Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:4862
Estimate Number:0009
Pay Period End Date:07.26.2003
Contract Location:
LAWRENCE EASTEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:10.10.2002
129 E 2ND STDate Awarded:10.17.2002
PO BOX 1087Date Contract Executed:10.22.2002
Date Notice to Proceed:10.22.2002
HASTINGS NE 68902-1087Date Work Began:03.24.2003
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
NUCKOLLS
Project Number PCT Fed State Project Number Description
41862 000  0.000 EACSTPD-4-5(103)  GR CULV SEED BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,199,286.36$1,835,481.01$363,805.35
$5,718,082.06Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,199,286.36$1,835,481.01$363,805.35
$5,644,665.62Retainage$-21,992.86$-18,354.81$-3,638.05
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
38.46%Net Earnings$2,177,293.50$1,817,126.20$360,167.30
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$2,177,293.50$1,817,126.20$360,167.30
Project ManagerDiv. Head/Dist. Eng.
Meyer, Steve07.29.2003Meyer, Keith07.29.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve07.29.2003
Controller Div. Processed
Burling, Laurie07.30.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 35,500.001.00035,500.00
MOBILIZATION LS 1.00035,500.00
1.00035,500.00
0.50017,750.00

0002                          1000.00 250.0010.0002,500.00
LARGE TREE REMOVAL EACH10.0002,500.00
8.0002,000.00
0.0000.00

0003                          1009.00 28,500.001.00028,500.00
GENERAL CLEARING AND GRUBBING LS 1.00028,500.00
0.90025,650.00
0.0000.00

0004                          1010.00 1.68413,500.000694,680.00
EXCAVATION m3 413,500.000694,680.00
154,711.900259,915.99
64,158.400107,786.11

0005                          1010.01 2.625,899.00015,455.38
EXCAVATION (ESTABLISHED QUANTITY) m3 5,899.00015,455.38
0.0000.00
0.0000.00

0006                          1011.00 3.907,668.00029,905.20
WATER kL 7,668.00029,905.20
30.300118.17
0.0000.00

0007                          1012.00 60.00228.00013,680.00
RIGHT-OF-WAY MARKERS EACH228.00013,680.00
209.00012,540.00
0.0000.00

0008                          1102.00 3.001,527.0004,581.00
REMOVE ASPHALT SURFACE m2 1,527.0004,581.00
124.000372.00
0.0000.00

0009                          1106.00 3.001,147.0003,441.00
REMOVE DRIVEWAY m2 1,147.0003,441.00
0.0000.00
0.0000.00

0010                          1107.00 3.0028.50085.50
REMOVE WALK m2 28.50085.50
0.0000.00
0.0000.00

0011                          1125.00 700.001.000700.00
CLEAR TRACT EACH1.000700.00
AT STA. 142+50 TO 144+50 LT. 0.0000.00
0.0000.00

0012                          1128.50 3.00244.000732.00
REMOVE SLAB m2 244.000732.00
0.0000.00
0.0000.00

0013                          1701.24 59.00862.00050,858.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 862.00050,858.00
99.7005,882.30
51.2003,020.80

0014                          1702.24 85.0012.9001,096.50
600 mm DRIVEWAY CULVERT PIPE, TYPE 3,4 OR 5 m 12.9001,096.50
0.0000.00
0.0000.00

0015                          7017.00 5.00408.3002,041.50
REMOVE GUARDRAIL m 408.3002,041.50
408.3002,041.50
0.0000.00

0016                          L006.00 250.0051.00012,750.00
COVER CROP SEEDING ha 51.00012,750.00
0.0000.00
0.0000.00

0017                          L006.50 6,981.000.6304,398.03
TEMPORARY SEEDING ha 0.6304,398.03
1.2308,586.63
0.0000.00

0018                          L020.01 4.8032,978.000158,294.40
EROSION CONTROL, TYPE A m2 32,978.000158,294.40
0.0000.00
0.0000.00

0019                          L020.08 4.859,021.10043,752.34
EROSION CONTROL, TYPE AA m2 9,021.10043,752.34
0.0000.00
0.0000.00

0020                          L020.09 8.9812,663.800113,720.92
EROSION CONTROL, TYPE AAA m2 12,663.800113,720.92
0.0000.00
0.0000.00

0021                          L020.10 1.4527,643.20040,082.64
EROSION CONTROL, TYPE HV m2 27,643.20040,082.64
0.0000.00
0.0000.00

0022                          L021.01 14.751,428.00021,063.00
EROSION CHECKS, TYPE A BALE1,428.00021,063.00
0.0000.00
0.0000.00

0023                          L021.06 13.252,611.00034,595.75
EROSION CHECKS, TYPE HV BALE2,611.00034,595.75
0.0000.00
0.0000.00

0024                          L021.11 17.50406.0007,105.00
EROSION CHECKS, TYPE ST-A BALE406.0007,105.00
0.0000.00
0.0000.00

0025                          L021.13 18.00252.0004,536.00
EROSION CHECKS, TYPE ST-AA BALE252.0004,536.00
0.0000.00
0.0000.00

0026                          L021.16 28.25245.0006,921.25
EROSION CHECKS, TYPE ST-AAA BALE245.0006,921.25
0.0000.00
0.0000.00

0027                          L021.21 15.25371.0005,657.75
EROSION CHECKS, TYPE AA BALE371.0005,657.75
0.0000.00
0.0000.00

0028                          L021.22 25.25525.00013,256.25
EROSION CHECKS, TYPE AAA BALE525.00013,256.25
0.0000.00
0.0000.00

0029                          L022.11 7.002,674.00018,718.00
FABRIC SILT FENCE-LOW POROSITY m 2,674.00018,718.00
266.0001,862.00
0.0000.00

0030                          L022.12 7.50450.0003,375.00
FABRIC SILT FENCE-HIGH POROSITY m 450.0003,375.00
375.0002,812.50
0.0000.00

0031                          L022.75 15.503,774.30058,501.65
TEMPORARY SILT CHECK m 3,774.30058,501.65
0.0000.00
0.0000.00

0032                          P300.24 70.0027.0001,890.00
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 27.0001,890.00
0.0000.00
0.0000.00

4002                          1017.50 55,750.000.0000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00055,750.00
0.1508,362.50
0.1005,575.00

GROUP 1 GRADINGContracted1,432,374.06
Current1,488,124.06
In place365,643.59
This Estimate134,131.91

GROUP 4 CULVERT
0033                          0030.40 40,000.001.00040,000.00
MOBILIZATION LS 1.00040,000.00
1.00040,000.00
0.0000.00

0034                          1043.50 2.402,288.0005,491.20
RIPRAP FILTER FABRIC m2 2,288.0005,491.20
1,251.3803,003.31
714.0801,713.79

0035                          4002.00 3.53114.000402.42
CAST IRON COVER AND FRAME kg 114.000402.42
0.0000.00
0.0000.00

0036                          4004.50 13.12252.0003,306.24
CAST IRON GRATE AND FRAME kg 252.0003,306.24
0.0000.00
0.0000.00

0037                          4018.00 695.003.0002,085.00
TAPPING EXISTING STRUCTURE EACH3.0002,085.00
0.0000.00
0.0000.00

0038                          4040.00 150.001.000150.00
REMOVE HEADWALLS FROM CULVERTS EACH1.000150.00
1.000150.00
0.0000.00

0039                          4043.50 36.0013.000468.00
REMOVE SEWER PIPE m 13.000468.00
0.0000.00
0.0000.00

0040                          4045.00 8,000.001.0008,000.00
REMOVE STRUCTURE EACH1.0008,000.00
AT STA. 40+49.14 1.0008,000.00
0.0000.00

0041                          4045.01 4,500.001.0004,500.00
REMOVE STRUCTURE EACH1.0004,500.00
AT STA. 60+81.16 1.0004,500.00
0.0000.00

0042                          4045.02 7,000.001.0007,000.00
REMOVE STRUCTURE EACH1.0007,000.00
AT STA. 65+61.01 1.0007,000.00
0.0000.00

0043                          4045.03 2,000.001.0002,000.00
REMOVE STRUCTURE EACH1.0002,000.00
AT STA. 88+54.15 1.0002,000.00
0.0000.00

0044                          4045.04 2,000.001.0002,000.00
REMOVE STRUCTURE EACH1.0002,000.00
AT STA. 91+78.4 1.0002,000.00
0.0000.00

0045                          4045.05 2,000.001.0002,000.00
REMOVE STRUCTURE EACH1.0002,000.00
AT STA. 109+43.41 1.0002,000.00
0.0000.00

0046                          4045.06 5,000.001.0005,000.00
REMOVE STRUCTURE EACH1.0005,000.00
AT STA. 129+60.61 1.0005,000.00
0.0000.00

0047                          4045.07 8,500.001.0008,500.00
REMOVE STRUCTURE EACH1.0008,500.00
AT STA. 142+12.72 1.0008,500.00
0.0000.00

0048                          4045.08 4,000.001.0004,000.00
REMOVE STRUCTURE EACH1.0004,000.00
AT STA. 158+54.11 1.0004,000.00
0.0000.00

0049                          4045.09 4,000.001.0004,000.00
REMOVE STRUCTURE EACH1.0004,000.00
AT STA. 160+17.91 1.0004,000.00
0.0000.00

0050                          4045.10 5,600.001.0005,600.00
REMOVE STRUCTURE EACH1.0005,600.00
AT STA. 168+93.7 1.0005,600.00
0.0000.00

0051                          4050.01 11.776,412.00075,469.24
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 6,412.00075,469.24
5,536.00065,158.72
432.0005,084.64

0052                          4051.01 9.168,870.00081,249.20
EXCAVATION FOR BOX CULVERTS m3 8,870.00081,249.20
10,329.00094,613.64
189.0001,731.24

0053                          4101.06 405.501,526.000618,793.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 1,526.000618,793.00
1,192.581483,591.60
113.26045,926.93

0054                          4105.59 759.004.7903,635.61
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 4.7903,635.61
0.0000.00
0.0000.00

0055                          4107.07 785.001.3701,075.45
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 1.3701,075.45
2.7402,150.90
0.0000.00

0056                          4151.00 1.1096,404.000106,044.40
REINFORCING STEEL FOR BOX CULVERT kg 96,404.000106,044.40
76,202.00083,822.20
7,396.0008,135.60

0057                          4155.50 2.76178.000491.28
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 178.000491.28
0.0000.00
0.0000.00

0058                          4157.00 2.7653.000146.28
REINFORCING STEEL FOR COLLARS kg 53.000146.28
106.000292.56
0.0000.00

0059                          4310.15 150.002.000300.00
375 mm FLARED-END SECTION EACH2.000300.00
0.0000.00
0.0000.00

0060                          4310.24 215.0031.0006,665.00
600 mm FLARED-END SECTION EACH31.0006,665.00
29.0006,235.00
0.0000.00

0061                          4310.30 300.008.0002,400.00
750 mm FLARED-END SECTION EACH8.0002,400.00
3.000900.00
0.0000.00

0062                          4310.36 410.0014.0005,740.00
900 mm FLARED-END SECTION EACH14.0005,740.00
10.0004,100.00
2.000820.00

0063                          4310.42 725.002.0001,450.00
1050 mm FLARED-END SECTION EACH2.0001,450.00
2.0001,450.00
0.0000.00

0064                          4310.48 790.008.0006,320.00
1200 mm FLARED-END SECTION EACH8.0006,320.00
8.0006,320.00
0.0000.00

0065                          4310.54 900.002.0001,800.00
1350 mm FLARED-END SECTION EACH2.0001,800.00
2.0001,800.00
0.0000.00

0066                          4310.60 1,300.002.0002,600.00
1500 mm FLARED-END SECTION EACH2.0002,600.00
2.0002,600.00
0.0000.00

0067                          4310.72 1,700.004.0006,800.00
1800 mm FLARED-END SECTION EACH4.0006,800.00
4.0006,800.00
0.0000.00

0068                          4320.30 350.002.000700.00
750 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.000700.00
2.000700.00
0.0000.00

0069                          4320.48 700.002.0001,400.00
1200 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0001,400.00
2.0001,400.00
0.0000.00

0070                          4670.05 144.0036.0005,184.00
CULVERT SANDFILL m3 36.0005,184.00
27.6003,974.40
0.0000.00

0071                          6105.01 40.00239.0009,560.00
ROCK RIPRAP, TYPE A Mg 239.0009,560.00
0.0000.00
0.0000.00

0072                          6105.02 35.00771.00026,985.00
ROCK RIPRAP, TYPE B Mg 771.00026,985.00
765.82426,803.85
415.25114,533.79

0073                          6105.03 35.001,524.00053,340.00
ROCK RIPRAP, TYPE C Mg 1,524.00053,340.00
474.17116,595.99
296.00010,360.00

0074                          P150.54 241.0060.60014,604.60
1350 mm CULVERT PIPE, TYPE 5 m 60.60014,604.60
60.00014,460.00
0.0000.00

0075                          P150.60 292.0052.50015,330.00
1500 mm CULVERT PIPE, TYPE 5 m 52.50015,330.00
52.00015,184.00
0.0000.00

0076                          P255.24 82.00111.1009,110.20
600 mm CULVERT PIPE, TYPE 4 OR 5 m 111.1009,110.20
52.5004,305.00
0.0000.00

0077                          P255.30 124.0032.2003,992.80
750 mm CULVERT PIPE, TYPE 4 OR 5 m 32.2003,992.80
0.0000.00
0.0000.00

0078                          P255.36 140.00174.70024,458.00
900 mm CULVERT PIPE, TYPE 4 OR 5 m 174.70024,458.00
169.50023,730.00
34.5004,830.00

0079                          P255.48 210.00110.70023,247.00
1200 mm CULVERT PIPE, TYPE 4 OR 5 m 110.70023,247.00
106.00022,260.00
0.0000.00

0080                          P255.72 443.0074.50033,003.50
1800 mm CULVERT PIPE, TYPE 4 OR 5 m 74.50033,003.50
74.00032,782.00
0.0000.00

0081                          P300.24 88.6099.4008,806.84
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 99.4008,806.84
120.00010,632.00
0.0000.00

0082                          P300.30 99.408.400834.96
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 8.400834.96
7.000695.80
0.0000.00

0083                          P300.36 101.7531.6003,215.30
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 31.6003,215.30
0.0000.00
0.0000.00

0084                          P300.42 173.0028.8004,982.40
1050 mm CULVERT PIPE, TYPE 3,4 OR 5 m 28.8004,982.40
26.5004,584.50
0.0000.00

0085                          P300.48 161.008.9001,432.90
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 8.9001,432.90
7.5001,207.50
0.0000.00

0086                          P300.72 269.0027.4007,370.60
1800 mm CULVERT PIPE, TYPE 3,4 OR 5 m 27.4007,370.60
26.5007,128.50
0.0000.00

0087                          P375.30 113.006.000678.00
750 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 3,4 OR 5 m 6.000678.00
6.000678.00
0.0000.00

0088                          P375.48 158.503.000475.50
1200 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 3,4 OR 5 m 3.000475.50
3.000475.50
0.0000.00

0089                          P500.24 86.00143.50012,341.00
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 143.50012,341.00
143.50012,341.00
0.0000.00

0090                          P500.30 149.0032.0004,768.00
750 mm CULVERT PIPE, TYPE 2,4,5,7 or 8 m 32.0004,768.00
27.8004,142.20
0.0000.00

0091                          P700.15 63.0021.5001,354.50
375 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 21.5001,354.50
0.0000.00
0.0000.00

0092                          P700.24 96.0021.0002,016.00
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 21.0002,016.00
0.0000.00
0.0000.00

GROUP 4 CULVERTContracted1,294,673.42
Current1,294,673.42
In place1,059,668.17
This Estimate93,135.99

GROUP 4A CONCRETE BOX CULVERT AT STA.139+32.1
0093                          0030.40 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0094                          4045.00 6,000.001.0006,000.00
REMOVE STRUCTURE EACH1.0006,000.00
AT STA. 139+39.10 1.0006,000.00
0.0000.00

0095                          4051.01 9.101,614.00014,687.40
EXCAVATION FOR BOX CULVERTS m3 1,614.00014,687.40
1,824.00016,598.40
0.0000.00

0096                          4101.06 405.50283.770115,068.73
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 283.770115,068.73
283.768115,067.92
0.0000.00

0097                          4151.00 1.0015,817.00015,817.00
REINFORCING STEEL FOR BOX CULVERT kg 15,817.00015,817.00
15,816.00015,816.00
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA.139+32.1Contracted157,573.13
Current157,573.13
In place159,482.32
This Estimate0.00

GROUP 4B SANITARY SEWER AND WATER MAIN
0098                          0030.40 4,500.001.0004,500.00
MOBILIZATION LS 1.0004,500.00
0.0000.00
0.0000.00

0099                          1117.00 1,000.001.0001,000.00
REMOVE MANHOLE EACH1.0001,000.00
0.0000.00
0.0000.00

0100                          4016.00 2,750.001.0002,750.00
MANHOLE EACH1.0002,750.00
AT STA. 11+78.02 - 2.09 m RT. 0.0000.00
0.0000.00

0101                          4016.01 2,750.001.0002,750.00
MANHOLE EACH1.0002,750.00
AT STA. 11+91.5 - 10.81 m RT. 0.0000.00
0.0000.00

0102                          4764.78 270.0014.0003,780.00
200 mm P.V.C. SEWER PIPE m 14.0003,780.00
0.0000.00
0.0000.00

0103                          4796.00 35.001.00035.00
150 mm PLUG EACH1.00035.00
1.00035.00
1.00035.00

0104                          W100.55 410.002.000820.00
WET TAP CUT-IN EACH2.000820.00
1.000410.00
1.000410.00

0105                          W175.00 210.006.0001,260.00
19 mm CORPORATION STOP EACH6.0001,260.00
0.0000.00
0.0000.00

0106                          W175.09 400.001.000400.00
50 mm CORPORATION STOP EACH1.000400.00
0.0000.00
0.0000.00

0107                          W176.24 33.4584.0002,809.80
19 mm WATER SERVICE m 84.0002,809.80
33.2201,111.21
33.2201,111.21

0108                          W176.30 50.5316.000808.48
50 mm WATER SERVICE m 16.000808.48
0.0000.00
0.0000.00

0109                          W176.34 60.0019.0001,140.00
100 mm WATER SERVICE m 19.0001,140.00
0.0000.00
0.0000.00

0110                          W176.70 65.008.000520.00
WATER SERVICE CONNECTION EACH8.000520.00
0.0000.00
0.0000.00

0111                          W180.00 200.002.300460.00
CONCRETE CLASS 47B-25 FOR BLOCKS AND ANCHORAGES m3 2.300460.00
1.920384.00
1.920384.00

0112                          W205.06 55.00274.00015,070.00
150 mm WATER MAIN PIPE m 274.00015,070.00
292.28016,075.40
292.28016,075.40

0113                          W219.64 460.001.000460.00
100 mm GATE VALVE AND BOX EACH1.000460.00
0.0000.00
0.0000.00

0114                          W219.66 527.002.0001,054.00
150 mm GATE VALVE AND BOX EACH2.0001,054.00
2.0001,054.00
2.0001,054.00

0115                          W222.80 1,850.002.0003,700.00
150 mm PUMPER HYDRANT, M.J. EACH2.0003,700.00
2.0003,700.00
2.0003,700.00

0116                          W222.91 250.001.000250.00
SALVAGE FIRE HYDRANT EACH1.000250.00
0.0000.00
0.0000.00

0117                          W355.10 226.832.000453.66
250 mm SLEEVE EACH2.000453.66
1.000226.83
1.000226.83

0118                          W356.10 185.001.000185.00
150 mm X 100 mm TEE EACH1.000185.00
0.0000.00
0.0000.00

0119                          W356.12 200.002.000400.00
150 mm X 150 mm TEE EACH2.000400.00
2.000400.00
2.000400.00

0120                          W356.18 326.001.000326.00
250 mm X 150 mm TEE EACH1.000326.00
1.000326.00
1.000326.00

0121                          W357.16 135.003.000405.00
150 mm - 45 DEGREE BEND EACH3.000405.00
2.000270.00
2.000270.00

0122                          W359.04 45.001.00045.00
100 mm CAP EACH1.00045.00
0.0000.00
0.0000.00

0123                          W359.08 65.001.00065.00
200 mm CAP EACH1.00065.00
0.0000.00
0.0000.00

0124                          W370.00 455.001.000455.00
150 mm X 150 mm 508 mm OFFSET EACH1.000455.00
1.000455.00
1.000455.00

0125                          W722.50 300.001.000300.00
ABANDON WATER MAIN EACH1.000300.00
0.0000.00
0.0000.00

0126                          W800.33 300.001.000300.00
REMOVE HYDRANT EACH1.000300.00
0.0000.00
0.0000.00

4003                          W800.92 41.060.0000.00
BORE 19 mm WATER SERVICE m 80.0003,284.80
28.9501,188.69
28.9501,188.69

GROUP 4B SANITARY SEWER AND WATER MAINContracted46,501.94
Current49,786.74
In place25,636.13
This Estimate25,636.13

GROUP 5 SEEDING
0127                          0030.50 300.001.000300.00
MOBILIZATION LS 1.000300.00
0.0000.00
0.0000.00

0128                          L001.01 1,245.0038.66048,131.70
SEEDING, TYPE A ha 38.66048,131.70
0.0000.00
0.0000.00

0129                          L001.02 739.0011.3508,387.65
SEEDING, TYPE B ha 11.3508,387.65
0.0000.00
0.0000.00

0130                          L001.03 939.001.3201,239.48
SEEDING, TYPE C ha 1.3201,239.48
0.0000.00
0.0000.00

0131                          L032.75 65.00257.00016,705.00
MULCH Mg 257.00016,705.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted74,763.83
Current74,763.83
In place0.00
This Estimate0.00

GROUP 6 BRIDGE AT STA. 48+40.8
0132                          0030.60 8,750.001.0008,750.00
MOBILIZATION LS 1.0008,750.00
1.0008,750.00
0.0000.00

0133                          1010.01 3.60870.0003,132.00
EXCAVATION (ESTABLISHED QUANTITY) m3 870.0003,132.00
0.0000.00
0.0000.00

0134                          1043.50 3.00128.000384.00
RIPRAP FILTER FABRIC m2 128.000384.00
0.0000.00
0.0000.00

0135                          3050.15 233.00116.70027,191.10
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 116.70027,191.10
109.50025,513.50
109.50025,513.50

0136                          3051.10 1.087,882.0008,512.56
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 7,882.0008,512.56
6,412.0006,924.96
6,412.0006,924.96

0137                          6000.10 1,125.001.0001,125.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,125.00
1.0001,125.00
0.0000.00

0138                          6000.11 1,125.001.0001,125.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,125.00
1.0001,125.00
0.0000.00

0139                          6005.35 167.0023.0003,841.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 23.0003,841.00
0.0000.00
0.0000.00

0140                          6005.78 875.004.0003,500.00
EXPANSION BEARING, TFE TYPE EACH4.0003,500.00
4.0003,500.00
0.0000.00

0141                          6005.83 640.004.0002,560.00
FIXED BEARING EACH4.0002,560.00
4.0002,560.00
0.0000.00

0142                          6010.22 416.0087.80036,524.80
CLASS 47B-20 CONCRETE FOR BRIDGE m3 87.80036,524.80
87.80036,524.80
0.0000.00

0143                          6010.26 398.00153.40061,053.20
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 153.40061,053.20
139.10055,361.80
107.70042,864.60

0144                          6011.11 131,000.001.000131,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000131,000.00
AT STA. 48+40.8 1.000131,000.00
0.0000.00

0145                          6040.00 5,350.001.0005,350.00
REMOVE STRUCTURE EACH1.0005,350.00
AT STA. 48+40.8 0.0000.00
0.0000.00

0146                          6080.00 4.661,470.0006,850.20
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 1,470.0006,850.20
1,470.0006,850.20
0.0000.00

0147                          6104.00 8.75371.0003,246.25
BROKEN CONCRETE RIPRAP Mg 371.0003,246.25
0.0000.00
0.0000.00

0148                          6105.01 43.0047.0002,021.00
ROCK RIPRAP, TYPE A Mg 47.0002,021.00
0.0000.00
0.0000.00

0149                          6131.50 1.0719,327.00020,679.89
EPOXY COATED REINFORCING STEEL kg 19,327.00020,679.89
17,634.00018,868.38
12,785.42513,680.40

0150                          6139.50 25.0071.0001,775.00
SUBSURFACE DRAINAGE MATTING m2 71.0001,775.00
0.0000.00
0.0000.00

0151                          6210.12 44.00687.00030,228.00
HP 250 mm X 62 kg STEEL PILING m 687.00030,228.00
709.60031,222.40
0.0000.00

0152                          6310.00 122.00161.10019,654.20
STEEL SHEET PILING m2 161.10019,654.20
161.10019,654.20
0.0000.00

0153                          8091.00 24.00235.0005,640.00
GRANULAR BACKFILL m3 235.0005,640.00
235.0005,640.00
0.0000.00

4004                          6210.61 88.000.0000.00
PILE SPLICE EACH5.000440.00
For additional length of piling 5.000440.00
0.0000.00

GROUP 6 BRIDGE AT STA. 48+40.8Contracted384,143.20
Current384,583.20
In place355,060.24
This Estimate88,983.46

GROUP 7 GUARDRAIL
0154                          0030.70 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
0.0000.00
0.0000.00

0155                          7011.20 40.2545.7201,840.23
W-BEAM GUARDRAIL m 45.7201,840.23
0.0000.00
0.0000.00

0156                          7020.00 2,619.004.00010,476.00
BRIDGE APPROACH SECTIONS EACH4.00010,476.00
0.0000.00
0.0000.00

0157                          7024.27 1,554.004.0006,216.00
GUARDRAIL END TREATMENT, TYPE II EACH4.0006,216.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted19,532.23
Current19,532.23
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0158                          0002.55 29.00166.4004,825.60
OVERLAY BROKEN LINES StaM166.4004,825.60
0.0000.00
0.0000.00

0159                          0030.90 139,000.001.000139,000.00
MOBILIZATION LS 1.000139,000.00
0.50069,500.00
0.0000.00

0160                          2001.00 11.252,371.00026,673.75
GRAVEL SURFACE COURSE m3 2,371.00026,673.75
1,403.48015,789.16
592.2806,663.15

0161                          2020.00 7.501,721.00012,907.50
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 1,721.00012,907.50
0.0000.00
0.0000.00

0162                          2021.00 50.0017.000850.00
MAILBOX POST EACH17.000850.00
0.0000.00
0.0000.00

0163                          3014.12 60.00180.03010,801.80
COMBINATION CONCRETE CLASS 47B-25 CURB AND GUTTER m 180.03010,801.80
0.0000.00
0.0000.00

0164                          3016.21 45.0028.5001,282.50
CONCRETE CLASS 47B-20 SIDEWALKS m2 28.5001,282.50
0.0000.00
0.0000.00

0165                          3020.26 48.0078.1003,748.80
CONCRETE CLASS 47B-25 DRIVEWAY m2 78.1003,748.80
0.0000.00
0.0000.00

0166                          4015.00 350.004.0001,400.00
ADJUST MANHOLE TO GRADE EACH4.0001,400.00
0.0000.00
0.0000.00

0167                          4024.55 240.004.6001,104.00
FLUME SPILLWAY m 4.6001,104.00
0.0000.00
0.0000.00

0168                          4024.70 2,400.002.0004,800.00
CONCRETE FLUME, TYPE I EACH2.0004,800.00
0.0000.00
0.0000.00

0169                          8022.00 126.59141.00017,849.19
HYDRATED LIME Mg 141.00017,849.19
0.0000.00
0.0000.00

0170                          8029.84 2.0972,541.000151,610.69
BITUMINOUS FOUNDATION COURSE 100 mm m2 72,541.000151,610.69
0.0000.00
0.0000.00

0171                          8110.50 1,759.0056.50199,385.26
HYDRATED LIME SLURRY STABILIZATION StaM56.50199,385.26
0.0000.00
0.0000.00

0172                          8111.00 750.002.2801,710.00
SHOULDER SUBGRADE PREPARATION StaM2.2801,710.00
0.0000.00
0.0000.00

0173                          9000.75 22.76500.00011,380.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.00011,380.00
SP2(12.5) 0.0000.00
0.0000.00

0174                          9005.00 31.93200.0006,386.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 200.0006,386.00
SP2(12.5) 0.0000.00
0.0000.00

0175                          9005.30 22.7638,420.000874,439.20
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 38,420.000874,439.20
0.0000.00
0.0000.00

0176                          9009.00 3.305,782.00019,080.60
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 5,782.00019,080.60
0.0000.00
0.0000.00

0177                          9020.91 196.0027.0005,292.00
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 27.0005,292.00
0.0000.00
0.0000.00

0178                          9021.01 196.002,085.480408,754.08
PERFORMANCE GRADED BINDER (64-22) Mg 2,085.480408,754.08
0.0000.00
0.0000.00

0179                          9030.00 8.95186.0001,664.70
CONSTRUCTING ASPHALTIC CONCRETE CURB m 186.0001,664.70
0.0000.00
0.0000.00

0180                          9034.00 2.504,180.00010,450.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 4,180.00010,450.00
0.0000.00
0.0000.00

0181                          9052.15 0.25142,890.00035,722.50
EMULSIFIED ASPHALT FOR HYDRATED LIME SLURRY STABILIZATION L 142,890.00035,722.50
0.0000.00
0.0000.00

0182                          9053.00 0.2662,520.00016,255.20
TACK COAT L 62,520.00016,255.20
0.0000.00
0.0000.00

0183                          9111.00 2.002,152.0004,304.00
WATER kL 2,152.0004,304.00
0.0000.00
0.0000.00

0184                          9170.00 270.00314.32584,867.75
EARTH SHOULDER CONSTRUCTION StaM314.32584,867.75
0.0000.00
0.0000.00

0185                          9173.00 695.00100.75270,022.64
SUBGRADE PREPARATION StaM100.75270,022.64
0.0000.00
0.0000.00

0186                          9179.23 850.0013.12911,159.65
COLD MILLING, CLASS 3 StaM13.12911,159.65
0.0000.00
0.0000.00

0187                          9179.24 975.00100.36497,854.90
COLD MILLING, CLASS 4 StaM0.0000.00
0.0000.00
-100.364-97,854.90

0188                          9188.50 25.00260.0006,500.00
SURFACING UNDER GUARDRAIL m2 260.0006,500.00
0.0000.00
0.0000.00

0189                          9300.52 5,000.001.0005,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0005,000.00
0.0000.00
0.0000.00

4005                          9179.24 1,083.340.0000.00
COLD MILLING, CLASS 4 StaM100.364108,728.34
Class 4 Milling, 128mm. 100.364108,728.34
100.364108,728.34

GROUP 9 BITUMINOUSContracted2,147,082.31
Current2,157,955.74
In place194,017.50
This Estimate17,536.59

GROUP 10 GENERAL ITEMS
0190                          0001.08 0.505,775.0002,887.50
BARRICADE, TYPE II BDAY5,775.0002,887.50
1,554.000777.00
294.000147.00

0191                          0001.10 2.5012,208.00030,520.00
BARRICADE, TYPE III BDAY12,208.00030,520.00
9,607.00024,017.50
1,480.0003,700.00

0192                          0001.75 5.00300.0001,500.00
TEMPORARY SIGN DAY EACH300.0001,500.00
0.0000.00
0.0000.00

0193                          0001.90 0.5014,328.0007,164.00
SIGN DAY EACH14,328.0007,164.00
5,282.0002,641.00
630.000315.00

0194                          0003.10 185.0030.0005,550.00
FLAGGING DAY 30.0005,550.00
0.0000.00
0.0000.00

0195                          0003.20 285.0015.0004,275.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 15.0004,275.00
0.0000.00
0.0000.00

0196                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
1.0001,500.00
0.0000.00

0197                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
0.8808,800.00
0.0000.00

0198                          9110.01 65.0095.0006,175.00
RENTAL OF LOADER, FULLY OPERATED HOUR95.0006,175.00
0.0000.00
0.0000.00

0199                          9110.02 65.0055.0003,575.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR55.0003,575.00
3.000195.00
0.0000.00

0200                          9110.03 50.0095.0004,750.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR95.0004,750.00
0.0000.00
0.0000.00

0201                          9110.06 75.0040.0003,000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR40.0003,000.00
0.0000.00
0.0000.00

0202                          9110.07 75.0095.0007,125.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR95.0007,125.00
0.0000.00
0.0000.00

4001                          0001.98 0.580.0000.00
CONTRACTOR FURNISHED SIGN EACH5,290.0003,068.20
3,186.0001,847.88
378.000219.24

GROUP 10 GENERAL ITEMSContracted88,021.50
Current91,089.70
In place39,778.38
This Estimate4,381.24

Totals for contractContracted5,644,665.62
Current5,718,082.06
In place2,199,286.33
This Estimate363,805.32