| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| Group 6 Bridge at Sta 4+74.00 | | |
|
| 0607 6960.02 | 3,217.25 | 0.000 | 0.00
|
| ADDITIONAL WORK | LS | 1.000 | 3,217.25
|
| Compensation for Plan Errors | | 1.000 | 3,217.25
|
| | 0.000 | 0.00
|
| | |
|
| Group 6 Bridge at Sta 4+74.00 | | Contracted | 0.00
|
| | Current | 3,217.25
|
| | In place | 3,217.25
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 1 GRADING | | |
|
| 0001 L006.00 | 260.00 | 1.300 | 338.00
|
| COVER CROP SEEDING | ha | 1.300 | 338.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0002 0030.10 | 3,700.00 | 1.000 | 3,700.00
|
| MOBILIZATION | LS | 1.000 | 3,700.00
|
| | | 1.000 | 3,700.00
|
| | 0.000 | 0.00
|
| | |
|
| 0003 1009.00 | 2,500.00 | 1.000 | 2,500.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 2,500.00
|
| | | 1.000 | 2,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0004 1010.01 | 1.70 | 15,847.000 | 26,939.90
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 15,847.000 | 26,939.90
|
| | | 15,847.000 | 26,939.90
|
| | 0.000 | 0.00
|
| | |
|
| 0005 1011.00 | 2.70 | 347.000 | 936.90
|
| WATER | kL | 347.000 | 936.90
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 4050.01 | 9.20 | 326.000 | 2,999.20
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 326.000 | 2,999.20
|
| | | 326.000 | 2,999.20
|
| | 0.000 | 0.00
|
| | |
|
| 0007 4350.24 | 46.00 | 13.400 | 616.40
|
| 600 mm CORRUGATED METAL PIPE | m | 13.400 | 616.40
|
| | | 13.400 | 616.40
|
| | 0.000 | 0.00
|
| | |
|
| 0008 4350.36 | 70.00 | 40.200 | 2,814.00
|
| 900 mm CORRUGATED METAL PIPE | m | 40.200 | 2,814.00
|
| | | 40.200 | 2,814.00
|
| | 0.000 | 0.00
|
| | |
|
| 0009 4350.42 | 104.00 | 20.400 | 2,121.60
|
| 1050 mm CORRUGATED METAL PIPE | m | 20.400 | 2,121.60
|
| | | 20.400 | 2,121.60
|
| | 0.000 | 0.00
|
| | |
|
| 0010 4360.24 | 124.00 | 1.000 | 124.00
|
| 600 mm METAL FLARED-END SECTION | EACH | 1.000 | 124.00
|
| | | 1.000 | 124.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 4360.36 | 260.00 | 2.000 | 520.00
|
| 900 mm METAL FLARED-END SECTION | EACH | 2.000 | 520.00
|
| | | 2.000 | 520.00
|
| | 0.000 | 0.00
|
| | |
|
| 0012 4360.42 | 400.00 | 1.000 | 400.00
|
| 1050 mm METAL FLARED-END SECTION | EACH | 1.000 | 400.00
|
| | | 1.000 | 400.00
|
| | 0.000 | 0.00
|
| | |
|
| 0013 6105.02 | 22.50 | 1,546.000 | 34,785.00
|
| ROCK RIPRAP, TYPE B | Mg | 1,546.000 | 34,785.00
|
| | | 1,545.250 | 34,768.12
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 1 GRADING | | Contracted | 78,795.00
|
| | Current | 78,795.00
|
| | In place | 77,503.22
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 4+74.00 | | |
|
| 0014 0030.60 | 30,000.00 | 1.000 | 30,000.00
|
| MOBILIZATION | LS | 1.000 | 30,000.00
|
| | | 1.000 | 30,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0015 6000.10 | 2,000.00 | 1.000 | 2,000.00
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 2,000.00
|
| | | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 6000.11 | 2,000.00 | 1.000 | 2,000.00
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 2,000.00
|
| | | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 6001.50 | 7,000.00 | 1.000 | 7,000.00
|
| BENT NO.1 EXCAVATION | LS | 1.000 | 7,000.00
|
| | | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0018 6001.51 | 7,000.00 | 1.000 | 7,000.00
|
| BENT NO.2 EXCAVATION | LS | 1.000 | 7,000.00
|
| | | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 6010.22 | 310.00 | 143.800 | 44,578.00
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 143.800 | 44,578.00
|
| | | 143.800 | 44,578.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 6010.26 | 300.00 | 88.800 | 26,640.00
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 88.800 | 26,640.00
|
| | | 92.400 | 27,720.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 6011.11 | 85,000.00 | 1.000 | 85,000.00
|
| PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE | LS | 1.000 | 85,000.00
|
| AT STA. 4+74 | | 1.000 | 85,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 6020.00 | 1.10 | 17,080.000 | 18,788.00
|
| REINFORCING STEEL FOR BRIDGE | kg | 17,080.000 | 18,788.00
|
| | | 17,182.000 | 18,900.20
|
| | 0.000 | 0.00
|
| | |
|
| 0023 6040.00 | 10,000.00 | 1.000 | 10,000.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 10,000.00
|
| AT STA. 4+80 | | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0024 6080.00 | 4.00 | 1,896.000 | 7,584.00
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 1,896.000 | 7,584.00
|
| | | 1,896.000 | 7,584.00
|
| | 0.000 | 0.00
|
| | |
|
| 0025 6105.02 | 24.00 | 2,294.000 | 55,056.00
|
| ROCK RIPRAP, TYPE B | Mg | 2,294.000 | 55,056.00
|
| | | 2,301.810 | 55,243.44
|
| | 0.000 | 0.00
|
| | |
|
| 0026 6139.50 | 40.00 | 25.200 | 1,008.00
|
| SUBSURFACE DRAINAGE MATTING | m2 | 25.200 | 1,008.00
|
| | | 25.200 | 1,008.00
|
| | 0.000 | 0.00
|
| | |
|
| 0027 6210.12 | 56.00 | 693.000 | 38,808.00
|
| HP 250 mm X 62 kg STEEL PILING | m | 693.000 | 38,808.00
|
| | | 659.836 | 36,950.82
|
| | 0.000 | 0.00
|
| | |
|
| 0028 6310.00 | 115.00 | 305.600 | 35,144.00
|
| STEEL SHEET PILING | m2 | 305.600 | 35,144.00
|
| | | 303.960 | 34,955.40
|
| | 0.000 | 0.00
|
| | |
|
| 0029 8091.00 | 24.00 | 60.000 | 1,440.00
|
| GRANULAR BACKFILL | m3 | 60.000 | 1,440.00
|
| | | 59.470 | 1,427.28
|
| | 0.000 | 0.00
|
| | |
|
| 0601 6210.32 | 33.60 | 0.000 | 0.00
|
| PAY CUT-OFF FOR 250 mm X 62 kg STEEL PILING | m | 10.000 | 336.00
|
| Paragragh 2, Subsection 703.05 of the 1997 Standard Specs. | | 32.804 | 1,102.20
|
| | 0.000 | 0.00
|
| | |
|
| 0602 6210.61 | 112.00 | 0.000 | 0.00
|
| PILE SPLICE | EACH | 10.000 | 1,120.00
|
| Paragraph 3, Subsection 703.05 of the 1997 Standard Specs. | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 4+74.00 | | Contracted | 372,046.00
|
| | Current | 373,502.00
|
| | In place | 372,469.34
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | |
|
| 0030 0030.70 | 600.00 | 1.000 | 600.00
|
| MOBILIZATION | LS | 1.000 | 600.00
|
| | | 1.000 | 600.00
|
| | 0.000 | 0.00
|
| | |
|
| 0031 7020.00 | 1,500.00 | 4.000 | 6,000.00
|
| BRIDGE APPROACH SECTIONS | EACH | 4.000 | 6,000.00
|
| | | 4.000 | 6,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0032 7021.45 | 1,300.00 | 4.000 | 5,200.00
|
| BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 5,200.00
|
| | | 4.000 | 5,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0603 7011.20 | 72.67 | 0.000 | 0.00
|
| W-BEAM GUARDRAIL | m | 76.200 | 5,537.45
|
| | | 76.200 | 5,537.45
|
| | 0.000 | 0.00
|
| | |
|
| 0604 7021.45 | 1,365.00 | 0.000 | 0.00
|
| BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 5,460.00
|
| | | 4.000 | 5,460.00
|
| | 0.000 | 0.00
|
| | |
|
| 0605 0030.71 | | 1.000 |
|
| MOBILIZATION | LS | 2.000 | 0.00
|
| | | 1.000 | 500.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 7 GUARDRAIL | | Contracted | 11,800.00
|
| | Current | 23,297.45
|
| | In place | 23,297.45
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | |
|
| 0033 0001.10 | 1.10 | 1,668.000 | 1,834.80
|
| BARRICADE, TYPE III | BDAY | 1,668.000 | 1,834.80
|
| | | 1,296.000 | 1,425.60
|
| | 0.000 | 0.00
|
| | |
|
| 0034 0001.30 | 1.10 | 278.000 | 305.80
|
| TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 278.000 | 305.80
|
| | | 308.000 | 338.80
|
| | 0.000 | 0.00
|
| | |
|
| 0035 0001.90 | 0.45 | 3,058.000 | 1,376.10
|
| SIGN DAY | EACH | 3,058.000 | 1,376.10
|
| | | 1,568.000 | 705.60
|
| | 0.000 | 0.00
|
| | |
|
| 0036 0030.10 | 200.00 | 1.000 | 200.00
|
| MOBILIZATION | LS | 1.000 | 200.00
|
| | | 1.000 | 200.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | Contracted | 3,716.70
|
| | Current | 3,716.70
|
| | In place | 2,670.00
|
| | This Estimate | 0.00
|
| | |
|
| Totals for contract | | Contracted | 466,357.70
|
|---|
| | Current | 482,028.40
|
|---|
| | In place | 479,157.26
|
|---|
| | This Estimate | 0.00
|
|---|