070.14 7.5010.20076.50
50 mm CONDUIT IN TRENCH m 10.20076.50
0.0000.00
0.0000.00

0124                          A072.10 7.00169.0001,183.00
38 mm CONDUIT UNDER ROADWAY m 169.0001,183.00
15.500108.50
15.500108.50

0125                          A072.18 11.0057.400631.40
75 mm CONDUIT UNDER ROADWAY m 57.400631.40
0.0000.00
0.0000.00

0126                          A074.12 32.004.000128.00
38 mm CONDUIT, JACKED m 4.000128.00
0.0000.00
0.0000.00

0127                          A080.22 1.301,517.0001,972.10
STREET LIGHTING CABLE, NO. 6 BARE m 1,517.0001,972.10
0.0000.00
0.0000.00

0128                          A080.24 1.403,034.0004,247.60
STREET LIGHTING CABLE, NO. 6 USE m 3,034.0004,247.60
0.0000.00
0.0000.00

0129                          A700.20 825.0023.00018,975.00
RELOCATE STREET LIGHTING UNIT EACH23.00018,975.00
4.0003,300.00
4.0003,300.00

GROUP 8B ELECTRICALContracted49,518.60
Current49,518.60
In place5,208.50
This Estimate5,208.50

GROUP 10 GENERAL ITEMS
0130                          0001.08 0.5022,590.00011,295.00
BARRICADE, TYPE II BDAY22,590.00011,295.00
0.0000.00
0.0000.00

0131                          0001.10 4.0026,571.000106,284.00
BARRICADE, TYPE III BDAY26,571.000106,284.00
1,963.0007,852.00
252.0001,008.00

0132                          0001.75 3.80100.000380.00
TEMPORARY SIGN DAY EACH100.000380.00
228.000866.40
0.0000.00

0133                          0001.90 0.9041,993.00037,793.70
SIGN DAY EACH41,993.00037,793.70
4,716.0004,244.40
634.000570.60

0134                          0002.30 0.9017,300.00015,570.00
PAVEMENT MARKING REMOVAL m 17,300.00015,570.00
0.0000.00
0.0000.00

0135                          0002.44 0.3615,750.0005,670.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 15,750.0005,670.00
0.0000.00
0.0000.00

0136                          0002.97 52.00263.00013,676.00
FLASHING ARROW PANEL DAY 263.00013,676.00
0.0000.00
0.0000.00

0137                          0003.10 245.0020.0004,900.00
FLAGGING DAY 20.0004,900.00
60.00014,700.00
0.0000.00

0138                          0003.51 36.00591.00021,276.00
INSTALL CONCRETE PROTECTION BARRIER m 591.00021,276.00
0.0000.00
0.0000.00

0139                          0010.04 2,300.001.0002,300.00
FIELD OFFICE EACH1.0002,300.00
0.0000.00
0.0000.00

0140                          0030.10 14,000.001.00014,000.00
MOBILIZATION LS 1.00014,000.00
1.00014,000.00
0.5007,000.00

0141                          9110.01 50.0010.000500.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000500.00
0.0000.00
0.0000.00

0142                          9110.02 50.0010.000500.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000500.00
13.000650.00
0.0000.00

0143                          9110.03 45.0010.000450.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000450.00
0.0000.00
0.0000.00

0144                          9110.07 45.0010.000450.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000450.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted235,044.70
Current235,044.70
In place42,312.80
This Estimate8,578.60

Totals for contractContracted8,552,774.73
Current8,557,825.23
In place1,878,403.56
This Estimate34,074.06