Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 2252 PAULSEN, INC. |
Contract ID: | 5174 |
Estimate Number: | 0003 |
Pay Period End Date: | 05.25.2002 |
Contract Location: | ||
NIOBRARA RIVER NORTH AND SOUTH | Estimate Type: | PROG |
Contractor: | ||
PAULSEN, INC. | Date Let: | 09.20.2001 |
1116 EAST HWY 30 | Date Awarded: | 09.27.2001 |
P O BOX 17 | Date Contract Executed: | 10.02.2001 |
Date Notice to Proceed: | 10.02.2001 | |
COZAD NE 69130 | Date Work Began: | 05.06.2002 |
Phone: | Date Physical Work Completed: | |
(308)784-3333 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
ST. PAUL FIRE AND MARINE INSURANCE COMPANY |
Counties |
---|
SIOUX |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
51174 000 |   | 0.000 |   | PEP-29-4(1005) |   | BITUMINOUS |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $309,538.36 | $53,247.31 | $256,291.05 |
$952,074.10 | Stockpiled Materials | $38,055.76 | $67,364.35 | $-29,308.59 |
Original Contract Amt | Gross Earnings | $347,594.12 | $120,611.66 | $226,982.46 |
$952,074.10 | Retainage | $-3,095.38 | $-532.47 | $-2,562.91 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
32.51% | Net Earnings | $344,498.74 | $120,079.19 | $224,419.55 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $344,498.74 | $120,079.19 | $224,419.55 | |
Project Manager | Div. Head/Dist. Eng. | |||
Applegate, Joe | 05.28.2002 | Lind, Craig | 05.28.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 05.29.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 05.29.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Est Nbr: | 0001 | |||
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr |
0012 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | ||
S.P. Initial Payment | 9,351.06 | 1299 | ||
2A Gravel | ||||
S.P. Initial Payment | 58,013.29 | 211394 | ||
Guernsey Rock | ||||
Total for estimate 0001: | 67,364.35 | |||
Est Nbr: | 0003 | |||
Item Nbr | Item Cd | Item Desc | Adj Amt | Invoice Nbr |
0012 | 9005.30 | ASPHALTIC CONCRETE, TYPE SP2(0.5) | ||
S.P. Adjustment | -9,351.06 | 1299 | ||
2A Gravel | ||||
S.P. Adjustment | -19,957.53 | 211394 | ||
Guernsey Rock | ||||
Total for estimate 0003: | -29,308.59 | |||
Total remaining for contract: | 38,055.76 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 9 BITUMINOUS | |||
0001 0001.10 | 4.50 | 192.000 | 864.00 |
BARRICADE, TYPE III | BDAY | 192.000 | 864.00 |
100.000 | 450.00 | ||
70.000 | 315.00 | ||
0002 0001.30 | 5.25 | 96.000 | 504.00 |
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 96.000 | 504.00 |
60.000 | 315.00 | ||
42.000 | 220.50 | ||
0003 0001.75 | 7.35 | 100.000 | 735.00 |
TEMPORARY SIGN DAY | EACH | 100.000 | 735.00 |
144.000 | 1,058.40 | ||
108.000 | 793.80 | ||
0004 0001.90 | 0.95 | 6,048.000 | 5,745.60 |
SIGN DAY | EACH | 6,048.000 | 5,745.60 |
2,465.000 | 2,341.75 | ||
1,882.000 | 1,787.90 | ||
0005 0002.55 | 6.45 | 1,557.000 | 10,042.65 |
OVERLAY BROKEN LINES | STA | 1,557.000 | 10,042.65 |
1,063.688 | 6,860.79 | ||
662.176 | 4,271.04 | ||
0006 0002.60 | 6.20 | 3,114.000 | 19,306.80 |
OVERLAY SOLID LINES | STA | 3,114.000 | 19,306.80 |
2,261.736 | 14,022.76 | ||
1,458.712 | 9,044.01 | ||
0007 0003.10 | 171.00 | 50.000 | 8,550.00 |
FLAGGING | DAY | 50.000 | 8,550.00 |
29.000 | 4,959.00 | ||
22.000 | 3,762.00 | ||
0008 0010.04 | 2,000.00 | 1.000 | 2,000.00 |
FIELD OFFICE | EACH | 1.000 | 2,000.00 |
1.000 | 2,000.00 | ||
0.000 | 0.00 | ||
0009 0030.90 | 45,000.00 | 1.000 | 45,000.00 |
MOBILIZATION | LS | 1.000 | 45,000.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0010 9000.75 | 16.30 | 200.000 | 3,260.00 |
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE | TON | 200.000 | 3,260.00 |
SP2(0.5) | 0.000 | 0.00 | |
0.000 | 0.00 | ||
0011 9005.00 | 23.00 | 200.000 | 4,600.00 |
ASPHALTIC CONCRETE FOR PATCHING, TYPE | TON | 200.000 | 4,600.00 |
SP2(0.5) | 40.030 | 920.69 | |
40.030 | 920.69 | ||
0012 9005.30 | 16.30 | 27,310.000 | 445,153.00 |
ASPHALTIC CONCRETE, TYPE SP2(0.5) | TON | 27,310.000 | 445,153.00 |
7,852.350 | 127,993.31 | ||
7,852.350 | 127,993.31 | ||
0013 9020.91 | 191.50 | 10.800 | 2,068.20 |
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING | TON | 10.800 | 2,068.20 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0014 9021.01 | 191.50 | 1,485.500 | 284,473.25 |
PERFORMANCE GRADED BINDER (64-22) | TON | 1,485.500 | 284,473.25 |
346.487 | 66,352.26 | ||
346.487 | 66,352.26 | ||
0015 9053.00 | 0.95 | 29,740.000 | 28,253.00 |
TACK COAT | GAL | 29,740.000 | 28,253.00 |
3,851.250 | 3,658.69 | ||
3,851.250 | 3,658.69 | ||
0016 9110.01 | 51.00 | 75.000 | 3,825.00 |
RENTAL OF LOADER, FULLY OPERATED | HOUR | 75.000 | 3,825.00 |
3.000 | 153.00 | ||
3.000 | 153.00 | ||
0017 9110.02 | 51.00 | 75.000 | 3,825.00 |
RENTAL OF MOTOR GRADER, FULLY OPERATED | HOUR | 75.000 | 3,825.00 |
9.000 | 459.00 | ||
9.000 | 459.00 | ||
0018 9110.03 | 45.00 | 75.000 | 3,375.00 |
RENTAL OF DUMP TRUCK, FULLY OPERATED | HOUR | 75.000 | 3,375.00 |
2.000 | 90.00 | ||
2.000 | 90.00 | ||
0019 9110.07 | 35.00 | 75.000 | 2,625.00 |
RENTAL OF SKID LOADER, FULLY OPERATED | HOUR | 75.000 | 2,625.00 |
1.000 | 35.00 | ||
1.000 | 35.00 | ||
0020 9179.23 | 105.50 | 738.091 | 77,868.60 |
COLD MILLING, CLASS 3 | STA | 738.091 | 77,868.60 |
738.092 | 77,868.71 | ||
345.354 | 36,434.85 | ||
GROUP 9 BITUMINOUS | Contracted | 952,074.10 | |
Current | 952,074.10 | ||
In place | 309,538.36 | ||
This Estimate | 256,291.05 | ||
Totals for contract | Contracted | 952,074.10 | |
Current | 952,074.10 | ||
In place | 309,538.36 | ||
This Estimate | 256,291.05 |