Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:4366B
Estimate Number:0027
Pay Period End Date:03.23.2002
Contract Location:
HARDY EASTEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:08.31.2000
129 E 2ND STDate Awarded:09.07.2000
PO BOX 1087Date Contract Executed:09.12.2000
Date Notice to Proceed:09.12.2000
HASTINGS NE 68902-1087Date Work Began:10.02.2000
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
NUCKOLLS
THAYER
Project Number PCT Fed State Project Number Description
40366B 000  0.000 EACSTPD-EACBR-8-5(105)  GRAD CULV BIT
41645 000  0.000 F-8-5(1008)  GRAD CULV BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$4,369,685.53$4,362,251.53$7,434.00
$4,406,018.15Stockpiled Materials$-.04$-.04$.00
Original Contract AmtGross Earnings$4,369,685.49$4,362,251.49$7,434.00
$4,327,948.18Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
99.18%Net Earnings$4,344,685.49$4,337,251.49$7,434.00
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$124.20$124.20$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$124.20$124.20$.00
Payment$4,344,809.69$4,337,375.69$7,434.00
Project ManagerDiv. Head/Dist. Eng.
Meyer, Steve03.25.2002Meyer, Keith03.25.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve03.25.2002
Controller Div. Processed
Burling, Laurie03.26.2002
Detailed breakdown of stockpiled materials
Est Nbr:0001
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01310030.90 MOBILIZATION
S.P. Initial Payment5,251.8213056
SURETY BOND
01680030.00 MOBILIZATION
S.P. Initial Payment1,023.8113056
SURETY BOND
Total for estimate 0001:6,275.63
Est Nbr:0006
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01680030.00 MOBILIZATION
S.P. Adjustment-511.9113056
SURETY BOND
Total for estimate 0006:-511.91
Est Nbr:0007
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0040P500.18 450 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8
S.P. Initial Payment687.6281-10-0063
450mm culvert pipe
0041P500.24 600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8
S.P. Initial Payment1,014.9481-10-0063
600mm culvert pipe
0042P500.36 900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8
S.P. Initial Payment1,505.1781-10-0063
900mm culvert pipe
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Initial Payment29,030.617652846
3/4" rock @ $7.89
S.P. Initial Payment27,947.76057773
3/4"rock @ $8.00
S.P. Initial Payment415.567654743
3/4" rock @ $7.89
S.P. Initial Payment2,094.08058269
3/4" rock @ $8.00
S.P. Initial Payment196.617655308
3/4" rock @ $7.89
Total for estimate 0007:62,892.35
Est Nbr:0008
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Initial Payment213.107656392
3/4" rock @ $7.89
Total for estimate 0008:213.10
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01680030.00 MOBILIZATION
S.P. Adjustment-511.9113056
SURETY BOND
Total for estimate 0009:-511.91
Est Nbr:0012
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01310030.90 MOBILIZATION
S.P. Adjustment-5,251.8213056
SURETY BOND
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-5,258.127652846
3/4" rock @ $7.89
S.P. Adjustment-5,331.43057773
3/4"rock @ $8.00
S.P. Adjustment-415.567654743
3/4" rock @ $7.89
S.P. Adjustment-2,094.08058269
3/4" rock @ $8.00
S.P. Adjustment-196.617655308
3/4" rock @ $7.89
S.P. Adjustment-213.107656392
3/4" rock @ $7.89
Total for estimate 0012:-18,760.72
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-3,426.797652846
3/4" rock @ $7.89
S.P. Adjustment-3,474.57057773
3/4"rock @ $8.00
Total for estimate 0013:-6,901.36
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-4,626.807652846
3/4" rock @ $7.89
S.P. Adjustment-4,691.31057773
3/4"rock @ $8.00
Total for estimate 0014:-9,318.11
Est Nbr:0016
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-7,724.817652846
3/4" rock @ $7.89
S.P. Adjustment-7,832.51057773
3/4"rock @ $8.00
Total for estimate 0016:-15,557.32
Est Nbr:0017
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0041P500.24 600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8
S.P. Adjustment-1,014.9481-10-0063
600mm culvert pipe
0042P500.36 900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8
S.P. Adjustment-1,505.1781-10-0063
900mm culvert pipe
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-247.277652846
3/4" rock @ $7.89
S.P. Adjustment-250.72057773
3/4"rock @ $8.00
Total for estimate 0017:-3,018.10
Est Nbr:0018
Item NbrItem CdItem DescAdj AmtInvoice Nbr
0040P500.18 450 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8
S.P. Adjustment-687.6281-10-0063
450mm culvert pipe
01429005.25 ASPHALTIC CONCRETE, TYPE SP1(12.5)
S.P. Adjustment-7,746.827652846
3/4" rock @ $7.89
S.P. Adjustment-6,367.23057773
3/4"rock @ $8.00
Total for estimate 0018:-14,801.67
Est Nbr:0001
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01310030.90 MOBILIZATION
S.P. Initial Payment6,373.1713056
SURETY BOND
01680030.00 MOBILIZATION
S.P. Initial Payment1,476.1913056
SURETY BOND
Total for estimate 0001:7,849.36
Est Nbr:0003
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01680030.00 MOBILIZATION
S.P. Adjustment-738.1013056
SURETY BOND
Total for estimate 0003:-738.10
Est Nbr:0009
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01680030.00 MOBILIZATION
S.P. Adjustment-738.1013056
SURETY BOND
Total for estimate 0009:-738.10
Est Nbr:0013
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01310030.90 MOBILIZATION
S.P. Adjustment-3,186.5913056
SURETY BOND
Total for estimate 0013:-3,186.59
Est Nbr:0014
Item NbrItem CdItem DescAdj AmtInvoice Nbr
01310030.90 MOBILIZATION
S.P. Adjustment-3,186.5913056
SURETY BOND
Total for estimate 0014:-3,186.59
Total remaining for contract:-0.04
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 138.0015.0002,070.00
COVER CROP SEEDING ha 15.0002,070.00
0.0000.00
0.0000.00

0003                          L020.01 6.253,303.00020,643.75
EROSION CONTROL, TYPE A m2 3,303.00020,643.75
3,456.48021,603.00
0.0000.00

0004                          L020.09 17.00376.5006,400.50
EROSION CONTROL, TYPE AAA m2 376.5006,400.50
417.7507,101.75
0.0000.00

0005                          L020.10 1.606,397.00010,235.20
EROSION CONTROL, TYPE HV m2 6,397.00010,235.20
7,232.90011,572.64
0.0000.00

0006                          L021.01 17.5060.0001,050.00
EROSION CHECKS, TYPE A BALE60.0001,050.00
120.0002,100.00
0.0000.00

0007                          L021.06 17.50252.0004,410.00
EROSION CHECKS, TYPE HV BALE252.0004,410.00
258.0004,515.00
0.0000.00

0008                          L021.11 17.5090.0001,575.00
EROSION CHECKS, TYPE ST-A BALE90.0001,575.00
60.0001,050.00
0.0000.00

0009                          L021.15 17.5096.0001,680.00
EROSION CHECKS, TYPE ST-HV BALE96.0001,680.00
72.0001,260.00
0.0000.00

0011                          L022.12 6.501,522.0009,893.00
FABRIC SILT FENCE-HIGH POROSITY m 1,522.0009,893.00
1,251.1008,132.15
0.0000.00

0012                          P500.24 34.5058.1002,004.45
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 58.1002,004.45
58.1002,004.45
0.0000.00

0013                          0030.10 14,765.211.00014,765.21
MOBILIZATION LS 1.00014,765.21
1.00014,765.21
0.0000.00

0014                          1009.00 10,000.001.00010,000.00
GENERAL CLEARING AND GRUBBING LS 1.00010,000.00
1.00010,000.00
0.0000.00

0015                          1010.00 1.1938,527.00045,847.13
EXCAVATION m3 0.0000.00
38,527.00045,847.13
0.0000.00

0016                          1010.01 2.196,445.00014,114.55
EXCAVATION (ESTABLISHED QUANTITY) m3 6,445.00014,114.55
6,445.00014,114.55
0.0000.00

0017                          1010.10 1.8975,648.000142,974.72
EXCAVATION, BORROW m3 54,441.000102,893.49
54,441.000102,893.49
0.0000.00

0018                          1011.00 1.003,783.0003,783.00
WATER kL 3,834.0003,834.00
11.80011.80
0.0000.00

0019                          1012.00 50.00110.0005,500.00
RIGHT-OF-WAY MARKERS EACH110.0005,500.00
136.0006,800.00
0.0000.00

0020                          1017.00 27,500.051.00027,500.05
CONSTRUCTION STAKING AND SURVEYING LS 1.00027,500.05
1.00027,500.05
0.0000.00

0022                          1040.05 0.385,030.0001,911.40
TEMPORARY SLOPE PROTECTION m2 5,030.0001,911.40
5,030.0001,911.40
0.0000.00

0024                          1102.00 3.50229.000801.50
REMOVE ASPHALT SURFACE m2 229.000801.50
300.3481,051.22
0.0000.00

0025                          1109.00 3.00521.6001,564.80
REMOVE CURB m 521.6001,564.80
445.1001,335.30
0.0000.00

0026                          1500.60 45.0076.2003,429.00
INSTALL 1500 mm CORRUGATED METAL PIPE m 76.2003,429.00
110.3004,963.50
0.0000.00

0027                          1500.72 50.0065.0003,250.00
INSTALL 1800 mm CORRUGATED METAL PIPE m 65.0003,250.00
31.7001,585.00
0.0000.00

0028                          1701.24 33.50433.80014,532.30
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 433.80014,532.30
471.50015,795.25
0.0000.00

0031                          7017.00 5.001,070.7005,353.50
REMOVE GUARDRAIL m 1,070.7005,353.50
1,078.3005,391.50
0.0000.00

175                           1900.02 7,148.400.0000.00
TRANSPORTATION CHARGES LS 1.0007,148.40
1.0007,148.40
0.0000.00

176                           3970.10 4,432.090.0000.00
MATERIALS LS 1.0004,432.09
Connecting Bands For Shoofly Pipes 1.0004,432.09
0.0000.00

177                           1500.48 42.000.0000.00
INSTALL 1200 mm CORRUGATED METAL PIPE m 36.5801,536.36
1200mm Culvert Pipe For Shoofly 36.5801,536.36
0.0000.00

178                           4976.05 2,231.250.0000.00
ADDITIONAL WORK LS 1.0002,231.25
Extra Work On Shoofly Culvert Pipes 1.0002,231.25
0.0000.00

4005                          1010.01 1.190.0000.00
EXCAVATION (ESTABLISHED QUANTITY) m3 38,530.00045,850.70
0.0000.00
0.0000.00

4012                          9110.06 127.000.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR16.0002,032.00
1998 Cat 330 BL Backhoe 16.0002,032.00
16.0002,032.00

4013                          9110.12 157.550.0000.00
RENTAL OF SCRAPER, FULLY OPERATED HOUR16.0002,520.80
1999 Cat 627F Scraper 16.0002,520.80
16.0002,520.80

4014                          9110.11 61.950.0000.00
RENTAL OF BULLDOZER, FULLY OPERATED HOUR16.000991.20
1999 Cat D6R LGP 16.000991.20
16.000991.20

4015                          0030.10 1.000
MOBILIZATION LS 2.0000.00
Transportation of equipment to project 1.0001,890.00
1.0001,890.00

GROUP 1 GRADINGContracted355,289.06
Current338,044.50
In place336,086.49
This Estimate7,434.00

GROUP 4 CULVERTS
0032                          P300.24 69.0020.9001,442.10
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 20.9001,442.10
21.3001,469.70
0.0000.00

0033                          P300.30 90.8042.7003,877.16
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 42.7003,877.16
40.8003,704.64
0.0000.00

0034                          P300.36 113.5037.8004,290.30
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 37.8004,290.30
39.0004,426.50
0.0000.00

0035                          P300.42 163.7043.2007,071.84
1050 mm CULVERT PIPE, TYPE 3,4 OR 5 m 43.2007,071.84
41.5006,793.55
0.0000.00

0036                          P300.48 173.908.3001,443.37
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 8.3001,443.37
8.2001,425.98
0.0000.00

0040                          P500.18 67.5027.5001,856.25
450 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 27.5001,856.25
27.5001,856.25
0.0000.00

0041                          P500.24 73.7078.5005,785.45
600 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 78.5005,785.45
78.5005,785.45
0.0000.00

0042                          P500.36 111.1053.9005,988.29
900 mm CULVERT PIPE, TYPE 2,4,5,7 OR 8 m 53.9005,988.29
24.0002,666.40
0.0000.00

0043                          0030.40 4,922.911.0004,922.91
MOBILIZATION LS 1.0004,922.91
1.0004,922.91
0.0000.00

0044                          1043.50 2.10104.000218.40
RIPRAP FILTER FABRIC m2 104.000218.40
127.830268.44
0.0000.00

0045                          4040.00 110.0033.0003,630.00
REMOVE HEADWALLS FROM CULVERTS EACH33.0003,630.00
34.0003,740.00
0.0000.00

0046                          4044.00 2,100.001.0002,100.00
PREPARATION OF STRUCTURE EACH1.0002,100.00
AT STA 125+87.352 1.0002,100.00
0.0000.00

0047                          4044.01 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 134+71.579 1.0001,800.00
0.0000.00

0048                          4044.02 2,790.001.0002,790.00
PREPARATION OF STRUCTURE EACH1.0002,790.00
AT STA 139+68.404 1.0002,790.00
0.0000.00

0049                          4044.03 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 146+65.178 1.0001,800.00
0.0000.00

0050                          4044.04 2,790.001.0002,790.00
PREPARATION OF STRUCTURE EACH1.0002,790.00
AT STA 148+11.482 1.0002,790.00
0.0000.00

0051                          4044.05 2,390.001.0002,390.00
PREPARATION OF STRUCTURE EACH1.0002,390.00
AT STA 153+38.178 1.0002,390.00
0.0000.00

0052                          4044.06 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 163+12.625 1.0001,800.00
0.0000.00

0053                          4044.07 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 180+95.404 1.0001,800.00
0.0000.00

0064                          4050.01 8.00392.0003,136.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 392.0003,136.00
390.0003,120.00
0.0000.00

0065                          4051.01 10.00251.0002,510.00
EXCAVATION FOR BOX CULVERTS m3 251.0002,510.00
266.0002,660.00
0.0000.00

0066                          4100.06 534.003.0201,612.68
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 3.0201,612.68
1.460779.64
0.0000.00

0067                          4101.06 355.00265.37094,206.35
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 265.37094,206.35
275.79997,908.66
0.0000.00

0069                          4150.00 1.50160.000240.00
REINFORCING STEEL FOR HEADWALL kg 160.000240.00
60.00090.00
0.0000.00

0070                          4151.00 1.2915,311.00019,751.19
REINFORCING STEEL FOR BOX CULVERT kg 15,311.00019,751.19
16,356.00021,099.24
0.0000.00

0071                          4310.24 160.4010.0001,604.00
600 mm FLARED-END SECTION EACH10.0001,604.00
10.0001,604.00
0.0000.00

0072                          4310.30 241.004.000964.00
750 mm FLARED-END SECTION EACH4.000964.00
4.000964.00
0.0000.00

0073                          4310.36 318.009.0002,862.00
900 mm FLARED-END SECTION EACH9.0002,862.00
7.0002,226.00
0.0000.00

0074                          4310.42 579.506.0003,477.00
1050 mm FLARED-END SECTION EACH6.0003,477.00
8.0004,636.00
0.0000.00

0075                          4310.48 656.102.0001,312.20
1200 mm FLARED-END SECTION EACH2.0001,312.20
2.0001,312.20
0.0000.00

0085                          6105.02 45.40100.0004,540.00
ROCK RIPRAP, TYPE B Mg 0.0000.00
0.0000.00
0.0000.00

0179                          6104.00 14.000.0000.00
BROKEN CONCRETE RIPRAP Mg 124.0001,736.00
124.0001,736.00
0.0000.00

174                           4670.05 157.500.0000.00
CULVERT SANDFILL m3 8.3201,310.40
Flowable Fill 8.3201,310.40
0.0000.00

GROUP 4 CULVERTSContracted194,011.49
Current192,517.89
In place193,775.96
This Estimate0.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 122+67.9
0086                          0030.40 4,000.001.0004,000.00
MOBILIZATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0087                          4051.01 33.00242.0007,986.00
EXCAVATION FOR BOX CULVERTS m3 242.0007,986.00
342.00011,286.00
0.0000.00

0088                          4101.06 325.00230.25074,831.25
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 230.25074,831.25
230.25074,831.26
0.0000.00

0089                          4151.00 1.1015,116.00016,627.60
REINFORCING STEEL FOR BOX CULVERT kg 15,116.00016,627.60
15,116.00016,627.60
0.0000.00

0090                          6040.01 4,000.001.0004,000.00
REMOVE STRUCTURE EACH1.0004,000.00
AT STA. 122+68.83 1.0004,000.00
0.0000.00

4002                          4051.20 32.500.0000.00
GRANULAR MATERIAL m3 100.0003,250.00
Granular Material for Structure Foundation at sta. 122+67 100.0003,250.00
0.0000.00

4004                          3970.05 2,054.850.0000.00
REPAIR LS 1.0002,054.85
REPAIR SHOOFLY PIPE AT STA.122+52 RT. 1.0002,054.85
0.0000.00

GROUP 4A CONCRETE BOX CULVERT AT STA. 122+67.9Contracted107,444.85
Current112,749.70
In place116,049.71
This Estimate0.00

GROUP 4B CONCRETE BOX CULVERT AT STA. 131+90.20
0091                          0030.40 4,000.001.0004,000.00
MOBILIZATION LS 1.0004,000.00
1.0004,000.00
0.0000.00

0092                          4051.01 33.00228.0007,524.00
EXCAVATION FOR BOX CULVERTS m3 228.0007,524.00
344.00011,352.00
0.0000.00

0093                          4101.06 325.00298.03096,859.75
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 298.03096,859.75
298.03096,859.75
0.0000.00

0094                          4151.00 1.1018,787.00020,665.70
REINFORCING STEEL FOR BOX CULVERT kg 18,787.00020,665.70
18,787.00020,665.70
0.0000.00

0095                          6040.01 9,000.001.0009,000.00
REMOVE STRUCTURE EACH1.0009,000.00
AT STA. 131+87.20 1.0009,000.00
0.0000.00

4003                          4051.20 32.500.0000.00
GRANULAR MATERIAL m3 116.0003,770.00
Granular Material for Structure Foundation at sta. 131+90 116.0003,770.00
0.0000.00

GROUP 4B CONCRETE BOX CULVERT AT STA. 131+90.20Contracted138,049.45
Current141,819.45
In place145,647.45
This Estimate0.00

GROUP 9 BITUMINOUS
0125                          L001.01 1,238.008.0009,904.00
SEEDING, TYPE A ha 8.0009,904.00
17.37321,507.77
0.0000.00

0126                          L001.02 799.007.0005,593.00
SEEDING, TYPE B ha 7.0005,593.00
6.7445,388.46
0.0000.00

0127                          L032.75 55.0072.0003,960.00
MULCH Mg 72.0003,960.00
108.5275,968.99
0.0000.00

0128                          P402.15 40.0066.7002,668.00
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 66.7002,668.00
70.0502,802.00
0.0000.00

0129                          0002.40 26.00552.24014,358.24
TEMPORARY SOLID LINES StaM552.24014,358.24
758.02719,708.70
0.0000.00

0130                          0002.45 23.00276.1206,350.76
TEMPORARY BROKEN LINES StaM276.1206,350.76
363.1878,353.30
0.0000.00

0131                          0030.90 21,007.301.00021,007.30
MOBILIZATION LS 1.00021,007.30
1.00021,007.30
0.0000.00

0132                          2001.00 13.75220.0003,025.00
GRAVEL SURFACE COURSE m3 220.0003,025.00
475.3366,535.88
0.0000.00

0133                          2020.00 7.50504.0003,780.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 504.0003,780.00
504.0003,780.00
0.0000.00

0134                          2021.00 50.008.000400.00
MAILBOX POST EACH8.000400.00
8.000400.00
0.0000.00

0135                          4024.55 100.008.200820.00
FLUME SPILLWAY m 8.200820.00
13.0401,304.00
0.0000.00

0136                          4024.70 2,000.003.0006,000.00
CONCRETE FLUME, TYPE I EACH3.0006,000.00
3.0006,000.00
0.0000.00

0137                          4024.73 2,000.003.0006,000.00
CONCRETE FLUME, TYPE IV EACH3.0006,000.00
3.0006,000.00
0.0000.00

0138                          4024.74 2,000.002.0004,000.00
CONCRETE FLUME, TYPE V EACH2.0004,000.00
2.0004,000.00
0.0000.00

0140                          9000.75 16.99250.0004,247.50
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 250.0004,247.50
SP1(12.5) 61.5201,045.22
0.0000.00

0141                          9005.00 26.99400.00010,796.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 400.00010,796.00
SP1(12.5) 72.2901,951.10
0.0000.00

0142                          9005.25 16.9930,040.000510,379.60
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 30,040.000510,379.60
30,582.220519,591.92
0.0000.00

0143                          9009.00 3.004,533.00013,599.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 4,533.00013,599.00
4,522.00013,566.00
0.0000.00

0144                          9009.75 24.664,792.000118,170.72
TEMPORARY SURFACING m2 4,792.000118,170.72
4,792.000118,170.72
0.0000.00

0145                          9020.91 226.0013.5003,051.00
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 13.5003,051.00
2.672603.87
0.0000.00

0146                          9021.01 226.001,643.760371,489.76
PERFORMANCE GRADED BINDER (64-22) Mg 1,643.760371,489.76
1,398.921316,156.15
0.0000.00

0147                          9030.00 9.00899.0008,091.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 899.0008,091.00
940.7008,466.30
0.0000.00

0148                          9034.00 2.501,740.0004,350.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,740.0004,350.00
1,839.0004,597.51
0.0000.00

0149                          9053.00 0.2565,370.00016,342.50
TACK COAT L 65,370.00016,342.50
127,227.97031,806.99
0.0000.00

0150                          9111.00 1.001,073.0001,073.00
WATER kL 1,073.0001,073.00
0.0000.00
0.0000.00

0151                          9170.00 165.00184.07430,372.21
EARTH SHOULDER CONSTRUCTION StaM184.07430,372.21
184.07430,372.21
0.0000.00

0152                          9173.10 85.00180.82715,370.30
SUBGRADE PREPARATION FOR WIDENING StaM180.82715,370.30
178.93215,209.22
0.0000.00

0153                          9173.20 2.50655.0001,637.50
SUBGRADE PREPARATION m2 655.0001,637.50
681.4921,703.73
0.0000.00

0154                          9179.21 205.0092.04118,868.41
COLD MILLING, CLASS 1 StaM92.04118,868.41
91.99818,859.59
0.0000.00

0157                          9300.50 2,275.041.0002,275.04
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0002,275.04
1.0002,275.04
0.0000.00

4006                          9300.56 0.5640.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 30,716.03017,323.84
Air void incentive 30,716.03017,323.84
0.0000.00

4007                          9300.60 0.790.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 8,559.2006,761.77
8,559.2006,761.77
0.0000.00

4008                          9300.77 10.550.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 427.9604,514.98
427.9604,514.98
0.0000.00

GROUP 9 BITUMINOUSContracted1,217,979.83
Current1,246,580.42
In place1,225,732.56
This Estimate0.00

GROUP 10 GENERAL ITEMS
0158                          0001.08 0.5014,981.0007,490.50
BARRICADE, TYPE II BDAY14,981.0007,490.50
6,041.0003,020.50
0.0000.00

0159                          0001.10 2.501,294.0003,235.00
BARRICADE, TYPE III BDAY1,294.0003,235.00
4,835.00012,087.50
0.0000.00

0160                          0001.30 2.50324.000810.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY324.000810.00
425.0001,062.50
0.0000.00

0161                          0001.90 0.508,062.0004,031.00
SIGN DAY EACH8,062.0004,031.00
32,408.00016,204.00
0.0000.00

0162                          0002.30 1.50500.000750.00
PAVEMENT MARKING REMOVAL m 500.000750.00
82.500123.75
0.0000.00

0163                          0002.31 1.503,100.0004,650.00
TEMPORARY PAVEMENT MARKING m 3,100.0004,650.00
0.0000.00
0.0000.00

0164                          0003.10 175.0070.00012,250.00
FLAGGING DAY 70.00012,250.00
68.50011,987.50
0.0000.00

0165                          0003.20 275.0020.0005,500.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 20.0005,500.00
23.0006,325.00
0.0000.00

0167                          0010.04 1,500.000.500750.00
FIELD OFFICE EACH0.500750.00
0.0000.00
0.0000.00

0168                          0030.00 4,095.241.0004,095.24
MOBILIZATION LS 1.0004,095.24
1.0004,095.24
0.0000.00

0169                          9110.01 60.0075.0004,500.00
RENTAL OF LOADER, FULLY OPERATED HOUR75.0004,500.00
16.500990.00
0.0000.00

0170                          9110.02 60.0030.0001,800.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR30.0001,800.00
11.500690.00
0.0000.00

0171                          9110.03 50.0075.0003,750.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR75.0003,750.00
19.000950.00
0.0000.00

0172                          9110.07 45.0075.0003,375.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR75.0003,375.00
0.0000.00
0.0000.00

0180                          0003.51 50.000.0000.00
INSTALL CONCRETE PROTECTION BARRIER m 109.0005,450.00
84.0004,200.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted56,986.74
Current62,436.74
In place61,735.99
This Estimate0.00

GROUP 1 GRADING
0002                          L020.00 1.60850.0001,360.00
EROSION CONTROL m2 850.0001,360.00
888.0001,420.80
0.0000.00

0010                          L022.11 6.50835.0005,427.50
FABRIC SILT FENCE-LOW POROSITY m 835.0005,427.50
417.2002,711.80
0.0000.00

0013                          0030.10 4,584.791.0004,584.79
MOBILIZATION LS 1.0004,584.79
1.0004,584.80
0.0000.00

0014                          1009.00 10,000.001.00010,000.00
GENERAL CLEARING AND GRUBBING LS 1.00010,000.00
1.00010,000.00
0.0000.00

0018                          1011.00 1.001,501.0001,501.00
WATER kL 1,501.0001,501.00
0.0000.00
0.0000.00

0019                          1012.00 50.0012.000600.00
RIGHT-OF-WAY MARKERS EACH12.000600.00
12.000600.00
0.0000.00

0020                          1017.00 27,499.951.00027,499.95
CONSTRUCTION STAKING AND SURVEYING LS 1.00027,499.95
1.00027,499.95
0.0000.00

0021                          1030.00 3.5023,684.00082,894.00
EARTHWORK MEASURED IN EMBANKMENT m3 23,684.00082,894.00
23,684.00082,894.00
0.0000.00

0023                          1101.00 3.50220.000770.00
REMOVE PAVEMENT m2 220.000770.00
243.340851.69
0.0000.00

0028                          1701.24 33.5011.600388.60
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 11.600388.60
0.0000.00
0.0000.00

0029                          4040.00 150.002.000300.00
REMOVE HEADWALLS FROM CULVERTS EACH2.000300.00
2.000300.00
0.0000.00

0030                          4390.30 275.002.000550.00
750 mm ROUND EQUIVALENT METAL PIPE FLARED-END SECTION EACH2.000550.00
2.000550.00
0.0000.00

0031                          7017.00 5.0030.500152.50
REMOVE GUARDRAIL m 30.500152.50
35.200176.00
0.0000.00

GROUP 1 GRADINGContracted136,028.34
Current136,028.34
In place131,589.04
This Estimate0.00

GROUP 4 CULVERTS
0032                          P300.24 69.001.00069.00
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 1.00069.00
1.500103.50
0.0000.00

0033                          P300.30 90.805.500499.40
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 5.500499.40
5.700517.56
0.0000.00

0034                          P300.36 113.5017.5001,986.25
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 17.5001,986.25
18.3002,077.05
0.0000.00

0036                          P300.48 173.9015.0002,608.50
1200 mm CULVERT PIPE, TYPE 3,4 OR 5 m 15.0002,608.50
16.2002,817.18
0.0000.00

0037                          P375.30 107.901.500161.85
750 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 3,4 OR 5 m 1.500161.85
1.500161.85
0.0000.00

0038                          P375.36 124.207.000869.40
900 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 3,4 OR 5 m 7.000869.40
11.5001,428.30
0.0000.00

0039                          P375.42 180.801.000180.80
1050 mm ROUND EQUIVALENT CULVERT PIPE, TYPE 3,4 OR 5 m 1.000180.80
1.500271.20
0.0000.00

0043                          0030.40 2,577.091.0002,577.09
MOBILIZATION LS 1.0002,577.09
1.0002,577.09
0.0000.00

0044                          1043.50 2.1077.000161.70
RIPRAP FILTER FABRIC m2 77.000161.70
83.700175.77
0.0000.00

0045                          4040.00 110.0034.0003,740.00
REMOVE HEADWALLS FROM CULVERTS EACH34.0003,740.00
34.0003,740.00
0.0000.00

0054                          4044.08 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 212+78.13 1.0001,800.00
0.0000.00

0055                          4044.09 800.001.000800.00
PREPARATION OF STRUCTURE EACH1.000800.00
AT STA 228+37.50 1.000800.00
0.0000.00

0056                          4044.10 2,990.001.0002,990.00
PREPARATION OF STRUCTURE EACH1.0002,990.00
AT STA 232+86.77 1.0002,990.00
0.0000.00

0057                          4044.11 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 238+87.22 1.0001,800.00
0.0000.00

0058                          4044.12 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 244+38 1.0001,800.00
0.0000.00

0059                          4044.13 800.001.000800.00
PREPARATION OF STRUCTURE EACH1.000800.00
AT STA 255+65.50 1.000800.00
0.0000.00

0060                          4044.14 800.001.000800.00
PREPARATION OF STRUCTURE EACH1.000800.00
AT STA 262+24.10 1.000800.00
0.0000.00

0061                          4044.15 1,200.001.0001,200.00
PREPARATION OF STRUCTURE EACH1.0001,200.00
AT STA 301+56.10 1.0001,200.00
0.0000.00

0062                          4044.16 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA 332+20.80 1.0001,800.00
0.0000.00

0063                          4044.17 1,000.001.0001,000.00
PREPARATION OF STRUCTURE EACH1.0001,000.00
AT STA 333+04 1.0001,000.00
0.0000.00

0064                          4050.01 8.0018.000144.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 18.000144.00
17.000136.00
0.0000.00

0065                          4051.01 10.00114.0001,140.00
EXCAVATION FOR BOX CULVERTS m3 114.0001,140.00
114.0001,140.00
0.0000.00

0066                          4100.06 534.004.2002,242.80
CLASS 47B-20 OR AX-20 CONCRETE FOR HEADWALL m3 4.2002,242.80
4.2002,242.80
0.0000.00

0067                          4101.06 355.00110.25039,138.75
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 110.25039,138.75
107.07538,011.63
0.0000.00

0068                          4107.07 534.005.1102,728.74
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 5.1102,728.74
3.2301,724.82
0.0000.00

0069                          4150.00 1.50274.000411.00
REINFORCING STEEL FOR HEADWALL kg 274.000411.00
274.000411.00
0.0000.00

0070                          4151.00 1.297,011.0009,044.19
REINFORCING STEEL FOR BOX CULVERT kg 7,011.0009,044.19
6,723.0008,672.67
0.0000.00

0076                          4360.24 161.008.0001,288.00
600 mm METAL FLARED-END SECTION EACH8.0001,288.00
8.0001,288.00
0.0000.00

0077                          4360.30 241.005.0001,205.00
750 mm METAL FLARED-END SECTION EACH5.0001,205.00
5.0001,205.00
0.0000.00

0078                          4360.36 326.505.0001,632.50
900 mm METAL FLARED-END SECTION EACH5.0001,632.50
1.000326.50
0.0000.00

0079                          4360.48 656.102.0001,312.20
1200 mm METAL FLARED-END SECTION EACH2.0001,312.20
2.0001,312.20
0.0000.00

0080                          4390.18 138.002.000276.00
450 mm ROUND EQUIVALENT METAL PIPE FLARED-END SECTION EACH2.000276.00
2.000276.00
0.0000.00

0081                          4390.30 274.203.000822.60
750 mm ROUND EQUIVALENT METAL PIPE FLARED-END SECTION EACH3.000822.60
3.000822.60
0.0000.00

0082                          4390.42 560.102.0001,120.20
1050 mm ROUND EQUIVALENT METAL PIPE FLARED-END SECTION EACH2.0001,120.20
2.0001,120.20
0.0000.00

0083                          4390.48 560.106.0003,360.60
1200 mm ROUND EQUIVALENT METAL PIPE FLARED-END SECTION EACH6.0003,360.60
6.0003,360.60
0.0000.00

0084                          6104.00 14.0074.0001,036.00
BROKEN CONCRETE RIPRAP Mg 74.0001,036.00
82.0001,148.00
0.0000.00

173                           4390.36 446.250.0000.00
900 mm ROUND EQUIVALENT METAL PIPE FLARED-END SECTION EACH2.000892.50
2.000892.50
0.0000.00

GROUP 4 CULVERTSContracted94,546.57
Current95,439.07
In place92,750.02
This Estimate0.00

GROUP 4C CULVERT AT STA. 272+99.5
0096                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0097                          4044.00 7,000.001.0007,000.00
PREPARATION OF STRUCTURE EACH1.0007,000.00
AT STA. 272+99.5 1.0007,000.00
0.0000.00

0098                          4051.01 10.0063.000630.00
EXCAVATION FOR BOX CULVERTS m3 63.000630.00
63.000630.00
0.0000.00

0099                          4101.06 355.0088.22031,318.10
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 88.22031,318.10
88.22031,318.11
0.0000.00

0100                          4151.00 1.295,209.0006,719.61
REINFORCING STEEL FOR BOX CULVERT kg 5,209.0006,719.61
5,209.0006,719.61
0.0000.00

GROUP 4C CULVERT AT STA. 272+99.5Contracted48,167.71
Current48,167.71
In place48,167.72
This Estimate0.00

GROUP 6 BRIDGE AT STA. 320+48.195
0101                          0030.60 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0102                          1030.00 4.202,700.00011,340.00
EARTHWORK MEASURED IN EMBANKMENT m3 2,700.00011,340.00
2,700.00011,340.00
0.0000.00

0103                          1043.50 3.0075.000225.00
RIPRAP FILTER FABRIC m2 75.000225.00
87.360262.08
0.0000.00

0104                          3050.15 270.00117.50031,725.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 117.50031,725.00
117.50031,725.00
0.0000.00

0105                          3051.10 1.307,685.0009,990.50
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 7,685.0009,990.50
7,685.0009,990.50
0.0000.00

0106                          6000.10 1,500.001.0001,500.00
ABUTMENT NO.1 EXCAVATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0107                          6000.11 1,500.001.0001,500.00
ABUTMENT NO.2 EXCAVATION LS 1.0001,500.00
1.0001,500.00
0.0000.00

0108                          6007.01 60.00125.0007,500.00
CLASS I REPAIR m2 125.0007,500.00
125.0007,500.00
0.0000.00

0109                          6007.02 250.0025.0006,250.00
CLASS II REPAIR m2 25.0006,250.00
24.2716,067.75
0.0000.00

0110                          6007.03 275.005.0001,375.00
CLASS III REPAIR m2 5.0001,375.00
0.0000.00
0.0000.00

0111                          6008.40 60.00180.00010,800.00
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 180.00010,800.00
180.00010,800.00
0.0000.00

0112                          6010.22 675.0023.00015,525.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 23.00015,525.00
23.00015,525.01
0.0000.00

0113                          6010.26 690.0023.90016,491.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 23.90016,491.00
23.90016,491.00
0.0000.00

0114                          6016.02 875.0011.0009,625.00
CONCRETE FOR OVERLAYS-SF m3 11.0009,625.00
16.44014,385.00
0.0000.00

0115                          6030.00 6,000.001.0006,000.00
PREPARATION OF BRIDGE EACH1.0006,000.00
AT STA. 320+48.195 1.0006,000.00
0.0000.00

0116                          6105.02 45.00188.0008,460.00
ROCK RIPRAP, TYPE B Mg 188.0008,460.00
180.8858,139.83
0.0000.00

0117                          6131.50 1.407,075.0009,905.00
EPOXY COATED REINFORCING STEEL kg 7,085.0009,919.00
7,085.0009,919.00
0.0000.00

0118                          6200.00 110.00192.10021,131.00
CONCRETE PILING m 192.10021,131.00
169.15518,607.05
0.0000.00

0119                          6510.55 6,500.001.0006,500.00
TEMPORARY BRIDGE SHORING LS 1.0006,500.00
1.0006,500.00
0.0000.00

0120                          8091.00 23.0040.000920.00
GRANULAR BACKFILL m3 40.000920.00
40.000920.00
0.0000.00

4001                          6200.50 66.000.0000.00
PAY CUT-OFF FOR CONCRETE PILING m 22.9251,513.05
1997 Metric Spec. 703.05, para. 2 22.9251,513.05
0.0000.00

GROUP 6 BRIDGE AT STA. 320+48.195Contracted191,762.50
Current193,289.55
In place193,685.27
This Estimate0.00

GROUP 7 GUARDRAIL
0121                          0030.70 1,750.001.0001,750.00
MOBILIZATION LS 1.0001,750.00
1.0001,750.00
0.0000.00

0122                          7011.20 56.0049.5302,773.68
W-BEAM GUARDRAIL m 49.5302,773.68
49.5302,773.68
0.0000.00

0123                          7020.00 1,250.004.0005,000.00
BRIDGE APPROACH SECTIONS EACH4.0005,000.00
4.0005,000.00
0.0000.00

0124                          7021.70 1,600.004.0006,400.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0006,400.00
4.0006,400.00
0.0000.00

GROUP 7 GUARDRAILContracted15,923.68
Current15,923.68
In place15,923.68
This Estimate0.00

GROUP 9 BITUMINOUS
0126                          L001.02 799.0014.00011,186.00
SEEDING, TYPE B ha 14.00011,186.00
38.57230,819.03
0.0000.00

0127                          L032.75 55.0070.0003,850.00
MULCH Mg 70.0003,850.00
178.7209,829.60
0.0000.00

0129                          0002.40 26.001,128.06029,329.56
TEMPORARY SOLID LINES StaM1,128.06029,329.56
1,090.15028,343.90
0.0000.00

0130                          0002.45 23.00564.03012,972.69
TEMPORARY BROKEN LINES StaM564.03012,972.69
551.53812,685.38
0.0000.00

0131                          0030.90 25,492.701.00025,492.70
MOBILIZATION LS 1.00025,492.70
1.00025,492.70
0.0000.00

0132                          2001.00 13.75288.0003,960.00
GRAVEL SURFACE COURSE m3 288.0003,960.00
348.4814,791.61
0.0000.00

0133                          2020.00 7.50718.0005,385.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 718.0005,385.00
718.0005,385.00
0.0000.00

0134                          2021.00 50.0017.000850.00
MAILBOX POST EACH17.000850.00
22.0001,100.00
0.0000.00

0139                          8029.75 4.75928.0004,408.00
BITUMINOUS FOUNDATION COURSE m2 928.0004,408.00
1,213.3725,763.52
0.0000.00

0140                          9000.75 16.99500.0008,495.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.0008,495.00
SP1(12.5) 1,982.13033,676.39
0.0000.00

0141                          9005.00 26.99500.00013,495.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 500.00013,495.00
SP1(12.5) 7.000188.93
0.0000.00

0142                          9005.25 16.9946,830.000795,641.70
ASPHALTIC CONCRETE, TYPE SP1(12.5) Mg 46,830.000795,641.70
47,388.350805,128.06
0.0000.00

0143                          9009.00 3.005,074.00015,222.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 5,074.00015,222.00
5,166.00015,498.00
0.0000.00

0144                          9009.75 24.66158.0003,896.28
TEMPORARY SURFACING m2 158.0003,896.28
254.2266,269.21
0.0000.00

0145                          9020.91 226.0026.0005,876.00
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 26.0005,876.00
89.49020,224.74
0.0000.00

0146                          9021.01 226.002,461.160556,222.16
PERFORMANCE GRADED BINDER (64-22) Mg 2,461.160556,222.16
2,105.475475,837.36
0.0000.00

0148                          9034.00 2.504,248.00010,620.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 4,248.00010,620.00
4,415.00011,037.50
0.0000.00

0149                          9053.00 0.25130,010.00032,502.50
TACK COAT L 130,010.00032,502.50
190,123.13247,530.79
0.0000.00

0150                          9111.00 1.001,135.0001,135.00
WATER kL 1,135.0001,135.00
0.0000.00
0.0000.00

0151                          9170.00 165.00374.13361,731.95
EARTH SHOULDER CONSTRUCTION StaM374.13361,731.95
374.13361,731.95
0.0000.00

0152                          9173.10 85.00347.00829,495.68
SUBGRADE PREPARATION FOR WIDENING StaM347.00829,495.68
349.64029,719.40
0.0000.00

0153                          9173.20 2.50928.0002,320.00
SUBGRADE PREPARATION m2 928.0002,320.00
1,213.3723,033.43
0.0000.00

0155                          9179.23 240.00189.42345,461.52
COLD MILLING, CLASS 3 StaM189.42345,461.52
189.16345,399.12
0.0000.00

0156                          9188.50 25.00219.0005,475.00
SURFACING UNDER GUARDRAIL m2 219.0005,475.00
219.0005,475.00
0.0000.00

0157                          9300.50 5,724.961.0005,724.96
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0005,724.96
1.0005,724.96
0.0000.00

4009                          9300.56 0.5860.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 49,377.48028,935.20
49,377.48028,935.20
0.0000.00

4010                          9300.60 0.760.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 17,601.88013,377.43
17,601.88013,377.43
0.0000.00

4011                          9300.77 10.170.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 880.0908,950.52
880.0908,950.52
0.0000.00

GROUP 9 BITUMINOUSContracted1,690,748.69
Current1,742,011.84
In place1,741,948.73
This Estimate0.00

GROUP 10 GENERAL ITEMS
0158                          0001.08 0.5014,370.0007,185.00
BARRICADE, TYPE II BDAY14,370.0007,185.00
4,280.0002,140.00
0.0000.00

0159                          0001.10 2.501,278.0003,195.00
BARRICADE, TYPE III BDAY1,278.0003,195.00
3,009.0007,522.50
0.0000.00

0160                          0001.30 2.50510.0001,275.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY510.0001,275.00
545.0001,362.50
0.0000.00

0161                          0001.90 0.5018,469.0009,234.50
SIGN DAY EACH18,469.0009,234.50
30,283.00015,141.50
0.0000.00

0162                          0002.30 1.50140.000210.00
PAVEMENT MARKING REMOVAL m 140.000210.00
31.50047.25
0.0000.00

0163                          0002.31 1.50320.000480.00
TEMPORARY PAVEMENT MARKING m 320.000480.00
604.600906.90
0.0000.00

0164                          0003.10 175.00100.00017,500.00
FLAGGING DAY 100.00017,500.00
95.50016,712.50
0.0000.00

0165                          0003.20 275.0040.00011,000.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 40.00011,000.00
34.0009,350.00
0.0000.00

0166                          0003.51 50.00150.0007,500.00
INSTALL CONCRETE PROTECTION BARRIER m 150.0007,500.00
126.0006,300.00
0.0000.00

0167                          0010.04 1,500.000.500750.00
FIELD OFFICE EACH0.500750.00
0.0000.00
0.0000.00

0168                          0030.00 5,904.761.0005,904.76
MOBILIZATION LS 1.0005,904.76
1.0005,904.76
0.0000.00

0169                          9110.01 60.0085.0005,100.00
RENTAL OF LOADER, FULLY OPERATED HOUR85.0005,100.00
15.500930.00
0.0000.00

0170                          9110.02 60.0060.0003,600.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR60.0003,600.00
0.0000.00
0.0000.00

0171                          9110.03 50.0085.0004,250.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR85.0004,250.00
5.500275.00
0.0000.00

0172                          9110.07 45.0085.0003,825.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR85.0003,825.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted81,009.26
Current81,009.26
In place66,592.91
This Estimate0.00

Totals for contractContracted4,327,948.17
Current4,404,128.15
In place4,369,685.53
This Estimate7,434.00