| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 6 BRIDGE AT STA. 5+83.00 | | |
|
0001 L006.00 | 70.00 | 4.000 | 280.00
|
COVER CROP SEEDING | ACRE | 4.000 | 280.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 0001.10 | 2.00 | 1,807.000 | 3,614.00
|
BARRICADE, TYPE III | BDAY | 1,807.000 | 3,614.00
|
| | 3,082.000 | 6,164.00
|
| | 133.000 | 266.00
|
| | |
|
0003 0001.30 | 2.00 | 278.000 | 556.00
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 278.000 | 556.00
|
| | 880.000 | 1,760.00
|
| | 35.000 | 70.00
|
| | |
|
0004 0001.90 | 0.62 | 2,919.000 | 1,809.78
|
SIGN DAY | EACH | 2,919.000 | 1,809.78
|
| | 2,912.000 | 1,805.44
|
| | 119.000 | 73.78
|
| | |
|
0005 0010.04 | 2,200.00 | 1.000 | 2,200.00
|
FIELD OFFICE | EACH | 1.000 | 2,200.00
|
| | 1.000 | 2,200.00
|
| | 0.000 | 0.00
|
| | |
|
0006 0030.60 | 9,000.00 | 1.000 | 9,000.00
|
MOBILIZATION | LS | 1.000 | 9,000.00
|
| | 1.000 | 9,000.00
|
| | 0.000 | 0.00
|
| | |
|
0007 1009.00 | 7,000.00 | 1.000 | 7,000.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 7,000.00
|
| | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
0008 1010.01 | 2.15 | 12,027.000 | 25,858.05
|
EXCAVATION (ESTABLISHED QUANTITY) | CY | 10,887.000 | 23,407.05
|
| | 10,887.000 | 23,407.05
|
| | 0.000 | 0.00
|
| | |
|
0009 1011.00 | 8.00 | 96.000 | 768.00
|
WATER | MGAL | 96.000 | 768.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0010 1300.36 | 22.00 | 50.000 | 1,100.00
|
36" DRIVEWAY CULVERT PIPE | LF | 50.000 | 1,100.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0011 2001.00 | 8.50 | 360.000 | 3,060.00
|
GRAVEL SURFACE COURSE | CY | 360.000 | 3,060.00
|
| | 277.407 | 2,357.96
|
| | 75.007 | 637.56
|
| | |
|
0012 4033.00 | 160.00 | 1.000 | 160.00
|
REMOVE AND REINSTALL AUTOMATIC FLOOD CONTROL GATE | EACH | 1.000 | 160.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0013 4050.01 | 4.00 | 339.000 | 1,356.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | CY | 339.000 | 1,356.00
|
| | 339.000 | 1,356.00
|
| | 0.000 | 0.00
|
| | |
|
0014 4300.36 | 24.00 | 74.000 | 1,776.00
|
36" CULVERT PIPE | LF | 74.000 | 1,776.00
|
| | 88.000 | 2,112.00
|
| | 0.000 | 0.00
|
| | |
|
0015 4310.36 | 350.00 | 2.000 | 700.00
|
36" FLARED-END SECTION | EACH | 2.000 | 700.00
|
| | 2.000 | 700.00
|
| | 0.000 | 0.00
|
| | |
|
0016 4380.36 | 25.00 | 84.000 | 2,100.00
|
36" ROUND EQUIVALENT CORRUGATED METAL PIPE | LF | 84.000 | 2,100.00
|
| | 82.000 | 2,050.00
|
| | -2.000 | -50.00
|
| | |
|
0017 4390.36 | 350.00 | 4.000 | 1,400.00
|
36" ROUND EQUIVALENT METAL PIPE FLARED-END SECTION | EACH | 4.000 | 1,400.00
|
| | 4.000 | 1,400.00
|
| | 0.000 | 0.00
|
| | |
|
0018 6000.10 | 1,400.00 | 1.000 | 1,400.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 1,400.00
|
| | 1.000 | 1,400.00
|
| | 0.000 | 0.00
|
| | |
|
0019 6000.11 | 1,400.00 | 1.000 | 1,400.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 1,400.00
|
| | 1.000 | 1,400.00
|
| | 0.000 | 0.00
|
| | |
|
0020 6001.50 | 4,300.00 | 1.000 | 4,300.00
|
BENT NO.1 EXCAVATION | LS | 1.000 | 4,300.00
|
| | 1.000 | 4,300.00
|
| | 0.000 | 0.00
|
| | |
|
0021 6001.51 | 4,300.00 | 1.000 | 4,300.00
|
BENT NO.2 EXCAVATION | LS | 1.000 | 4,300.00
|
| | 1.000 | 4,300.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6010.22 | 286.50 | 175.700 | 50,338.05
|
CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 175.700 | 50,338.05
|
| | 175.700 | 50,338.06
|
| | -1.000 | -286.50
|
| | |
|
0023 6010.26 | 290.50 | 268.100 | 77,883.05
|
CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 268.100 | 77,883.05
|
| | 268.100 | 77,883.05
|
| | 0.000 | 0.00
|
| | |
|
0024 6020.00 | 0.48 | 64,065.000 | 30,751.20
|
REINFORCING STEEL FOR BRIDGE | LB | 60,361.000 | 28,973.28
|
| | 60,361.000 | 28,973.28
|
| | 642.000 | 308.16
|
| | |
|
0025 6040.00 | 3,220.00 | 1.000 | 3,220.00
|
REMOVE STRUCTURE | EACH | 1.000 | 3,220.00
|
AT STA. 5+85 RT. | | 1.000 | 3,220.00
|
| | 0.000 | 0.00
|
| | |
|
0026 6080.00 | 4.00 | 1,765.000 | 7,060.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 1,765.000 | 7,060.00
|
| | 1,765.000 | 7,060.00
|
| | 0.000 | 0.00
|
| | |
|
0027 6105.01 | 41.00 | 40.000 | 1,640.00
|
ROCK RIPRAP, TYPE A | TON | 40.000 | 1,640.00
|
| | 43.210 | 1,771.61
|
| | 43.210 | 1,771.61
|
| | |
|
0028 6105.02 | 40.00 | 241.000 | 9,640.00
|
ROCK RIPRAP, TYPE B | TON | 241.000 | 9,640.00
|
| | 250.940 | 10,037.60
|
| | 0.000 | 0.00
|
| | |
|
0029 6200.00 | 31.00 | 1,320.000 | 40,920.00
|
CONCRETE PILING | LF | 1,310.000 | 40,610.00
|
| | 1,310.000 | 40,610.00
|
| | 0.000 | 0.00
|
| | |
|
0030 7020.00 | 1,025.00 | 4.000 | 4,100.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,100.00
|
| | 4.000 | 4,100.00
|
| | 0.000 | 0.00
|
| | |
|
0031 7021.45 | 925.00 | 4.000 | 3,700.00
|
BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 3,700.00
|
| | 4.000 | 3,700.00
|
| | 0.000 | 0.00
|
| | |
|
4000 L999.00 | 226.25 | 0.000 | 0.00
|
COMPENSATION FOR ADDITIONAL COST | LS | 1.000 | 226.25
|
(Reinforcing Steel for Bridges) | | 1.000 | 226.25
|
| | 1.000 | 226.25
|
| | |
|
4001 6200.00 | 18.60 | 0.000 | 0.00
|
CONCRETE PILING | LF | 10.000 | 186.00
|
Contingency- Authorized Pile Cut-Off (Ref Std Specs Sec 703) | | 10.000 | 186.00
|
| | 10.000 | 186.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 5+83.00 | | Contracted | 303,390.13
|
| | Current | 299,263.46
|
| | In place | 300,818.30
|
| | This Estimate | 3,202.86
|
| | |
|
Totals for contract | | Contracted | 303,390.13
|
---|
| | Current | 299,263.46
|
---|
| | In place | 300,818.30
|
---|
| | This Estimate | 3,202.86
|
---|