Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:4913
Estimate Number:0001
Pay Period End Date:06.28.2003
Contract Location:
KEARNEY NORTHEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:05.22.2003
129 E 2ND STDate Awarded:05.29.2003
PO BOX 1087Date Contract Executed:06.04.2003
Date Notice to Proceed:06.04.2003
HASTINGS NE 68902-1087Date Work Began:06.26.2003
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
BUFFALO
Project Number PCT Fed State Project Number Description
41913 000  0.000 EACSTPD-EACBR-10-2(111)  GR CP CULV SEED BR GDRL ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$22,976.69$.00$22,976.69
$5,884,195.46Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$22,976.69$.00$22,976.69
$5,884,195.46Retainage$-229.77$.00$-229.77
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
0.39%Net Earnings$22,746.92$.00$22,746.92
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$22,746.92$.00$22,746.92
Project ManagerDiv. Head/Dist. Eng.
Farber, Tom07.01.2003Heermann, Dennis07.01.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve07.01.2003
Controller Div. Processed
Burling, Laurie07.02.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 21,000.001.00021,000.00
MOBILIZATION LS 1.00021,000.00
0.0000.00
0.0000.00

0002                          1000.00 555.5610.0005,555.60
LARGE TREE REMOVAL EACH10.0005,555.60
6.0003,333.36
6.0003,333.36

0003                          1009.00 11,111.111.00011,111.11
GENERAL CLEARING AND GRUBBING LS 1.00011,111.11
0.0000.00
0.0000.00

0004                          1010.00 1.3182,877.000108,568.87
EXCAVATION m3 82,877.000108,568.87
0.0000.00
0.0000.00

0005                          1010.10 2.7841,062.000114,152.36
EXCAVATION, BORROW m3 41,062.000114,152.36
0.0000.00
0.0000.00

0006                          1011.00 2.649,295.00024,538.80
WATER kL 9,295.00024,538.80
0.0000.00
0.0000.00

0007                          1012.00 62.00110.0006,820.00
RIGHT-OF-WAY MARKERS EACH110.0006,820.00
0.0000.00
0.0000.00

0008                          1090.00 555.563.0001,666.68
ABANDON WELLS EACH3.0001,666.68
0.0000.00
0.0000.00

0009                          1101.25 8.201,700.00013,940.00
SAWING PAVEMENT m 1,700.00013,940.00
0.0000.00
0.0000.00

0010                          1102.00 1.3928,631.00039,797.09
REMOVE ASPHALT SURFACE m2 28,631.00039,797.09
0.0000.00
0.0000.00

0011                          1106.00 1.943,924.0007,612.56
REMOVE DRIVEWAY m2 3,924.0007,612.56
0.0000.00
0.0000.00

0012                          1124.00 277.781.000277.78
REMOVE BUILDING EACH1.000277.78
AT STA. 110+00 RT. 0.0000.00
0.0000.00

0013                          1125.00 733.331.000733.33
CLEAR TRACT EACH1.000733.33
AT STA. 99+99 TO STA. 100+20 LT. 1.000733.33
1.000733.33

0014                          1125.01 277.781.000277.78
CLEAR TRACT EACH1.000277.78
AT STA. 109+35 TO STA. 109+54 LT. 0.0000.00
0.0000.00

0015                          1125.02 733.331.000733.33
CLEAR TRACT EACH1.000733.33
AT STA. 111+46 TO STA. 111+83 LT. 0.0000.00
0.0000.00

0016                          1128.00 500.001.000500.00
REMOVE SLAB EACH1.000500.00
0.0000.00
0.0000.00

0017                          1701.18 46.27101.7004,705.66
450 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 101.7004,705.66
0.0000.00
0.0000.00

0018                          1701.24 61.39208.00012,769.12
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 208.00012,769.12
0.0000.00
0.0000.00

0019                          1701.30 90.6650.0004,533.00
750 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 50.0004,533.00
0.0000.00
0.0000.00

0020                          1701.36 108.2058.0006,275.60
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 58.0006,275.60
0.0000.00
0.0000.00

0021                          1703.48 185.7649.2009,139.39
1200 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4 OR 5 m 49.2009,139.39
0.0000.00
0.0000.00

0022                          1703.54 212.3052.00011,039.60
1350 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4 OR 5 m 52.00011,039.60
0.0000.00
0.0000.00

0023                          1705.30 97.2217.0001,652.74
750 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE,TYPE 2,3,4 OR 5 m 17.0001,652.74
0.0000.00
0.0000.00

0024                          1705.36 114.9464.0007,356.16
900 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE,TYPE 2,3,4 OR 5 m 64.0007,356.16
0.0000.00
0.0000.00

0025                          4040.00 277.784.0001,111.12
REMOVE HEADWALLS FROM CULVERTS EACH4.0001,111.12
0.0000.00
0.0000.00

0026                          4045.00 555.561.000555.56
REMOVE STRUCTURE EACH1.000555.56
AT STA. 107+60.34 LT. 0.0000.00
0.0000.00

0027                          4045.01 555.561.000555.56
REMOVE STRUCTURE EACH1.000555.56
AT STA. 114+19.18 LT. 0.0000.00
0.0000.00

0028                          4310.48 1,204.384.0004,817.52
1200 mm FLARED-END SECTION EACH4.0004,817.52
0.0000.00
0.0000.00

0029                          4310.54 1,391.808.00011,134.40
1350 mm FLARED-END SECTION EACH8.00011,134.40
0.0000.00
0.0000.00

0030                          7017.00 3.33356.4001,186.81
REMOVE GUARDRAIL m 356.4001,186.81
0.0000.00
0.0000.00

0031                          L006.00 67.8722.1001,499.93
COVER CROP SEEDING ha 22.1001,499.93
0.0000.00
0.0000.00

0032                          L020.01 5.2011,393.20059,244.64
EROSION CONTROL, TYPE A m2 11,393.20059,244.64
0.0000.00
0.0000.00

0033                          L020.08 5.751,223.3007,033.98
EROSION CONTROL, TYPE AA m2 1,223.3007,033.98
0.0000.00
0.0000.00

0034                          L020.09 12.002,389.50028,674.00
EROSION CONTROL, TYPE AAA m2 2,389.50028,674.00
0.0000.00
0.0000.00

0035                          L020.10 1.551,102.2001,708.41
EROSION CONTROL, TYPE HV m2 1,102.2001,708.41
0.0000.00
0.0000.00

0036                          L021.01 15.00408.0006,120.00
EROSION CHECKS, TYPE A BALE408.0006,120.00
0.0000.00
0.0000.00

0037                          L021.06 15.00652.0009,780.00
EROSION CHECKS, TYPE HV BALE652.0009,780.00
0.0000.00
0.0000.00

0038                          L021.11 16.00192.0003,072.00
EROSION CHECKS, TYPE ST-A BALE192.0003,072.00
0.0000.00
0.0000.00

0039                          L021.21 16.0084.0001,344.00
EROSION CHECKS, TYPE AA BALE84.0001,344.00
0.0000.00
0.0000.00

0040                          L022.11 6.004,033.00024,198.00
FABRIC SILT FENCE-LOW POROSITY m 4,033.00024,198.00
0.0000.00
0.0000.00

0041                          L022.75 19.75873.00017,241.75
TEMPORARY SILT CHECK m 873.00017,241.75
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted594,034.24
Current594,034.24
In place4,066.69
This Estimate4,066.69

GROUP 3 CONCRETE PAVEMENT
0042                          0030.30 155,000.001.000155,000.00
MOBILIZATION LS 1.000155,000.00
0.12218,910.00
0.12218,910.00

0043                          2001.00 7.00331.0002,317.00
GRAVEL SURFACE COURSE m3 331.0002,317.00
0.0000.00
0.0000.00

0044                          2009.10 500.004.0722,036.00
GRAVEL EMBEDMENT StaM4.0722,036.00
0.0000.00
0.0000.00

0045                          2021.00 40.0031.0001,240.00
MAILBOX POST EACH31.0001,240.00
0.0000.00
0.0000.00

0046                          3011.25 29.0081.0002,349.00
CONCRETE CLASS 47B-25 CURB TYPE II m 81.0002,349.00
0.0000.00
0.0000.00

0047                          3017.40 27.00695.00018,765.00
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 695.00018,765.00
0.0000.00
0.0000.00

0048                          3020.24 27.50178.4004,906.00
CONCRETE CLASS 47B-25 DRIVEWAY m2 178.4004,906.00
0.0000.00
0.0000.00

0049                          3075.46 36.8525,413.200936,476.42
230 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 25,413.200936,476.42
0.0000.00
0.0000.00

0050                          3089.25 32.915,835.000192,029.85
TEMPORARY SURFACING m2 5,835.000192,029.85
200 mm 0.0000.00
0.0000.00

0051                          3300.50 2,500.001.0002,500.00
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.0002,500.00
0.0000.00
0.0000.00

0052                          7500.32 225.008.0001,800.00
ARROW, PREFORMED PAVEMENT MARKING, TYPE 4 EACH8.0001,800.00
0.0000.00
0.0000.00

0053                          7502.14 7.053,700.00026,085.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 3,700.00026,085.00
0.0000.00
0.0000.00

0054                          7503.14 7.383,200.00023,616.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 3,200.00023,616.00
0.0000.00
0.0000.00

0055                          7508.14 24.6075.0001,845.00
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 75.0001,845.00
0.0000.00
0.0000.00

0056                          7509.14 26.2535.000918.75
300 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 35.000918.75
0.0000.00
0.0000.00

0057                          8022.00 126.73105.00013,306.65
HYDRATED LIME Mg 105.00013,306.65
0.0000.00
0.0000.00

0058                          8029.84 2.3325,413.00059,212.29
BITUMINOUS FOUNDATION COURSE 100 mm m2 25,413.00059,212.29
0.0000.00
0.0000.00

0059                          8110.50 1,598.0056.47290,242.26
HYDRATED LIME SLURRY STABILIZATION StaM56.47290,242.26
0.0000.00
0.0000.00

0060                          8111.00 300.00168.10850,432.40
SHOULDER SUBGRADE PREPARATION StaM168.10850,432.40
0.0000.00
0.0000.00

0061                          9000.75 12.46300.0003,738.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 300.0003,738.00
SPS 0.0000.00
0.0000.00

0062                          9005.00 28.35300.0008,505.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 300.0008,505.00
SP4(12.5) 0.0000.00
0.0000.00

0063                          9005.23 12.4617,720.000220,791.20
ASPHALTIC CONCRETE, TYPE SPS Mg 17,720.000220,791.20
0.0000.00
0.0000.00

0064                          9005.45 20.4914,850.000304,276.50
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 14,850.000304,276.50
0.0000.00
0.0000.00

0065                          9009.00 0.258,654.0002,163.50
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 8,654.0002,163.50
0.0000.00
0.0000.00

0066                          9020.92 210.0016.2003,402.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 16.2003,402.00
0.0000.00
0.0000.00

0067                          9021.01 210.00956.880200,944.80
PERFORMANCE GRADED BINDER (64-22) Mg 956.880200,944.80
0.0000.00
0.0000.00

0068                          9021.03 210.00818.100171,801.00
PERFORMANCE GRADED BINDER (58-28) Mg 818.100171,801.00
0.0000.00
0.0000.00

0069                          9034.00 0.258,654.0002,163.50
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 8,654.0002,163.50
0.0000.00
0.0000.00

0070                          9052.15 0.28106,365.00029,782.20
EMULSIFIED ASPHALT FOR HYDRATED LIME SLURRY STABILIZATION L 106,365.00029,782.20
0.0000.00
0.0000.00

0071                          9053.00 0.2563,030.00015,757.50
TACK COAT L 63,030.00015,757.50
0.0000.00
0.0000.00

0072                          9111.00 2.001,575.0003,150.00
WATER kL 1,575.0003,150.00
0.0000.00
0.0000.00

0073                          9140.00 345.0024.3178,389.37
JOINT SEALING - ASPHALT TO CONCRETE StaM24.3178,389.37
0.0000.00
0.0000.00

0074                          9170.00 350.0011.2823,948.70
EARTH SHOULDER CONSTRUCTION StaM11.2823,948.70
0.0000.00
0.0000.00

0075                          9173.20 1.4538,010.00055,114.50
SUBGRADE PREPARATION m2 38,010.00055,114.50
0.0000.00
0.0000.00

0076                          9188.50 25.00932.00023,300.00
SURFACING UNDER GUARDRAIL m2 932.00023,300.00
0.0000.00
0.0000.00

0077                          9300.52 2,500.001.0002,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0002,500.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted2,644,805.38
Current2,644,805.38
In place18,910.00
This Estimate18,910.00

GROUP 4 CULVERTS
0078                          0030.40 5,200.001.0005,200.00
MOBILIZATION LS 1.0005,200.00
0.0000.00
0.0000.00

0079                          1043.50 2.40769.5201,846.85
RIPRAP FILTER FABRIC m2 769.5201,846.85
0.0000.00
0.0000.00

0080                          4004.50 2.805,305.00014,854.00
CAST IRON GRATE AND FRAME kg 5,305.00014,854.00
0.0000.00
0.0000.00

0081                          4035.00 85.004.000340.00
REMOVE FLARED-END SECTION EACH4.000340.00
0.0000.00
0.0000.00

0082                          4040.00 100.0040.0004,000.00
REMOVE HEADWALLS FROM CULVERTS EACH40.0004,000.00
0.0000.00
0.0000.00

0083                          4044.01 1,600.001.0001,600.00
PREPARATION OF STRUCTURE EACH1.0001,600.00
AT STA. 177+62.78 0.0000.00
0.0000.00

0084                          4050.01 10.001,169.00011,690.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 1,169.00011,690.00
0.0000.00
0.0000.00

0085                          4051.01 11.00140.0001,540.00
EXCAVATION FOR BOX CULVERTS m3 140.0001,540.00
0.0000.00
0.0000.00

0086                          4100.06 600.0013.5008,100.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 13.5008,100.00
0.0000.00
0.0000.00

0087                          4101.06 376.0092.40034,742.40
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 92.40034,742.40
0.0000.00
0.0000.00

0088                          4105.59 575.0023.53013,529.75
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 23.53013,529.75
0.0000.00
0.0000.00

0089                          4150.00 2.00990.0001,980.00
REINFORCING STEEL FOR HEADWALL kg 990.0001,980.00
0.0000.00
0.0000.00

0090                          4151.00 1.506,397.0009,595.50
REINFORCING STEEL FOR BOX CULVERT kg 6,397.0009,595.50
0.0000.00
0.0000.00

0091                          4155.50 2.00896.0001,792.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 896.0001,792.00
0.0000.00
0.0000.00

0092                          4310.15 360.001.000360.00
375 mm FLARED-END SECTION EACH1.000360.00
0.0000.00
0.0000.00

0093                          4310.18 385.001.000385.00
450 mm FLARED-END SECTION EACH1.000385.00
0.0000.00
0.0000.00

0094                          4310.24 200.0023.0004,600.00
600 mm FLARED-END SECTION EACH23.0004,600.00
0.0000.00
0.0000.00

0095                          4310.30 270.004.0001,080.00
750 mm FLARED-END SECTION EACH4.0001,080.00
0.0000.00
0.0000.00

0096                          4310.36 360.006.0002,160.00
900 mm FLARED-END SECTION EACH6.0002,160.00
0.0000.00
0.0000.00

0097                          4310.48 810.008.0006,480.00
1200 mm FLARED-END SECTION EACH8.0006,480.00
0.0000.00
0.0000.00

0098                          4320.48 700.002.0001,400.00
1200 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0001,400.00
0.0000.00
0.0000.00

0099                          4670.05 50.0026.7801,339.00
CULVERT SANDFILL m3 26.7801,339.00
0.0000.00
0.0000.00

0100                          4870.15 440.0019.8008,712.00
JACKING 375 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 19.8008,712.00
0.0000.00
0.0000.00

0101                          4875.18 465.0026.00012,090.00
JACKING 450 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 26.00012,090.00
0.0000.00
0.0000.00

0102                          4885.48 1,000.0050.00050,000.00
JACKING 1200 mm CULVERT PIPE, TYPE 2 CLASS V m 50.00050,000.00
0.0000.00
0.0000.00

0103                          6040.00 700.001.000700.00
REMOVE STRUCTURE EACH1.000700.00
AT STA. 163+17.57 RT. 0.0000.00
0.0000.00

0104                          6105.01 41.0067.7002,775.70
ROCK RIPRAP, TYPE A Mg 67.7002,775.70
0.0000.00
0.0000.00

0105                          6105.02 41.0055.8002,287.80
ROCK RIPRAP, TYPE B Mg 55.8002,287.80
0.0000.00
0.0000.00

0106                          6105.03 41.00621.30025,473.30
ROCK RIPRAP, TYPE C Mg 621.30025,473.30
0.0000.00
0.0000.00

0107                          P120.48 290.0028.0008,120.00
1200 mm CULVERT PIPE, TYPE 2 m 28.0008,120.00
0.0000.00
0.0000.00

0108                          P129.48 284.0050.00014,200.00
1200 mm CULVERT PIPE, TYPE 2 CLASS V m 50.00014,200.00
0.0000.00
0.0000.00

0109                          P300.24 71.00189.80013,475.80
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 189.80013,475.80
0.0000.00
0.0000.00

0110                          P300.30 97.0018.4001,784.80
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 18.4001,784.80
0.0000.00
0.0000.00

0111                          P300.36 103.0028.8002,966.40
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 28.8002,966.40
0.0000.00
0.0000.00

0112                          P300.48 175.0035.6006,230.00
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 35.6006,230.00
0.0000.00
0.0000.00

0113                          P372.48 212.0028.0005,936.00
1200 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2,4 OR 5 m 28.0005,936.00
0.0000.00
0.0000.00

0114                          P500.30 118.0014.0001,652.00
750 mm CULVERT PIPE, TYPE 2,4,5,7 or 8 m 14.0001,652.00
0.0000.00
0.0000.00

0115                          P500.36 137.0045.0006,165.00
900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 45.0006,165.00
0.0000.00
0.0000.00

0116                          P700.15 70.0028.0001,960.00
375 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 28.0001,960.00
0.0000.00
0.0000.00

0117                          P700.18 86.004.000344.00
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 4.000344.00
0.0000.00
0.0000.00

0118                          P700.24 116.00294.00034,104.00
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 294.00034,104.00
0.0000.00
0.0000.00

0119                          P702.15 70.0010.200714.00
375 mm STORM SEWER PIPE, TYPE 1 m 10.200714.00
0.0000.00
0.0000.00

0120                          P702.18 86.0018.0001,548.00
450 mm STORM SEWER PIPE, TYPE 1 m 18.0001,548.00
0.0000.00
0.0000.00

0121                          P705.15 50.0019.800990.00
375 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 19.800990.00
0.0000.00
0.0000.00

0122                          P705.18 46.0026.0001,196.00
450 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 26.0001,196.00
0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted332,039.30
Current332,039.30
In place0.00
This Estimate0.00

GROUP 4A CULVERT AT STA. 161+27.67
0123                          0030.40 750.001.000750.00
MOBILIZATION LS 1.000750.00
0.0000.00
0.0000.00

0124                          4044.00 2,200.001.0002,200.00
PREPARATION OF STRUCTURE EACH1.0002,200.00
AT STA. 161+27.67 0.0000.00
0.0000.00

0125                          4051.01 12.00220.0002,640.00
EXCAVATION FOR BOX CULVERTS m3 220.0002,640.00
0.0000.00
0.0000.00

0126                          4101.06 396.0082.43032,642.28
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 82.43032,642.28
0.0000.00
0.0000.00

0127                          4151.00 1.426,164.0008,752.88
REINFORCING STEEL FOR BOX CULVERT kg 6,164.0008,752.88
0.0000.00
0.0000.00

GROUP 4A CULVERT AT STA. 161+27.67Contracted46,985.16
Current46,985.16
In place0.00
This Estimate0.00

GROUP 5 SEEDING
0128                          0030.50 3,250.001.0003,250.00
MOBILIZATION LS 1.0003,250.00
0.0000.00
0.0000.00

0129                          L001.01 999.009.8009,790.20
SEEDING, TYPE A ha 9.8009,790.20
0.0000.00
0.0000.00

0130                          L001.02 903.005.1004,605.30
SEEDING, TYPE B ha 5.1004,605.30
0.0000.00
0.0000.00

0131                          L001.03 1,293.002.0002,586.00
SEEDING, TYPE C ha 2.0002,586.00
0.0000.00
0.0000.00

0132                          L001.32 805.007.2005,796.00
SEEDING, TYPE B-1 ha 7.2005,796.00
0.0000.00
0.0000.00

0133                          L032.75 70.0074.5005,215.00
MULCH Mg 74.5005,215.00
0.0000.00
0.0000.00

0134                          L032.80 485.0024.84012,047.40
HYDROMULCH Mg 24.84012,047.40
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted43,289.90
Current43,289.90
In place0.00
This Estimate0.00

GROUP 6 BRIDGE AT STA. 94+18
0135                          0030.60 8,500.001.0008,500.00
MOBILIZATION LS 1.0008,500.00
0.0000.00
0.0000.00

0136                          1010.01 13.00550.0007,150.00
EXCAVATION (ESTABLISHED QUANTITY) m3 550.0007,150.00
0.0000.00
0.0000.00

0137                          1043.50 2.4072.000172.80
RIPRAP FILTER FABRIC m2 72.000172.80
0.0000.00
0.0000.00

0138                          3050.15 300.00251.60075,480.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 251.60075,480.00
0.0000.00
0.0000.00

0139                          3051.10 1.4218,280.00025,957.60
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 18,280.00025,957.60
0.0000.00
0.0000.00

0140                          6000.10 2,200.001.0002,200.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,200.00
0.0000.00
0.0000.00

0141                          6000.11 2,200.001.0002,200.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,200.00
0.0000.00
0.0000.00

0142                          6010.22 395.00116.90046,175.50
CLASS 47B-20 CONCRETE FOR BRIDGE m3 116.90046,175.50
0.0000.00
0.0000.00

0143                          6010.26 395.00114.60045,267.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 114.60045,267.00
0.0000.00
0.0000.00

0144                          6011.11 165,000.001.000165,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000165,000.00
AT STA. 94+18 0.0000.00
0.0000.00

0145                          6040.00 6,900.001.0006,900.00
REMOVE STRUCTURE EACH1.0006,900.00
AT STA. 94+11.18 RT. 0.0000.00
0.0000.00

0146                          6080.00 3.902,985.00011,641.50
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 2,985.00011,641.50
0.0000.00
0.0000.00

0147                          6104.00 19.0029.000551.00
BROKEN CONCRETE RIPRAP Mg 29.000551.00
0.0000.00
0.0000.00

0148                          6131.50 1.3224,340.00032,128.80
EPOXY COATED REINFORCING STEEL kg 24,340.00032,128.80
0.0000.00
0.0000.00

0149                          6210.50 84.001,708.000143,472.00
PIPE PILING m 1,708.000143,472.00
0.0000.00
0.0000.00

0150                          6251.00 2,000.004.0008,000.00
TEST PILE EACH4.0008,000.00
0.0000.00
0.0000.00

0151                          6310.00 85.00500.10042,508.50
STEEL SHEET PILING m2 500.10042,508.50
0.0000.00
0.0000.00

0152                          6510.55 4,900.001.0004,900.00
TEMPORARY BRIDGE SHORING LS 1.0004,900.00
0.0000.00
0.0000.00

0153                          8091.00 12.00310.0003,720.00
GRANULAR BACKFILL m3 310.0003,720.00
0.0000.00
0.0000.00

GROUP 6 BRIDGE AT STA. 94+18Contracted631,924.70
Current631,924.70
In place0.00
This Estimate0.00

GROUP 6A BRIDGE AT STA. 104+77.5
0154                          0030.60 8,500.001.0008,500.00
MOBILIZATION LS 1.0008,500.00
0.0000.00
0.0000.00

0155                          1010.01 12.002,065.00024,780.00
EXCAVATION (ESTABLISHED QUANTITY) m3 2,065.00024,780.00
0.0000.00
0.0000.00

0156                          1043.50 2.001,032.0002,064.00
RIPRAP FILTER FABRIC m2 1,032.0002,064.00
0.0000.00
0.0000.00

0157                          3050.15 300.00185.00055,500.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 185.00055,500.00
0.0000.00
0.0000.00

0158                          3051.10 1.4213,825.00019,631.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 13,825.00019,631.50
0.0000.00
0.0000.00

0159                          6000.10 2,200.001.0002,200.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,200.00
0.0000.00
0.0000.00

0160                          6000.11 2,200.001.0002,200.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,200.00
0.0000.00
0.0000.00

0161                          6001.00 4,800.001.0004,800.00
BENT NO.1 EXCAVATION LS 1.0004,800.00
0.0000.00
0.0000.00

0162                          6001.01 4,800.001.0004,800.00
BENT NO.2 EXCAVATION LS 1.0004,800.00
0.0000.00
0.0000.00

0163                          6010.22 395.00267.900105,820.50
CLASS 47B-20 CONCRETE FOR BRIDGE m3 267.900105,820.50
0.0000.00
0.0000.00

0164                          6010.26 395.00169.40066,913.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 169.40066,913.00
0.0000.00
0.0000.00

0165                          6011.11 194,000.001.000194,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000194,000.00
AT STA. 104+77.5 0.0000.00
0.0000.00

0166                          6040.01 11,500.001.00011,500.00
REMOVE STRUCTURE EACH1.00011,500.00
AT STA. 104+82.04 0.0000.00
0.0000.00

0167                          6080.00 3.253,315.00010,773.75
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 3,315.00010,773.75
0.0000.00
0.0000.00

0168                          6104.00 12.0027.000324.00
BROKEN CONCRETE RIPRAP Mg 27.000324.00
0.0000.00
0.0000.00

0169                          6105.02 44.00937.00041,228.00
ROCK RIPRAP, TYPE B Mg 937.00041,228.00
0.0000.00
0.0000.00

0170                          6131.50 1.3233,345.00044,015.40
EPOXY COATED REINFORCING STEEL kg 33,345.00044,015.40
0.0000.00
0.0000.00

0171                          6210.50 84.00850.50071,442.00
PIPE PILING m 850.50071,442.00
0.0000.00
0.0000.00

0172                          6251.00 2,000.002.0004,000.00
TEST PILE EACH2.0004,000.00
0.0000.00
0.0000.00

0173                          6310.00 85.00499.20042,432.00
STEEL SHEET PILING m2 499.20042,432.00
0.0000.00
0.0000.00

0174                          6510.55 5,800.001.0005,800.00
TEMPORARY BRIDGE SHORING LS 1.0005,800.00
0.0000.00
0.0000.00

0175                          8091.00 12.00260.0003,120.00
GRANULAR BACKFILL m3 260.0003,120.00
0.0000.00
0.0000.00

GROUP 6A BRIDGE AT STA. 104+77.5Contracted725,844.15
Current725,844.15
In place0.00
This Estimate0.00

GROUP 6B BRIDGE AT STA. 125+03.6
0176                          0030.60 8,500.001.0008,500.00
MOBILIZATION LS 1.0008,500.00
0.0000.00
0.0000.00

0177                          1010.01 12.00935.00011,220.00
EXCAVATION (ESTABLISHED QUANTITY) m3 935.00011,220.00
0.0000.00
0.0000.00

0178                          1043.50 2.00709.0001,418.00
RIPRAP FILTER FABRIC m2 709.0001,418.00
0.0000.00
0.0000.00

0179                          3050.15 300.00150.40045,120.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 150.40045,120.00
0.0000.00
0.0000.00

0180                          3051.10 1.3210,545.00013,919.40
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 10,545.00013,919.40
0.0000.00
0.0000.00

0181                          6000.10 2,400.001.0002,400.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,400.00
0.0000.00
0.0000.00

0182                          6000.11 2,400.001.0002,400.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,400.00
0.0000.00
0.0000.00

0183                          6010.22 460.0047.30021,758.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 47.30021,758.00
0.0000.00
0.0000.00

0184                          6010.26 440.0075.90033,396.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 75.90033,396.00
0.0000.00
0.0000.00

0185                          6011.11 101,600.001.000101,600.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000101,600.00
AT STA. 125+03.6 0.0000.00
0.0000.00

0186                          6040.02 5,200.001.0005,200.00
REMOVE STRUCTURE EACH1.0005,200.00
AT STA. 125+04.13 0.0000.00
0.0000.00

0187                          6080.00 3.752,455.0009,206.25
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 2,455.0009,206.25
0.0000.00
0.0000.00

0188                          6104.00 12.0026.000312.00
BROKEN CONCRETE RIPRAP Mg 26.000312.00
0.0000.00
0.0000.00

0189                          6105.02 44.00613.00026,972.00
ROCK RIPRAP, TYPE B Mg 613.00026,972.00
0.0000.00
0.0000.00

0190                          6131.50 1.3211,790.00015,562.80
EPOXY COATED REINFORCING STEEL kg 11,790.00015,562.80
0.0000.00
0.0000.00

0191                          6210.50 84.00571.50048,006.00
PIPE PILING m 571.50048,006.00
0.0000.00
0.0000.00

0192                          6310.00 85.00433.70036,864.50
STEEL SHEET PILING m2 433.70036,864.50
0.0000.00
0.0000.00

0193                          6510.55 5,200.001.0005,200.00
TEMPORARY BRIDGE SHORING LS 1.0005,200.00
0.0000.00
0.0000.00

0194                          8091.00 12.00330.0003,960.00
GRANULAR BACKFILL m3 330.0003,960.00
0.0000.00
0.0000.00

GROUP 6B BRIDGE AT STA. 125+03.6Contracted393,014.95
Current393,014.95
In place0.00
This Estimate0.00

GROUP 7 GUARDRAIL
0195                          0030.70 1,600.001.0001,600.00
MOBILIZATION LS 1.0001,600.00
0.0000.00
0.0000.00

0196                          7011.20 36.07312.60011,275.48
W-BEAM GUARDRAIL m 312.60011,275.48
0.0000.00
0.0000.00

0197                          7020.00 1,582.0012.00018,984.00
BRIDGE APPROACH SECTIONS EACH12.00018,984.00
0.0000.00
0.0000.00

0198                          7024.27 1,350.0012.00016,200.00
GUARDRAIL END TREATMENT, TYPE II EACH12.00016,200.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted48,059.48
Current48,059.48
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0199                          0030.81 2,100.001.0002,100.00
MOBILIZATION LS 1.0002,100.00
0.0000.00
0.0000.00

0200                          A001.12 305.002.000610.00
PULL BOX, TYPE PB-5 EACH2.000610.00
0.0000.00
0.0000.00

0201                          A001.16 365.001.000365.00
PULL BOX, TYPE PB-6 EACH1.000365.00
0.0000.00
0.0000.00

0202                          A009.14 1,650.004.0006,600.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH4.0006,600.00
0.0000.00
0.0000.00

0203                          A070.10 7.20469.0003,376.80
38 mm CONDUIT IN TRENCH m 469.0003,376.80
0.0000.00
0.0000.00

0204                          A072.10 7.20109.000784.80
38 mm CONDUIT UNDER ROADWAY m 109.000784.80
0.0000.00
0.0000.00

0205                          A080.22 1.70578.000982.60
STREET LIGHTING CABLE, NO. 6 BARE m 578.000982.60
0.0000.00
0.0000.00

0206                          A080.24 2.251,156.0002,601.00
STREET LIGHTING CABLE, NO. 6 USE m 1,156.0002,601.00
0.0000.00
0.0000.00

0207                          A630.20 130.001.000130.00
REMOVE PULL BOX EACH1.000130.00
0.0000.00
0.0000.00

0208                          A700.20 735.007.0005,145.00
RELOCATE STREET LIGHTING UNIT EACH7.0005,145.00
0.0000.00
0.0000.00

0209                          A705.20 670.001.000670.00
RELOCATE LIGHTING CONTROL CENTER, TYPE EACH1.000670.00
R 0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted23,365.20
Current23,365.20
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0210                          0001.08 0.5053,314.00026,657.00
BARRICADE, TYPE II BDAY53,314.00026,657.00
0.0000.00
0.0000.00

0211                          0001.10 1.0017,321.00017,321.00
BARRICADE, TYPE III BDAY17,321.00017,321.00
0.0000.00
0.0000.00

0212                          0001.75 2.00320.000640.00
TEMPORARY SIGN DAY EACH320.000640.00
0.0000.00
0.0000.00

0213                          0001.90 0.5041,235.00020,617.50
SIGN DAY EACH41,235.00020,617.50
0.0000.00
0.0000.00

0214                          0001.99 0.855,536.0004,705.60
CONTRACTOR FURNISHED SIGN DAY EACH5,536.0004,705.60
0.0000.00
0.0000.00

0215                          0002.30 1.155,000.0005,750.00
PAVEMENT MARKING REMOVAL m 5,000.0005,750.00
0.0000.00
0.0000.00

0216                          0002.39 2.4615,500.00038,130.00
TEMPORARY PAVEMENT MARKING, TYPE II m 15,500.00038,130.00
0.0000.00
0.0000.00

0217                          0002.47 1.807,500.00013,500.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 7,500.00013,500.00
0.0000.00
0.0000.00

0218                          0002.55 19.70263.0005,181.10
OVERLAY BROKEN LINES StaM263.0005,181.10
0.0000.00
0.0000.00

0219                          0002.60 19.70526.00010,362.20
OVERLAY SOLID LINES StaM526.00010,362.20
0.0000.00
0.0000.00

0220                          0002.97 15.00496.0007,440.00
FLASHING ARROW PANEL DAY 496.0007,440.00
0.0000.00
0.0000.00

0221                          0003.10 185.0060.00011,100.00
FLAGGING DAY 60.00011,100.00
0.0000.00
0.0000.00

0222                          0003.20 285.0025.0007,125.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 25.0007,125.00
0.0000.00
0.0000.00

0223                          0003.50 90.00491.50044,235.00
CONCRETE PROTECTION BARRIER m 491.50044,235.00
0.0000.00
0.0000.00

0224                          0003.56 12.00335.3004,023.60
RELOCATE CONCRETE PROTECTION BARRIER m 335.3004,023.60
0.0000.00
0.0000.00

0225                          0003.70 350.008.0002,800.00
TEMPORARY RUMBLE STRIP EACH8.0002,800.00
0.0000.00
0.0000.00

0226                          0003.75 7,850.002.00015,700.00
TEMPORARY TRAFFIC SIGNAL EACH2.00015,700.00
0.0000.00
0.0000.00

0227                          0005.10 105.00439.00046,095.00
TRAFFIC CONTROL MANAGEMENT DAY 439.00046,095.00
0.0000.00
0.0000.00

0228                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
0.0000.00
0.0000.00

0229                          0020.00 0.802,000.0001,600.00
TRAINING HOUR2,000.0001,600.00
0.0000.00
0.0000.00

0230                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
0.0000.00
0.0000.00

0231                          1017.00 75,000.001.00075,000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00075,000.00
0.0000.00
0.0000.00

0232                          9110.01 65.00150.0009,750.00
RENTAL OF LOADER, FULLY OPERATED HOUR150.0009,750.00
0.0000.00
0.0000.00

0233                          9110.02 75.0030.0002,250.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR30.0002,250.00
0.0000.00
0.0000.00

0234                          9110.03 45.00150.0006,750.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR150.0006,750.00
0.0000.00
0.0000.00

0235                          9110.06 55.00120.0006,600.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR120.0006,600.00
0.0000.00
0.0000.00

0236                          9110.07 40.00150.0006,000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR150.0006,000.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted400,833.00
Current400,833.00
In place0.00
This Estimate0.00

Totals for contractContracted5,884,195.46
Current5,884,195.46
In place22,976.69
This Estimate22,976.69