Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2853 SIMON CONTRACTORS AND SUBSIDIARIES
Contract ID:5740
Estimate Number:0009
Pay Period End Date:08.09.2003
Contract Location:
IN ALLIANCEEstimate Type:PROG
Contractor:
SIMON CONTRACTORS AND SUBSIDIARIESDate Let:02.06.2003
4819 S INDUSTRIAL SERVICE RDDate Awarded:02.13.2003
PO BOX 347Date Contract Executed:02.24.2003
Date Notice to Proceed:02.24.2003
CHEYENNE WY 82003-0347Date Work Began:03.31.2003
Phone:Date Physical Work Completed:
(307)632-7900Date Accepted:
Escrow Agent:
Surety Co:
LIBERTY MUTUAL INSURANCE COMPANY
Counties
BOX BUTTE
Project Number PCT Fed State Project Number Description
50740 000  0.000 EACNH-2-1(116)  GR CP CULV ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$885,499.77$812,867.71$72,632.06
$2,008,593.23Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$885,499.77$812,867.71$72,632.06
$1,957,596.79Retainage$-8,855.00$-8,128.68$-726.32
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
44.09%Net Earnings$876,644.77$804,739.03$71,905.74
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-94.91$-94.91$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$94.91-$94.91$.00
Payment$876,549.86$804,644.12$71,905.74
Project ManagerDiv. Head/Dist. Eng.
Frickey, Russ08.11.2003Hoevet, Doug08.15.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve08.15.2003
Controller Div. Processed
Burling, Laurie08.18.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 4,600.001.0004,600.00
MOBILIZATION LS 1.0004,600.00
1.0004,600.00
0.0000.00

0002                          1009.00 1,886.491.0001,886.49
GENERAL CLEARING AND GRUBBING LS 1.0001,886.49
1.0001,886.49
0.0000.00

0003                          1011.00 1.171,185.0001,386.45
WATER kL 1,185.0001,386.45
0.0000.00
0.0000.00

0004                          1030.00 4.896,770.00033,105.30
EARTHWORK MEASURED IN EMBANKMENT m3 7,788.42038,085.37
3,450.29016,871.91
0.0000.00

0005                          1101.00 4.3112,056.00051,961.36
REMOVE PAVEMENT m2 12,056.00051,961.36
5,203.73322,428.09
0.0000.00

0006                          1101.25 8.201,500.00012,300.00
SAWING PAVEMENT m 2,118.00017,367.60
1,200.7509,846.15
0.0000.00

0007                          1102.00 1.585,080.5008,027.19
REMOVE ASPHALT SURFACE m2 5,859.5009,258.01
3,343.3605,282.51
0.0000.00

0008                          1106.00 4.842,415.00011,688.60
REMOVE DRIVEWAY m2 2,415.00011,688.60
1,640.7617,941.28
223.1391,079.99

0009                          1107.00 3.6274.000267.88
REMOVE WALK m2 74.000267.88
96.910350.81
0.0000.00

0010                          1109.00 9.94210.0002,087.40
REMOVE CURB m 210.0002,087.40
168.0001,669.92
0.0000.00

0011                          1116.00 18.0514.000252.70
REMOVE GUARD POST EACH14.000252.70
20.000361.00
0.0000.00

0012                          1120.00 758.161.000758.16
REMOVE DISCHARGE STRUCTURE EACH1.000758.16
1.000758.16
0.0000.00

0013                          1122.01 3.631,188.0004,312.44
REMOVE CONCRETE MEDIAN SURFACING m2 1,188.0004,312.44
1,197.3594,346.41
0.0000.00

0014                          1123.00 37.9180.0003,032.80
REMOVE CONCRETE DITCH LINER m2 80.0003,032.80
100.0003,791.00
0.0000.00

0015                          1701.24 89.5819.0001,702.02
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 19.0001,702.02
0.0000.00
0.0000.00

0016                          4310.24 294.362.000588.72
600 mm FLARED-END SECTION EACH2.000588.72
0.0000.00
0.0000.00

0017                          7017.00 7.1553.000378.95
REMOVE GUARDRAIL m 53.000378.95
45.000321.75
0.0000.00

4004                          4976.05 4,051.420.0000.00
ADDITIONAL WORK LS 1.0004,051.42
1.0004,051.42
0.0000.00

4005                          8091.00 22.780.0000.00
GRANULAR BACKFILL m3 81.1001,847.46
$27.67 - $4.89 = $22.78 Agreed Price 81.1001,847.46
0.0000.00

4006                          1000.00 500.000.0000.00
LARGE TREE REMOVAL EACH2.0001,000.00
649+68 23 m Lt.649+74 22 m Lt. 2.0001,000.00
0.0000.00

4007                          9110.01 58.000.0000.00
RENTAL OF LOADER, FULLY OPERATED HOUR60.0003,480.00
0.0000.00
0.0000.00

4008                          9110.02 89.000.0000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR40.0003,560.00
0.0000.00
0.0000.00

4009                          9110.03 60.000.0000.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR40.0002,400.00
0.0000.00
0.0000.00

4010                          9110.07 38.000.0000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR30.0001,140.00
0.0000.00
0.0000.00

4011                          9110.06 45.000.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR30.0001,350.00
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted138,336.46
Current168,443.83
In place87,354.36
This Estimate1,079.99

GROUP 3 CONCRETE PAVEMENT
0018                          0030.30 51,766.901.00051,766.90
MOBILIZATION LS 1.00051,766.90
1.00051,766.90
0.0000.00

0019                          2001.00 21.7612.000261.12
GRAVEL SURFACE COURSE m3 12.000261.12
0.0000.00
0.0000.00

0020                          2010.00 45.76100.0004,576.00
CRUSHED ROCK SURFACE COURSE m3 100.0004,576.00
0.0000.00
0.0000.00

0021                          2021.05 75.078.000600.56
REMOVE AND RESET MAILBOX EACH8.000600.56
6.000450.42
0.0000.00

0022                          3008.05 6.54626.0004,094.04
TIE BARS EACH626.0004,094.04
0.0000.00
0.0000.00

0023                          3013.10 201.6072.00014,515.20
CONCRETE CLASS 47B-20 BARRIER CURB m 72.00014,515.20
0.0000.00
0.0000.00

0024                          3016.21 22.091,587.00035,056.83
CONCRETE CLASS 47B-20 SIDEWALKS m2 1,587.00035,056.83
41.493916.58
0.0000.00

0025                          3017.40 21.961,398.00030,700.08
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 1,398.00030,700.08
0.0000.00
0.0000.00

0026                          3020.24 25.812,561.00066,099.41
CONCRETE CLASS 47B-25 DRIVEWAY m2 2,561.00066,099.41
1,351.98234,894.65
326.0008,414.06

0027                          3075.12 30.601,366.00041,799.60
155 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 1,366.00041,799.60
517.66015,840.27
0.0000.00

0028                          3075.42 31.734,351.000138,057.23
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 4,351.000138,057.23
292.0009,265.16
292.0009,265.16

0029                          3075.46 36.0016,923.000609,228.00
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 16,923.000609,228.00
7,586.643273,119.15
661.17723,802.37

0030                          3089.25 30.481,231.00037,520.88
TEMPORARY SURFACING m2 0.0000.00
200 mm 0.0000.00
0.0000.00

0031                          3300.65 202.1412.0002,425.68
CONCRETE PAVEMENT THICKNESS CORE EACH12.0002,425.68
0.0000.00
0.0000.00

0032                          4015.00 419.216.0002,515.26
ADJUST MANHOLE TO GRADE EACH6.0002,515.26
0.0000.00
0.0000.00

0033                          7500.32 224.0012.0002,688.00
ARROW, PREFORMED PAVEMENT MARKING, TYPE 4 EACH12.0002,688.00
0.0000.00
0.0000.00

0034                          7502.14 2.521,350.0003,402.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 1,350.0003,402.00
0.0000.00
0.0000.00

0035                          7503.14 2.521,975.0004,977.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 1,975.0004,977.00
0.0000.00
0.0000.00

0036                          7508.03 7.8440.000313.60
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 3 m 40.000313.60
0.0000.00
0.0000.00

0037                          7509.14 9.3575.000701.25
300 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 75.000701.25
0.0000.00
0.0000.00

0038                          7512.03 15.6875.0001,176.00
600 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 3 m 75.0001,176.00
0.0000.00
0.0000.00

0039                          8029.10 3.2922,408.00073,722.32
AGGREGATE FOUNDATION COURSE-D 100 mm m2 22,408.00073,722.32
8,316.16827,360.20
525.1551,727.76

0040                          9111.00 4.04423.0001,708.92
WATER kL 423.0001,708.92
0.0000.00
0.0000.00

0041                          9170.00 343.8323.2507,994.05
EARTH SHOULDER CONSTRUCTION StaM23.2507,994.05
0.0000.00
0.0000.00

0042                          9173.20 1.8325,201.00046,117.83
SUBGRADE PREPARATION m2 25,201.00046,117.83
8,940.49516,361.11
622.6611,139.47

0043                          L001.02 2,240.000.6801,523.20
SEEDING, TYPE B ha 0.6801,523.20
0.0000.00
0.0000.00

0044                          L010.00 10.081,863.00018,779.04
SODDING m2 1,863.00018,779.04
0.0000.00
0.0000.00

0045                          L032.80 2,240.001.8004,032.00
HYDROMULCH Mg 1.8004,032.00
0.0000.00
0.0000.00

0046                          W600.03 183.5620.0003,671.20
ADJUST VALVE BOX TO GRADE EACH20.0003,671.20
0.0000.00
0.0000.00

0047                          W600.21 1,680.005.0008,400.00
ADJUST FIRE HYDRANT TO GRADE EACH5.0008,400.00
0.0000.00
0.0000.00

4001                          3089.25 22.000.0000.00
TEMPORARY SURFACING m2 1,580.00034,760.00
150mm SP3 1,386.04430,492.97
441.1549,705.39

4002                          9005.35 44.500.0000.00
ASPHALTIC CONCRETE, TYPE SP3(12.5) Mg 410.00018,245.00
North Sided 3rd Street 422.36418,795.20
0.0000.00

4003                          9179.23 420.000.0000.00
COLD MILLING, CLASS 3 StaM6.1802,595.60
North Side 3rd Street 5.9002,478.00
0.0000.00

4012                          4015.50 6,759.030.0000.00
RECONSTRUCT MANHOLE EACH1.0006,759.03
AT STA. 651+14.48 RT. 0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,218,423.20
Current1,243,261.95
In place481,740.61
This Estimate54,054.21

GROUP 4 CULVERTS
0048                          0030.40 3,920.001.0003,920.00
MOBILIZATION LS 1.0003,920.00
1.0003,920.00
0.0000.00

0049                          1119.00 560.001.000560.00
REMOVE INLET EACH1.000560.00
0.0000.00
0.0000.00

0050                          4002.00 3.363,181.00010,688.16
CAST IRON COVER AND FRAME kg 3,181.00010,688.16
0.0000.00
0.0000.00

0051                          4004.50 3.08474.0001,459.92
CAST IRON GRATE AND FRAME kg 474.0001,459.92
487.0001,499.96
340.0001,047.20

0052                          4016.00 2,576.001.0002,576.00
MANHOLE EACH1.0002,576.00
AT STA. 649+76.86 RT. 1.0002,576.00
0.0000.00

0053                          4016.01 2,352.001.0002,352.00
MANHOLE EACH1.0002,352.00
AT STA. 650+48.84 RT. 1.0002,352.00
0.0000.00

0054                          4016.02 2,352.001.0002,352.00
MANHOLE EACH1.0002,352.00
AT STA. 651+14.48 RT. 1.0002,352.00
0.0000.00

0055                          4016.03 2,576.001.0002,576.00
MANHOLE EACH1.0002,576.00
AT STA. 651+92.73 RT. 1.0002,576.00
0.0000.00

0056                          4016.04 2,576.001.0002,576.00
MANHOLE EACH1.0002,576.00
AT STA. 652+11.68 RT. 1.0002,576.00
0.0000.00

0057                          4016.05 2,688.001.0002,688.00
MANHOLE EACH1.0002,688.00
AT STA. 652+95.84 RT. 1.0002,688.00
0.0000.00

0058                          4016.06 4,480.001.0004,480.00
MANHOLE EACH1.0004,480.00
AT STA. 653+50.13 RT. 1.0004,480.00
0.0000.00

0059                          4016.07 2,688.001.0002,688.00
MANHOLE EACH1.0002,688.00
AT STA. 654+09.13 RT. 1.0002,688.00
0.0000.00

0060                          4016.08 2,576.001.0002,576.00
MANHOLE EACH1.0002,576.00
AT STA. 654+61.10 RT. 1.0002,576.00
0.0000.00

0061                          4016.09 2,576.001.0002,576.00
MANHOLE EACH1.0002,576.00
AT STA. 655+11.57 RT. 0.0000.00
0.0000.00

0062                          4016.10 2,352.001.0002,352.00
MANHOLE EACH1.0002,352.00
AT STA. 656+21.53 RT. 0.0000.00
0.0000.00

0063                          4035.00 224.004.000896.00
REMOVE FLARED-END SECTION EACH4.000896.00
3.000672.00
0.0000.00

0064                          4044.00 5,600.001.0005,600.00
PREPARATION OF STRUCTURE EACH1.0005,600.00
AT STA. 652+02.21 1.0005,600.00
0.0000.00

0065                          4050.01 28.00313.0008,764.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 313.0008,764.00
307.0008,596.00
0.0000.00

0066                          4051.01 112.006.000672.00
EXCAVATION FOR BOX CULVERTS m3 6.000672.00
6.000672.00
0.0000.00

0067                          4101.06 448.9564.28028,858.51
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 64.28028,858.51
66.39029,805.80
0.0000.00

0068                          4105.59 728.0060.24043,854.72
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 60.24043,854.72
18.38013,380.64
14.40010,483.20

0069                          4151.00 1.784,033.0007,178.74
REINFORCING STEEL FOR BOX CULVERT kg 4,033.0007,178.74
4,033.0007,178.75
0.0000.00

0070                          4155.50 1.441,878.0002,704.32
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 1,878.0002,704.32
157.000226.08
99.000142.56

0071                          4310.24 532.004.0002,128.00
600 mm FLARED-END SECTION EACH4.0002,128.00
3.0001,596.00
0.0000.00

0072                          P500.24 106.40104.00011,065.60
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 104.00011,065.60
104.00011,065.60
0.0000.00

0073                          P700.12 78.404.000313.60
300 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 4.000313.60
4.000313.60
0.0000.00

0074                          P700.18 86.24181.00015,609.44
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 181.00015,609.44
33.4002,880.42
0.0000.00

0075                          P700.24 106.40284.00030,217.60
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 284.00030,217.60
222.48023,671.87
0.0000.00

0076                          P700.30 140.00250.00035,000.00
750 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 250.00035,000.00
250.00035,000.00
0.0000.00

0077                          P700.36 201.607.0001,411.20
900 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 7.0001,411.20
0.0000.00
0.0000.00

0078                          P775.30 190.4018.0003,427.20
750 mm ROUND EQUIVALENT STORM SEWER PIPE, TYPE 1 m 18.0003,427.20
6.0001,142.40
0.0000.00

0079                          P775.36 280.008.0002,240.00
900 mm ROUND EQUIVALENT STORM SEWER PIPE, TYPE 1 m 8.0002,240.00
15.0004,200.00
0.0000.00

0080                          P775.48 403.2086.00034,675.20
1200 mm ROUND EQUIVALENT STORM SEWER PIPE, TYPE 1 m 86.00034,675.20
86.00034,675.20
0.0000.00

GROUP 4 CULVERTSContracted281,036.21
Current281,036.21
In place210,960.32
This Estimate11,672.96

GROUP 8B ELECTRICAL
0081                          0003.76 5,040.001.0005,040.00
TEMPORARY TRAFFIC SIGNAL EACH1.0005,040.00
AT 3rd STREET & CODY AVENUE 1.0005,040.00
0.0000.00

0082                          0030.81 1,634.081.0001,634.08
MOBILIZATION LS 1.0001,634.08
1.0001,634.08
0.0000.00

0083                          A001.01 504.0012.0006,048.00
PULL BOX, TYPE PB-1 EACH7.0003,528.00
1.000504.00
1.000504.00

0084                          A001.02 448.005.0002,240.00
PULL BOX, TYPE PB-1A EACH3.0001,344.00
3.0001,344.00
0.0000.00

0085                          A001.05 672.001.000672.00
PULL BOX, TYPE PB-2 EACH1.000672.00
0.0000.00
0.0000.00

0086                          A001.06 616.006.0003,696.00
PULL BOX, TYPE PB-2A EACH6.0003,696.00
4.0002,464.00
0.0000.00

0087                          A001.12 392.0011.0004,312.00
PULL BOX, TYPE PB-5 EACH11.0004,312.00
0.0000.00
0.0000.00

0088                          A001.16 448.002.000896.00
PULL BOX, TYPE PB-6 EACH2.000896.00
0.0000.00
0.0000.00

0089                          A004.00 672.0024.00016,128.00
TRAFFIC SIGNAL, TYPE TS-1 EACH24.00016,128.00
0.0000.00
0.0000.00

0090                          A004.04 1,120.001.0001,120.00
TRAFFIC SIGNAL, TYPE TS-1LL EACH1.0001,120.00
0.0000.00
0.0000.00

0091                          A006.15 560.008.0004,480.00
PEDESTRIAN SIGNAL, TYPE PS-1 EACH24.00013,440.00
4.0002,240.00
0.0000.00

0092                          A006.70 168.004.000672.00
PEDESTRIAN PUSHBUTTON, TYPE PPB EACH4.000672.00
2.000336.00
0.0000.00

0093                          A006.98 308.0030.0009,240.00
VEHICLE DETECTOR, TYPE A PREFORMED EACH16.0004,928.00
0.0000.00
0.0000.00

0094                          A007.00 336.0024.0008,064.00
VEHICLE DETECTOR, TYPE B PREFORMED EACH14.0004,704.00
7.0002,352.00
0.0000.00

0095                          A007.08 448.005.0002,240.00
VEHICLE DETECTOR, TYPE TD-3 EACH5.0002,240.00
0.0000.00
0.0000.00

0096                          A009.09 1,456.0018.00026,208.00
STREET LIGHTING UNIT TYPE SL-A-12.2-2.4-0.25 EACH18.00026,208.00
0.0000.00
0.0000.00

0097                          A009.14 1,792.0012.00021,504.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH12.00021,504.00
0.0000.00
0.0000.00

0098                          A010.70 280.001.000280.00
LUMINAIRE EACH1.000280.00
0.0000.00
0.0000.00

0099                          A010.76 392.001.000392.00
LUMINAIRE ARM EACH1.000392.00
0.0000.00
0.0000.00

0100                          A011.15 4,480.008.00035,840.00
COMBINATION MAST ARM SIGNAL AND LIGHTING POLE,TYPE CMP-9.5-0.0 EACH8.00035,840.00
0.0000.00
0.0000.00

0101                          A012.05 6,160.001.0006,160.00
COMBINATION MAST ARM SIGNAL AND LIGHTING POLE,TYPE CMP-14-3.7 EACH1.0006,160.00
0.0000.00
0.0000.00

0102                          A016.60 3,360.001.0003,360.00
MAST ARM SIGNAL POLE, TYPE MP-12.5 EACH1.0003,360.00
0.0000.00
0.0000.00

0103                          A020.30 1,120.002.0002,240.00
LIGHTING CONTROL CENTER, TYPE R EACH2.0002,240.00
0.0000.00
0.0000.00

0104                          A070.10 7.28983.0007,156.24
38 mm CONDUIT IN TRENCH m 983.0007,156.24
148.5001,081.08
0.0000.00

0105                          A070.14 7.84145.0001,136.80
50 mm CONDUIT IN TRENCH m 128.0001,003.52
83.050651.11
0.0000.00

0106                          A072.10 7.84454.0003,559.36
38 mm CONDUIT UNDER ROADWAY m 454.0003,559.36
141.0391,105.74
0.0000.00

0107                          A072.14 8.4097.000814.80
50 mm CONDUIT UNDER ROADWAY m 56.000470.40
46.900393.96
0.0000.00

0108                          A072.18 11.2075.000840.00
75 mm CONDUIT UNDER ROADWAY m 75.000840.00
0.0000.00
0.0000.00

0109                          A077.12 1.12131.000146.72
2/C #14 AWG TRAFFIC SIGNAL CABLE m 131.000146.72
0.0000.00
0.0000.00

0110                          A077.22 3.36337.0001,132.32
12/C #14 AWG TRAFFIC SIGNAL CABLE m 337.0001,132.32
0.0000.00
0.0000.00

0111                          A079.01 1.01827.000835.27
2/C #14 AWG DETECTOR LEAD-IN CABLE m 827.000835.27
0.0000.00
0.0000.00

0112                          A079.50 1.01260.000262.60
GROUNDING CONDUCTOR m 260.000262.60
0.0000.00
0.0000.00

0113                          A079.55 2.249.00020.16
SERVICE CABLE m 9.00020.16
0.0000.00
0.0000.00

0114                          A080.22 1.621,437.0002,327.94
STREET LIGHTING CABLE, NO. 6 BARE m 1,437.0002,327.94
0.0000.00
0.0000.00

0115                          A080.24 1.792,874.0005,144.46
STREET LIGHTING CABLE, NO. 6 USE m 2,874.0005,144.46
0.0000.00
0.0000.00

0116                          A110.70 840.001.000840.00
LUMINAIRE EXTENSION EACH1.000840.00
0.0000.00
0.0000.00

0117                          A500.00 1,120.002.0002,240.00
INSTALL TRAFFIC SIGNAL CONTROLLER EACH2.0002,240.00
TYPE TC-4 0.0000.00
0.0000.00

0118                          A500.20 1,344.001.0001,344.00
INSTALL TRAFFIC SIGNAL CONTROLLER, TYPE TC-170 EACH1.0001,344.00
0.0000.00
0.0000.00

0119                          A502.03 168.008.0001,344.00
INSTALL PEDESTRIAN SIGNAL EACH0.0000.00
TYPE PS-2 0.0000.00
0.0000.00

0120                          A610.00 1,344.001.0001,344.00
REMOVE TRAFFIC SIGNAL EACH1.0001,344.00
AT JUNCTION OF N-2/US-385 1.0001,344.00
0.0000.00

0121                          A610.01 2,800.001.0002,800.00
REMOVE TRAFFIC SIGNAL EACH1.0002,800.00
AT 3rd STREET & CODY AVENUE 0.5001,400.00
0.0000.00

0122                          A639.90 560.008.0004,480.00
REMOVE COMBINATION MAST ARM SIGNAL AND LIGHTING POLE EACH8.0004,480.00
0.0000.00
0.0000.00

0123                          A703.60 1,232.001.0001,232.00
RELOCATE MAST ARM SIGNAL POLE EACH1.0001,232.00
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted201,466.75
Current197,517.07
In place21,889.97
This Estimate504.00

GROUP 10 GENERAL ITEMS
0124                          0001.08 0.5022,300.00011,150.00
BARRICADE, TYPE II BDAY22,300.00011,150.00
27,865.00013,932.50
2,976.0001,488.00

0125                          0001.10 2.914,965.00014,448.15
BARRICADE, TYPE III BDAY4,965.00014,448.15
5,207.00015,152.37
565.0001,644.15

0126                          0001.75 2.91240.000698.40
TEMPORARY SIGN DAY EACH240.000698.40
0.0000.00
0.0000.00

0127                          0001.90 0.8315,322.00012,717.26
SIGN DAY EACH15,322.00012,717.26
8,163.0006,775.29
845.000701.35

0128                          0001.98 0.822,822.0002,314.04
CONTRACTOR FURNISHED SIGN EACH2,822.0002,314.04
0.0000.00
0.0000.00

0129                          0002.30 1.122,550.0002,856.00
PAVEMENT MARKING REMOVAL m 2,550.0002,856.00
743.000832.16
0.0000.00

0130                          0002.44 0.567,400.0004,144.00
TEMPORARY PAVEMENT MARKING, TYPE PAINT m 7,400.0004,144.00
5,633.0003,154.48
0.0000.00

0131                          0002.47 1.122,500.0002,800.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 2,500.0002,800.00
0.0000.00
0.0000.00

0132                          0002.97 17.47308.0005,380.76
FLASHING ARROW PANEL DAY 308.0005,380.76
232.0004,053.04
26.000454.22

0133                          0003.10 215.5240.0008,620.80
FLAGGING DAY 40.0008,620.80
62.50013,470.00
2.000431.04

0134                          0003.75 3,784.481.0003,784.48
TEMPORARY TRAFFIC SIGNAL EACH1.0003,784.48
1.0003,784.48
0.0000.00

0135                          0005.10 54.74244.00013,356.56
TRAFFIC CONTROL MANAGEMENT DAY 244.00013,356.56
124.0006,787.76
11.000602.14

0136                          0010.04 2,795.331.0002,795.33
FIELD OFFICE EACH1.0002,795.33
1.0002,795.33
0.0000.00

0137                          0030.00 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0138                          1017.00 27,268.401.00027,268.40
CONSTRUCTION STAKING AND SURVEYING LS 1.00027,268.40
0.2506,817.10
0.0000.00

GROUP 10 GENERAL ITEMSContracted118,334.18
Current118,334.18
In place83,554.51
This Estimate5,320.90

Totals for contractContracted1,957,596.79
Current2,008,593.24
In place885,499.77
This Estimate72,632.06