Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:3437 HOOKER BROTHERS CONSTRUCTION COMPANY
Contract ID:4866
Estimate Number:0009
Pay Period End Date:01.11.2002
Contract Location:
KEARNEY NORTHWESTEstimate Type:PROG
Contractor:
HOOKER BROTHERS CONSTRUCTION COMPANYDate Let:12.07.2000
2510 S NORTH RDDate Awarded:12.27.2000
PO BOX 5288Date Contract Executed:01.18.2001
Date Notice to Proceed:01.18.2001
GRAND ISLAND NE 68802-5288Date Work Began:08.13.2001
Phone:Date Physical Work Completed:
(308)384-2030Date Accepted:
Escrow Agent:
Surety Co:
CONTINENTAL CASUALTY COMPANY
Counties
BUFFALO
Project Number PCT Fed State Project Number Description
41866 000  0.000 EACSTPE-1880(2)  GR CONC PAVE CULV
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,581,736.97$1,575,983.57$5,753.40
$1,584,488.42Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,581,736.97$1,575,983.57$5,753.40
$1,571,488.42Retainage$-15,817.37$-15,759.84$-57.53
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.83%Net Earnings$1,565,919.60$1,560,223.73$5,695.87
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-368.20$-368.20$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$368.20-$368.20$.00
Payment$1,565,551.40$1,559,855.53$5,695.87
Project ManagerDiv. Head/Dist. Eng.
Farber, Tom01.14.2002Meyer, Keith01.14.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve01.15.2002
Controller Div. Processed
Burling, Laurie01.15.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 160.0010.0001,600.00
COVER CROP SEEDING ha 10.0001,600.00
8.0001,280.00
0.0000.00

0002                          0030.10 29,600.001.00029,600.00
MOBILIZATION LS 1.00029,600.00
1.00029,600.00
0.0000.00

0003                          1009.00 10,200.001.00010,200.00
GENERAL CLEARING AND GRUBBING LS 1.00010,200.00
1.00010,200.00
0.0000.00

0004                          1011.00 0.505,910.0002,955.00
WATER kL 5,910.0002,955.00
9,152.8004,576.40
0.0000.00

0005                          1030.00 2.40147,690.000354,456.00
EARTHWORK MEASURED IN EMBANKMENT m3 147,690.000354,456.00
147,690.000354,456.00
0.0000.00

0006                          1041.00 0.656,624.0004,305.60
SALVAGING AND PLACING TOPSOIL m2 6,624.0004,305.60
6,624.0004,305.60
0.0000.00

0007                          1102.00 2.001,363.0002,726.00
REMOVE ASPHALT SURFACE m2 1,363.0002,726.00
1,363.0002,726.00
0.0000.00

0008                          1300.18 33.00191.0006,303.00
450 mm DRIVEWAY CULVERT PIPE m 191.0006,303.00
207.8006,857.40
4.200138.60

0009                          1300.24 41.0028.0001,148.00
600 mm DRIVEWAY CULVERT PIPE m 28.0001,148.00
28.0001,148.00
0.0000.00

0010                          1300.36 68.0012.000816.00
900 mm DRIVEWAY CULVERT PIPE m 12.000816.00
14.600992.80
0.0000.00

4001                          6960.02 5,200.000.0000.00
ADDITIONAL WORK LS 1.0005,200.00
Irrigation and water line under driveway at Sta. 18+28.1 Rt. 1.0005,200.00
1.0005,200.00

GROUP 1 GRADINGContracted414,109.60
Current419,309.60
In place421,342.20
This Estimate5,338.60

GROUP 3 CONCRETE PAVEMENT
0011                          W600.03 100.003.000300.00
ADJUST VALVE BOX TO GRADE EACH3.000300.00
4.000400.00
0.0000.00

0012                          W600.30 200.003.000600.00
ADJUST SANITARY SEWER CLEAN-OUT TO GRADE EACH3.000600.00
4.000800.00
0.0000.00

0013                          0030.90 13,100.001.00013,100.00
MOBILIZATION LS 1.00013,100.00
1.00013,100.00
0.0000.00

0014                          1112.00 150.002.000300.00
REMOVE HEADER EACH2.000300.00
3.000450.00
0.0000.00

0015                          2001.00 6.00378.6002,271.60
GRAVEL SURFACE COURSE m3 1,678.60010,071.60
804.0004,824.00
0.0000.00

0016                          2020.00 5.00312.0001,560.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 312.0001,560.00
312.0001,560.00
0.0000.00

0017                          2021.00 45.0013.000585.00
MAILBOX POST EACH13.000585.00
13.000585.00
0.0000.00

0018                          3070.10 75.0059.9204,494.00
CONCRETE FOR HEADERS, CLASS 47B-20 m3 59.9204,494.00
64.2004,815.00
0.0000.00

0019                          3075.11 32.25660.00021,285.00
155 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 660.00021,285.00
660.00021,285.00
0.0000.00

0020                          3075.41 22.8044,303.6001,010,122.08
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 44,303.6001,010,122.08
44,320.8301,010,514.93
0.0000.00

0021                          4015.00 200.009.0001,800.00
ADJUST MANHOLE TO GRADE EACH9.0001,800.00
9.0001,800.00
0.0000.00

0022                          4024.55 275.006.0001,650.00
FLUME SPILLWAY m 6.0001,650.00
6.0001,650.00
0.0000.00

0023                          4024.70 1,725.004.0006,900.00
CONCRETE FLUME, TYPE I EACH4.0006,900.00
4.0006,900.00
0.0000.00

0024                          8111.00 350.004.4001,540.00
SHOULDER SUBGRADE PREPARATION StaM4.4001,540.00
4.4001,540.00
0.0000.00

0025                          9034.00 1.50626.000939.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 626.000939.00
639.000958.50
0.0000.00

0026                          9111.00 0.501,177.000588.50
WATER kL 1,177.000588.50
0.0000.00
0.0000.00

0027                          9170.00 198.00116.93623,153.33
EARTH SHOULDER CONSTRUCTION StaM116.93623,153.33
116.93623,153.32
0.0000.00

0028                          9173.00 525.0066.66835,000.70
SUBGRADE PREPARATION StaM66.66835,000.70
60.63431,832.85
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,126,189.21
Current1,133,989.21
In place1,126,168.60
This Estimate0.00

GROUP 4 CULVERTS
0029                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0030                          4050.01 9.45533.0005,036.85
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 533.0005,036.85
533.0005,036.85
0.0000.00

0031                          4350.12 38.257.700294.53
300 mm CORRUGATED METAL PIPE m 7.700294.53
8.300317.48
0.0000.00

0032                          4350.18 48.0030.9001,483.20
450 mm CORRUGATED METAL PIPE m 30.9001,483.20
25.3001,214.40
0.0000.00

0033                          4350.24 58.0085.3304,949.14
600 mm CORRUGATED METAL PIPE m 85.3304,949.14
85.6304,966.54
0.0000.00

0034                          4350.42 117.001.500175.50
1050 mm CORRUGATED METAL PIPE m 1.500175.50
2.800327.60
0.0000.00

0035                          4360.12 115.002.000230.00
300 mm METAL FLARED-END SECTION EACH2.000230.00
2.000230.00
0.0000.00

0036                          4360.18 156.004.000624.00
450 mm METAL FLARED-END SECTION EACH4.000624.00
4.000624.00
0.0000.00

0037                          4360.24 200.0011.0002,200.00
600 mm METAL FLARED-END SECTION EACH11.0002,200.00
11.0002,200.00
0.0000.00

0038                          4360.42 635.002.0001,270.00
1050 mm METAL FLARED-END SECTION EACH2.0001,270.00
2.0001,270.00
0.0000.00

GROUP 4 CULVERTSContracted19,263.22
Current19,263.22
In place19,186.87
This Estimate0.00

GROUP 10 GENERAL ITEMS
0039                          0001.10 2.501,998.0004,995.00
BARRICADE, TYPE III BDAY1,998.0004,995.00
3,354.0008,385.00
136.000340.00

0040                          0001.30 1.20222.000266.40
TYPE B HIGH INTENSITY WARNING LIGHT LDAY222.000266.40
264.000316.80
34.00040.80

0041                          0001.90 0.503,330.0001,665.00
SIGN DAY EACH3,330.0001,665.00
2,675.0001,337.50
68.00034.00

0042                          0010.04 2,500.001.0002,500.00
FIELD OFFICE EACH1.0002,500.00
1.0002,500.00
0.0000.00

0043                          0030.10 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted11,926.40
Current11,926.40
In place15,039.30
This Estimate414.80

Totals for contractContracted1,571,488.42
Current1,584,488.42
In place1,581,736.97
This Estimate5,753.40