| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 6 BRIDGE AT STA. 24+67.0 | | |
|
| 0001 L006.00 | 150.00 | 1.000 | 150.00
|
| COVER CROP SEEDING | ACRE | 1.000 | 150.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 0001.10 | 1.50 | 1,500.000 | 2,250.00
|
| BARRICADE, TYPE III | BDAY | 1,500.000 | 2,250.00
|
| | | 1,822.000 | 2,733.00
|
| | 208.000 | 312.00
|
| | |
|
| 0003 0001.30 | 2.50 | 250.000 | 625.00
|
| TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 250.000 | 625.00
|
| | | 520.000 | 1,300.00
|
| | 64.000 | 160.00
|
| | |
|
| 0004 0001.90 | 0.50 | 2,750.000 | 1,375.00
|
| SIGN DAY | EACH | 2,750.000 | 1,375.00
|
| | | 1,538.000 | 769.00
|
| | 186.000 | 93.00
|
| | |
|
| 0005 0030.60 | 16,500.00 | 1.000 | 16,500.00
|
| MOBILIZATION | LS | 1.000 | 16,500.00
|
| | | 1.000 | 16,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 1009.00 | 2,500.00 | 1.000 | 2,500.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 2,500.00
|
| | | 1.000 | 2,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0007 1011.00 | 10.00 | 40.000 | 400.00
|
| WATER | MGAL | 40.000 | 400.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0008 1030.00 | 3.05 | 4,072.000 | 12,419.60
|
| EARTHWORK MEASURED IN EMBANKMENT | CY | 4,072.000 | 12,419.60
|
| | | 4,072.000 | 12,419.60
|
| | 4,072.000 | 12,419.60
|
| | |
|
| 0009 1043.50 | 1.99 | 553.000 | 1,100.47
|
| RIPRAP FILTER FABRIC | SY | 553.000 | 1,100.47
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0010 1300.24 | 13.38 | 82.000 | 1,097.16
|
| 24" DRIVEWAY CULVERT PIPE | LF | 82.000 | 1,097.16
|
| | | 82.000 | 1,097.16
|
| | 82.000 | 1,097.16
|
| | |
|
| 0011 4050.01 | 7.17 | 68.000 | 487.56
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | CY | 68.000 | 487.56
|
| | | 68.000 | 487.56
|
| | 68.000 | 487.56
|
| | |
|
| 0012 4350.30 | 21.00 | 70.000 | 1,470.00
|
| 30" CORRUGATED METAL PIPE | LF | 70.000 | 1,470.00
|
| | | 70.000 | 1,470.00
|
| | 70.000 | 1,470.00
|
| | |
|
| 0013 4360.30 | 225.00 | 2.000 | 450.00
|
| 30" METAL FLARED-END SECTION | EACH | 2.000 | 450.00
|
| | | 2.000 | 450.00
|
| | 2.000 | 450.00
|
| | |
|
| 0014 6000.10 | 2,000.00 | 1.000 | 2,000.00
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,000.00
|
| | | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 6000.11 | 2,000.00 | 1.000 | 2,000.00
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,000.00
|
| | | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 6001.50 | 3,000.00 | 1.000 | 3,000.00
|
| BENT NO.1 EXCAVATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 6001.51 | 3,000.00 | 1.000 | 3,000.00
|
| BENT NO.2 EXCAVATION | LS | 1.000 | 3,000.00
|
| | | 1.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 6010.22 | 210.00 | 295.000 | 61,950.00
|
| CLASS 47B-3000 CONCRETE FOR BRIDGE | CY | 295.000 | 61,950.00
|
| | | 295.000 | 61,950.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 6010.26 | 230.00 | 213.800 | 49,174.00
|
| CLASS 47BD-4000 CONCRETE FOR BRIDGE | CY | 213.800 | 49,174.00
|
| | | 213.800 | 49,174.00
|
| | 14.400 | 3,312.00
|
| | |
|
| 0020 6020.00 | 0.50 | 54,843.000 | 27,421.50
|
| REINFORCING STEEL FOR BRIDGE | LB | 54,843.000 | 27,421.50
|
| | | 54,843.000 | 27,421.50
|
| | 3,655.000 | 1,827.50
|
| | |
|
| 0021 6040.00 | 12,000.00 | 1.000 | 12,000.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 12,000.00
|
| AT STA. 24+57.0 | | 1.000 | 12,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 6080.00 | 2.64 | 1,705.000 | 4,501.20
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | LB | 1,705.000 | 4,501.20
|
| | | 1,705.000 | 4,501.20
|
| | 0.000 | 0.00
|
| | |
|
| 0023 6104.00 | 15.00 | 373.000 | 5,595.00
|
| BROKEN CONCRETE RIPRAP | TON | 373.000 | 5,595.00
|
| | | 492.100 | 7,381.50
|
| | 0.000 | 0.00
|
| | |
|
| 0024 6200.00 | 28.00 | 1,370.000 | 38,360.00
|
| CONCRETE PILING | LF | 1,370.000 | 38,360.00
|
| | | 1,370.000 | 38,360.00
|
| | 0.000 | 0.00
|
| | |
|
| 0025 7020.00 | 1,175.00 | 4.000 | 4,700.00
|
| BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,700.00
|
| | | 4.000 | 4,700.00
|
| | 4.000 | 4,700.00
|
| | |
|
| 0026 7021.45 | 1,125.00 | 4.000 | 4,500.00
|
| BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 4,500.00
|
| | | 4.000 | 4,500.00
|
| | 4.000 | 4,500.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 24+67.0 | | Contracted | 259,026.49
|
| | Current | 259,026.49
|
| | In place | 259,714.52
|
| | This Estimate | 30,828.82
|
| | |
|
| Totals for contract | | Contracted | 259,026.49
|
|---|
| | Current | 259,026.49
|
|---|
| | In place | 259,714.52
|
|---|
| | This Estimate | 30,828.82
|
|---|