Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2762 A & R CONSTRUCTION CO.
Contract ID:3470
Estimate Number:0005
Pay Period End Date:12.17.2002
Contract Location:
MARTINSBURG NORTHEASTEstimate Type:PROG
Contractor:
A & R CONSTRUCTION CO.Date Let:02.07.2002
701 N 9TH STDate Awarded:02.14.2002
PO BOX 121Date Contract Executed:02.25.2002
Date Notice to Proceed:02.25.2002
PLAINVIEW NE 68769Date Work Began:09.30.2002
Phone:Date Physical Work Completed:
(402)582-3663Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
DIXON
Project Number PCT Fed State Project Number Description
31470 000  0.000 RD-9-4(1009)  CULVERT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$152,173.28$148,399.49$3,773.79
$149,081.97Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$152,173.28$148,399.49$3,773.79
$146,143.60Retainage$-1,521.73$-1,483.99$-37.74
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
102.07%Net Earnings$150,651.55$146,915.50$3,736.05
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$482.66$482.66$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$482.66$482.66$.00
Payment$151,134.21$147,398.16$3,736.05
Project ManagerDiv. Head/Dist. Eng.
Brummond, Scott12.17.2002Boyle, Pat12.17.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve12.18.2002
Controller Div. Processed
Burling, Laurie12.18.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 4 CULVERT
0001                          L020.07 1.92675.0001,296.00
EROSION CONTROL, TYPE B-1 SY 675.0001,296.00
0.0000.00
0.0000.00

0002                          L020.10 1.892,906.0005,492.34
EROSION CONTROL, TYPE HV SY 2,906.0005,492.34
4,102.4197,753.57
398.099752.41

0003                          L020.11 9.323,113.00029,013.16
EROSION CONTROL, TYPE AAAA SY 3,113.00029,013.16
3,113.00029,013.16
0.0000.00

0004                          0001.08 0.50760.000380.00
BARRICADE, TYPE II BDAY760.000380.00
0.0000.00
0.0000.00

0005                          0001.10 3.00380.0001,140.00
BARRICADE, TYPE III BDAY380.0001,140.00
264.000792.00
6.00018.00

0006                          0001.30 2.36152.000358.72
TYPE B HIGH INTENSITY WARNING LIGHT LDAY152.000358.72
0.0000.00
0.0000.00

0007                          0001.90 1.001,368.0001,368.00
SIGN DAY EACH1,368.0001,368.00
924.000924.00
56.00056.00

0008                          0003.10 150.0020.0003,000.00
FLAGGING DAY 20.0003,000.00
0.0000.00
0.0000.00

0009                          0010.04 800.001.000800.00
FIELD OFFICE EACH1.000800.00
0.0000.00
0.0000.00

0010                          0030.40 6,000.001.0006,000.00
MOBILIZATION LS 1.0006,000.00
1.0006,000.00
0.0000.00

0011                          1009.00 3,500.001.0003,500.00
GENERAL CLEARING AND GRUBBING LS 1.0003,500.00
1.0003,500.00
0.0000.00

0012                          1010.00 1.7512,582.00022,018.50
EXCAVATION CY 12,582.00022,018.50
12,772.00022,351.00
0.0000.00

0013                          1011.00 10.0085.000850.00
WATER MGAL85.000850.00
0.0000.00
0.0000.00

0014                          1012.00 200.004.000800.00
RIGHT-OF-WAY MARKERS EACH4.000800.00
4.000800.00
0.0000.00

0015                          1042.00 3.301,330.0004,389.00
SALVAGING AND PLACING HYDRIC SOIL SY 1,330.0004,389.00
1,330.0004,389.00
0.0000.00

0016                          1043.50 1.342,200.0002,948.00
RIPRAP FILTER FABRIC SY 2,200.0002,948.00
2,200.0002,948.00
0.0000.00

0017                          4044.00 1,900.001.0001,900.00
PREPARATION OF STRUCTURE EACH1.0001,900.00
AT STA. 1194+64 1.0001,900.00
0.0000.00

0018                          4051.01 11.00152.0001,672.00
EXCAVATION FOR BOX CULVERTS CY 152.0001,672.00
172.0001,892.00
0.0000.00

0019                          4101.06 275.00109.50030,112.50
CLASS 47B-3000 OR AX-3000 CONCRETE FOR BOX CULVERT CY 109.50030,112.50
108.00729,701.93
0.0000.00

0020                          4151.00 0.6112,658.0007,721.38
REINFORCING STEEL FOR BOX CULVERT LB 12,658.0007,721.38
12,712.4007,754.56
0.0000.00

0021                          6105.01 27.00319.0008,613.00
ROCK RIPRAP, TYPE A TON 319.0008,613.00
441.37011,916.99
0.0000.00

0022                          6105.03 27.00473.00012,771.00
ROCK RIPRAP, TYPE C TON 473.00012,771.00
651.47017,589.69
0.0000.00

4000                          L001.01 630.000.0000.00
SEEDING, TYPE A ACRE1.454916.02
1.470926.10
1.470926.10

4001                          L001.02 540.000.0000.00
SEEDING, TYPE B ACRE0.202109.08
0.200108.00
0.200108.00

4002                          L032.75 489.500.0000.00
MULCH TON 3.5701,747.52
3.5701,747.52
3.5701,747.52

4003                          9110.06 82.880.0000.00
RENTAL OF BACKHOE, FULLY OPERATED HOUR2.000165.76
320CL Crawler Mounted Hydraulic Excavator, 2001 year 2.000165.76
2.000165.76

GROUP 4 CULVERTContracted146,143.60
Current149,081.98
In place152,173.28
This Estimate3,773.79

Totals for contractContracted146,143.60
Current149,081.98
In place152,173.28
This Estimate3,773.79