Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:1826 REED CONSTRUCTION & SUPPLY, INC./PAUL
Contract ID:5777A
Estimate Number:0022
Pay Period End Date:04.13.2002
Contract Location:
MINATARE EASTEstimate Type:PROG
Contractor:
REED CONSTRUCTION & SUPPLY, INC./PAULDate Let:03.29.2001
880 E COUNTRY CLUB RDDate Awarded:04.06.2001
Date Contract Executed:04.13.2001
Date Notice to Proceed:04.13.2001
GERING NE 69341Date Work Began:
Phone:Date Physical Work Completed:
(308)635-2213Date Accepted:
Escrow Agent:
Surety Co:
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
Counties
MORRILL
SCOTTS BLUFF
Project Number PCT Fed State Project Number Description
50777A 000  0.000 S-26-1(1047)  GR CP CULV BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,645,741.39$1,627,552.60$18,188.79
$2,278,470.29Stockpiled Materials$744.54$744.54$.00
Original Contract AmtGross Earnings$1,646,485.93$1,628,297.14$18,188.79
$1,944,898.92Retainage$-16,457.41$-16,275.53$-181.88
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
72.23%Net Earnings$1,630,028.52$1,612,021.61$18,006.91
Liquidated Damages-$74,844.00-$74,844.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$111.10$111.10$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$74,732.90-$74,732.90$.00
Payment$1,555,295.62$1,537,288.71$18,006.91
Project ManagerDiv. Head/Dist. Eng.
Fast, Dean04.15.2002Lind, Craig04.18.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve04.19.2002
Controller Div. Processed
Burling, Laurie04.19.2002
Detailed breakdown of stockpiled materials
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00846200.00 CONCRETE PILING
S.P. Initial Payment14,581.841
Concrete Piling - Stored
40196011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Initial Payment36,696.00117
IT Girders - Stored
Total for estimate 0013:51,277.84
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00846200.00 CONCRETE PILING
S.P. Adjustment-6,862.441
Concrete Piling - Stored
Total for estimate 0016:-6,862.44
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00846200.00 CONCRETE PILING
S.P. Adjustment-4,521.401
Concrete Piling - Stored
40196011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-12,274.18117
IT Girders - Stored
Total for estimate 0017:-16,795.58
Est Nbr:0018
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00846200.00 CONCRETE PILING
S.P. Adjustment-2,453.461
Concrete Piling - Stored
40196011.11 PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE
S.P. Adjustment-24,421.82117
IT Girders - Stored
Total for estimate 0018:-26,875.28
Total remaining for contract:744.54
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.00 1.75920.0001,610.00
EROSION CONTROL m2 920.0001,610.00
0.0000.00
0.0000.00

0002                          L022.25 10.00816.0008,160.00
FABRIC SILT FENCE, TYPE COIR FIBER m 816.0008,160.00
587.8005,878.00
65.000650.00

0003                          L022.75 18.0052.900952.20
TEMPORARY SILT CHECK m 52.900952.20
13.400241.20
0.0000.00

0004                          0030.10 8.001.0008.00
MOBILIZATION LS 1.0008.00
1.0008.00
0.0000.00

0005                          1009.00 10,000.001.00010,000.00
GENERAL CLEARING AND GRUBBING LS 1.00010,000.00
1.00010,000.00
0.0000.00

0006                          1010.01 3.002,382.0007,146.00
EXCAVATION (ESTABLISHED QUANTITY) m3 2,382.0007,146.00
0.0000.00
0.0000.00

0007                          1011.00 1.253,954.0004,942.50
WATER kL 3,954.0004,942.50
0.0000.00
0.0000.00

0008                          1012.00 60.0068.0004,080.00
RIGHT-OF-WAY MARKERS EACH68.0004,080.00
75.0004,500.00
0.0000.00

0009                          1030.00 5.9521,088.000125,473.60
EARTHWORK MEASURED IN EMBANKMENT m3 21,088.000125,473.60
18,706.000111,300.70
0.0000.00

0010                          1040.05 0.505,975.0002,987.50
TEMPORARY SLOPE PROTECTION m2 5,975.0002,987.50
0.0000.00
0.0000.00

0011                          1101.00 3.25580.0001,885.00
REMOVE PAVEMENT m2 580.0001,885.00
958.9113,116.46
0.0000.00

0012                          1102.00 2.257,607.00017,115.75
REMOVE ASPHALT SURFACE m2 7,607.00017,115.75
3,486.3567,844.32
0.0000.00

0013                          1300.18 70.0013.200924.00
450 mm DRIVEWAY CULVERT PIPE m 13.200924.00
13.200924.00
0.0000.00

0014                          1300.54 300.0025.6007,680.00
1350 mm DRIVEWAY CULVERT PIPE m 25.6007,680.00
25.6007,680.00
0.0000.00

0015                          1320.48 272.0012.0003,264.00
1200 mm CORRUGATED METAL PIPE FOR DRIVEWAY CULVERT PIPE m 12.0003,264.00
12.0003,264.00
0.0000.00

0016                          4040.00 500.002.0001,000.00
REMOVE HEADWALLS FROM CULVERTS EACH2.0001,000.00
2.0001,000.00
0.0000.00

0017                          7017.00 6.00922.3505,534.10
REMOVE GUARDRAIL m 922.3505,534.10
681.8174,090.90
0.0000.00

0018                          7151.65 500.001.000500.00
REMOVE AND RESET CATTLE GUARD EACH1.000500.00
1.000500.00
1.000500.00

0019                          9110.01 75.0020.0001,500.00
RENTAL OF LOADER, FULLY OPERATED HOUR20.0001,500.00
3.000225.00
0.0000.00

0020                          9110.03 45.0020.000900.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR20.000900.00
0.0000.00
0.0000.00

0021                          9110.07 35.0020.000700.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR20.000700.00
0.0000.00
0.0000.00

4001                          1143.00 16.650.0000.00
REMOVE DRIVEWAY CULVERT PIPE m 7.900131.54
7.900131.54
0.0000.00

4002                          1405.00 42.600.0000.00
RELAYING DRIVEWAY CULVERT PIPE m 7.900336.54
7.900336.54
0.0000.00

4003                          1300.24 116.670.0000.00
600 mm DRIVEWAY CULVERT PIPE m 3.000350.01
Extension 3.000350.01
0.0000.00

GROUP 1 GRADINGContracted206,362.65
Current207,180.74
In place161,390.67
This Estimate1,150.00

GROUP 3 CONCRETE PAVEMENT
0022                          L001.02 1,500.002.5003,750.00
SEEDING, TYPE B ha 2.5003,750.00
1.2811,921.50
1.2811,921.50

0023                          L032.75 200.0012.5002,500.00
MULCH Mg 12.5002,500.00
6.4051,281.00
6.4051,281.00

0024                          0030.30 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
1.0001,000.00
0.0000.00

0025                          2001.00 20.0068.0001,360.00
GRAVEL SURFACE COURSE m3 68.0001,360.00
29.555591.10
0.0000.00

0026                          3008.05 7.302,127.00015,527.10
TIE BARS EACH2,127.00015,527.10
27.000197.10
0.0000.00

0027                          3075.11 24.00306.0007,344.00
155 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 306.0007,344.00
253.2896,078.94
0.0000.00

0028                          3075.31 25.008,565.000214,125.00
205 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 8,565.000214,125.00
2,235.55255,888.82
0.0000.00

0029                          8111.20 2.307,015.00016,134.50
SHOULDER SUBGRADE PREPARATION m2 7,015.00016,134.50
4,399.33010,118.45
0.0000.00

0030                          9009.75 33.008,060.000265,980.00
TEMPORARY SURFACING m2 8,060.000265,980.00
205 mm 3,817.547125,979.06
0.0000.00

0031                          9111.00 1.25114.000142.50
WATER kL 114.000142.50
0.0000.00
0.0000.00

0032                          9173.20 30.001,396.00041,880.00
SUBGRADE PREPARATION m2 1,396.00041,880.00
1,994.30359,829.09
-6.171-185.13

0033                          9188.50 33.00142.0004,686.00
SURFACING UNDER GUARDRAIL m2 142.0004,686.00
222.3837,338.64
-6.171-203.64

GROUP 3 CONCRETE PAVEMENTContracted574,429.10
Current574,429.10
In place270,223.70
This Estimate2,813.73

GROUP 4 CULVERTS
0034                          0030.40 7,000.001.0007,000.00
MOBILIZATION LS 1.0007,000.00
1.0007,000.00
0.0000.00

0035                          1043.50 4.00180.000720.00
RIPRAP FILTER FABRIC m2 180.000720.00
282.0181,128.07
0.0000.00

0036                          4040.00 250.0010.0002,500.00
REMOVE HEADWALLS FROM CULVERTS EACH10.0002,500.00
6.0001,500.00
0.0000.00

0037                          4044.00 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 38+91.3 1.0002,500.00
0.0000.00

0038                          4044.01 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 87+62.8 1.0002,500.00
0.0000.00

0039                          4044.02 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 95+89 1.0002,500.00
0.0000.00

0040                          4044.03 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 110+98 1.0002,500.00
0.0000.00

0041                          4044.04 2,500.001.0002,500.00
PREPARATION OF STRUCTURE EACH1.0002,500.00
AT STA. 123+83 1.0002,500.00
0.0000.00

0042                          4045.00 10,000.001.00010,000.00
REMOVE STRUCTURE EACH1.00010,000.00
AT STA. 30+10.38 RT. 1.00010,000.00
0.0000.00

0043                          4050.01 12.5028.000350.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 28.000350.00
0.0000.00
0.0000.00

0044                          4051.01 12.50307.0003,837.50
EXCAVATION FOR BOX CULVERTS m3 307.0003,837.50
307.0003,837.50
0.0000.00

0045                          4101.06 330.00220.54072,778.20
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 220.54072,778.20
222.56973,447.77
0.0000.00

0046                          4107.07 200.001.000200.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 1.000200.00
1.000200.00
0.0000.00

0047                          4130.06 400.000.320128.00
CLASS 47B-20 OR AX-20 CONCRETE FOR PIPE CULVERT PLUG m3 0.320128.00
0.320128.00
0.0000.00

0048                          4151.00 1.4111,786.00016,618.26
REINFORCING STEEL FOR BOX CULVERT kg 11,786.00016,618.26
11,875.17416,744.00
0.0000.00

0049                          4350.72 450.0016.5007,425.00
1800 mm CORRUGATED METAL PIPE m 16.5007,425.00
16.5007,425.00
0.0000.00

0050                          4360.30 425.002.000850.00
750 mm METAL FLARED-END SECTION EACH2.000850.00
2.000850.00
0.0000.00

0051                          4450.42 210.006.0001,260.00
1050 mm REINFORCED CONCRETE PIPE m 6.0001,260.00
6.0001,260.00
0.0000.00

0052                          4460.42 850.002.0001,700.00
1050 mm CONCRETE FLARED-END SECTION EACH2.0001,700.00
2.0001,700.00
0.0000.00

0053                          6040.00 1,000.001.0001,000.00
REMOVE STRUCTURE EACH1.0001,000.00
AT STA. 18+38 1.0001,000.00
0.0000.00

0054                          6040.02 1,000.001.0001,000.00
REMOVE STRUCTURE EACH1.0001,000.00
AT STA. 58+43-15 m RT. 0.0000.00
0.0000.00

0055                          6104.00 10.0056.000560.00
BROKEN CONCRETE RIPRAP Mg 56.000560.00
231.0422,310.42
0.0000.00

0056                          6105.02 27.0072.0001,944.00
ROCK RIPRAP, TYPE B Mg 72.0001,944.00
70.0001,890.00
0.0000.00

4004                          4048.25 16.500.0000.00
REMODEL EACH22.000363.00
Remodel Wing Steel 22.000363.00
0.0000.00

4005                          4051.10 20.000.0000.00
GRANULAR BACKFILL FOR BOX CULVERT m3 10.000200.00
3" Crushed Concrete 4.98099.60
0.0000.00

GROUP 4 CULVERTSContracted142,370.96
Current142,933.96
In place143,383.36
This Estimate0.00

GROUP 4A CULVERT AT STA. 36+08
0057                          0030.40 11,000.001.00011,000.00
MOBILIZATION LS 1.00011,000.00
1.00011,000.00
0.0000.00

0058                          4051.01 12.001,278.00015,336.00
EXCAVATION FOR BOX CULVERTS m3 1,278.00015,336.00
1,278.00015,336.00
0.0000.00

0059                          4101.06 330.00456.330150,588.90
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 456.330150,588.90
456.330150,588.90
0.0000.00

0060                          4151.00 1.4131,198.00043,989.18
REINFORCING STEEL FOR BOX CULVERT kg 31,198.00043,989.18
31,221.75944,022.68
0.0000.00

0061                          6040.02 10,000.001.00010,000.00
REMOVE STRUCTURE EACH1.00010,000.00
AT STA. 36+11.8 1.00010,000.00
0.0000.00

GROUP 4A CULVERT AT STA. 36+08Contracted230,914.08
Current230,914.08
In place230,947.58
This Estimate0.00

GROUP 4B CULVERT AT STA. 102+29
0062                          0030.40 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0063                          4051.01 12.00388.0004,656.00
EXCAVATION FOR BOX CULVERTS m3 388.0004,656.00
388.0004,656.00
0.0000.00

0064                          4101.06 330.00191.30763,131.31
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 191.30763,131.31
191.30763,131.31
0.0000.00

0065                          4151.00 1.4113,083.00018,447.03
REINFORCING STEEL FOR BOX CULVERT kg 13,083.00018,447.03
13,083.37118,447.56
0.0000.00

0066                          6040.04 10,000.001.00010,000.00
REMOVE STRUCTURE EACH1.00010,000.00
AT STA. 102+29.6 1.00010,000.00
0.0000.00

GROUP 4B CULVERT AT STA. 102+29Contracted101,234.34
Current101,234.34
In place101,234.87
This Estimate0.00

GROUP 4C CULVERT AT STA. 134+17
0067                          0030.40 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0068                          4051.01 12.00292.0003,504.00
EXCAVATION FOR BOX CULVERTS m3 292.0003,504.00
292.0003,504.00
0.0000.00

0069                          4101.06 330.00239.51379,039.29
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 239.51379,039.29
239.51379,039.29
0.0000.00

0070                          4151.00 1.4115,408.00021,725.28
REINFORCING STEEL FOR BOX CULVERT kg 15,408.00021,725.28
15,407.71721,724.88
0.0000.00

0071                          6040.05 10,000.001.00010,000.00
REMOVE STRUCTURE EACH1.00010,000.00
AT STA. 134+20.5 1.00010,000.00
0.0000.00

GROUP 4C CULVERT AT STA. 134+17Contracted120,268.57
Current120,268.57
In place120,268.17
This Estimate0.00

GROUP 6 BRIDGE AT STA. 30+44.5
0072                          0030.60 19,600.001.00019,600.00
MOBILIZATION LS 0.0000.00
0.0000.00
0.0000.00

0073                          1010.01 12.50380.0004,750.00
EXCAVATION (ESTABLISHED QUANTITY) m3 0.0000.00
0.0000.00
0.0000.00

0074                          3050.15 340.00140.00047,600.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 0.0000.00
0.0000.00
0.0000.00

0075                          3051.10 1.959,655.00018,827.25
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 0.0000.00
0.0000.00
0.0000.00

0076                          6000.10 10,450.001.00010,450.00
ABUTMENT NO.1 EXCAVATION LS 0.0000.00
0.0000.00
0.0000.00

0077                          6000.11 10,450.001.00010,450.00
ABUTMENT NO.2 EXCAVATION LS 0.0000.00
0.0000.00
0.0000.00

0078                          6010.22 580.0058.50033,930.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 0.0000.00
0.0000.00
0.0000.00

0079                          6010.26 580.00144.20083,636.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 0.0000.00
0.0000.00
0.0000.00

0080                          6040.01 22,900.001.00022,900.00
REMOVE STRUCTURE EACH0.0000.00
AT STA. 30+45 0.0000.00
0.0000.00

0081                          6105.01 35.00207.0007,245.00
ROCK RIPRAP, TYPE A Mg 207.0007,245.00
204.0307,141.05
0.0000.00

0082                          6131.50 1.9520,820.00040,599.00
EPOXY COATED REINFORCING STEEL kg 0.0000.00
0.0000.00
0.0000.00

0083                          6139.50 69.0016.0001,104.00
SUBSURFACE DRAINAGE MATTING m2 0.0000.00
0.0000.00
0.0000.00

0084                          6200.00 120.00560.80067,296.00
CONCRETE PILING m 560.80067,296.00
536.26064,351.20
0.0000.00

0085                          6310.00 148.00221.40032,767.20
STEEL SHEET PILING m2 0.0000.00
0.0000.00
0.0000.00

0086                          8091.00 14.50140.0002,030.00
GRANULAR BACKFILL m3 0.0000.00
0.0000.00
0.0000.00

0405                          0030.60 1.000
MOBILIZATION LS 2.0000.00
Revised 0.0000.00
0.0000.00

0406                          1010.01 12.530.0000.00
EXCAVATION (ESTABLISHED QUANTITY) m3 380.0004,761.40
Revised 0.0000.00
0.0000.00

0407                          3050.15 341.000.0000.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 152.40051,968.40
Revised 0.0000.00
0.0000.00

0408                          3051.10 1.620.0000.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,502.00015,393.24
Revised 0.0000.00
0.0000.00

0409                          6000.10 5,220.000.0000.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,220.00
Revised 0.0000.00
0.0000.00

0410                          6000.11 5,220.000.0000.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,220.00
Revised 0.0000.00
0.0000.00

0411                          6010.22 590.000.0000.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 62.40036,816.00
Revised 0.0000.00
0.0000.00

0412                          6010.26 375.000.0000.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 81.30030,487.50
Revised 0.0000.00
0.0000.00

0413                          6040.01 20,880.000.0000.00
REMOVE STRUCTURE EACH1.00020,880.00
Revised 0.0000.00
0.0000.00

0414                          6131.50 1.600.0000.00
EPOXY COATED REINFORCING STEEL kg 15,415.00024,664.00
Revised 0.0000.00
0.0000.00

0415                          6139.50 70.000.0000.00
SUBSURFACE DRAINAGE MATTING m2 16.0001,120.00
Revised 0.0000.00
0.0000.00

0416                          6310.00 150.000.0000.00
STEEL SHEET PILING m2 221.40033,210.00
Revised 0.0000.00
0.0000.00

0417                          8091.00 14.590.0000.00
GRANULAR BACKFILL m3 140.0002,042.60
Revised 0.0000.00
0.0000.00

0418                          6011.11 77,360.000.0000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00077,360.00
Revised 0.0000.00
0.0000.00

4006                          0030.60 1.000
MOBILIZATION LS 2.0000.00
1.00019,500.00
0.0000.00

4007                          1010.01 12.530.0000.00
EXCAVATION (ESTABLISHED QUANTITY) m3 380.0004,761.40
380.0004,761.40
0.0000.00

4008                          3050.15 341.000.0000.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 152.40051,968.40
152.40051,968.40
0.0000.00

4009                          3051.10 1.620.0000.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,502.00015,393.24
11,213.10018,165.22
0.0000.00

4010                          6000.10 5,220.000.0000.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,220.00
1.0005,220.00
0.0000.00

4011                          6000.11 5,220.000.0000.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,220.00
1.0005,220.00
0.0000.00

4012                          6010.22 590.000.0000.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 62.40036,816.00
62.40036,816.00
0.0000.00

4013                          6010.26 375.000.0000.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 81.30030,487.50
81.30030,487.50
0.0000.00

4014                          6040.01 20,880.000.0000.00
REMOVE STRUCTURE EACH1.00020,880.00
1.00020,880.00
0.0000.00

4015                          6131.50 1.600.0000.00
EPOXY COATED REINFORCING STEEL kg 15,415.00024,664.00
15,415.00024,664.00
0.0000.00

4016                          6139.50 70.000.0000.00
SUBSURFACE DRAINAGE MATTING m2 16.0001,120.00
0.0000.00
0.0000.00

4017                          6310.00 150.000.0000.00
STEEL SHEET PILING m2 221.40033,210.00
221.40033,210.00
0.0000.00

4018                          8091.00 14.590.0000.00
GRANULAR BACKFILL m3 140.0002,042.60
140.0002,042.60
0.0000.00

4019                          6011.11 77,360.000.0000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00077,360.00
1.00077,360.00
0.0000.00

4020                          6200.50 72.000.0000.00
PAY CUT-OFF FOR CONCRETE PILING m 8.000576.00
24.5801,769.76
0.0000.00

4022                          6970.00 766.450.0000.00
FREIGHT LS 1.000766.45
1.000766.45
1.000766.45

GROUP 6 BRIDGE AT STA. 30+44.5Contracted403,184.45
Current733,169.73
In place404,323.58
This Estimate766.45

GROUP 7 GUARDRAIL
0087                          0030.70 2,200.001.0002,200.00
MOBILIZATION LS 1.0002,200.00
1.0002,200.00
0.0000.00

0088                          7011.20 54.4068.5803,730.75
W-BEAM GUARDRAIL m 68.5803,730.75
68.5803,730.76
34.2901,865.38

0089                          7020.00 1,250.004.0005,000.00
BRIDGE APPROACH SECTIONS EACH4.0005,000.00
4.0005,000.00
2.0002,500.00

0090                          7021.70 2,000.004.0008,000.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0008,000.00
4.0008,000.00
2.0004,000.00

0091                          7023.00 1,500.002.0003,000.00
TERMINAL ANCHORAGE SECTIONS EACH2.0003,000.00
4.0006,000.00
0.0000.00

4021                          7015.00 22.050.0000.00
CABLE GUARDRAIL m 100.0002,205.00
90.5001,995.53
90.5001,995.53

GROUP 7 GUARDRAILContracted21,930.75
Current24,135.75
In place26,926.29
This Estimate10,360.91

GROUP 10 GENERAL ITEMS
0092                          0001.08 0.506,910.0003,455.00
BARRICADE, TYPE II BDAY6,910.0003,455.00
17,818.0008,909.00
251.000125.50

0093                          0001.10 2.123,296.0006,987.52
BARRICADE, TYPE III BDAY3,296.0006,987.52
6,396.00013,559.52
70.000148.40

0094                          0001.30 2.401,552.0003,724.80
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,552.0003,724.80
650.0001,560.00
10.00024.00

0095                          0001.90 0.5514,594.0008,026.70
SIGN DAY EACH14,594.0008,026.70
22,787.00012,532.85
270.000148.50

0096                          0002.30 3.201,600.0005,120.00
PAVEMENT MARKING REMOVAL m 1,600.0005,120.00
4,744.30415,181.76
441.0001,411.20

0097                          0002.44 1.1010,400.00011,440.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 10,400.00011,440.00
9,034.1259,937.54
741.000815.10

0098                          0003.10 425.0050.00021,250.00
FLAGGING DAY 50.00021,250.00
67.50028,687.50
1.000425.00

0099                          0003.51 25.00528.00013,200.00
INSTALL CONCRETE PROTECTION BARRIER m 528.00013,200.00
1,027.00025,675.00
0.0000.00

0100                          0003.70 425.0020.0008,500.00
TEMPORARY RUMBLE STRIP EACH20.0008,500.00
20.0008,500.00
0.0000.00

0101                          0003.75 9,400.005.00047,000.00
TEMPORARY TRAFFIC SIGNAL EACH5.00047,000.00
5.00047,000.00
0.0000.00

0102                          0010.04 7,500.001.0007,500.00
FIELD OFFICE EACH1.0007,500.00
1.0007,500.00
0.0000.00

0103                          0030.00 8,000.001.0008,000.00
MOBILIZATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted144,204.02
Current144,204.02
In place187,043.17
This Estimate3,097.70

Totals for contractContracted1,944,898.92
Current2,239,470.29
In place1,645,741.39
This Estimate18,188.79