Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0462 WEBB CONTRACTOR, INC./L. J.
Contract ID:4503A
Estimate Number:0009
Pay Period End Date:08.09.2003
Contract Location:
WOLBACH WESTEstimate Type:PROG
Contractor:
WEBB CONTRACTOR, INC./L. J.Date Let:12.19.2002
918 N 13TH STDate Awarded:12.27.2002
PO BOX 386Date Contract Executed:01.07.2003
Date Notice to Proceed:01.07.2003
GENEVA NE 68361-0386Date Work Began:01.14.2003
Phone:Date Physical Work Completed:
(402)759-4160Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
GREELEY
HOWARD
Project Number PCT Fed State Project Number Description
41503A 000  0.000 F-22-4(1006)  GR CULV SEED BR GDRL ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,187,164.83$1,106,188.14$80,976.69
$2,493,995.47Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,187,164.83$1,106,188.14$80,976.69
$2,308,111.47Retainage$-11,871.65$-11,061.88$-809.77
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
47.60%Net Earnings$1,175,293.18$1,095,126.26$80,166.92
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$4.51$4.51$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$4.51$4.51$.00
Payment$1,175,297.69$1,095,130.77$80,166.92
Project ManagerDiv. Head/Dist. Eng.
Woodgate, Gerald08.12.2003Meyer, Keith08.12.2003
Constr. Estimate Eng.Materials Eng.
Hitzeman, Bill08.12.2003
Controller Div. Processed
Burling, Laurie08.12.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          0030.10 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0002                          1000.00 150.008.0001,200.00
LARGE TREE REMOVAL EACH8.0001,200.00
25.0003,750.00
-264.000-39,600.00

0003                          1009.00 17,000.001.00017,000.00
GENERAL CLEARING AND GRUBBING LS 1.00017,000.00
0.2504,250.00
0.0000.00

0004                          1010.00 1.14208,605.000237,809.70
EXCAVATION m3 212,750.000242,535.00
94,548.153107,784.89
15,381.74017,535.18

0005                          1010.01 1.304,072.0005,293.60
EXCAVATION (ESTABLISHED QUANTITY) m3 6,081.0007,905.30
5,074.0006,596.20
0.0000.00

0006                          1011.00 4.007,600.00030,400.00
WATER kL 7,740.00030,960.00
9,643.00238,572.02
91.560366.24

0007                          1012.00 65.00116.0007,540.00
RIGHT-OF-WAY MARKERS EACH116.0007,540.00
105.0006,825.00
5.000325.00

0008                          1101.00 5.86256.0001,500.16
REMOVE PAVEMENT m2 256.0001,500.16
0.0000.00
0.0000.00

0009                          1102.00 4.434,266.00018,898.38
REMOVE ASPHALT SURFACE m2 7,270.00032,206.10
3,409.17415,102.64
0.0000.00

0010                          1124.00 500.001.000500.00
REMOVE BUILDING EACH1.000500.00
AT STA. 1008+16 TO STA. 1008+20 RT. 1.000500.00
0.0000.00

0011                          1124.01 500.001.000500.00
REMOVE BUILDING EACH1.000500.00
AT STA. 1008+45 TO STA. 1008+59 RT. 1.000500.00
0.0000.00

0012                          1125.00 500.001.000500.00
CLEAR TRACT EACH1.000500.00
AT STA. 1008+00 TO STA. 1008+75 RT. 1.000500.00
0.0000.00

0013                          1125.01 200.001.000200.00
CLEAR TRACT EACH1.000200.00
AT STA. 1007+04 TO STA. 1008+85 LT. 1.000200.00
0.0000.00

0014                          1701.24 45.00128.6005,787.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 128.6005,787.00
23.2001,044.00
0.0000.00

0015                          7017.00 5.00102.800514.00
REMOVE GUARDRAIL m 102.800514.00
45.720228.60
0.0000.00

0016                          7017.50 6.002,680.29016,081.74
REMOVE & SALVAGE GUARDRAIL m 2,680.29016,081.74
647.1003,882.60
0.0000.00

0017                          L006.00 75.0051.0003,825.00
COVER CROP SEEDING ha 51.0003,825.00
0.0000.00
0.0000.00

0018                          L006.50 1,750.000.6201,085.00
TEMPORARY SEEDING ha 1.1502,012.50
0.7501,312.50
0.0000.00

0019                          L020.00 1.497,504.00011,180.96
EROSION CONTROL m2 7,504.00011,180.96
0.0000.00
0.0000.00

0020                          L020.01 4.9612,159.00060,308.64
EROSION CONTROL, TYPE A m2 12,159.00060,308.64
261.0001,294.56
0.0000.00

0021                          L020.08 4.984,119.00020,512.62
EROSION CONTROL, TYPE AA m2 4,119.00020,512.62
0.0000.00
0.0000.00

0022                          L020.09 13.503,331.00044,968.50
EROSION CONTROL, TYPE AAA m2 3,331.00044,968.50
91.0001,228.50
0.0000.00

0023                          L020.10 1.604,057.0006,491.20
EROSION CONTROL, TYPE HV m2 5,282.0008,451.20
1,225.0001,960.00
0.0000.00

0024                          L021.00 15.00180.0002,700.00
EROSION CHECKS BALE180.0002,700.00
0.0000.00
0.0000.00

0025                          L021.01 16.00454.0007,264.00
EROSION CHECKS, TYPE A BALE454.0007,264.00
11.000176.00
0.0000.00

0026                          L021.06 13.00188.0002,444.00
EROSION CHECKS, TYPE HV BALE208.0002,704.00
20.000260.00
0.0000.00

0027                          L021.21 13.00144.0001,872.00
EROSION CHECKS, TYPE AA BALE144.0001,872.00
0.0000.00
0.0000.00

0028                          L021.22 13.0044.000572.00
EROSION CHECKS, TYPE AAA BALE44.000572.00
3.00039.00
0.0000.00

0029                          L022.11 6.001,720.00010,320.00
FABRIC SILT FENCE-LOW POROSITY m 1,720.00010,320.00
1,085.8006,514.80
0.0000.00

0030                          L022.75 22.001,488.00032,736.00
TEMPORARY SILT CHECK m 1,488.00032,736.00
30.100662.20
0.0000.00

0031                          L032.80 2,000.002.4004,800.00
HYDROMULCH Mg 5.40010,800.00
3.5227,044.00
0.0000.00

4002                          4061.01 3.900.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 107.530419.37
496.8521,937.72
0.0000.00

GROUP 1 GRADINGContracted557,804.50
Current588,576.09
In place215,165.23
This Estimate-21,373.58

GROUP 4 CULVERTS
0032                          0030.40 13,000.001.00013,000.00
MOBILIZATION LS 1.00013,000.00
1.00013,000.00
0.0000.00

0033                          1043.50 2.00425.000850.00
RIPRAP FILTER FABRIC m2 255.000510.00
0.0000.00
0.0000.00

0034                          4005.00 3.50158.000553.00
CAST IRON RING AND COVER kg 158.000553.00
158.000553.00
158.000553.00

0035                          4016.00 2,500.001.0002,500.00
MANHOLE EACH1.0002,500.00
AT STA. 1044+83 RT. 1.0002,500.00
0.0000.00

0036                          4035.00 95.0017.0001,615.00
REMOVE FLARED-END SECTION EACH17.0001,615.00
16.0001,520.00
2.000190.00

0037                          4040.00 160.009.0001,440.00
REMOVE HEADWALLS FROM CULVERTS EACH9.0001,440.00
9.0001,440.00
4.000640.00

0038                          4044.00 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH0.0000.00
AT STA. 1002+14.2 0.0000.00
0.0000.00

0039                          4044.01 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 1026+76.7 1.0002,000.00
0.0000.00

0040                          4045.00 2,500.001.0002,500.00
REMOVE STRUCTURE EACH1.0002,500.00
AT STA. 1021+25 LT. 1.0002,500.00
0.0000.00

0041                          4050.01 8.502,169.00018,436.50
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 2,169.00018,436.50
1,677.60014,259.60
0.0000.00

0042                          4051.01 11.00175.0001,925.00
EXCAVATION FOR BOX CULVERTS m3 1,986.00021,846.00
2,036.00022,396.00
0.0000.00

0043                          4100.06 575.002.2001,265.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 2.2001,265.00
1.200690.00
0.0000.00

0044                          4101.06 320.00168.23053,833.60
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 358.629114,761.28
358.629114,761.28
0.0000.00

0045                          4150.00 1.00119.000119.00
REINFORCING STEEL FOR HEADWALL kg 119.000119.00
90.00090.00
0.0000.00

0046                          4151.00 0.6511,349.0007,376.85
REINFORCING STEEL FOR BOX CULVERT kg 20,386.00013,250.90
20,386.00013,250.91
0.0000.00

0047                          4310.24 175.0018.0003,150.00
600 mm FLARED-END SECTION EACH18.0003,150.00
16.0002,800.00
1.000175.00

0048                          4310.30 315.009.0002,835.00
750 mm FLARED-END SECTION EACH9.0002,835.00
6.0001,890.00
0.0000.00

0049                          4310.36 310.004.0001,240.00
900 mm FLARED-END SECTION EACH4.0001,240.00
4.0001,240.00
0.0000.00

0050                          4310.42 625.003.0001,875.00
1050 mm FLARED-END SECTION EACH3.0001,875.00
3.0001,875.00
0.0000.00

0051                          4310.48 650.002.0001,300.00
1200 mm FLARED-END SECTION EACH2.0001,300.00
2.0001,300.00
0.0000.00

0052                          4310.60 975.002.0001,950.00
1500 mm FLARED-END SECTION EACH2.0001,950.00
2.0001,950.00
0.0000.00

0053                          4670.05 95.00176.00016,720.00
CULVERT SANDFILL m3 176.00016,720.00
69.5776,609.82
0.0000.00

0054                          4850.42 521.0030.00015,630.00
JACKING 1050 mm CULVERT PIPE, TYPE m 30.00015,630.00
2 CLASS V 30.00015,630.00
0.0000.00

0055                          4850.60 1,204.0056.00067,424.00
JACKING 1500 mm CULVERT PIPE, TYPE m 56.00067,424.00
2 CLASS V 56.00067,424.00
0.0000.00

0056                          6105.02 32.50457.00014,852.50
ROCK RIPRAP, TYPE B Mg 221.0007,182.50
0.0000.00
0.0000.00

0057                          P120.42 250.0035.0008,750.00
1050 mm CULVERT PIPE TYPE 2 m 35.0008,750.00
35.0008,750.00
0.0000.00

0058                          P120.60 500.0022.50011,250.00
1500 mm CULVERT PIPE, TYPE 2 m 22.50011,250.00
22.50011,250.00
0.0000.00

0059                          P129.42 210.0030.0006,300.00
1050 mm CULVERT PIPE, TYPE 2 CLASS V m 30.0006,300.00
30.0006,300.00
0.0000.00

0060                          P129.60 400.0056.00022,400.00
1500 mm CULVERT PIPE, TYPE 2 CLASS V m 56.00022,400.00
56.00022,400.00
0.0000.00

0061                          P300.24 55.00114.0006,270.00
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 140.2007,711.00
177.4309,758.65
11.350624.25

0062                          P300.30 80.0059.7004,776.00
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 59.7004,776.00
56.6004,528.00
0.0000.00

0063                          P300.36 90.0036.0003,240.00
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 36.0003,240.00
32.9002,961.00
0.0000.00

0064                          P300.48 155.0052.7008,168.50
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 52.7008,168.50
61.0009,455.00
0.0000.00

0065                          P402.24 55.00300.40016,522.00
600 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 300.40016,522.00
268.30014,756.50
0.0000.00

0066                          P402.30 80.0028.5002,280.00
750 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 28.5002,280.00
0.0000.00
0.0000.00

0067                          P406.42 140.0012.0001,680.00
1050 mm CULVERT PIPE, TYPE 2,3,4 OR 5 m 12.0001,680.00
12.0001,680.00
0.0000.00

0068                          P600.30 80.0042.4003,392.00
750 mm CULVERT PIPE, TYPE 2, 3, 4, 5, 7 OR 8 m 42.4003,392.00
19.0001,520.00
0.0000.00

4000                          4045.00 6,250.000.0000.00
REMOVE STRUCTURE EACH1.0006,250.00
1.0006,250.00
0.0000.00

GROUP 4 CULVERTSContracted331,418.95
Current415,822.68
In place389,288.76
This Estimate2,182.25

GROUP 5 SEEDING
0069                          0030.50 550.001.000550.00
MOBILIZATION LS 1.000550.00
0.0000.00
0.0000.00

0070                          L001.01 1,084.0048.00052,032.00
SEEDING, TYPE A ha 48.00052,032.00
0.0000.00
0.0000.00

0071                          L001.02 887.003.2402,873.88
SEEDING, TYPE B ha 3.2402,873.88
0.0000.00
0.0000.00

0072                          L032.75 61.00240.00014,640.00
MULCH Mg 240.00014,640.00
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted70,095.88
Current70,095.88
In place0.00
This Estimate0.00

GROUP 6A BRIDGE AT STA. 1041+66
0094                          0030.60 60,000.001.00060,000.00
MOBILIZATION LS 1.00060,000.00
1.00060,000.00
0.0000.00

0095                          1030.00 13.0890.0001,177.20
EARTHWORK MEASURED IN EMBANKMENT m3 90.0001,177.20
60.000784.80
60.000784.80

0096                          1043.50 2.39212.000506.68
RIPRAP FILTER FABRIC m2 212.000506.68
79.200189.29
79.200189.29

0097                          3050.15 261.59127.20033,274.25
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 127.20033,274.25
0.0000.00
0.0000.00

0098                          3051.10 1.438,947.00012,794.21
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 8,947.00012,794.21
0.0000.00
0.0000.00

0099                          6000.10 5,000.001.0005,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0100                          6000.11 5,000.001.0005,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0101                          6001.50 12,000.001.00012,000.00
BENT NO.1 EXCAVATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0102                          6001.51 12,000.001.00012,000.00
BENT NO.2 EXCAVATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

0103                          6005.35 164.1323.0003,774.99
PRECOMPRESSED POLYURETHANE FOAM JOINT m 23.0003,774.99
0.0000.00
0.0000.00

0104                          6005.78 800.0012.0009,600.00
EXPANSION BEARING, TFE TYPE EACH12.0009,600.00
4.0003,200.00
4.0003,200.00

0105                          6005.83 800.004.0003,200.00
FIXED BEARING EACH4.0003,200.00
4.0003,200.00
4.0003,200.00

0106                          6010.22 412.00151.40062,376.80
CLASS 47B-20 CONCRETE FOR BRIDGE m3 151.40062,376.80
151.40062,376.80
40.50016,686.00

0107                          6010.26 412.00147.10060,605.20
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 147.10060,605.20
0.0000.00
0.0000.00

0108                          6040.00 50,000.001.00050,000.00
REMOVE STRUCTURE EACH1.00050,000.00
AT STA. 1041+64.45 1.00050,000.00
0.0000.00

0109                          6071.11 103,000.001.000103,000.00
STEEL SUPERSTRUCTURE LS 1.000103,000.00
AT STA. 1041+66 0.28128,943.00
0.28128,943.00

0110                          6080.00 6.061,400.0008,484.00
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 1,400.0008,484.00
1,400.0008,484.00
818.6004,960.72

0111                          6104.00 16.53529.0008,744.37
BROKEN CONCRETE RIPRAP Mg 529.0008,744.37
281.1844,647.97
281.1844,647.97

0112                          6131.50 1.4324,280.00034,720.40
EPOXY COATED REINFORCING STEEL kg 24,280.00034,720.40
6,410.0009,166.31
2,496.0003,569.28

0113                          6210.50 90.22874.20078,870.32
PIPE PILING m 874.20078,870.32
886.20079,952.96
118.50010,691.07

0114                          6310.00 129.16246.20031,799.19
STEEL SHEET PILING m2 246.20031,799.19
246.20031,799.20
123.10015,899.60

0115                          8091.00 26.19210.0005,499.90
GRANULAR BACKFILL m3 210.0005,499.90
0.0000.00
0.0000.00

GROUP 6A BRIDGE AT STA. 1041+66Contracted602,427.51
Current602,427.51
In place376,744.33
This Estimate92,771.73

GROUP 6B BRIDGE AT STA. 2041+72.4
0116                          0030.60 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
1.00010,000.00
0.0000.00

0117                          6000.10 2,000.001.0002,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0118                          6000.11 2,000.001.0002,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0119                          6041.00 15,000.001.00015,000.00
REMOVE DETOUR BRIDGE EACH1.00015,000.00
0.0000.00
0.0000.00

0120                          6052.00 30,000.001.00030,000.00
ERECTING DETOUR BRIDGE EACH1.00030,000.00
AT STA. 2041+72.4 1.00030,000.00
0.0000.00

0121                          6210.12 88.58160.00014,172.80
HP 250 mm X 62 kg STEEL PILING m 160.00014,172.80
276.70024,510.09
0.0000.00

0122                          6510.55 45,000.001.00045,000.00
TEMPORARY BRIDGE SHORING LS 1.00045,000.00
1.00045,000.00
0.0000.00

4001                          6210.61 177.160.0000.00
PILE SPLICE EACH11.0001,948.76
15.0002,657.40
4.000708.64

4005                          3050.15 223.6680.0000.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 10.0042,237.57
Temporary bridge at Sta. 2041+72.4 10.0042,237.57
0.0000.00

GROUP 6B BRIDGE AT STA. 2041+72.4Contracted118,172.80
Current122,359.13
In place118,405.06
This Estimate708.64

GROUP 7 GUARDRAIL
0123                          0030.70 756.631.000756.63
MOBILIZATION LS 1.000756.63
1.000756.63
0.0000.00

0124                          7011.20 55.0075.4704,150.85
W-BEAM GUARDRAIL m 75.4704,150.85
14.000770.00
0.0000.00

0125                          7018.01 88.0034.2903,017.52
RESET GUARDRAIL m 34.2903,017.52
0.0000.00
0.0000.00

0126                          7019.50 12,000.001.00012,000.00
IMPACT ATTENUATOR EACH1.00012,000.00
0.0000.00
0.0000.00

0127                          7020.00 1,825.003.0005,475.00
BRIDGE APPROACH SECTIONS EACH3.0005,475.00
3.0005,475.00
0.0000.00

0128                          7022.00 500.001.000500.00
END ANCHORAGE ASSEMBLY EACH1.000500.00
1.000500.00
0.0000.00

0129                          7024.27 1,550.003.0004,650.00
GUARDRAIL END TREATMENT, TYPE II EACH3.0004,650.00
3.0004,650.00
0.0000.00

GROUP 7 GUARDRAILContracted30,550.00
Current30,550.00
In place12,151.63
This Estimate0.00

GROUP 8B ELECTRICAL
0130                          0030.81 750.001.000750.00
MOBILIZATION LS 1.000750.00
0.0000.00
0.0000.00

0131                          A001.12 250.005.0001,250.00
PULL BOX, TYPE PB-5 EACH5.0001,250.00
0.0000.00
0.0000.00

0132                          A009.14 1,780.0010.00017,800.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH10.00017,800.00
0.0000.00
0.0000.00

0133                          A020.30 1,200.002.0002,400.00
LIGHTING CONTROL CENTER, TYPE R EACH2.0002,400.00
0.0000.00
0.0000.00

0134                          A070.10 5.00479.0002,395.00
38 mm CONDUIT IN TRENCH m 479.0002,395.00
0.0000.00
0.0000.00

0135                          A074.12 44.0068.0002,992.00
38 mm CONDUIT, JACKED m 68.0002,992.00
0.0000.00
0.0000.00

0136                          A080.22 1.30547.000711.10
STREET LIGHTING CABLE, NO. 6 BARE m 547.000711.10
0.0000.00
0.0000.00

0137                          A080.24 1.901,094.0002,078.60
STREET LIGHTING CABLE, NO. 6 USE m 1,094.0002,078.60
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted30,376.70
Current30,376.70
In place0.00
This Estimate0.00

GROUP 9 BITUMINOUS
0138                          0030.90 45,400.001.00045,400.00
MOBILIZATION LS 1.00045,400.00
0.0000.00
0.0000.00

0139                          2001.00 19.00218.0004,142.00
GRAVEL SURFACE COURSE m3 218.0004,142.00
43.264822.01
0.0000.00

0140                          2009.10 2,200.001.3372,941.40
GRAVEL EMBEDMENT StaM1.3372,941.40
0.0000.00
0.0000.00

0141                          2020.00 12.2136.000439.56
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 36.000439.56
0.0000.00
0.0000.00

0142                          2021.00 100.001.000100.00
MAILBOX POST EACH1.000100.00
0.0000.00
0.0000.00

0143                          3011.23 49.5038.3001,895.85
CONCRETE CLASS 47B-25 CURB, TYPE 1 m 38.3001,895.85
0.0000.00
0.0000.00

0144                          4024.55 170.003.000510.00
FLUME SPILLWAY m 3.000510.00
0.0000.00
0.0000.00

0145                          4024.70 2,025.001.0002,025.00
CONCRETE FLUME, TYPE I EACH1.0002,025.00
0.0000.00
0.0000.00

0146                          4024.73 2,030.005.00010,150.00
CONCRETE FLUME, TYPE IV EACH5.00010,150.00
2.0004,060.00
2.0004,060.00

0147                          8008.00 33.0036.0001,188.00
ARMOR COAT AGGREGATE m3 0.0000.00
58.0001,914.00
0.0000.00

0148                          9000.75 25.10500.00012,550.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.00012,550.00
SP1(12.5) 0.0000.00
0.0000.00

0149                          9005.00 32.10250.0008,025.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 250.0008,025.00
SP1(12.5) 0.0000.00
0.0000.00

0150                          9005.25 26.108,860.000231,246.00
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 8,860.000231,246.00
0.0000.00
0.0000.00

0151                          9009.00 3.301,828.0006,032.40
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 1,828.0006,032.40
0.0000.00
0.0000.00

0152                          9020.91 172.0027.0004,644.00
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 27.0004,644.00
0.0000.00
0.0000.00

0153                          9021.01 172.00491.94084,613.68
PERFORMANCE GRADED BINDER (64-22) Mg 491.94084,613.68
0.0000.00
0.0000.00

0154                          9030.00 7.20414.0002,980.80
CONSTRUCTING ASPHALTIC CONCRETE CURB m 414.0002,980.80
0.0000.00
0.0000.00

0155                          9034.00 1.851,004.0001,857.40
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,004.0001,857.40
0.0000.00
0.0000.00

0156                          9052.03 0.404,700.0001,880.00
ARMOR COAT EMULSIFIED ASPHALT L 1,020.000408.00
9,020.0003,608.00
0.0000.00

0157                          9053.00 0.3232,473.00010,391.36
TACK COAT L 32,473.00010,391.36
0.0000.00
0.0000.00

0158                          9053.20 0.209,659.0001,931.80
FOG SEAL L 2,859.000571.80
16,859.0003,371.80
0.0000.00

0159                          9111.00 3.00305.000915.00
WATER kL 353.0001,059.00
0.0000.00
0.0000.00

0160                          9170.00 135.00100.91213,623.12
EARTH SHOULDER CONSTRUCTION StaM108.87214,697.72
0.0000.00
0.0000.00

0161                          9173.00 385.008.2403,172.40
SUBGRADE PREPARATION StaM12.2204,704.70
0.0000.00
0.0000.00

0162                          9173.15 29.0021.322618.34
TRENCHED WIDENING StaM21.322618.34
0.0000.00
0.0000.00

0163                          9179.23 400.0041.21616,486.40
COLD MILLING, CLASS 3 StaM41.21616,486.40
0.0000.00
0.0000.00

0164                          9188.01 4.533,917.00017,744.01
BITUMINOUS SURFACE COURSE m2 1,797.0008,140.41
6,797.00030,790.41
0.0000.00

0165                          9188.50 24.55215.0005,278.25
SURFACING UNDER GUARDRAIL m2 215.0005,278.25
0.0000.00
0.0000.00

0166                          9300.52 3,500.001.0003,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING I/D LS 1.0003,500.00
0.0000.00
0.0000.00

0167                          P402.15 57.50119.8006,888.50
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 119.8006,888.50
23.3001,339.75
23.3001,339.75

4006                          9000.01 42.6560.0000.00
ASPHALTIC CONCRETE Mg 1,814.40077,395.05
0.0000.00
0.0000.00

GROUP 9 BITUMINOUSContracted503,170.27
Current569,692.61
In place45,905.97
This Estimate5,399.75

GROUP 10 GENERAL ITEMS
0168                          0001.08 0.5012,875.0006,437.50
BARRICADE, TYPE II BDAY12,875.0006,437.50
3,095.0001,547.50
630.000315.00

0169                          0001.10 1.003,920.0003,920.00
BARRICADE, TYPE III BDAY3,920.0003,920.00
2,321.0002,321.00
252.000252.00

0170                          0001.75 10.00200.0002,000.00
TEMPORARY SIGN DAY EACH200.0002,000.00
1.00010.00
0.0000.00

0171                          0001.90 0.458,694.0003,912.30
SIGN DAY EACH8,694.0003,912.30
12,323.0005,545.35
1,406.000632.70

0172                          0001.98 0.70720.000504.00
CONTRACTOR FURNISHED SIGN EACH720.000504.00
619.000433.30
126.00088.20

0173                          0002.30 1.00900.000900.00
PAVEMENT MARKING REMOVAL m 900.000900.00
818.000818.00
0.0000.00

0174                          0002.39 2.901,500.0004,350.00
TEMPORARY PAVEMENT MARKING, TYPE II m 1,500.0004,350.00
2,903.0008,418.70
0.0000.00

0175                          0002.47 1.30800.0001,040.00
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 800.0001,040.00
0.0000.00
0.0000.00

0176                          0002.55 21.50134.7602,897.34
OVERLAY BROKEN LINES StaM134.7602,897.34
0.0000.00
0.0000.00

0177                          0002.60 23.50269.5206,333.72
OVERLAY SOLID LINES StaM269.5206,333.72
0.0000.00
0.0000.00

0178                          0003.10 200.0040.0008,000.00
FLAGGING DAY 40.0008,000.00
3.000600.00
0.0000.00

0179                          0003.20 300.0020.0006,000.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 20.0006,000.00
0.0000.00
0.0000.00

0180                          0010.04 3,000.001.0003,000.00
FIELD OFFICE EACH1.0003,000.00
1.0003,000.00
0.0000.00

0181                          0030.00 5,500.001.0005,500.00
MOBILIZATION LS 1.0005,500.00
1.0005,500.00
0.0000.00

0182                          9110.01 45.0060.0002,700.00
RENTAL OF LOADER, FULLY OPERATED HOUR60.0002,700.00
4.000180.00
0.0000.00

0183                          9110.02 40.0020.000800.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR20.000800.00
0.0000.00
0.0000.00

0184                          9110.03 40.0060.0002,400.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR60.0002,400.00
0.0000.00
0.0000.00

0185                          9110.06 40.0040.0001,600.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR40.0001,600.00
26.0001,040.00
0.0000.00

0186                          9110.07 30.0060.0001,800.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR60.0001,800.00
3.00090.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted64,094.86
Current64,094.86
In place29,503.85
This Estimate1,287.90

Totals for contractContracted2,308,111.47
Current2,493,995.47
In place1,187,164.83
This Estimate80,976.69