| Nebraska Department of Roads | |
|---|---|
| Estimate Summary to Contractor | |
| Vendor ID: | 0880 CHRISTENSEN BROS., INC. |
| Contract ID: | 3508 |
| Estimate Number: | 0003 |
| Pay Period End Date: | 05.18.2002 |
| Contract Location: | ||
| FORDYCE SPUR | Estimate Type: | PROG |
| Contractor: | ||
| CHRISTENSEN BROS., INC. | Date Let: | 12.06.2001 |
| 644 RIVER ROAD | Date Awarded: | 12.18.2001 |
| PO BOX 478 | Date Contract Executed: | 01.11.2002 |
| Date Notice to Proceed: | 01.11.2002 | |
| CHEROKEE IA 51012 | Date Work Began: | 04.15.2002 |
| Phone: | Date Physical Work Completed: | |
| (712)225-6146 | Date Accepted: | |
| Escrow Agent: | ||
| Surety Co: | ||
| NATIONAL FIRE INSURANCE COMPANY OF HARTFORD |
| Counties |
|---|
| CEDAR |
| Project Number |   | PCT |   | Fed State Project Number |   | Description | |
|---|---|---|---|---|---|---|---|
| 31508 000 |   | 0.000 |   | STR-S14A(1002) |   | BRIDGE |
| Total to Date | Prev to Date | This Estimate | ||
| Current Contract Amt | Total Earnings | $140,767.67 | $81,839.47 | $58,928.20 |
| $144,994.20 | Stockpiled Materials | $.00 | $.00 | $.00 |
| Original Contract Amt | Gross Earnings | $140,767.67 | $81,839.47 | $58,928.20 |
| $144,994.20 | Retainage | $-1,407.68 | $-818.39 | $-589.29 |
| Escrow Amount | $.00 | $.00 | $.00 | |
| Percent Complete | Securities Encumbered | $.00 | $.00 | $.00 |
| 97.09% | Net Earnings | $139,359.99 | $81,021.08 | $58,338.91 |
| Liquidated Damages | $.00 | $.00 | $.00 | |
| Incentives | $.00 | $.00 | $.00 | |
| Disincentives | $.00 | $.00 | $.00 | |
| Other Contract Adj | $.00 | $.00 | $.00 | |
| Appl of Training Adj | $.00 | $.00 | $.00 | |
| Training Rates Adj | $.00 | $.00 | $.00 | |
| Fuel Adj | $.00 | $.00 | $.00 | |
| Bituminous Adj | $.00 | $.00 | $.00 | |
| Autopay Adj | $.00 | $.00 | $.00 | |
| Gasoline Adj | $.00 | $.00 | $.00 | |
| Other Adj | $.00 | $.00 | $.00 | |
| Price Adj | $.00 | $.00 | $.00 | |
| Substandard Item Adj | $.00 | $.00 | $.00 | |
| Asphalt Adj | $.00 | $.00 | $.00 | |
| Diesel Fuel Adj | $.00 | $.00 | $.00 | |
| Petrol Adj | $.00 | $.00 | $.00 | |
| Total for Adjustments | $.00 | $.00 | $.00 | |
| Payment | $139,359.99 | $81,021.08 | $58,338.91 | |
| Project Manager | Div. Head/Dist. Eng. | |||
| Becker, Roger | 05.21.2002 | Boyle, Pat | 05.21.2002 | |
| Constr. Estimate Eng. | Materials Eng. | |||
| Bartos, Steve | 05.22.2002 | |||
| Controller Div. Processed | ||||
| Burling, Laurie | 05.22.2002 |
| Detailed breakdown of stockpiled materials | ||||
|---|---|---|---|---|
| Total remaining for contract: | 0.00 |
| 1. Contracted | |||
|---|---|---|---|
| 2. Current | |||
| 3. To date | |||
| Item Nbr Item Code | Unit Price | 4. This Est | |
| Item Description | Units | Qty | Amount |
| GROUP 6 BRIDGE AT STA. 93+60.00 | |||
| 0001 L020.00 | 2.50 | 1,028.000 | 2,570.00 |
| EROSION CONTROL | SY | 1,028.000 | 2,570.00 |
| 0.000 | 0.00 | ||
| 0.000 | 0.00 | ||
| 0002 0001.08 | 0.50 | 250.000 | 125.00 |
| BARRICADE, TYPE II | BDAY | 250.000 | 125.00 |
| 884.000 | 442.00 | ||
| 416.000 | 208.00 | ||
| 0003 0001.10 | 3.00 | 118.000 | 354.00 |
| BARRICADE, TYPE III | BDAY | 118.000 | 354.00 |
| 102.000 | 306.00 | ||
| 48.000 | 144.00 | ||
| 0004 0001.30 | 3.00 | 68.000 | 204.00 |
| TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 68.000 | 204.00 |
| 68.000 | 204.00 | ||
| 32.000 | 96.00 | ||
| 0005 0001.90 | 1.20 | 958.000 | 1,149.60 |
| SIGN DAY | EACH | 958.000 | 1,149.60 |
| 665.000 | 798.00 | ||
| 304.000 | 364.80 | ||
| 0006 0003.10 | 160.00 | 20.000 | 3,200.00 |
| FLAGGING | DAY | 20.000 | 3,200.00 |
| 1.000 | 160.00 | ||
| 1.000 | 160.00 | ||
| 0007 0030.60 | 14,000.00 | 1.000 | 14,000.00 |
| MOBILIZATION | LS | 1.000 | 14,000.00 |
| 1.000 | 14,000.00 | ||
| 0.000 | 0.00 | ||
| 0008 1009.00 | 3,000.00 | 1.000 | 3,000.00 |
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 3,000.00 |
| 1.000 | 3,000.00 | ||
| 1.000 | 3,000.00 | ||
| 0009 1033.00 | 940.00 | 4.940 | 4,643.60 |
| ROADWAY GRADING | STA | 4.940 | 4,643.60 |
| 2.840 | 2,669.60 | ||
| 2.840 | 2,669.60 | ||
| 0010 6007.01 | 20.00 | 1,124.000 | 22,480.00 |
| CLASS I REPAIR | SY | 1,124.000 | 22,480.00 |
| 1,021.132 | 20,422.64 | ||
| 450.000 | 9,000.00 | ||
| 0011 6007.02 | 90.00 | 299.000 | 26,910.00 |
| CLASS II REPAIR | SY | 299.000 | 26,910.00 |
| 270.603 | 24,354.27 | ||
| 123.340 | 11,100.60 | ||
| 0012 6007.03 | 200.00 | 5.000 | 1,000.00 |
| CLASS III REPAIR | SY | 5.000 | 1,000.00 |
| 0.827 | 165.40 | ||
| 0.000 | 0.00 | ||
| 0013 6008.40 | 27.00 | 1,124.000 | 30,348.00 |
| PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF | SY | 1,124.000 | 30,348.00 |
| 1,021.132 | 27,570.56 | ||
| 450.000 | 12,150.00 | ||
| 0014 6016.02 | 360.00 | 61.000 | 21,960.00 |
| CONCRETE FOR OVERLAYS-SF | CY | 61.000 | 21,960.00 |
| 128.690 | 46,328.40 | ||
| 54.690 | 19,688.40 | ||
| 0015 7017.00 | 5.00 | 150.000 | 750.00 |
| REMOVE GUARDRAIL | LF | 150.000 | 750.00 |
| 0.000 | 0.00 | ||
| 0.000 | 0.00 | ||
| 0016 7024.27 | 1,800.00 | 4.000 | 7,200.00 |
| GUARDRAIL END TREATMENT, TYPE II | EACH | 4.000 | 7,200.00 |
| 0.000 | 0.00 | ||
| 0.000 | 0.00 | ||
| 0017 9000.01 | 170.00 | 30.000 | 5,100.00 |
| ASPHALTIC CONCRETE | TON | 30.000 | 5,100.00 |
| 2.040 | 346.80 | ||
| 2.040 | 346.80 | ||
| GROUP 6 BRIDGE AT STA. 93+60.00 | Contracted | 144,994.20 | |
| Current | 144,994.20 | ||
| In place | 140,767.67 | ||
| This Estimate | 58,928.20 | ||
| Totals for contract | Contracted | 144,994.20 | |
| Current | 144,994.20 | ||
| In place | 140,767.67 | ||
| This Estimate | 58,928.20 |