Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:4574
Estimate Number:0031
Pay Period End Date:06.08.2002
Contract Location:
BRUNING - STRANGEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:08.31.2000
129 E 2ND STDate Awarded:09.08.2000
PO BOX 1087Date Contract Executed:09.12.2000
Date Notice to Proceed:09.12.2000
HASTINGS NE 68902-1087Date Work Began:09.25.2000
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
FILLMORE
THAYER
Project Number PCT Fed State Project Number Description
41574 000  0.000 F-81-1(1021)  GRAD CONCPAVE CULV BR GDRL
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$4,624,438.96$4,458,995.12$165,443.84
$4,955,030.42Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$4,624,438.96$4,458,995.12$165,443.84
$4,936,420.44Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
93.33%Net Earnings$4,599,438.96$4,433,995.12$165,443.84
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-137.03$-137.03$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$137.03-$137.03$.00
Payment$4,599,301.93$4,433,858.09$165,443.84
Project ManagerDiv. Head/Dist. Eng.
Cuda, Bill06.11.2002Meyer, Keith06.12.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve06.12.2002
Controller Div. Processed
Burling, Laurie06.13.2002
Detailed breakdown of stockpiled materials
Est Nbr:0005
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01366095.00 STEEL DIAPHRAGM
S.P. Initial Payment1,470.0019756
Total for estimate 0005:1,470.00
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment16,110.5121006
Coarse Aggregate
S.P. Initial Payment22,867.4221006
Coarse Aggregate
Total for estimate 0006:38,977.93
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment32,444.6821040
Coarse Aggregate
S.P. Initial Payment24,337.8421087
Coarse Aggregate
S.P. Initial Payment5,623.0621219
Coarse Aggregate
Total for estimate 0007:62,405.58
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment1,006.4221374
Coarse Aggregate
Total for estimate 0008:1,006.42
Est Nbr:0011
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment12,401.0721374
Coarse Aggregate
Total for estimate 0011:12,401.07
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-16,110.5121006
Coarse Aggregate
S.P. Adjustment-22,867.4221006
Coarse Aggregate
S.P. Adjustment-381.7821040
Coarse Aggregate
Total for estimate 0016:-39,359.71
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-32,062.9021040
Coarse Aggregate
S.P. Adjustment-8,267.0321087
Coarse Aggregate
Total for estimate 0017:-40,329.93
Est Nbr:0018
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-16,070.8121087
Coarse Aggregate
S.P. Adjustment-5,623.0621219
Coarse Aggregate
S.P. Adjustment-1,006.4221374
Coarse Aggregate
S.P. Adjustment-12,401.0721374
Coarse Aggregate
Total for estimate 0018:-35,101.36
Est Nbr:0024
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01366095.00 STEEL DIAPHRAGM
S.P. Adjustment-1,470.0019756
Total for estimate 0024:-1,470.00
Est Nbr:0026
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment12,782.3823505
Coarse Aggregate
Total for estimate 0026:12,782.38
Est Nbr:0027
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Initial Payment19,603.5523536
Coarse Aggregate
Total for estimate 0027:19,603.55
Est Nbr:0029
Item NbrItem CdItem DescAdj AmtInvoice Nbr
00433075.55 255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25
S.P. Adjustment-12,782.3823505
Coarse Aggregate
S.P. Adjustment-19,603.5523536
Coarse Aggregate
Total for estimate 0029:-32,385.93
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 160.5519.5003,130.73
COVER CROP SEEDING ha 19.5003,130.73
13.3502,143.34
0.0000.00

0002                          L020.01 6.001,058.0006,348.00
EROSION CONTROL, TYPE A m2 1,058.0006,348.00
1,520.0609,120.36
0.0000.00

0003                          L020.08 6.00534.0003,204.00
EROSION CONTROL, TYPE AA m2 534.0003,204.00
0.0000.00
0.0000.00

0004                          L020.09 20.0032.000640.00
EROSION CONTROL, TYPE AAA m2 32.000640.00
0.0000.00
0.0000.00

0005                          L020.10 1.615,424.0008,732.64
EROSION CONTROL, TYPE HV m2 5,424.0008,732.64
3,804.3506,125.00
0.0000.00

0006                          L021.00 10.00426.0004,260.00
EROSION CHECKS BALE426.0004,260.00
262.0002,620.00
0.0000.00

0007                          L021.01 12.0021.000252.00
EROSION CHECKS, TYPE A BALE21.000252.00
99.0001,188.00
0.0000.00

0008                          L021.06 10.00108.0001,080.00
EROSION CHECKS, TYPE HV BALE108.0001,080.00
89.000890.00
0.0000.00

0009                          L022.11 6.56506.9003,325.26
FABRIC SILT FENCE-LOW POROSITY m 506.9003,325.26
782.5005,133.20
0.0000.00

0010                          L022.12 8.20289.0002,369.80
FABRIC SILT FENCE-HIGH POROSITY m 289.0002,369.80
0.0000.00
0.0000.00

0011                          P400.18 100.00334.20033,420.00
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 334.20033,420.00
325.40032,540.00
0.0000.00

0012                          0030.10 24,500.001.00024,500.00
MOBILIZATION LS 1.00024,500.00
1.00024,500.00
0.0000.00

0013                          1009.00 12,000.001.00012,000.00
GENERAL CLEARING AND GRUBBING LS 1.00012,000.00
1.00012,000.00
0.0000.00

0014                          1010.00 1.1478,275.00089,233.50
EXCAVATION m3 78,275.00089,233.50
87,079.00099,270.06
0.0000.00

0015                          1010.10 1.74104,231.000181,361.94
EXCAVATION, BORROW m3 104,231.000181,361.94
115,918.000201,697.32
0.0000.00

0016                          1011.00 1.007,300.0007,300.00
WATER kL 7,300.0007,300.00
995.555995.56
0.0000.00

0017                          1012.00 50.00154.0007,700.00
RIGHT-OF-WAY MARKERS EACH154.0007,700.00
79.0003,950.00
0.0000.00

0018                          1043.50 1.00653.000653.00
RIPRAP FILTER FABRIC m2 653.000653.00
499.150499.15
0.0000.00

0019                          1101.00 3.1516,563.00052,173.45
REMOVE PAVEMENT m2 16,563.00052,173.45
15,232.18047,981.37
0.0000.00

0020                          1101.25 8.2022.000180.40
SAWING PAVEMENT m 22.000180.40
0.0000.00
0.0000.00

0021                          1102.00 2.503,971.0009,927.50
REMOVE ASPHALT SURFACE m2 3,971.0009,927.50
16,285.00040,712.50
0.0000.00

0022                          1106.00 4.0084.000336.00
REMOVE DRIVEWAY m2 84.000336.00
0.0000.00
0.0000.00

0023                          1124.00 500.001.000500.00
REMOVE BUILDING EACH1.000500.00
AT STA. 1242+44 LT 1.000500.00
0.0000.00

0024                          1125.00 500.001.000500.00
CLEAR TRACT EACH1.000500.00
AT STA. 1242+00 LT TO 1243+00 LT 1.000500.00
0.0000.00

0025                          1143.00 6.00177.3001,063.80
REMOVE DRIVEWAY CULVERT PIPE m 177.3001,063.80
38.400230.40
0.0000.00

0026                          1701.24 33.50147.5004,941.25
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 147.5004,941.25
61.1002,046.85
0.0000.00

0027                          4004.50 2.852,040.0005,814.00
CAST IRON GRATE AND FRAME kg 2,040.0005,814.00
2,040.0005,814.00
0.0000.00

0028                          4105.59 710.0011.0507,845.50
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 11.0507,845.50
11.0507,845.50
0.0000.00

0029                          4155.50 2.20357.000785.40
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 357.000785.40
357.000785.40
0.0000.00

0030                          4310.18 310.0015.0004,650.00
450 mm FLARED-END SECTION EACH15.0004,650.00
16.0004,960.00
0.0000.00

0031                          6105.02 26.50193.0005,114.50
ROCK RIPRAP, TYPE B Mg 0.0000.00
0.0000.00
0.0000.00

0032                          7017.00 4.50335.0001,507.50
REMOVE GUARDRAIL m 335.0001,507.50
335.0001,507.50
0.0000.00

4028                          6104.00 13.000.0000.00
BROKEN CONCRETE RIPRAP Mg 193.0002,509.00
Item to Group #1 243.5803,166.54
0.0000.00

GROUP 1 GRADINGContracted484,850.17
Current482,244.67
In place518,722.05
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0033                          0030.30 108,750.001.000108,750.00
MOBILIZATION LS 1.000108,750.00
1.000108,750.00
0.0000.00

0034                          1020.06 22.00170.0003,740.00
FLEXIBLE POST DELINEATOR EACH170.0003,740.00
0.0000.00
0.0000.00

0035                          2001.00 12.95189.0002,447.55
GRAVEL SURFACE COURSE m3 189.0002,447.55
56.100726.49
0.0000.00

0036                          2009.10 575.003.0571,757.78
GRAVEL EMBEDMENT StaM3.0571,757.78
0.0000.00
0.0000.00

0037                          2020.50 13.3913,111.000175,556.29
SURFACING m2 13,111.000175,556.29
150 mm 3,437.25046,024.78
0.0000.00

0038                          2020.51 29.451,462.00043,055.90
SURFACING m2 0.0000.00
205 mm 0.0000.00
0.0000.00

0039                          2021.00 50.002.000100.00
MAILBOX POST EACH2.000100.00
0.0000.00
0.0000.00

0040                          3040.13 125.0066.6008,325.00
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH m2 66.6008,325.00
29.5003,687.50
0.0000.00

0041                          3040.18 265.002.100556.50
CONCRETE PAVEMENT REPAIR, TYPE A, PARTIAL DEPTH m2 2.100556.50
3.378895.17
0.0000.00

0042                          3075.51 39.73365.00014,501.45
255 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 365.00014,501.45
0.0000.00
0.0000.00

0043                          3075.55 26.5677,224.0002,051,069.44
255 mm DOWELED CONCRETE PAVEMENT, CLASS 47B-25 m2 77,224.0002,051,069.44
75,695.4502,010,471.16
0.0000.00

0044                          3211.00 3.006,475.00019,425.00
SEALING TRANSVERSE JOINT m 6,475.00019,425.00
6,255.00018,765.00
3,255.0009,765.00

0045                          3211.10 5.50102.000561.00
SEALING TRANSVERSE WORKING CRACK m 102.000561.00
40.970225.34
0.0000.00

0046                          3221.05 125.004.400550.00
CONCRETE PAVEMENT, CLASS PR-25 m2 4.400550.00
JOINT REPAIR 6.372796.50
0.0000.00

0047                          3300.50 2,500.001.0002,500.00
PORTLAND CEMENT CONCRETE SMOOTHNESS TESTING LS 1.0002,500.00
0.9502,375.00
0.0000.00

0048                          7550.03 1.1849,000.00057,820.00
100 mm YELLOW EPOXY PAVEMENT MARKING m 49,000.00057,820.00
0.0000.00
0.0000.00

0049                          7550.04 1.1861,200.00072,216.00
100 mm WHITE EPOXY PAVEMENT MARKING m 61,200.00072,216.00
0.0000.00
0.0000.00

0050                          8029.04 4.6477,589.000360,012.96
AGGREGATE FOUNDATION COURSE 100 mm m2 77,589.000360,012.96
75,659.000351,057.75
0.0000.00

0051                          8060.05 75.00114.0008,550.00
GRANULAR SUBDRAIN EACH114.0008,550.00
41.0003,075.00
0.0000.00

0052                          8111.00 220.0086.30718,987.54
SHOULDER SUBGRADE PREPARATION StaM86.30718,987.54
30.4136,690.86
0.0000.00

0053                          9000.75 23.55500.00011,775.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.00011,775.00
SPS 0.0000.00
0.0000.00

0054                          9005.00 33.55100.0003,355.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0003,355.00
SPS 239.4448,033.34
127.6574,282.89

0055                          9005.23 23.555,210.000122,695.50
ASPHALTIC CONCRETE, TYPE SPS Mg 5,210.000122,695.50
6,200.770146,028.13
4,360.159102,681.74

0056                          9009.00 3.501,445.0005,057.50
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 1,445.0005,057.50
611.0002,138.50
0.0000.00

0057                          9009.75 36.95897.00033,144.15
TEMPORARY SURFACING m2 0.0000.00
205 mm 0.0000.00
0.0000.00

0058                          9020.92 225.0027.0006,075.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 27.0006,075.00
0.0000.00
0.0000.00

0059                          9021.03 225.00286.74064,516.50
PERFORMANCE GRADED BINDER (58-28) Mg 286.74064,516.50
200.34845,078.31
121.92327,432.68

0060                          9034.00 2.501,445.0003,612.50
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,445.0003,612.50
611.0001,527.50
0.0000.00

0061                          9053.00 0.2616,230.0004,219.80
TACK COAT L 16,230.0004,219.80
4,443.0001,155.18
4,143.0001,077.18

0062                          9111.00 2.002,226.0004,452.00
WATER kL 2,226.0004,452.00
708.8001,417.60
0.0000.00

0063                          9140.00 105.7577.3208,176.59
JOINT SEALING - ASPHALT TO CONCRETE StaM77.3208,176.59
84.1328,896.96
84.1328,896.96

0064                          9170.00 195.0089.60117,472.20
EARTH SHOULDER CONSTRUCTION StaM89.60117,472.20
0.0000.00
0.0000.00

0065                          9173.20 0.9286,003.00079,122.76
SUBGRADE PREPARATION m2 86,003.00079,122.76
81,611.84075,082.89
5,790.8605,327.59

0066                          9179.23 250.0077.32019,330.00
COLD MILLING, CLASS 3 StaM77.32019,330.00
85.38021,345.00
0.0000.00

0067                          9179.24 425.0043.30718,405.48
COLD MILLING, CLASS 4 StaM43.30718,405.48
40.48017,204.00
0.0000.00

0068                          9185.76 50.0083.3204,166.00
RUMBLE STRIPS, ASPHALT StaM83.3204,166.00
0.0000.00
0.0000.00

0069                          9185.77 85.00166.92014,188.20
RUMBLE STRIPS, CONCRETE StaM166.92014,188.20
0.0000.00
0.0000.00

0070                          9188.50 25.00356.0008,900.00
SURFACING UNDER GUARDRAIL m2 356.0008,900.00
61.8251,545.63
0.0000.00

4003                          9009.75 35.090.0000.00
TEMPORARY SURFACING m2 897.00031,475.73
1,894.90366,492.15
0.0000.00

4004                          2020.51 27.590.0000.00
SURFACING m2 1,462.00040,336.58
205 mm surfacing 1,758.90048,528.05
0.0000.00

4010                          3300.60 0.9750.0000.00
SMOOTHNESS INCENTIVE - CONCRETE PAVEMENT m2 56,457.00055,045.58
Pay Factor 103.67% 56,457.00055,045.58
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted3,379,146.58
Current3,429,804.41
In place3,053,059.37
This Estimate159,464.04

GROUP 4 CULVERTS
0071                          P120.24 93.0038.4003,571.20
600 mm CULVERT PIPE, TYPE 2 m 38.4003,571.20
79.2007,365.60
0.0000.00

0072                          P127.36 248.0011.3002,802.40
900 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 2 m 11.3002,802.40
11.4002,827.20
0.0000.00

0073                          P300.24 55.5045.8002,541.90
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 45.8002,541.90
0.0000.00
0.0000.00

0074                          P300.48 144.0017.5002,520.00
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 0.0000.00
0.0000.00
0.0000.00

0075                          P400.18 200.003.600720.00
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 3.600720.00
3.600720.00
0.0000.00

0076                          P400.36 128.0040.0005,120.00
900 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 40.0005,120.00
42.3005,414.40
0.0000.00

0077                          P402.24 58.5027.6001,614.60
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 0.0000.00
0.0000.00
0.0000.00

0078                          0030.40 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0079                          4035.00 100.0012.0001,200.00
REMOVE FLARED-END SECTION EACH9.000900.00
3.000300.00
0.0000.00

0080                          4040.00 100.002.000200.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000200.00
1.000100.00
0.0000.00

0081                          4044.00 1,000.001.0001,000.00
PREPARATION OF STRUCTURE EACH1.0001,000.00
AT STA. 1210+00 1.0001,000.00
0.0000.00

0082                          4044.01 1,000.001.0001,000.00
PREPARATION OF STRUCTURE EACH1.0001,000.00
AT STA. 1232+50 1.0001,000.00
0.0000.00

0083                          4044.02 1,000.001.0001,000.00
PREPARATION OF STRUCTURE EACH1.0001,000.00
AT STA. 1261+53 1.0001,000.00
0.0000.00

0084                          4044.03 1,300.001.0001,300.00
PREPARATION OF STRUCTURE EACH1.0001,300.00
AT STA. 1267+25 1.0001,300.00
0.0000.00

0085                          4050.01 26.00397.00010,322.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 291.0007,566.00
318.0008,268.00
0.0000.00

0086                          4051.01 25.00353.0008,825.00
EXCAVATION FOR BOX CULVERTS m3 546.00013,650.00
546.00013,650.00
0.0000.00

0087                          4100.06 1,200.000.8401,008.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 0.0000.00
0.0000.00
0.0000.00

0088                          4101.06 375.00174.07065,276.25
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 199.30074,737.50
198.65174,494.13
0.0000.00

0089                          4107.07 1,000.000.800800.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 0.800800.00
2.4702,470.00
0.0000.00

0090                          4150.00 2.2540.00090.00
REINFORCING STEEL FOR HEADWALL kg 0.0000.00
0.0000.00
0.0000.00

0091                          4151.00 1.3510,260.00013,851.00
REINFORCING STEEL FOR BOX CULVERT kg 12,127.00016,371.45
12,642.90017,067.91
0.0000.00

0092                          4157.00 2.2534.00076.50
REINFORCING STEEL FOR COLLARS kg 34.00076.50
91.000204.75
0.0000.00

0093                          4310.24 275.005.0001,375.00
600 mm FLARED-END SECTION EACH2.000550.00
3.000825.00
0.0000.00

0094                          4310.36 425.002.000850.00
900 mm FLARED-END SECTION EACH2.000850.00
2.000850.00
0.0000.00

0095                          4310.48 700.001.000700.00
1200 mm FLARED-END SECTION EACH0.0000.00
0.0000.00
0.0000.00

0096                          4320.36 850.002.0001,700.00
900 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0001,700.00
2.0001,700.00
0.0000.00

0165                          P200.48 260.400.0000.00
1200 mm CULVERT PIPE, TYPE 2 OR 5 m 17.0004,426.80
17.0004,426.80
0.0000.00

0166                          4310.48 981.750.0000.00
1200 mm FLARED END SECTION EACH1.000981.75
1.000981.75
0.0000.00

0167                          4030.08 189.000.0000.00
REMOVE AND RELAYING EACH3.000567.00
600 mm Flared End Sections 3.000567.00
0.0000.00

4005                          0095.00 315.000.0000.00
ADDITIONAL FREIGHT COSTS LS 1.000315.00
For Steel 1.000315.00
0.0000.00

4006                          0030.02 4,725.000.0000.00
REMOBILIZATION LS 1.0004,725.00
1.0004,725.00
0.0000.00

4007                          4044.00 2,123.6250.0000.00
PREPARATION OF STRUCTURE AT STATION EACH2.0004,247.25
1267+.25 2.0004,247.25
0.0000.00

4008                          5100.00 4,247.250.0000.00
REMOVAL OF EXISTING STRUCTURES EACH1.0004,247.25
Sta. 1267+25 1.0004,247.25
0.0000.00

4009                          4300.24 35.470.0000.00
600 mm CULVERT PIPE m 25.600908.03
Taken in stock not used 25.600908.03
0.0000.00

GROUP 4 CULVERTSContracted132,463.85
Current159,875.03
In place163,975.07
This Estimate0.00

GROUP 4A CULVERTS AT STA. 1221+77
0097                          0030.40 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0098                          4044.00 5,000.001.0005,000.00
PREPARATION OF STRUCTURE EACH1.0005,000.00
AT STA. 1221+77 1.0005,000.00
0.0000.00

0099                          4051.01 25.00152.0003,800.00
EXCAVATION FOR BOX CULVERTS m3 152.0003,800.00
152.0003,800.00
0.0000.00

0100                          4101.06 360.00129.10046,476.00
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 129.10046,476.00
129.52946,630.44
0.0000.00

0101                          4151.00 1.306,474.0008,416.20
REINFORCING STEEL FOR BOX CULVERT kg 6,474.0008,416.20
6,522.0008,478.60
0.0000.00

GROUP 4A CULVERTS AT STA. 1221+77Contracted65,692.20
Current65,692.20
In place65,909.04
This Estimate0.00

GROUP 6 BRIDGE AT STA. 1250+88.276 LT
0102                          0030.60 17,000.001.00017,000.00
MOBILIZATION LS 1.00017,000.00
1.00017,000.00
0.0000.00

0103                          1010.01 5.25630.0003,307.50
EXCAVATION (ESTABLISHED QUANTITY) m3 630.0003,307.50
630.0003,307.50
0.0000.00

0104                          3050.15 198.00125.30024,809.40
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 125.30024,809.40
125.30024,809.40
0.0000.00

0105                          3051.10 1.258,150.00010,187.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,150.00010,187.50
8,150.00010,187.50
0.0000.00

0106                          6000.10 2,000.001.0002,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0107                          6000.11 2,000.001.0002,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0108                          6005.35 160.0024.8003,968.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 24.8003,968.00
24.8003,968.00
0.0000.00

0109                          6005.60 180.008.0001,440.00
ELASTOMERIC BEARING EACH8.0001,440.00
8.0001,440.00
0.0000.00

0110                          6010.22 370.0085.50031,635.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 85.50031,635.00
85.50031,635.00
0.0000.00

0111                          6010.26 380.0064.10024,358.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 99.10037,658.00
99.10037,658.00
0.0000.00

0112                          6011.11 53,500.001.00053,500.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00053,500.00
AT STA 1250+88.276 1.00053,500.00
0.0000.00

0113                          6011.25 83,000.001.00083,000.00
NU-DECK PANELS LS 0.0000.00
0.0000.00
0.0000.00

0114                          6080.00 4.501,915.0008,617.50
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 1,915.0008,617.50
1,915.0008,617.50
0.0000.00

0115                          6095.00 710.003.0002,130.00
STEEL DIAPHRAGM EACH3.0002,130.00
3.0002,130.00
0.0000.00

0116                          6105.02 34.00472.00016,048.00
ROCK RIPRAP, TYPE B Mg 472.00016,048.00
535.68318,213.22
0.0000.00

0117                          6131.50 1.2515,090.00018,862.50
EPOXY COATED REINFORCING STEEL kg 14,955.00018,693.75
14,955.00018,693.76
0.0000.00

0118                          6139.50 26.0083.0002,158.00
SUBSURFACE DRAINAGE MATTING m2 83.0002,158.00
83.0002,158.00
0.0000.00

0119                          6200.00 75.00457.20034,290.00
CONCRETE PILING m 457.20034,290.00
343.35025,751.25
0.0000.00

0120                          6310.00 94.00305.90028,754.60
STEEL SHEET PILING m2 305.90028,754.60
279.97026,317.18
0.0000.00

0121                          6801.21 1,000.003.0003,000.00
GROUT FOR NU-DECK PANELS m3 0.0000.00
0.0000.00
0.0000.00

0122                          8091.00 28.00180.0005,040.00
GRANULAR BACKFILL m3 180.0005,040.00
305.8108,562.68
0.0000.00

0162                          6200.50 45.000.0000.00
PAY CUT-OFF FOR CONCRETE PILING m 50.0002,250.00
Metric Spec. 703.05, Para. 2 58.9502,652.75
0.0000.00

0164                          6310.15 56.400.0000.00
PAY CUT-OFF FOR STEEL SHEET PILING m2 20.0001,128.00
See Metric Spec 703.05 Para 2 18.5641,047.01
0.0000.00

4000                          1043.50 2.6250.0000.00
FILTER FABRIC m2 370.000971.25
Rip Rap 537.0301,409.70
0.0000.00

GROUP 6 BRIDGE AT STA. 1250+88.276 LTContracted376,106.00
Current307,586.50
In place303,058.45
This Estimate0.00

GROUP 6A BRIDGE AT STA. 1250+88.276 RT
0123                          0030.60 17,000.001.00017,000.00
MOBILIZATION LS 1.00017,000.00
1.00017,000.00
0.0000.00

0124                          1010.01 5.25630.0003,307.50
EXCAVATION (ESTABLISHED QUANTITY) m3 630.0003,307.50
630.0003,307.50
0.0000.00

0125                          3050.15 198.00125.30024,809.40
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 125.30024,809.40
125.30024,809.40
0.0000.00

0126                          3051.10 1.258,150.00010,187.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,150.00010,187.50
8,150.00010,187.50
0.0000.00

0127                          6000.10 2,000.001.0002,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0128                          6000.11 2,000.001.0002,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0129                          6005.35 160.0024.8003,968.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 24.8003,968.00
24.8003,968.00
0.0000.00

0130                          6005.60 180.008.0001,440.00
ELASTOMERIC BEARING EACH8.0001,440.00
8.0001,440.00
0.0000.00

0131                          6010.22 370.0084.60031,302.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 84.60031,302.00
84.60031,302.00
0.0000.00

0132                          6010.26 380.0099.10037,658.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 99.10037,658.00
99.10037,658.00
0.0000.00

0133                          6011.11 53,350.001.00053,350.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00053,350.00
AT STA. 1250+88.276 1.00053,350.00
0.0000.00

0134                          6040.00 16,000.001.00016,000.00
REMOVE STRUCTURE EACH1.00016,000.00
AT STA. 1250+88.276 1.00016,000.00
0.0000.00

0135                          6080.00 4.501,915.0008,617.50
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 1,915.0008,617.50
1,915.0008,617.50
0.0000.00

0136                          6095.00 710.003.0002,130.00
STEEL DIAPHRAGM EACH3.0002,130.00
3.0002,130.00
0.0000.00

0137                          6104.00 13.00351.0004,563.00
BROKEN CONCRETE RIPRAP Mg 351.0004,563.00
850.82011,060.66
0.0000.00

0138                          6131.50 1.2514,955.00018,693.75
EPOXY COATED REINFORCING STEEL kg 14,955.00018,693.75
14,955.00018,693.75
0.0000.00

0139                          6139.50 26.0083.0002,158.00
SUBSURFACE DRAINAGE MATTING m2 83.0002,158.00
83.0002,158.00
0.0000.00

0140                          6200.00 75.00457.20034,290.00
CONCRETE PILING m 457.20034,290.00
329.70424,727.80
0.0000.00

0141                          6310.00 94.00305.90028,754.60
STEEL SHEET PILING m2 305.90028,754.60
290.72827,328.43
0.0000.00

0142                          8091.00 28.00180.0005,040.00
GRANULAR BACKFILL m3 180.0005,040.00
180.0005,040.00
0.0000.00

4001                          1043.50 2.6250.0000.00
FILTER FABRIC m2 370.000971.25
Rip Rap 537.0301,409.70
0.0000.00

4011                          6200.50 45.000.0000.00
PAY CUT-OFF FOR CONCRETE PILING m 1.50067.50
Metric Spec. 703.05 Para2 14.508652.86
0.0000.00

4012                          6310.15 56.400.0000.00
PAY CUT-OFF FOR STEEL SHEET PILING m2 10.000564.00
See Metric Spec 703.05 Para 2 7.810440.48
0.0000.00

4027                          9110.06 131.250.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR6.000787.50
Removal of Bridge Approaches 6.000787.50
0.0000.00

4029                          4045.00 3,064.410.0000.00
REMOVE STRUCTURE EACH1.0003,064.41
At abutment #1. 1.0003,064.41
0.0000.00

GROUP 6A BRIDGE AT STA. 1250+88.276 RTContracted307,269.25
Current312,723.91
In place309,133.49
This Estimate0.00

GROUP 7 GUARDRAIL
0143                          0030.70 1,750.001.0001,750.00
MOBILIZATION LS 1.0001,750.00
0.0000.00
0.0000.00

0144                          7011.20 60.00192.48011,548.80
W-BEAM GUARDRAIL m 192.48011,548.80
0.0000.00
0.0000.00

0145                          7020.00 1,400.008.00011,200.00
BRIDGE APPROACH SECTIONS EACH8.00011,200.00
0.0000.00
0.0000.00

0146                          7021.70 1,750.004.0007,000.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0007,000.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted31,498.80
Current31,498.80
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0147                          0001.08 0.5030,755.00015,377.50
BARRICADE, TYPE II BDAY30,755.00015,377.50
35,237.00017,618.50
2,060.0001,030.00

0148                          0001.10 2.953,167.0009,342.65
BARRICADE, TYPE III BDAY3,167.0009,342.65
21,088.00062,209.60
524.0001,545.80

0149                          0001.30 1.591,250.0001,987.50
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,250.0001,987.50
1,791.0002,847.69
0.0000.00

0150                          0001.90 1.0019,819.00019,819.00
SIGN DAY EACH19,819.00019,819.00
45,781.00045,781.00
1,014.0001,014.00

0151                          0002.30 1.501,500.0002,250.00
PAVEMENT MARKING REMOVAL m 1,500.0002,250.00
1,067.0001,600.50
0.0000.00

0152                          0002.39 1.0030,800.00030,800.00
TEMPORARY PAVEMENT MARKING, TYPE II m 30,800.00030,800.00
3,672.9003,672.90
0.0000.00

0153                          0002.97 9.45851.0008,041.95
FLASHING ARROW PANEL DAY 851.0008,041.95
0.0000.00
0.0000.00

0154                          0003.10 175.0015.0002,625.00
FLAGGING DAY 15.0002,625.00
12.5002,187.50
4.500787.50

0155                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
1.0001,500.00
0.0000.00

0156                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

0157                          1017.00 55,000.001.00055,000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00055,000.00
0.98053,900.00
0.0000.00

0158                          9110.01 75.0010.000750.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000750.00
6.000450.00
0.0000.00

0159                          9110.02 75.0010.000750.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000750.00
13.000975.00
2.000150.00

0160                          9110.03 60.0010.000600.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000600.00
14.000840.00
10.000600.00

0161                          9110.07 55.0010.000550.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000550.00
20.5001,127.50
15.500852.50

0163                          9112.51 85.000.0000.00
TWO PARTY SURVEY CREW HOUR6.000510.00
Additional Survey Work 2.000170.00
0.0000.00

4002                          0003.51 55.000.0000.00
INSTALLING CONCRETE PROTECTION BARRIER m 103.6605,701.30
103.6605,701.30
0.0000.00

GROUP 10 GENERAL ITEMSContracted159,393.60
Current165,604.90
In place210,581.49
This Estimate5,979.80

Totals for contractContracted4,936,420.44
Current4,955,030.42
In place4,624,438.96
This Estimate165,443.84