Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:4415B
Estimate Number:0010
Pay Period End Date:01.25.2003
Contract Location:
GRAND ISLAND SOUTHEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:04.18.2002
129 E 2ND STDate Awarded:05.15.2002
PO BOX 1087Date Contract Executed:06.24.2002
Date Notice to Proceed:06.24.2002
HASTINGS NE 68902-1087Date Work Began:09.03.2002
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
HALL
Project Number PCT Fed State Project Number Description
41415B 000  0.000 EACSTPE-2235(3)  GR CP CULV SEED ELEC
41667 000  0.000 EACIM-STPAA-80-7(100)  GR CP CULV SEED BR GDRL FENCE ELEC SIGN
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,870,964.09$1,630,939.09$240,025.00
$9,801,179.79Stockpiled Materials$113,784.50$192,086.90$-78,302.40
Original Contract AmtGross Earnings$1,984,748.59$1,823,025.99$161,722.60
$9,800,324.79Retainage$-18,709.64$-16,309.39$-2,400.25
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
19.09%Net Earnings$1,966,038.95$1,806,716.60$159,322.35
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$1,129.87$982.45$147.42
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$1,129.87$982.45$147.42
Payment$1,967,168.82$1,807,699.05$159,469.77
Project ManagerDiv. Head/Dist. Eng.
Weber, Kirk01.30.2003Heermann, Dennis01.30.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve01.31.2003
Controller Div. Processed
Burling, Laurie01.31.2003
Detailed breakdown of stockpiled materials
Est Nbr:0002
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01756005.78 EXPANSION BEARING, TFE TYPE
S.P. Initial Payment996.00E22341
Anchor Bolt Assembly
Total for estimate 0002:996.00
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01796071.12 STEEL SUPERSTRUCTURE
S.P. Initial Payment230,000.0001-S-03
Steel Superstructure @ Sta 107+09.194
S.P. Adjustment-51,869.6001-S-03
Steel Superstructure @ Sta 107+09.194
01866610.45 STRIP SEALS
S.P. Initial Payment6,604.5021143
Strip Seals for Bridge 6A @ Sta 107+09.194
02026095.00 STEEL DIAPHRAGM
S.P. Initial Payment6,356.0021144
Steel Diaphragm(s)-Bridge 6B @Sta604+02.955
Total for estimate 0009:191,090.90
Est Nbr:0010
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01756005.78 EXPANSION BEARING, TFE TYPE
S.P. Adjustment-498.00E22341
Anchor Bolt Assembly
01796071.12 STEEL SUPERSTRUCTURE
S.P. Adjustment-77,804.4001-S-03
Steel Superstructure @ Sta 107+09.194
Total for estimate 0010:-78,302.40
Total remaining for contract:113,784.50
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 75.0021.8001,635.00
COVER CROP SEEDING ha 21.8001,635.00
7.190539.25
0.0000.00

0002                          L020.00 1.055,935.0006,231.75
EROSION CONTROL m2 5,935.0006,231.75
0.0000.00
0.0000.00

0003                          L020.09 15.70734.00011,523.80
EROSION CONTROL, TYPE AAA m2 734.00011,523.80
0.0000.00
0.0000.00

0004                          L021.00 14.00157.0002,198.00
EROSION CHECKS BALE157.0002,198.00
0.0000.00
0.0000.00

0005                          L022.11 6.501,597.00010,380.50
FABRIC SILT FENCE-LOW POROSITY m 1,597.00010,380.50
0.0000.00
0.0000.00

0008                          0030.10 28,836.501.00028,836.50
MOBILIZATION LS 1.00028,836.50
1.00028,836.50
0.0000.00

0009                          1009.00 56,200.001.00056,200.00
GENERAL CLEARING AND GRUBBING LS 1.00056,200.00
FOR PROJECT STPE-2235(3) 0.97054,514.00
0.0000.00

0011                          1011.00 2.127,120.00015,094.40
WATER kL 7,120.00015,094.40
0.0000.00
0.0000.00

0013                          1030.00 4.4394,866.000420,256.38
EARTHWORK MEASURED IN EMBANKMENT m3 94,866.000420,256.38
21,570.00095,555.10
0.0000.00

0014                          1041.00 0.23102,800.00023,644.00
SALVAGING AND PLACING TOPSOIL m2 102,800.00023,644.00
47,500.00010,925.00
0.0000.00

0017                          1102.00 2.522,300.0005,796.00
REMOVE ASPHALT SURFACE m2 2,300.0005,796.00
36.00090.72
0.0000.00

0018                          1106.00 2.88402.0001,157.76
REMOVE DRIVEWAY m2 402.0001,157.76
72.000207.36
0.0000.00

0020                          1300.18 36.2062.0002,244.40
450 mm DRIVEWAY CULVERT PIPE m 62.0002,244.40
12.000434.40
0.0000.00

0021                          1300.24 42.20280.00011,816.00
600 mm DRIVEWAY CULVERT PIPE m 280.00011,816.00
203.0008,566.60
0.0000.00

0022                          1300.36 68.9024.0001,653.60
900 mm DRIVEWAY CULVERT PIPE m 24.0001,653.60
24.0001,653.60
0.0000.00

0023                          1305.54 165.5017.5002,896.25
1350 mm ROUND EQUIVALENT DRIVEWAY CULVERT PIPE m 17.5002,896.25
17.5002,896.25
0.0000.00

0024                          1315.24 89.4026.0002,324.40
600 mm REINFORCED CONCRETE PIPE FOR DRIVEWAY CULVERT PIPE m 26.0002,324.40
CLASS V 0.0000.00
0.0000.00

0026                          4035.00 100.002.000200.00
REMOVE FLARED-END SECTION EACH2.000200.00
2.000200.00
0.0000.00

0027                          6105.02 46.70100.0004,670.00
ROCK RIPRAP, TYPE B Mg 100.0004,670.00
0.0000.00
0.0000.00

0028                          7017.00 5.9515.40091.63
REMOVE GUARDRAIL m 15.40091.63
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted608,850.37
Current608,850.37
In place204,418.78
This Estimate0.00

GROUP 3 CONCRETE PAVEMENT
0030                          0030.30 37,935.971.00037,935.97
MOBILIZATION LS 1.00037,935.97
0.0000.00
0.0000.00

0034                          2001.00 9.00438.0003,942.00
GRAVEL SURFACE COURSE m3 438.0003,942.00
217.1601,954.44
0.0000.00

0035                          2009.10 1,000.000.633633.00
GRAVEL EMBEDMENT StaM0.633633.00
0.0000.00
0.0000.00

0036                          2010.25 32.50335.00010,887.50
ROCK SURFACE COURSE m3 335.00010,887.50
37.3001,212.25
0.0000.00

0037                          2021.00 45.0015.000675.00
MAILBOX POST EACH15.000675.00
0.0000.00
0.0000.00

0038                          3008.05 4.505,045.00022,702.50
TIE BARS EACH5,045.00022,702.50
0.0000.00
0.0000.00

0040                          3031.08 32.535,994.000194,984.82
205 mm CONCRETE BASE COURSE m2 5,994.000194,984.82
0.0000.00
0.0000.00

0051                          8111.00 250.0091.71222,928.00
SHOULDER SUBGRADE PREPARATION StaM91.71222,928.00
0.0000.00
0.0000.00

0053                          9005.00 30.86100.0003,086.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0003,086.00
SP4(12.5) 0.0000.00
0.0000.00

0054                          9005.23 14.036,600.00092,598.00
ASPHALTIC CONCRETE, TYPE SPS Mg 6,600.00092,598.00
0.0000.00
0.0000.00

0055                          9005.45 20.8613,650.000284,739.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 13,650.000284,739.00
0.0000.00
0.0000.00

0056                          9009.00 3.503,057.00010,699.50
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 3,057.00010,699.50
0.0000.00
0.0000.00

0058                          9021.01 195.00742.500144,787.50
PERFORMANCE GRADED BINDER (64-22) Mg 742.500144,787.50
0.0000.00
0.0000.00

0059                          9021.03 195.00356.40069,498.00
PERFORMANCE GRADED BINDER (58-28) Mg 356.40069,498.00
0.0000.00
0.0000.00

0060                          9030.00 11.50103.0001,184.50
CONSTRUCTING ASPHALTIC CONCRETE CURB m 103.0001,184.50
0.0000.00
0.0000.00

0061                          9034.00 2.503,057.0007,642.50
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 3,057.0007,642.50
0.0000.00
0.0000.00

0062                          9053.00 0.2655,240.00014,362.40
TACK COAT L 55,240.00014,362.40
0.0000.00
0.0000.00

0063                          9111.00 2.00200.000400.00
WATER kL 200.000400.00
0.0000.00
0.0000.00

0065                          9170.00 225.0016.2913,665.48
EARTH SHOULDER CONSTRUCTION StaM16.2913,665.48
0.0000.00
0.0000.00

0066                          9173.20 1.2011,139.00013,366.80
SUBGRADE PREPARATION m2 11,139.00013,366.80
0.0000.00
0.0000.00

0067                          9179.23 435.0054.00223,490.87
COLD MILLING, CLASS 3 StaM54.00223,490.87
0.0000.00
0.0000.00

0069                          9300.50 2,000.001.0002,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0002,000.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted966,209.34
Current966,209.34
In place3,166.69
This Estimate0.00

GROUP 4 CULVERTS
0077                          0030.40 10,920.221.00010,920.22
MOBILIZATION LS 1.00010,920.22
1.00010,920.22
0.0000.00

0078                          1043.50 2.50483.0001,207.50
RIPRAP FILTER FABRIC m2 483.0001,207.50
255.000637.50
255.000637.50

0080                          4004.50 2.70756.0002,041.20
CAST IRON GRATE AND FRAME kg 756.0002,041.20
756.0002,041.20
756.0002,041.20

0081                          4035.00 120.004.000480.00
REMOVE FLARED-END SECTION EACH4.000480.00
6.000720.00
0.0000.00

0082                          4040.00 160.008.0001,280.00
REMOVE HEADWALLS FROM CULVERTS EACH8.0001,280.00
4.000640.00
0.0000.00

0085                          4044.02 1,200.001.0001,200.00
PREPARATION OF STRUCTURE EACH1.0001,200.00
AT STA. 10+00.09 RT. 1.0001,200.00
0.0000.00

0086                          4044.03 2,000.001.0002,000.00
PREPARATION OF STRUCTURE EACH1.0002,000.00
AT STA. 13+64.37 1.0002,000.00
0.0000.00

0087                          4044.04 1,200.001.0001,200.00
PREPARATION OF STRUCTURE EACH1.0001,200.00
AT STA. 174+70.31 1.0001,200.00
0.0000.00

0088                          4044.05 1,200.001.0001,200.00
PREPARATION OF STRUCTURE EACH1.0001,200.00
AT STA. 182+73.29 1.0001,200.00
1.0001,200.00

0089                          4050.01 12.00315.0003,780.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 315.0003,780.00
268.0003,216.00
0.0000.00

0090                          4051.01 15.00730.00010,950.00
EXCAVATION FOR BOX CULVERTS m3 730.00010,950.00
704.00010,560.00
95.5001,432.50

0091                          4100.06 650.008.5005,525.00
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 8.5005,525.00
0.0000.00
0.0000.00

0092                          4101.06 317.00269.04085,285.68
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 269.04085,285.68
282.13089,435.22
19.9616,327.64

0093                          4105.59 675.003.9702,679.75
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 3.9702,679.75
3.9702,679.75
0.0000.00

0094                          4107.07 675.002.3601,593.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 2.3601,593.00
0.0000.00
0.0000.00

0095                          4150.00 1.60706.0001,129.60
REINFORCING STEEL FOR HEADWALL kg 706.0001,129.60
0.0000.00
0.0000.00

0096                          4151.00 1.2819,209.00024,587.52
REINFORCING STEEL FOR BOX CULVERT kg 19,209.00024,587.52
17,174.60521,983.51
1,329.2331,701.42

0097                          4155.50 1.60239.000382.40
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 239.000382.40
239.000382.40
0.0000.00

0098                          4157.00 1.6096.000153.60
REINFORCING STEEL FOR COLLARS kg 96.000153.60
0.0000.00
0.0000.00

0104                          4350.36 98.00177.50017,395.00
900 mm CORRUGATED METAL PIPE m 177.50017,395.00
132.00012,936.00
0.0000.00

0105                          4360.36 400.006.0002,400.00
900 mm METAL FLARED-END SECTION EACH6.0002,400.00
4.0001,600.00
0.0000.00

0106                          4450.36 205.0063.50013,017.50
900 mm REINFORCED CONCRETE PIPE m 63.50013,017.50
63.50013,017.50
0.0000.00

0107                          4452.18 150.0085.00012,750.00
450 mm REINFORCED CONCRETE PIPE CLASS V m 85.00012,750.00
85.00012,750.00
85.00012,750.00

0108                          4460.18 325.004.0001,300.00
450 mm CONCRETE FLARED-END SECTION EACH4.0001,300.00
4.0001,300.00
4.0001,300.00

0109                          4460.36 600.004.0002,400.00
900 mm CONCRETE FLARED-END SECTION EACH4.0002,400.00
2.0001,200.00
0.0000.00

0111                          4831.18 470.0028.00013,160.00
JACKING 450 mm REINFORCED CONCRETE PIPE CLASS V m 28.00013,160.00
28.00013,160.00
28.00013,160.00

0113                          6040.00 3,000.001.0003,000.00
REMOVE STRUCTURE EACH1.0003,000.00
AT STA. 15+53.8 RT. 1.0003,000.00
0.0000.00

0114                          6105.02 30.00455.00013,650.00
ROCK RIPRAP, TYPE B Mg 455.00013,650.00
480.00014,400.00
240.0007,200.00

GROUP 4 CULVERTSContracted236,667.97
Current236,667.97
In place222,179.30
This Estimate47,750.26

GROUP 5 SEEDING
0121                          L001.02 943.4821.80020,567.86
SEEDING, TYPE B ha 21.80020,567.86
0.0000.00
0.0000.00

0122                          L001.17 2,106.256.85014,427.81
SEEDING, TYPE WETLAND ha 6.85014,427.81
0.0000.00
0.0000.00

0126                          L032.75 73.00100.0007,300.00
MULCH Mg 100.0007,300.00
0.0000.00
0.0000.00

0127                          0030.50 585.081.000585.08
MOBILIZATION LS 1.000585.08
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted42,880.76
Current42,880.76
In place0.00
This Estimate0.00

GROUP 8B ELECTRICAL
0249                          A001.12 350.003.0001,050.00
PULL BOX, TYPE PB-5 EACH3.0001,050.00
0.0000.00
0.0000.00

0250                          A009.14 1,350.004.0005,400.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH4.0005,400.00
0.0000.00
0.0000.00

0251                          A020.10 986.002.0001,972.00
LIGHTING CONTROL CENTER, TYPE D EACH2.0001,972.00
0.0000.00
0.0000.00

0253                          A070.10 6.00161.000966.00
38 mm CONDUIT IN TRENCH m 161.000966.00
0.0000.00
0.0000.00

0255                          A074.12 55.0079.0004,345.00
38 mm CONDUIT, JACKED m 79.0004,345.00
0.0000.00
0.0000.00

0257                          A080.22 1.70197.000334.90
STREET LIGHTING CABLE, NO. 6 BARE m 197.000334.90
0.0000.00
0.0000.00

0258                          A080.24 1.80394.000709.20
STREET LIGHTING CABLE, NO. 6 USE m 394.000709.20
0.0000.00
0.0000.00

0259                          A082.34 5.0060.000300.00
DIRECT BURIAL CABLE, NO. 6 USE m 60.000300.00
0.0000.00
0.0000.00

0260                          0030.81 363.581.000363.58
MOBILIZATION LS 1.000363.58
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted15,440.68
Current15,440.68
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0270                          0001.10 1.005,020.0005,020.00
BARRICADE, TYPE III BDAY5,020.0005,020.00
0.0000.00
0.0000.00

0271                          0001.30 0.751,396.0001,047.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY1,396.0001,047.00
0.0000.00
0.0000.00

0272                          0001.75 5.501,095.0006,022.50
TEMPORARY SIGN DAY EACH1,095.0006,022.50
0.0000.00
0.0000.00

0273                          0001.90 0.5010,616.0005,308.00
SIGN DAY EACH10,616.0005,308.00
0.0000.00
0.0000.00

0276                          0002.55 23.75112.2382,665.65
OVERLAY BROKEN LINES StaM112.2382,665.65
0.0000.00
0.0000.00

0278                          0003.10 185.00110.00020,350.00
FLAGGING DAY 110.00020,350.00
0.0000.00
0.0000.00

0283                          0010.04 1,500.000.200300.00
FIELD OFFICE EACH0.200300.00
0.0000.00
0.0000.00

0284                          0030.00 2,254.471.0002,254.47
MOBILIZATION LS 1.0002,254.47
0.0000.00
0.0000.00

0286                          9110.01 75.0055.0004,125.00
RENTAL OF LOADER, FULLY OPERATED HOUR55.0004,125.00
8.000600.00
0.0000.00

0287                          9110.02 75.0015.0001,125.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR15.0001,125.00
9.330699.75
0.0000.00

0288                          9110.03 55.0055.0003,025.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR55.0003,025.00
8.180449.90
0.0000.00

0289                          9110.06 65.0040.0002,600.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR40.0002,600.00
1.00065.00
0.0000.00

0290                          9110.07 50.0055.0002,750.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR55.0002,750.00
2.000100.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted56,592.62
Current56,592.62
In place1,914.65
This Estimate0.00

GROUP 1 GRADING
0001                          L006.00 75.0043.0003,225.00
COVER CROP SEEDING ha 43.0003,225.00
0.0000.00
0.0000.00

0002                          L020.00 1.056,046.0006,348.30
EROSION CONTROL m2 6,046.0006,348.30
0.0000.00
0.0000.00

0003                          L020.09 15.70532.0008,352.40
EROSION CONTROL, TYPE AAA m2 532.0008,352.40
0.0000.00
0.0000.00

0006                          L022.25 8.001,536.20012,289.60
FABRIC SILT FENCE, TYPE COIR FIBER m 1,536.20012,289.60
0.0000.00
0.0000.00

0007                          L022.75 22.6260.0001,357.20
TEMPORARY SILT CHECK m 60.0001,357.20
0.0000.00
0.0000.00

0008                          0030.10 51,763.501.00051,763.50
MOBILIZATION LS 1.00051,763.50
1.00051,763.50
0.0000.00

0010                          1009.01 119,902.001.000119,902.00
GENERAL CLEARING AND GRUBBING LS 1.000119,902.00
FOR PROJECT IM-STPAA-80-7(100) 0.950113,906.90
0.0000.00

0011                          1011.00 2.1217,790.00037,714.80
WATER kL 17,790.00037,714.80
1,194.4502,532.23
116.520247.02

0012                          1012.00 58.0052.0003,016.00
RIGHT-OF-WAY MARKERS EACH52.0003,016.00
0.0000.00
0.0000.00

0013                          1030.00 4.43317,624.0001,407,074.32
EARTHWORK MEASURED IN EMBANKMENT m3 317,624.0001,407,074.32
84,486.000374,272.98
7,678.00034,013.54

0014                          1041.00 0.23288,870.00066,440.10
SALVAGING AND PLACING TOPSOIL m2 288,870.00066,440.10
24,375.0005,606.25
0.0000.00

0015                          1101.00 2.8811,205.00032,270.40
REMOVE PAVEMENT m2 11,205.00032,270.40
0.0000.00
0.0000.00

0016                          1101.25 8.2025.000205.00
SAWING PAVEMENT m 25.000205.00
0.0000.00
0.0000.00

0019                          1111.00 0.804,460.8003,568.64
REMOVE FENCE m 4,460.8003,568.64
6,250.2005,000.16
0.0000.00

0025                          1701.36 68.9059.0004,065.10
900 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 59.0004,065.10
0.0000.00
0.0000.00

0028                          7017.00 5.95322.8001,920.66
REMOVE GUARDRAIL m 322.8001,920.66
0.0000.00
0.0000.00

GROUP 1 GRADINGContracted1,759,513.02
Current1,759,513.02
In place553,082.02
This Estimate34,260.56

GROUP 3 CONCRETE PAVEMENT
0029                          0002.61 52.5048.0002,520.00
PLOWABLE PAVEMENT MARKER EACH48.0002,520.00
0.0000.00
0.0000.00

0030                          0030.30 61,364.031.00061,364.03
MOBILIZATION LS 1.00061,364.03
0.0000.00
0.0000.00

0031                          1020.01 17.0081.0001,377.00
DELINEATOR, TYPE I EACH81.0001,377.00
0.0000.00
0.0000.00

0032                          1020.02 17.3081.0001,401.30
DELINEATOR, TYPE II EACH81.0001,401.30
0.0000.00
0.0000.00

0033                          1020.20 25.5020.000510.00
INSTALL CHEVRONS EACH20.000510.00
0.0000.00
0.0000.00

0034                          2001.00 9.00138.5001,246.50
GRAVEL SURFACE COURSE m3 138.5001,246.50
0.0000.00
0.0000.00

0038                          3008.05 4.501,248.0005,616.00
TIE BARS EACH1,248.0005,616.00
0.0000.00
0.0000.00

0039                          3017.40 32.292,241.00072,361.89
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 2,241.00072,361.89
0.0000.00
0.0000.00

0041                          3075.52 30.6511,119.000340,797.35
255 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 11,119.000340,797.35
0.0000.00
0.0000.00

0042                          3075.56 36.5529,637.0001,083,232.35
255 mm DOWELED CONCRETE PAVMENT, CLASS 47B-25 m2 29,637.0001,083,232.35
0.0000.00
0.0000.00

0043                          3090.10 47.50184.0008,740.00
255 mm CONCRETE PAVEMENT m2 184.0008,740.00
CLASS 47BD-30 0.0000.00
0.0000.00

0044                          3300.65 90.0025.0002,250.00
CONCRETE PAVEMENT THICKNESS CORE EACH25.0002,250.00
0.0000.00
0.0000.00

0045                          6010.40 525.0027.70014,542.50
CLASS 47BD-30 CONCRETE FOR BARRIER m3 27.70014,542.50
0.0000.00
0.0000.00

0046                          6131.61 2.257,160.00016,110.00
EPOXY COATED REINFORCING STEEL FOR BARRIER kg 7,160.00016,110.00
0.0000.00
0.0000.00

0047                          7502.14 3.854,500.00017,325.00
100 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 4,500.00017,325.00
0.0000.00
0.0000.00

0048                          7503.14 3.903,500.00013,650.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 3,500.00013,650.00
0.0000.00
0.0000.00

0049                          7508.14 11.551,000.00011,550.00
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 1,000.00011,550.00
0.0000.00
0.0000.00

0050                          8029.10 3.6045,526.000163,893.60
AGGREGATE FOUNDATION COURSE-D 100 mm m2 45,526.000163,893.60
0.0000.00
0.0000.00

0052                          9000.75 14.03500.0007,015.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.0007,015.00
SPS 0.0000.00
0.0000.00

0054                          9005.23 14.031,810.00025,394.30
ASPHALTIC CONCRETE, TYPE SPS Mg 1,810.00025,394.30
0.0000.00
0.0000.00

0056                          9009.00 3.50242.000847.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 242.000847.00
0.0000.00
0.0000.00

0057                          9020.92 195.0027.0005,265.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 27.0005,265.00
0.0000.00
0.0000.00

0059                          9021.03 195.0097.74019,059.30
PERFORMANCE GRADED BINDER (58-28) Mg 97.74019,059.30
0.0000.00
0.0000.00

0061                          9034.00 2.50242.000605.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 242.000605.00
0.0000.00
0.0000.00

0062                          9053.00 0.262,130.000553.80
TACK COAT L 2,130.000553.80
0.0000.00
0.0000.00

0063                          9111.00 2.00842.0001,684.00
WATER kL 842.0001,684.00
0.0000.00
0.0000.00

0064                          9140.00 100.0020.2992,029.90
JOINT SEALING - ASPHALT TO CONCRETE StaM20.2992,029.90
0.0000.00
0.0000.00

0065                          9170.00 225.0074.00716,651.58
EARTH SHOULDER CONSTRUCTION StaM74.00716,651.58
0.0000.00
0.0000.00

0066                          9173.20 1.2045,526.00054,631.20
SUBGRADE PREPARATION m2 45,526.00054,631.20
0.0000.00
0.0000.00

0068                          9188.50 25.00345.0008,625.00
SURFACING UNDER GUARDRAIL m2 345.0008,625.00
0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,960,848.60
Current1,960,848.60
In place0.00
This Estimate0.00

GROUP 4 CULVERTS
0070                          P120.24 120.005.000600.00
600 mm CULVERT PIPE, TYPE 2 m 5.000600.00
0.0000.00
0.0000.00

0071                          P120.36 180.0015.5002,790.00
900 mm CULVERT PIPE, TYPE 2 m 15.5002,790.00
8.5001,530.00
0.0000.00

0072                          P120.48 260.004.0001,040.00
1200 mm CULVERT PIPE, TYPE 2 m 4.0001,040.00
4.0001,040.00
0.0000.00

0073                          P200.42 180.0040.0007,200.00
1050 mm CULVERT PIPE, TYPE 2 OR 5 m 40.0007,200.00
0.0000.00
0.0000.00

0074                          P200.48 220.0027.0005,940.00
1200 mm CULVERT PIPE, TYPE 2 OR 5 m 27.0005,940.00
27.0005,940.00
0.0000.00

0075                          P400.18 70.00126.2008,834.00
450 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 126.2008,834.00
0.0000.00
0.0000.00

0076                          P400.24 95.00152.00014,440.00
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 152.00014,440.00
152.00014,440.00
0.0000.00

0077                          0030.40 7,079.781.0007,079.78
MOBILIZATION LS 1.0007,079.78
0.9316,596.08
0.0000.00

0078                          1043.50 2.50324.000810.00
RIPRAP FILTER FABRIC m2 324.000810.00
0.0000.00
0.0000.00

0079                          1119.00 250.004.0001,000.00
REMOVE INLET EACH4.0001,000.00
2.000500.00
0.0000.00

0080                          4004.50 2.702,450.0006,615.00
CAST IRON GRATE AND FRAME kg 2,450.0006,615.00
0.0000.00
0.0000.00

0081                          4035.00 120.007.000840.00
REMOVE FLARED-END SECTION EACH7.000840.00
1.000120.00
0.0000.00

0083                          4044.00 1,000.001.0001,000.00
PREPARATION OF STRUCTURE EACH1.0001,000.00
AT STA. 104+15.3 0.0000.00
0.0000.00

0084                          4044.01 700.001.000700.00
PREPARATION OF STRUCTURE EACH1.000700.00
AT STA. 605+07.566 1.000700.00
0.0000.00

0089                          4050.01 12.00612.0007,344.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 612.0007,344.00
193.0002,316.00
0.0000.00

0090                          4051.01 15.0055.000825.00
EXCAVATION FOR BOX CULVERTS m3 55.000825.00
0.0000.00
0.0000.00

0092                          4101.06 317.0029.1009,224.70
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 29.1009,224.70
0.0000.00
0.0000.00

0093                          4105.59 675.007.4505,028.75
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 7.4505,028.75
0.0000.00
0.0000.00

0094                          4107.07 675.003.0702,072.25
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 3.0702,072.25
0.0000.00
0.0000.00

0096                          4151.00 1.281,193.0001,527.04
REINFORCING STEEL FOR BOX CULVERT kg 1,193.0001,527.04
0.0000.00
0.0000.00

0097                          4155.50 1.60295.000472.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 295.000472.00
0.0000.00
0.0000.00

0098                          4157.00 1.60123.000196.80
REINFORCING STEEL FOR COLLARS kg 123.000196.80
0.0000.00
0.0000.00

0099                          4310.18 218.007.0001,526.00
450 mm FLARED-END SECTION EACH7.0001,526.00
0.0000.00
0.0000.00

0100                          4310.24 252.007.0001,764.00
600 mm FLARED-END SECTION EACH7.0001,764.00
6.0001,512.00
0.0000.00

0101                          4310.36 410.003.0001,230.00
900 mm FLARED-END SECTION EACH3.0001,230.00
0.0000.00
0.0000.00

0102                          4310.42 730.002.0001,460.00
1050 mm FLARED-END SECTION EACH2.0001,460.00
0.0000.00
0.0000.00

0103                          4310.48 650.003.0001,950.00
1200 mm FLARED-END SECTION EACH3.0001,950.00
2.0001,300.00
0.0000.00

0110                          4670.05 95.00480.00045,600.00
CULVERT SANDFILL m3 480.00045,600.00
480.00045,600.00
0.0000.00

0112                          4900.24 475.005.0002,375.00
AREA INLET SEDIMENT FILTER EACH5.0002,375.00
0.0000.00
0.0000.00

0114                          6105.02 30.00280.0008,400.00
ROCK RIPRAP, TYPE B Mg 280.0008,400.00
0.0000.00
0.0000.00

GROUP 4 CULVERTSContracted149,884.32
Current149,884.32
In place81,594.08
This Estimate0.00

GROUP 4A CULVERT AT STA. 606+26.631
0115                          0030.40 8,000.001.0008,000.00
MOBILIZATION LS 1.0008,000.00
0.0000.00
0.0000.00

0116                          4045.00 4,000.001.0004,000.00
REMOVE STRUCTURE EACH1.0004,000.00
AT STA. 606+26.631 0.0000.00
0.0000.00

0117                          4051.01 12.00580.0006,960.00
EXCAVATION FOR BOX CULVERTS m3 580.0006,960.00
0.0000.00
0.0000.00

0118                          4101.06 317.00363.810115,327.77
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 363.810115,327.77
0.0000.00
0.0000.00

0119                          4151.00 1.2818,454.00023,621.12
REINFORCING STEEL FOR BOX CULVERT kg 18,454.00023,621.12
0.0000.00
0.0000.00

GROUP 4A CULVERT AT STA. 606+26.631Contracted157,908.89
Current157,908.89
In place0.00
This Estimate0.00

GROUP 5 SEEDING
0120                          L001.01 1,574.8634.50054,332.67
SEEDING, TYPE A ha 34.50054,332.67
0.0000.00
0.0000.00

0121                          L001.02 943.488.5008,019.58
SEEDING, TYPE B ha 8.5008,019.58
0.0000.00
0.0000.00

0123                          L001.18 1,806.309.70017,521.11
SEEDING, TYPE WETLAND-HIGH ha 9.70017,521.11
0.0000.00
0.0000.00

0124                          L001.19 2,300.4016.50037,956.60
SEEDING, TYPE WETLAND-LOW ha 16.50037,956.60
0.0000.00
0.0000.00

0125                          L020.07 3.832,986.00011,436.38
EROSION CONTROL, TYPE B-1 m2 2,986.00011,436.38
0.0000.00
0.0000.00

0126                          L032.75 73.00194.00014,162.00
MULCH Mg 194.00014,162.00
0.0000.00
0.0000.00

0127                          0030.50 2,214.921.0002,214.92
MOBILIZATION LS 1.0002,214.92
0.0000.00
0.0000.00

GROUP 5 SEEDINGContracted145,643.26
Current145,643.26
In place0.00
This Estimate0.00

GROUP 6A BRIDGE AT STA. 107+09.194
0158                          0020.00 0.801,000.000800.00
TRAINING HOUR1,000.000800.00
0.0000.00
0.0000.00

0159                          0030.60 115,000.001.000115,000.00
MOBILIZATION LS 1.000115,000.00
1.000115,000.00
0.0000.00

0160                          1043.50 2.5052.000130.00
RIPRAP FILTER FABRIC m2 52.000130.00
0.0000.00
0.0000.00

0161                          3050.15 188.00105.00019,740.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 105.00019,740.00
0.0000.00
0.0000.00

0162                          3051.10 1.257,135.0008,918.75
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 7,135.0008,918.75
0.0000.00
0.0000.00

0163                          6000.10 4,000.001.0004,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0164                          6000.11 4,000.001.0004,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0165                          6000.60 16,000.001.00016,000.00
PIER NO.1 EXCAVATION LS 1.00016,000.00
1.00016,000.00
0.0000.00

0166                          6001.50 8,000.001.0008,000.00
BENT NO.1 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0167                          6001.51 8,000.001.0008,000.00
BENT NO.2 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0168                          6001.52 8,000.001.0008,000.00
BENT NO.3 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0169                          6001.53 8,000.001.0008,000.00
BENT NO.4 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0170                          6001.54 8,000.001.0008,000.00
BENT NO.5 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0171                          6001.55 8,000.001.0008,000.00
BENT NO.6 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0172                          6001.56 8,000.001.0008,000.00
BENT NO.7 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0173                          6001.57 8,000.001.0008,000.00
BENT NO.8 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0174                          6001.58 8,000.001.0008,000.00
BENT NO.9 EXCAVATION LS 1.0008,000.00
1.0008,000.00
0.0000.00

0175                          6005.78 550.0033.00018,150.00
EXPANSION BEARING, TFE TYPE EACH33.00018,150.00
15.0008,250.00
15.0008,250.00

0176                          6005.83 396.503.0001,189.50
FIXED BEARING EACH3.0001,189.50
3.0001,189.50
3.0001,189.50

0177                          6010.22 440.00411.100180,884.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 411.100180,884.00
416.782183,384.08
140.81961,960.36

0178                          6010.26 440.00573.300252,252.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 573.300252,252.00
0.0000.00
0.0000.00

0179                          6071.12 285,000.001.000285,000.00
STEEL SUPERSTRUCTURE LS 1.000285,000.00
AT STA. 107+09.194 0.455129,675.00
0.27377,805.00

0180                          6080.00 6.901,375.0009,487.50
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 1,375.0009,487.50
1,111.5007,669.35
0.0000.00

0181                          6104.00 15.00700.00010,500.00
BROKEN CONCRETE RIPRAP Mg 700.00010,500.00
214.9793,224.69
214.9793,224.69

0182                          6131.50 1.2594,215.000117,768.75
EPOXY COATED REINFORCING STEEL kg 94,215.000117,768.75
14,417.46518,021.84
3,954.1014,942.63

0183                          6139.50 35.0031.0001,085.00
SUBSURFACE DRAINAGE MATTING m2 31.0001,085.00
0.0000.00
0.0000.00

0184                          6200.00 95.001,512.200143,659.00
CONCRETE PILING m 1,512.200143,659.00
1,419.000134,805.00
0.0000.00

0185                          6310.00 92.00437.60040,259.20
STEEL SHEET PILING m2 437.60040,259.20
418.68038,518.56
0.0000.00

0186                          6610.45 345.0025.5008,797.50
STRIP SEALS m 25.5008,797.50
0.0000.00
0.0000.00

0187                          8091.00 28.0090.0002,520.00
GRANULAR BACKFILL m3 90.0002,520.00
0.0000.00
0.0000.00

4000                          6200.00 57.000.0000.00
CONCRETE PILING m 15.000855.00
Cut-Off for Conc Bearing Piling (Unit Price = 60%($95.00/m) 27.6001,573.20
0.0000.00

GROUP 6A BRIDGE AT STA. 107+09.194Contracted1,312,141.20
Current1,312,996.20
In place737,311.22
This Estimate157,372.18

GROUP 6B BRIDGE AT STA. 604+02.955
0188                          0020.00 0.80500.000400.00
TRAINING HOUR500.000400.00
0.0000.00
0.0000.00

0189                          0030.60 60,000.001.00060,000.00
MOBILIZATION LS 1.00060,000.00
0.0000.00
0.0000.00

0190                          3050.15 188.00258.10048,522.80
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 258.10048,522.80
0.0000.00
0.0000.00

0191                          3051.10 1.2514,730.00018,412.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 14,730.00018,412.50
0.0000.00
0.0000.00

0192                          6000.10 4,000.001.0004,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0004,000.00
0.0000.00
0.0000.00

0193                          6000.11 4,000.001.0004,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0004,000.00
0.0000.00
0.0000.00

0194                          6000.20 10,000.001.00010,000.00
PIER NO.1 EXCAVATION LS 1.00010,000.00
0.0000.00
0.0000.00

0195                          6005.35 120.0044.6005,352.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 44.6005,352.00
0.0000.00
0.0000.00

0196                          6005.78 467.0016.0007,472.00
EXPANSION BEARING, TFE TYPE EACH16.0007,472.00
0.0000.00
0.0000.00

0197                          6005.83 440.0016.0007,040.00
FIXED BEARING EACH16.0007,040.00
0.0000.00
0.0000.00

0198                          6010.22 420.00234.70098,574.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 234.70098,574.00
0.0000.00
0.0000.00

0199                          6010.26 420.00502.100210,882.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 502.100210,882.00
0.0000.00
0.0000.00

0200                          6011.11 325,000.001.000325,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000325,000.00
AT STA. 604+02.955 0.0000.00
0.0000.00

0201                          6040.00 35,000.001.00035,000.00
REMOVE STRUCTURE EACH1.00035,000.00
AT STA. 604+02.955 0.0000.00
0.0000.00

0202                          6095.00 676.0014.0009,464.00
STEEL DIAPHRAGM EACH14.0009,464.00
0.0000.00
0.0000.00

0203                          6107.00 46.50578.00026,877.00
CONCRETE SLOPE PROTECTION m2 578.00026,877.00
0.0000.00
0.0000.00

0204                          6131.50 1.2589,205.000111,506.25
EPOXY COATED REINFORCING STEEL kg 89,205.000111,506.25
0.0000.00
0.0000.00

0205                          6139.50 26.00128.0003,328.00
SUBSURFACE DRAINAGE MATTING m2 128.0003,328.00
0.0000.00
0.0000.00

0206                          6200.00 95.001,452.400137,978.00
CONCRETE PILING m 1,452.400137,978.00
0.0000.00
0.0000.00

0207                          8091.00 28.00380.00010,640.00
GRANULAR BACKFILL m3 380.00010,640.00
0.0000.00
0.0000.00

GROUP 6B BRIDGE AT STA. 604+02.955Contracted1,134,448.55
Current1,134,448.55
In place0.00
This Estimate0.00

GROUP 6C BRIDGE AT STA. 608+75.404
0208                          0020.00 0.80500.000400.00
TRAINING HOUR500.000400.00
0.0000.00
0.0000.00

0209                          0030.60 60,000.001.00060,000.00
MOBILIZATION LS 1.00060,000.00
0.0000.00
0.0000.00

0210                          1010.01 3.40470.0001,598.00
EXCAVATION (ESTABLISHED QUANTITY) m3 470.0001,598.00
0.0000.00
0.0000.00

0211                          1043.50 2.50572.0001,430.00
RIPRAP FILTER FABRIC m2 572.0001,430.00
0.0000.00
0.0000.00

0212                          3050.15 188.00271.10050,966.80
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 271.10050,966.80
0.0000.00
0.0000.00

0213                          3051.10 1.4517,024.00024,684.80
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 17,024.00024,684.80
0.0000.00
0.0000.00

0214                          6000.10 4,000.001.0004,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0004,000.00
0.0000.00
0.0000.00

0215                          6000.11 4,000.001.0004,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0004,000.00
0.0000.00
0.0000.00

0216                          6001.50 10,000.001.00010,000.00
BENT NO.1 EXCAVATION LS 1.00010,000.00
0.0000.00
0.0000.00

0217                          6001.51 10,000.001.00010,000.00
BENT NO.2 EXCAVATION LS 1.00010,000.00
0.0000.00
0.0000.00

0218                          6005.60 325.00144.00046,800.00
ELASTOMERIC BEARING EACH144.00046,800.00
0.0000.00
0.0000.00

0219                          6010.22 480.00183.30087,984.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 183.30087,984.00
0.0000.00
0.0000.00

0220                          6010.26 480.00217.800104,544.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 217.800104,544.00
0.0000.00
0.0000.00

0221                          6011.11 182,000.001.000182,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.000182,000.00
AT STA. 608+75.404 0.0000.00
0.0000.00

0222                          6030.00 35,000.001.00035,000.00
PREPARATION OF BRIDGE EACH1.00035,000.00
AT STA. 608+75.404 0.0000.00
0.0000.00

0223                          6080.00 6.90244.0001,683.60
STRUCTURAL STEEL FOR SUBSTRUCTURE kg 244.0001,683.60
0.0000.00
0.0000.00

0224                          6104.00 16.00103.0001,648.00
BROKEN CONCRETE RIPRAP Mg 103.0001,648.00
0.0000.00
0.0000.00

0225                          6105.02 41.00407.00016,687.00
ROCK RIPRAP, TYPE B Mg 407.00016,687.00
0.0000.00
0.0000.00

0226                          6131.50 1.4542,008.00060,911.60
EPOXY COATED REINFORCING STEEL kg 42,008.00060,911.60
0.0000.00
0.0000.00

0227                          6139.50 29.0096.0002,784.00
SUBSURFACE DRAINAGE MATTING m2 96.0002,784.00
0.0000.00
0.0000.00

0228                          6200.00 95.00835.20079,344.00
CONCRETE PILING m 835.20079,344.00
0.0000.00
0.0000.00

0229                          6310.00 92.00519.00047,748.00
STEEL SHEET PILING m2 519.00047,748.00
0.0000.00
0.0000.00

0230                          6510.55 8,300.001.0008,300.00
TEMPORARY BRIDGE SHORING LS 1.0008,300.00
0.0000.00
0.0000.00

0231                          8091.00 28.00180.0005,040.00
GRANULAR BACKFILL m3 180.0005,040.00
0.0000.00
0.0000.00

GROUP 6C BRIDGE AT STA. 608+75.404Contracted847,553.80
Current847,553.80
In place0.00
This Estimate0.00

GROUP 7 GUARDRAIL
0232                          0030.70 850.001.000850.00
MOBILIZATION LS 1.000850.00
0.0000.00
0.0000.00

0233                          6010.26 1,550.002.0003,100.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 2.0003,100.00
0.0000.00
0.0000.00

0234                          6030.05 1,200.001.0001,200.00
PREPARATION OF BRIDGE EACH1.0001,200.00
AT STA. 599+17.73 0.0000.00
0.0000.00

0235                          6131.50 2.50330.000825.00
EPOXY COATED REINFORCING STEEL kg 330.000825.00
0.0000.00
0.0000.00

0236                          7011.20 37.26205.7407,665.87
W-BEAM GUARDRAIL m 205.7407,665.87
0.0000.00
0.0000.00

0237                          7011.30 58.1768.5803,989.30
THRIE-BEAM GUARDRAIL m 68.5803,989.30
0.0000.00
0.0000.00

0238                          7019.50 36,168.001.00036,168.00
IMPACT ATTENUATOR EACH1.00036,168.00
0.0000.00
0.0000.00

0239                          7020.00 969.339.0008,723.97
BRIDGE APPROACH SECTIONS EACH9.0008,723.97
0.0000.00
0.0000.00

0240                          7022.50 4,179.002.0008,358.00
BULLNOSE-3.8 m EACH2.0008,358.00
0.0000.00
0.0000.00

0241                          7024.25 1,517.001.0001,517.00
GUARDRAIL END TREATMENT, TYPE I EACH1.0001,517.00
0.0000.00
0.0000.00

0242                          7024.27 1,433.008.00011,464.00
GUARDRAIL END TREATMENT, TYPE II EACH8.00011,464.00
0.0000.00
0.0000.00

GROUP 7 GUARDRAILContracted83,861.14
Current83,861.14
In place0.00
This Estimate0.00

GROUP 7B FENCING
0243                          0030.71 500.001.000500.00
MOBILIZATION LS 1.000500.00
1.000500.00
0.0000.00

0244                          7100.00 13.752,644.80036,366.00
RIGHT-OF-WAY FENCE m 2,644.80036,366.00
1,089.00014,973.75
0.0000.00

0245                          7103.00 200.0011.0002,200.00
END POSTS EACH11.0002,200.00
0.0000.00
0.0000.00

0246                          7104.00 200.0014.0002,800.00
PULL POSTS EACH14.0002,800.00
9.0001,800.00
0.0000.00

0247                          7105.00 200.0022.0004,400.00
CORNER POSTS EACH22.0004,400.00
9.0001,800.00
0.0000.00

0248                          7106.02 600.001.000600.00
9.1 m GATE EACH1.000600.00
0.0000.00
0.0000.00

GROUP 7B FENCINGContracted46,866.00
Current46,866.00
In place19,073.75
This Estimate0.00

GROUP 8B ELECTRICAL
0249                          A001.12 350.0014.0004,900.00
PULL BOX, TYPE PB-5 EACH14.0004,900.00
0.0000.00
0.0000.00

0250                          A009.14 1,350.0031.00041,850.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25 EACH31.00041,850.00
0.0000.00
0.0000.00

0252                          A020.30 1,235.003.0003,705.00
LIGHTING CONTROL CENTER, TYPE R EACH3.0003,705.00
0.0000.00
0.0000.00

0253                          A070.10 6.002,480.00014,880.00
38 mm CONDUIT IN TRENCH m 2,480.00014,880.00
0.0000.00
0.0000.00

0254                          A072.10 7.00130.000910.00
38 mm CONDUIT UNDER ROADWAY m 130.000910.00
0.0000.00
0.0000.00

0256                          A080.10 2.005,220.00010,440.00
STREET LIGHTING CABLE, NO. 2 USE m 5,220.00010,440.00
0.0000.00
0.0000.00

0257                          A080.22 1.702,610.0004,437.00
STREET LIGHTING CABLE, NO. 6 BARE m 2,610.0004,437.00
0.0000.00
0.0000.00

0260                          0030.81 2,195.421.0002,195.42
MOBILIZATION LS 1.0002,195.42
0.0000.00
0.0000.00

GROUP 8B ELECTRICALContracted83,317.42
Current83,317.42
In place0.00
This Estimate0.00

GROUP 8C SIGNING
0261                          0030.82 1,000.001.0001,000.00
MOBILIZATION LS 1.0001,000.00
0.0000.00
0.0000.00

0262                          7320.00 250.002.000500.00
INSTALL SIGN EACH2.000500.00
0.0000.00
0.0000.00

0263                          7321.01 180.001.040187.20
TYPE A SIGN m2 1.040187.20
0.0000.00
0.0000.00

0264                          7322.01 185.0062.49811,562.13
TYPE B SIGN m2 62.49811,562.13
0.0000.00
0.0000.00

0265                          7340.00 2.753,284.0009,031.00
STRUCTURAL STEEL FOR SIGN SUPPORTS kg 3,284.0009,031.00
0.0000.00
0.0000.00

0266                          7360.24 300.008.0002,400.00
600 mm SIGN SUPPORT FOOTING EACH8.0002,400.00
0.0000.00
0.0000.00

0267                          7360.30 320.0014.0004,480.00
750 mm SIGN SUPPORT FOOTING EACH14.0004,480.00
0.0000.00
0.0000.00

0268                          7390.00 250.003.000750.00
REMOVE SIGN AND POST EACH3.000750.00
0.0000.00
0.0000.00

GROUP 8C SIGNINGContracted29,910.33
Current29,910.33
In place0.00
This Estimate0.00

GROUP 10 GENERAL ITEMS
0269                          0001.08 1.002,016.0002,016.00
BARRICADE, TYPE II BDAY2,016.0002,016.00
327.000327.00
157.500157.50

0270                          0001.10 1.003,002.0003,002.00
BARRICADE, TYPE III BDAY3,002.0003,002.00
4,420.0004,420.00
1,496.0001,496.00

0271                          0001.30 0.752,792.0002,094.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY2,792.0002,094.00
0.0000.00
0.0000.00

0272                          0001.75 5.501,216.0006,688.00
TEMPORARY SIGN DAY EACH1,216.0006,688.00
0.0000.00
-385.000-2,117.50

0273                          0001.90 0.5015,420.0007,710.00
SIGN DAY EACH15,420.0007,710.00
5,612.0002,806.00
2,212.0001,106.00

0274                          0002.30 1.481,000.0001,480.00
PAVEMENT MARKING REMOVAL m 1,000.0001,480.00
0.0000.00
0.0000.00

0275                          0002.39 3.28700.0002,296.00
TEMPORARY PAVEMENT MARKING, TYPE II m 700.0002,296.00
0.0000.00
0.0000.00

0277                          0002.97 30.0066.0001,980.00
FLASHING ARROW PANEL DAY 66.0001,980.00
0.0000.00
0.0000.00

0278                          0003.10 185.0020.0003,700.00
FLAGGING DAY 20.0003,700.00
0.0000.00
0.0000.00

0279                          0003.51 40.00330.00013,200.00
INSTALL CONCRETE PROTECTION BARRIER m 330.00013,200.00
0.0000.00
0.0000.00

0280                          0003.58 3,000.001.0003,000.00
INERTIAL BARRIER SYSTEM EACH1.0003,000.00
0.0000.00
0.0000.00

0281                          0003.64 400.005.0002,000.00
REPLACEMENT MODULE EACH5.0002,000.00
0.0000.00
0.0000.00

0282                          0005.10 150.00100.00015,000.00
TRAFFIC CONTROL MANAGEMENT DAY 100.00015,000.00
0.0000.00
0.0000.00

0283                          0010.04 1,500.000.8001,200.00
FIELD OFFICE EACH0.8001,200.00
0.0000.00
0.0000.00

0284                          0030.00 7,745.531.0007,745.53
MOBILIZATION LS 1.0007,745.53
1.0007,745.53
0.0000.00

0285                          1017.00 85,000.001.00085,000.00
CONSTRUCTION STAKING AND SURVEYING LS 1.00085,000.00
0.37031,450.00
0.0000.00

0286                          9110.01 75.0015.0001,125.00
RENTAL OF LOADER, FULLY OPERATED HOUR15.0001,125.00
15.0001,125.00
0.0000.00

0288                          9110.03 55.0015.000825.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR15.000825.00
0.0000.00
0.0000.00

0289                          9110.06 65.0015.000975.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR15.000975.00
0.0000.00
0.0000.00

0290                          9110.07 50.0015.000750.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR15.000750.00
7.000350.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted161,786.53
Current161,786.53
In place48,223.53
This Estimate642.00

Totals for contractContracted9,800,324.79
Current9,801,179.79
In place1,870,964.02
This Estimate240,025.00