Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:3606 DOBSON BROTHERS CONSTRUCTION CO. & AFFIL
Contract ID:4869X
Estimate Number:0007
Pay Period End Date:07.26.2003
Contract Location:
COTESFIELD NORTH AND SOUTHEstimate Type:PROG
Contractor:
DOBSON BROTHERS CONSTRUCTION CO. & AFFILDate Let:02.06.2003
410 S 7THDate Awarded:02.13.2003
PO BOX 81409Date Contract Executed:02.21.2003
Date Notice to Proceed:02.21.2003
LINCOLN NE 68501Date Work Began:04.14.2003
Phone:Date Physical Work Completed:
(402)474-5115Date Accepted:
Escrow Agent:
Surety Co:
WESTERN SURETY COMPANY
Counties
HOWARD
Project Number PCT Fed State Project Number Description
41869 000  0.000 EACSTPD-11-2(111)  GRAD CULV BR SEED GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,421,568.24$943,858.14$477,710.10
$1,642,662.68Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,421,568.24$943,858.14$477,710.10
$1,623,386.61Retainage$-14,215.68$-9,438.58$-4,777.10
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
86.54%Net Earnings$1,407,352.56$934,419.56$472,933.00
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-1,493.60$-1,451.66$-41.94
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$1,493.60-$1,451.66-$41.94
Payment$1,405,858.96$932,967.90$472,891.06
Project ManagerDiv. Head/Dist. Eng.
Kwiatkowski, Rick08.08.2003Heermann, Dennis08.08.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve08.08.2003
Controller Div. Processed
Burling, Laurie08.11.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 20,000.001.00020,000.00
MOBILIZATION LS 1.00020,000.00
1.00020,000.00
0.0000.00

0002                          1000.00 182.5823.0004,199.34
LARGE TREE REMOVAL EACH23.0004,199.34
105.00019,170.90
0.0000.00

0003                          1009.00 2,703.001.0002,703.00
GENERAL CLEARING AND GRUBBING LS 1.0002,703.00
1.0002,703.00
0.0000.00

0004                          1010.00 1.5155,204.00083,358.04
EXCAVATION m3 55,204.00083,358.04
58,559.00088,424.09
3,355.0005,066.05

0005                          1010.10 3.0324,342.00073,756.26
EXCAVATION, BORROW m3 24,342.00073,756.26
27,697.00083,921.91
0.0000.00

0006                          1011.00 0.205,966.0001,193.20
WATER kL 5,966.0001,193.20
0.0000.00
0.0000.00

0007                          1012.00 56.36150.0008,454.00
RIGHT-OF-WAY MARKERS EACH150.0008,454.00
94.0005,297.84
0.0000.00

0008                          1090.00 816.002.0001,632.00
ABANDON WELLS EACH2.0001,632.00
2.0001,632.00
0.0000.00

0009                          1102.00 3.164,516.00014,270.56
REMOVE ASPHALT SURFACE m2 4,516.00014,270.56
4,516.00014,270.56
0.0000.00

0010                          1106.00 3.06497.0001,520.82
REMOVE DRIVEWAY m2 497.0001,520.82
563.0001,722.78
0.0000.00

0011                          1111.00 0.771,855.0001,428.35
REMOVE FENCE m 1,855.0001,428.35
3,584.0002,759.68
0.0000.00

0012                          1124.00 4,845.001.0004,845.00
REMOVE BUILDING EACH1.0004,845.00
STA. 182+62.9 TO STA. 183+00.4 LT. 1.0004,845.00
0.0000.00

0013                          1124.01 561.001.000561.00
REMOVE BUILDING EACH1.000561.00
STA. 183+32.7 TO STA. 183+42.4 LT. 1.000561.00
0.0000.00

0014                          1124.02 10.201.00010.20
REMOVE BUILDING EACH1.00010.20
STA. 184+27.4 TO STA. 184+36.0 LT. 1.00010.20
0.0000.00

0015                          1125.00 612.001.000612.00
CLEAR TRACT EACH1.000612.00
STA. 182+62.9 TO STA. 183+00.4 LT. 1.000612.00
0.0000.00

0016                          1125.01 510.001.000510.00
CLEAR TRACT EACH1.000510.00
STA. 183+32.7 TO STA. 183+42.4 LT. 1.000510.00
0.0000.00

0017                          1125.02 255.001.000255.00
CLEAR TRACT EACH1.000255.00
STA. 184+27.4 TO STA. 184+36.0 LT. 1.000255.00
0.0000.00

0018                          1125.03 816.001.000816.00
CLEAR TRACT EACH1.000816.00
STA. 184+55.5 TO STA. 185+62.4 RT. 1.000816.00
0.0000.00

0019                          1125.04 102.001.000102.00
CLEAR TRACT EACH1.000102.00
STA. 185+20.4 TO STA. 185+43.7 LT. 1.000102.00
0.0000.00

0020                          1701.24 43.35222.0009,623.70
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 222.0009,623.70
222.0009,623.70
0.0000.00

0021                          1703.48 111.1818.0002,001.24
1200 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4 OR 5 m 18.0002,001.24
18.0002,001.24
0.0000.00

0022                          7017.00 5.61306.0001,716.66
REMOVE GUARDRAIL m 306.0001,716.66
306.0001,716.66
0.0000.00

0023                          L006.00 153.0033.0005,049.00
COVER CROP SEEDING ha 33.0005,049.00
33.0005,049.00
0.0000.00

0024                          L020.09 11.22330.0003,702.60
EROSION CONTROL, TYPE AAA m2 330.0003,702.60
0.0000.00
0.0000.00

0025                          L020.10 1.334,414.0005,870.62
EROSION CONTROL, TYPE HV m2 4,414.0005,870.62
0.0000.00
0.0000.00

0026                          L021.06 25.50306.0007,803.00
EROSION CHECKS, TYPE HV BALE306.0007,803.00
0.0000.00
0.0000.00

0027                          L022.11 10.20310.0003,162.00
FABRIC SILT FENCE-LOW POROSITY m 310.0003,162.00
310.0003,162.00
0.0000.00

0028                          L022.24 30.6012.000367.20
FABRIC SILT FENCE-WP-WW-HIGH POROSITY m 12.000367.20
12.000367.20
0.0000.00

GROUP 1 GRADINGContracted259,522.79
Current259,522.79
In place269,533.76
This Estimate5,066.05

GROUP 4 CULVERTS
0029                          0030.40 12,000.001.00012,000.00
MOBILIZATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0030                          1043.50 2.04120.000244.80
RIPRAP FILTER FABRIC m2 120.000244.80
120.000244.80
0.0000.00

0031                          1119.00 193.801.000193.80
REMOVE INLET EACH1.000193.80
1.000193.80
0.0000.00

0032                          1136.01 887.401.000887.40
REMOVE EACH1.000887.40
CONCRETE APRON 1.000887.40
0.0000.00

0033                          4004.50 2.75449.0001,234.75
CAST IRON GRATE AND FRAME kg 449.0001,234.75
449.0001,234.75
0.0000.00

0034                          4040.00 168.3016.0002,692.80
REMOVE HEADWALLS FROM CULVERTS EACH16.0002,692.80
16.0002,692.80
0.0000.00

0035                          4041.00 1,938.001.0001,938.00
CULVERT CLEANOUT EACH1.0001,938.00
at sta. 131+24.97 1.0001,938.00
0.0000.00

0036                          4050.01 8.772,354.00020,644.58
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 2,354.00020,644.58
2,354.00020,644.58
0.0000.00

0037                          4100.06 734.400.300220.32
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 0.300220.32
0.300220.32
0.0000.00

0038                          4105.59 729.302.2001,604.46
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 2.2001,604.46
2.2001,604.46
0.0000.00

0039                          4150.00 1.8922.00041.58
REINFORCING STEEL FOR HEADWALL kg 22.00041.58
22.00041.58
0.0000.00

0040                          4155.50 1.8972.000136.08
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 72.000136.08
72.000136.08
0.0000.00

0041                          4310.24 214.2033.0007,068.60
600 mm FLARED-END SECTION EACH33.0007,068.60
33.0007,068.60
0.0000.00

0042                          4310.30 295.804.0001,183.20
750 mm FLARED-END SECTION EACH4.0001,183.20
2.000591.60
0.0000.00

0043                          4310.36 402.9012.0004,834.80
900 mm FLARED-END SECTION EACH12.0004,834.80
14.0005,640.60
0.0000.00

0044                          4310.60 805.804.0003,223.20
1500 mm FLARED-END SECTION EACH4.0003,223.20
4.0003,223.20
0.0000.00

0045                          6105.01 41.82146.0006,105.72
ROCK RIPRAP, TYPE A Mg 146.0006,105.72
151.7216,344.97
0.0000.00

0046                          P300.36 142.8019.7002,813.16
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 19.7002,813.16
18.0002,570.40
0.0000.00

0047                          P310.60 170.3447.5008,091.15
1500 mm CULVERT PIPE, TYPE 2,4 OR 5 m 47.5008,091.15
47.0008,005.98
0.0000.00

0048                          P402.24 98.9413.6001,345.58
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 13.6001,345.58
13.5001,335.69
0.0000.00

0049                          P500.24 98.94345.50034,183.77
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 345.50034,183.77
351.50034,777.41
0.0000.00

0050                          P500.30 120.3641.1004,946.80
750 mm CULVERT PIPE, TYPE 2,4,5,7 or 8 m 41.1004,946.80
27.5003,309.90
0.0000.00

0051                          P500.36 142.80133.50019,063.80
900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 133.50019,063.80
146.00020,848.80
0.0000.00

GROUP 4 CULVERTSContracted134,698.35
Current134,698.35
In place135,555.72
This Estimate0.00

GROUP 5 SEEDING
0052                          0030.50 3,060.001.0003,060.00
MOBILIZATION LS 1.0003,060.00
0.0000.00
0.0000.00

0053                          L001.01 1,428.0024.00034,272.00
SEEDING, TYPE A ha 24.00034,272.00
0.0000.00
0.0000.00

0054                          L001.02 1,173.009.00010,557.00
SEEDING, TYPE B ha 9.00010,557.00
0.0000.00
0.0000.00

0055                          L032.75 112.20165.00018,513.00
MULCH Mg 165.00018,513.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted66,402.00
Current66,402.00
In place0.00
This Estimate0.00

GROUP 7 GUARDRAIL
0056                          0030.70 448.801.000448.80
MOBILIZATION LS 1.000448.80
1.000448.80
0.0000.00

0057                          6010.26 3,861.725.40020,853.29
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 5.40020,853.29
5.40020,853.29
0.0000.00

0058                          6020.00 3.57820.0002,927.40
REINFORCING STEEL FOR BRIDGE kg 820.0002,927.40
820.0002,927.40
0.0000.00

0059                          7011.20 38.41125.7304,829.29
W-BEAM GUARDRAIL m 125.7304,829.29
0.0000.00
0.0000.00

0060                          7020.00 2,058.368.00016,466.88
BRIDGE APPROACH SECTIONS EACH8.00016,466.88
0.0000.00
0.0000.00

0061                          7024.27 1,527.968.00012,223.68
GUARDRAIL END TREATMENT, TYPE II EACH8.00012,223.68
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted57,749.34
Current57,749.34
In place24,229.49
This Estimate0.00

GROUP 9 BITUMINOUS
0062                          0002.55 22.95120.6002,767.77
OVERLAY BROKEN LINES StaM120.6002,767.77
231.8265,320.41
202.8264,654.86

0063                          0002.60 22.95241.2005,535.54
OVERLAY SOLID LINES StaM241.2005,535.54
407.6559,355.69
344.3557,902.95

0064                          0030.90 75,000.001.00075,000.00
MOBILIZATION LS 1.00075,000.00
1.00075,000.00
0.0000.00

0065                          2001.00 13.6668.000928.88
GRAVEL SURFACE COURSE m3 68.000928.88
0.0000.00
0.0000.00

0066                          2020.00 35.7664.0002,288.64
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 64.0002,288.64
64.0002,288.64
0.0000.00

0067                          2021.00 102.002.000204.00
MAILBOX POST EACH2.000204.00
0.0000.00
0.0000.00

0068                          8022.00 83.64282.33023,614.08
HYDRATED LIME Mg 282.33023,614.08
192.91016,134.99
68.4485,724.99

0069                          8110.50 1,116.90114.106127,444.99
HYDRATED LIME SLURRY STABILIZATION StaM114.106127,444.99
114.418127,793.47
16.19518,088.20

0070                          9000.73 18.35500.0009,175.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.0009,175.00
SP3(9.5) 0.0000.00
0.0000.00

0071                          9005.00 32.74900.00029,466.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 900.00029,466.00
SP3(9.5) 653.46021,394.28
266.2328,716.44

0072                          9005.34 18.3517,800.000326,630.00
ASPHALTIC CONCRETE, TYPE SP3(9.5) Mg 17,800.000326,630.00
19,486.781357,582.42
12,549.532230,283.91

0073                          9009.00 3.205,477.00017,526.40
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 5,477.00017,526.40
5,477.00017,526.40
0.0000.00

0074                          9020.91 238.2827.0006,433.56
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 27.0006,433.56
0.0000.00
0.0000.00

0075                          9021.01 238.281,046.000249,240.88
PERFORMANCE GRADED BINDER (64-22) Mg 1,046.000249,240.88
1,045.162249,041.20
644.795153,641.75

0076                          9034.00 1.225,477.0006,681.94
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 5,477.0006,681.94
5,477.0006,681.94
0.0000.00

0077                          9052.15 0.32286,565.00091,700.80
EMULSIFIED ASPHALT FOR HYDRATED LIME SLURRY STABILIZATION L 286,565.00091,700.80
1,391.348445.23
178.41757.09

0078                          9053.00 0.2447,009.00011,282.16
TACK COAT L 47,009.00011,282.16
48,545.00011,650.80
38,000.0009,120.00

0079                          9111.00 1.02802.000818.04
WATER kL 802.000818.04
0.0000.00
0.0000.00

0080                          9170.00 147.51241.21135,581.03
EARTH SHOULDER CONSTRUCTION StaM241.21135,581.03
137.60020,297.38
137.60020,297.38

0081                          9173.00 751.726.5004,886.18
SUBGRADE PREPARATION StaM6.5004,886.18
6.5004,886.18
0.0000.00

0082                          9173.15 66.30241.21115,992.29
TRENCHED WIDENING StaM241.21115,992.29
226.43015,012.31
0.0000.00

0083                          9188.50 15.02464.0006,969.28
SURFACING UNDER GUARDRAIL m2 464.0006,969.28
464.0006,969.28
464.0006,969.28

0084                          9300.52 1,000.001.0001,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0001,000.00
0.0000.00
0.0000.00

4000                          9179.34 4.0530.0000.00
COLD MILLING, CLASS 4 m2 4,756.00019,276.07
4,756.00019,276.07
0.0000.00

GROUP 9 BITUMINOUSContracted1,051,167.47
Current1,070,443.53
In place966,656.69
This Estimate465,456.85

GROUP 10 GENERAL ITEMS
0085                          0001.10 3.061,496.0004,577.76
BARRICADE, TYPE III BDAY1,496.0004,577.76
1,779.0005,443.74
316.000966.96

0086                          0001.75 2.30630.0001,449.00
TEMPORARY SIGN DAY EACH630.0001,449.00
56.000128.80
56.000128.80

0087                          0001.90 0.517,567.0003,859.17
SIGN DAY EACH7,567.0003,859.17
5,238.0002,671.38
740.000377.40

0088                          0001.98 1.02372.000379.44
CONTRACTOR FURNISHED SIGN EACH372.000379.44
0.0000.00
0.0000.00

0089                          0003.10 170.46120.00020,455.20
FLAGGING DAY 120.00020,455.20
36.0006,136.56
16.0002,727.36

0090                          0003.20 226.4635.0007,926.10
FURNISHING AND OPERATING PILOT VEHICLE DAY 35.0007,926.10
10.0002,264.60
8.0001,811.68

0091                          0010.04 500.001.000500.00
FIELD OFFICE EACH1.000500.00
0.0000.00
0.0000.00

0092                          0030.10 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0093                          9110.01 55.0050.0002,750.00
RENTAL OF LOADER, FULLY OPERATED HOUR50.0002,750.00
0.0000.00
0.0000.00

0094                          9110.02 55.0040.0002,200.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR40.0002,200.00
49.5002,722.50
15.000825.00

0095                          9110.03 45.0050.0002,250.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR50.0002,250.00
0.0000.00
0.0000.00

0096                          9110.06 75.0010.000750.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR10.000750.00
0.0000.00
0.0000.00

0097                          9110.07 35.0050.0001,750.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR50.0001,750.00
35.0001,225.00
10.000350.00

GROUP 10 GENERAL ITEMSContracted53,846.67
Current53,846.67
In place25,592.58
This Estimate7,187.20

Totals for contractContracted1,623,386.61
Current1,642,662.68
In place1,421,568.24
This Estimate477,710.10