Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0875 BROWER CONSTRUCTION CO.
Contract ID:3532
Estimate Number:0003
Pay Period End Date:06.01.2002
Contract Location:
MASKELL - NEWCASTLEEstimate Type:PROG
Contractor:
BROWER CONSTRUCTION CO.Date Let:12.06.2001
2220 HAWKEYE DRIVEDate Awarded:12.18.2001
PO BOX 1137Date Contract Executed:01.15.2002
Date Notice to Proceed:01.15.2002
SIOUX CITY IA 51102Date Work Began:
Phone:Date Physical Work Completed:
(712)252-2766Date Accepted:
Escrow Agent:
Surety Co:
FEDERAL INSURANCE COMPANY
Counties
DAKOTA
DIXON
Project Number PCT Fed State Project Number Description
31532 000  0.000 S-12-6(1010)  BITUMINOUS
31571 000  0.000 PEP-20-6(1012)  BITUMINOUS
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$1,249,602.78$452,231.47$797,371.31
$1,554,109.03Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$1,249,602.78$452,231.47$797,371.31
$1,534,978.45Retainage$-12,496.03$-4,522.31$-7,973.72
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
80.41%Net Earnings$1,237,106.75$447,709.16$789,397.59
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$.00$.00$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$.00$.00$.00
Payment$1,237,106.75$447,709.16$789,397.59
Project ManagerDiv. Head/Dist. Eng.
Wiebelhaus, Bob06.04.2002Boyle, Pat06.06.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve06.06.2002
Controller Div. Processed
Burling, Laurie06.06.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 9 BITUMINOUS
0001                          L001.02 806.993.0002,420.97
SEEDING, TYPE B ACRE3.0002,420.97
0.0000.00
0.0000.00

0002                          L032.75 70.707.000494.90
MULCH TON 7.000494.90
0.0000.00
0.0000.00

0003                          0001.10 1.50100.000150.00
BARRICADE, TYPE III BDAY100.000150.00
204.000306.00
150.000225.00

0004                          0001.30 1.5050.00075.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY50.00075.00
68.000102.00
50.00075.00

0005                          0001.75 2.00210.000420.00
TEMPORARY SIGN DAY EACH210.000420.00
32.00064.00
24.00048.00

0006                          0001.90 0.251,125.000281.25
SIGN DAY EACH1,125.000281.25
1,522.000380.50
1,133.000283.25

0007                          0002.55 5.25327.3201,718.43
OVERLAY BROKEN LINES STA 327.3201,718.43
49.410259.40
49.410259.40

0008                          0002.60 5.25654.6403,436.86
OVERLAY SOLID LINES STA 654.6403,436.86
94.570496.49
94.570496.49

0009                          0003.10 205.0030.0006,150.00
FLAGGING DAY 30.0006,150.00
25.5005,227.50
17.5003,587.50

0010                          0003.20 305.005.0001,525.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 5.0001,525.00
12.0003,660.00
8.0002,440.00

0011                          0010.04 2,500.000.5001,250.00
FIELD OFFICE EACH0.5001,250.00
0.0000.00
0.0000.00

0012                          0030.90 36,982.231.00036,982.23
MOBILIZATION LS 1.00036,982.23
1.00036,982.23
1.00036,982.23

0013                          1020.01 25.0015.000375.00
DELINEATOR, TYPE I EACH15.000375.00
15.000375.00
0.0000.00

0014                          1021.00 25.0085.0002,125.00
REMOVE AND RESET DELINEATORS EACH85.0002,125.00
0.0000.00
0.0000.00

0015                          4764.35 5.317,983.00042,389.73
4" PERFORATED PIPE UNDERDRAIN LF 7,983.00042,389.73
7,402.00039,304.62
421.0002,235.51

0017                          9000.75 17.46100.0001,746.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE TON 100.0001,746.00
SP2(0.5) 0.0000.00
0.0000.00

0018                          9005.00 65.9550.0003,297.50
ASPHALTIC CONCRETE FOR PATCHING, TYPE TON 50.0003,297.50
SP2(0.5) 569.23037,540.72
569.23037,540.72

0021                          9005.30 17.4610,270.000179,314.20
ASPHALTIC CONCRETE, TYPE SP2(0.5) TON 10,270.000179,314.20
0.0000.00
0.0000.00

0023                          9020.91 154.795.400835.87
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING TON 5.400835.87
0.0000.00
0.0000.00

0025                          9021.01 154.79557.28086,261.37
PERFORMANCE GRADED BINDER (64-22) TON 0.0000.00
22.4363,472.87
22.4363,472.87

0027                          9053.00 0.7211,460.0008,251.20
TACK COAT GAL 11,460.0008,251.20
0.0000.00
0.0000.00

0028                          9110.01 65.0010.000650.00
RENTAL OF LOADER, FULLY OPERATED HOUR10.000650.00
26.7501,738.75
26.7501,738.75

0029                          9110.02 65.0010.000650.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000650.00
20.0001,300.00
20.0001,300.00

0030                          9110.03 35.0010.000350.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR10.000350.00
50.7501,776.25
50.7501,776.25

0031                          9110.07 50.0010.000500.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR10.000500.00
39.0001,950.00
39.0001,950.00

0032                          9111.00 8.00123.000984.00
WATER MGAL123.000984.00
0.0000.00
0.0000.00

0033                          9170.00 41.71490.63620,464.43
EARTH SHOULDER CONSTRUCTION STA 490.63620,464.43
0.0000.00
0.0000.00

0034                          9179.23 124.4047.1615,866.83
COLD MILLING, CLASS 3 STA 47.1615,866.83
49.4606,152.82
49.4606,152.82

0402                          9022.01 165.290.0000.00
ANTI-STRIPPING ADDITIVE TON 557.28092,112.81
Maskell to Newcastle SP2 Asph. Conc. (64-22)Anti strip additive premixed with PG Binder (.25% appl rate) 0.0000.00
0.0000.00

0003                          0001.10 1.50332.000498.00
BARRICADE, TYPE III BDAY332.000498.00
238.000357.00
98.000147.00

0004                          0001.30 1.50166.000249.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY166.000249.00
102.000153.00
42.00063.00

0005                          0001.75 2.001,300.0002,600.00
TEMPORARY SIGN DAY EACH1,300.0002,600.00
180.000360.00
98.000196.00

0006                          0001.90 0.257,802.0001,950.50
SIGN DAY EACH7,802.0001,950.50
5,272.0001,318.00
1,911.000477.75

0007                          0002.55 5.251,460.0007,665.00
OVERLAY BROKEN LINES STA 1,460.0007,665.00
1,706.1238,957.15
858.7634,508.51

0008                          0002.60 5.251,920.00010,080.00
OVERLAY SOLID LINES STA 1,920.00010,080.00
2,125.80011,160.45
565.1302,966.93

0009                          0003.10 205.00100.00020,500.00
FLAGGING DAY 100.00020,500.00
70.00014,350.00
23.5004,817.50

0010                          0003.20 305.0017.0005,185.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 17.0005,185.00
29.0008,845.00
10.0003,050.00

0011                          0010.04 2,500.000.5001,250.00
FIELD OFFICE EACH0.5001,250.00
0.0000.00
0.0000.00

0012                          0030.90 72,979.531.00072,979.53
MOBILIZATION LS 1.00072,979.53
1.00072,979.53
0.0000.00

0016                          9000.74 14.12100.0001,412.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE TON 100.0001,412.00
SPS 0.0000.00
0.0000.00

0019                          9005.01 66.05100.0006,605.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE TON 100.0006,605.00
SP4(0.5) 2,063.540136,296.82
203.97013,472.22

0020                          9005.23 14.129,200.000129,904.00
ASPHALTIC CONCRETE, TYPE SPS TON 9,200.000129,904.00
4,629.02065,361.76
4,629.02065,361.76

0022                          9005.45 17.1023,320.000398,772.00
ASPHALTIC CONCRETE, TYPE SP4(0.5) TON 23,320.000398,772.00
23,533.580402,424.22
22,519.800385,088.58

0024                          9020.92 154.795.400835.87
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING TON 5.400835.87
0.0000.00
0.0000.00

0025                          9021.01 154.791,264.680195,759.82
PERFORMANCE GRADED BINDER (64-22) TON 0.0000.00
0.0000.00
-128.073-19,824.42

0026                          9021.03 154.79496.80076,899.67
PERFORMANCE GRADED BINDER (58-28) TON 496.80076,899.67
147.21922,788.03
147.21922,788.03

0027                          9053.00 0.7250,210.00036,151.20
TACK COAT GAL 50,210.00036,151.20
25,867.00018,624.24
24,467.00017,616.24

0028                          9110.01 65.0070.0004,550.00
RENTAL OF LOADER, FULLY OPERATED HOUR70.0004,550.00
41.5002,697.50
0.0000.00

0029                          9110.02 65.0070.0004,550.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR70.0004,550.00
38.2502,486.25
4.500292.50

0030                          9110.03 35.0070.0002,450.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR70.0002,450.00
134.5004,707.50
8.000280.00

0031                          9110.07 50.0070.0003,500.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR70.0003,500.00
137.2506,862.50
29.0001,450.00

0034                          9179.23 124.40777.46696,716.77
COLD MILLING, CLASS 3 STA 777.46696,716.77
804.750100,110.90
99.38012,362.87

0035                          9179.43 63.49707.97544,949.33
COLD MILLING, CLASS 3 STA 707.97544,949.33
A 724.22045,980.73
0.0000.00

0401                          9022.01 165.290.0000.00
ANTI-STRIPPING ADDITIVE TON 1,264.680209,038.96
Jackson West SP4 Asph.Conc. (64-22)Anti strip additive, premixed with PG Binder (.25% app rate) 1,099.238181,693.05
1,099.238181,693.05

GROUP 9 BITUMINOUSContracted1,534,978.45
Current1,554,109.03
In place1,249,602.78
This Estimate797,371.31

Totals for contractContracted1,534,978.45
Current1,554,109.03
In place1,249,602.78
This Estimate797,371.31