Estimate Summary to Contractor
Vendor ID:0299 MICHEELS CONSTRUCTION CO.
Contract ID:4903D
Estimate Number:0002
Pay Period End Date:08.03.2002
Contract Location:
GRESHAM - SHELBYEstimate Type:PROG
Contractor:
MICHEELS CONSTRUCTION CO.Date Let:05.23.2002
11700 NORTH POST RDDate Awarded:05.30.2002
Date Contract Executed:06.11.2002
Date Notice to Proceed:06.11.2002
OMAHA NE 68112Date Work Began:07.15.2002
Phone:Date Physical Work Completed:
(402)455-2983Date Accepted:
Escrow Agent:
Surety Co:
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA
Counties
POLK
YORK
Project Number PCT Fed State Project Number Description
49903D 000  0.000 PM-69-2(1004)  BITUMINOUS
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$79,680.04$79,644.04$36.00
$80,604.25Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$79,680.04$79,644.04$36.00
$80,604.25Retainage$-796.80$-796.44$-.36
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
98.85%Net Earnings$78,883.24$78,847.60$35.64
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$78,883.24$78,847.60$35.64
Project ManagerDiv. Head/Dist. Eng.
Anderson, Tom12.05.2002Meyer, Keith12.05.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve12.06.2002
Controller Div. Processed
Burling, Laurie12.06.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 9 BITUMINOUS
0001                          0001.10 1.5052.00078.00
BARRICADE, TYPE III BDAY52.00078.00
24.00036.00
0.0000.00

0002                          0001.30 1.0026.00026.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY26.00026.00
12.00012.00
0.0000.00

0003                          0001.75 7.0060.000420.00
TEMPORARY SIGN DAY EACH60.000420.00
122.000854.00
0.0000.00

0004                          0001.90 0.401,131.000452.40
SIGN DAY EACH1,131.000452.40
635.000254.00
90.00036.00

0005                          0002.45 2.00613.0001,226.00
TEMPORARY BROKEN LINES STA 613.0001,226.00
606.6201,213.24
0.0000.00

0006                          0003.10 10.0020.000200.00
FLAGGING DAY 20.000200.00
9.00090.00
0.0000.00

0007                          0003.20 25.008.000200.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 8.000200.00
4.500112.50
0.0000.00

0008                          0030.90 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0009                          8008.00 21.791,630.00035,517.70
ARMOR COAT AGGREGATE CY 1,630.00035,517.70
1,595.00034,755.05
0.0000.00

0010                          9052.00 0.8544,099.00037,484.15
ARMOR COAT EMULSIFIED ASPHALT GAL 44,099.00037,484.15
43,945.00037,353.25
0.0000.00

GROUP 9 BITUMINOUSContracted80,604.25
Current80,604.25
In place79,680.04
This Estimate36.00

Totals for contractContracted80,604.25
Current80,604.25
In place79,680.04
This Estimate36.00