Estimate Summary to Contractor | |
Vendor ID: | 1587 NEBRASKA HYDRO-SEEDING CO. |
Contract ID: | 3840B1 |
Estimate Number: | 0005 |
Pay Period End Date: | 10.25.2002 |
Contract Location: | ||
WINSIDE SOUTH | Estimate Type: | FINL |
Contractor: | ||
NEBRASKA HYDRO-SEEDING CO. | Date Let: | 08.16.2001 |
19411 SCHRAM RD | Date Awarded: | 08.23.2001 |
Date Contract Executed: | 08.30.2001 | |
Date Notice to Proceed: | 08.30.2001 | |
GRETNA NE 68028 | Date Work Began: | 07.23.2002 |
Phone: | Date Physical Work Completed: | |
(402)332-3310 | Date Accepted: | 08.28.2002 |
Escrow Agent: | ||
Surety Co: | ||
INLAND INSURANCE COMPANY |
Counties |
---|
WAYNE |
Project Number |   | PCT |   | Fed State Project Number |   | Description | |
---|---|---|---|---|---|---|---|
30840B1001 |   | 0.000 |   | S-35-4(1012) |   | SEEDING |
Total to Date | Prev to Date | This Estimate | ||
Current Contract Amt | Total Earnings | $93,044.30 | $93,044.30 | $.00 |
$84,271.40 | Stockpiled Materials | $.00 | $.00 | $.00 |
Original Contract Amt | Gross Earnings | $93,044.30 | $93,044.30 | $.00 |
$81,271.40 | Retainage | $.00 | $-930.44 | $930.44 |
Escrow Amount | $.00 | $.00 | $.00 | |
Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
110.41% | Net Earnings | $93,044.30 | $92,113.86 | $930.44 |
Liquidated Damages | $.00 | $.00 | $.00 | |
Incentives | $.00 | $.00 | $.00 | |
Disincentives | $.00 | $.00 | $.00 | |
Other Contract Adj | $.00 | $.00 | $.00 | |
Appl of Training Adj | $.00 | $.00 | $.00 | |
Training Rates Adj | $.00 | $.00 | $.00 | |
Fuel Adj | $.00 | $.00 | $.00 | |
Bituminous Adj | $.00 | $.00 | $.00 | |
Autopay Adj | $.00 | $.00 | $.00 | |
Gasoline Adj | $.00 | $.00 | $.00 | |
Other Adj | $.00 | $.00 | $.00 | |
Price Adj | $.00 | $.00 | $.00 | |
Substandard Item Adj | $.00 | $.00 | $.00 | |
Asphalt Adj | $.00 | $.00 | $.00 | |
Diesel Fuel Adj | $.00 | $.00 | $.00 | |
Petrol Adj | $.00 | $.00 | $.00 | |
Total for Adjustments | $.00 | $.00 | $.00 | |
Payment | $93,044.30 | $92,113.86 | $930.44 | |
Project Manager | Div. Head/Dist. Eng. | |||
Mueting, Curt | 12.02.2002 | Boyle, Pat | 02.07.2003 | |
Constr. Estimate Eng. | Materials Eng. | |||
Davis, Carl | 02.10.2003 | Hall, David | 02.10.2003 | |
Controller Div. Processed | ||||
Harring, Joyce | 02.18.2003 |
Detailed breakdown of stockpiled materials | ||||
---|---|---|---|---|
Total remaining for contract: | 0.00 |
1. Contracted | |||
---|---|---|---|
2. Current | |||
3. To date | |||
Item Nbr Item Code | Unit Price | 4. This Est | |
Item Description | Units | Qty | Amount |
GROUP 5 SEEDING | |||
0001 L001.01 | 520.00 | 102.000 | 53,040.00 |
SEEDING, TYPE A | ACRE | 102.000 | 53,040.00 |
127.100 | 66,092.00 | ||
0.000 | 0.00 | ||
0002 L001.02 | 380.00 | 18.000 | 6,840.00 |
SEEDING, TYPE B | ACRE | 18.000 | 6,840.00 |
13.600 | 5,168.00 | ||
0.000 | 0.00 | ||
0003 L020.02 | 1.80 | 1,223.000 | 2,201.40 |
EROSION CONTROL, TYPE B | SY | 1,223.000 | 2,201.40 |
480.000 | 864.00 | ||
0.000 | 0.00 | ||
0004 L032.75 | 65.00 | 270.000 | 17,550.00 |
MULCH | TON | 270.000 | 17,550.00 |
279.820 | 18,188.30 | ||
0.000 | 0.00 | ||
0005 0001.75 | 18.00 | 80.000 | 1,440.00 |
TEMPORARY SIGN DAY | EACH | 80.000 | 1,440.00 |
24.000 | 432.00 | ||
0.000 | 0.00 | ||
0006 0030.50 | 200.00 | 1.000 | 200.00 |
MOBILIZATION | LS | 1.000 | 200.00 |
1.000 | 200.00 | ||
0.000 | 0.00 | ||
0401 9110.80 | 75.00 | 0.000 | 0.00 |
RENTAL | HOUR | 40.000 | 3,000.00 |
Tractor and 15' Batwing Mower | 28.000 | 2,100.00 | |
0.000 | 0.00 | ||
GROUP 5 SEEDING | Contracted | 81,271.40 | |
Current | 84,271.40 | ||
In place | 93,044.30 | ||
This Estimate | 0.00 | ||
Totals for contract | Contracted | 81,271.40 | |
Current | 84,271.40 | ||
In place | 93,044.30 | ||
This Estimate | 0.00 |