Nebraska Department of Roads | |
---|---|
Estimate Summary to Contractor | |
Vendor ID: | 1613 COLLINS CONTRACTING COMPANY, INC./M. E. |
Contract ID: | 5024 |
Estimate Number: | 0001 |
Pay Period End Date: | 11.21.2002 |
Contract Location: | ||
CHAPPELL WB REST AREA | Estimate Type: | PROG |
Contractor: | ||
COLLINS CONTRACTING COMPANY, INC./M. E. | Date Let: | 10.10.2002 |
980 E 25TH ST | Date Awarded: | 10.17.2002 |
PO BOX 83 | Date Contract Executed: | 10.23.2002 |
Date Notice to Proceed: | 10.23.2002 | |
WAHOO NE 68066 | Date Work Began: | |
Phone: | Date Physical Work Completed: | |
(402)443-3663 | Date Accepted: | |
Escrow Agent: | ||
Surety Co: | ||
UNIVERSAL SURETY COMPANY |
Counties |
---|
DEUEL |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
51024 000 |   | 0.000 |   | EACIM-80-2(83) |   | BUILDING CONSTRUCTION |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $1,000.00 | $.00 | $1,000.00 |
$185,353.97 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $1,000.00 | $.00 | $1,000.00 |
$185,353.97 | Retainage | $-10.00 | $.00 | $-10.00 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
0.54% | Net Earnings | $990.00 | $.00 | $990.00 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $990.00 | $.00 | $990.00 | |
Project Manager | Div. Head/Dist. Eng. | |||
Smith, Don | 11.21.2002 | Lind, Craig | 11.22.2002 | |
Constr. Estimate Eng. | Materials Eng. | |||
Bartos, Steve | 11.26.2002 | |||
Controller Div. Processed | ||||
Burling, Laurie | 11.26.2002 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 8A BUILDING CONSTRUCTION | |||
0001 0001.90 | 1.30 | 97.000 | 126.10 |
SIGN DAY | EACH | 97.000 | 126.10 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0002 0030.80 | 4,000.00 | 1.000 | 4,000.00 |
MOBILIZATION | LS | 1.000 | 4,000.00 |
0.250 | 1,000.00 | ||
0.250 | 1,000.00 | ||
0003 5875.75 | 59,547.54 | 1.000 | 59,547.54 |
TREATMENT SYSTEM | EACH | 1.000 | 59,547.54 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0004 5875.76 | 26,572.63 | 1.000 | 26,572.63 |
VALVE PIT/CONTROL BUILDING | EACH | 1.000 | 26,572.63 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0005 5875.77 | 8,710.00 | 1.000 | 8,710.00 |
ELECTRICAL WORK FOR TREATMENT SYSTEM | EACH | 1.000 | 8,710.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0006 5875.78 | 7,800.00 | 1.000 | 7,800.00 |
ABANDONMENT OF TREATMENT PLANT | EACH | 1.000 | 7,800.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0007 5875.79 | 71,387.70 | 1.000 | 71,387.70 |
ABSORPTION FIELD | EACH | 1.000 | 71,387.70 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
0008 5895.25 | 7,210.00 | 1.000 | 7,210.00 |
SITE WORK | EACH | 1.000 | 7,210.00 |
0.000 | 0.00 | ||
0.000 | 0.00 | ||
GROUP 8A BUILDING CONSTRUCTION | Contracted | 185,353.97 | |
Current | 185,353.97 | ||
In place | 1,000.00 | ||
This Estimate | 1,000.00 | ||
Totals for contract | Contracted | 185,353.97 | |
Current | 185,353.97 | ||
In place | 1,000.00 | ||
This Estimate | 1,000.00 |