Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:3339
Estimate Number:0016
Pay Period End Date:01.04.2003
Contract Location:
VERDIGRE SOUTHEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:02.07.2002
129 E 2ND STDate Awarded:02.14.2002
PO BOX 1087Date Contract Executed:02.21.2002
Date Notice to Proceed:02.21.2002
HASTINGS NE 68902-1087Date Work Began:05.06.2002
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
KNOX
Project Number PCT Fed State Project Number Description
31339 000B  0.000 EACSTPD-14-4(107)  GRAD CULV SEED BR GDRL ELEC BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,465,483.00$2,452,831.70$12,651.30
$2,604,640.99Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,465,483.00$2,452,831.70$12,651.30
$2,308,102.85Retainage$-24,654.83$-24,528.32$-126.51
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
94.66%Net Earnings$2,440,828.17$2,428,303.38$12,524.79
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$1,324.15$1,324.15$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments$1,324.15$1,324.15$.00
Payment$2,442,152.32$2,429,627.53$12,524.79
Project ManagerDiv. Head/Dist. Eng.
Becker, Roger01.09.2003Boyle, Pat01.09.2003
Constr. Estimate Eng.Materials Eng.
Henrichson, Roger01.10.2003
Controller Div. Processed
Burling, Laurie01.10.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 4A CULVERT ITEMS
0401                          0030.40 9,450.000.0000.00
MOBILIZATION LS 1.0009,450.00
1.0009,450.00
0.0000.00

0402                          4044.00 14,091.000.0000.00
PREPARATION OF STRUCTURE EACH1.00014,091.00
1.00014,091.00
0.0000.00

0403                          4051.01 26.250.0000.00
EXCAVATION FOR BOX CULVERTS m3 132.4003,475.50
132.4003,475.50
0.0000.00

0404                          4101.08 408.450.0000.00
CLASS 47B-20 CONCRETE FOR BOX CULVERT m3 197.07380,494.47
197.07380,494.47
0.0000.00

0405                          4151.00 1.500.0000.00
REINFORCING STEEL FOR BOX CULVERT kg 8,441.49812,662.25
8,441.49812,662.25
0.0000.00

0406                          4051.12 40.850.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 39.7001,621.75
39.7001,621.75
0.0000.00

0407                          4061.01 26.250.0000.00
EXCAVATION OF UNSUITABLE MATERIAL m3 39.7001,042.13
39.7001,042.13
0.0000.00

GROUP 4A CULVERT ITEMSContracted0.00
Current122,837.08
In place122,837.10
This Estimate0.00

GROUP 6A BRIDGE AT STA. 316+05.4
0412                          0030.60 2,100.000.0000.00
MOBILIZATION LS 1.0002,100.00
1.0002,100.00
1.0002,100.00

0413                          6010.26 1,470.000.0000.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 3.5005,145.00
3.5005,145.00
3.5005,145.00

0414                          6020.00 4.200.0000.00
REINFORCING STEEL FOR BRIDGE kg 604.0002,536.80
604.0002,536.80
604.0002,536.80

0415                          6030.00 840.000.0000.00
PREPARATION OF BRIDGE EACH1.000840.00
1.000840.00
1.000840.00

GROUP 6A BRIDGE AT STA. 316+05.4Contracted0.00
Current10,621.80
In place10,621.80
This Estimate10,621.80

GROUP 1 GRADING
0001                          L006.50 500.001.000500.00
TEMPORARY SEEDING ha 1.000500.00
0.720360.00
0.0000.00

0002                          L020.01 5.75887.0005,100.25
EROSION CONTROL, TYPE A m2 887.0005,100.25
604.8003,477.60
0.0000.00

0003                          L020.08 5.20423.0002,199.60
EROSION CONTROL, TYPE AA m2 423.0002,199.60
373.7701,943.60
0.0000.00

0004                          L020.09 13.00729.0009,477.00
EROSION CONTROL, TYPE AAA m2 825.00010,725.00
0.0000.00
0.0000.00

0005                          L020.10 1.65504.000831.60
EROSION CONTROL, TYPE HV m2 504.000831.60
245.772405.52
0.0000.00

0006                          L021.06 15.0012.000180.00
EROSION CHECKS, TYPE HV BALE12.000180.00
21.000315.00
0.0000.00

0007                          L021.11 17.0054.000918.00
EROSION CHECKS, TYPE ST-A BALE54.000918.00
0.0000.00
0.0000.00

0008                          L021.21 17.0024.000408.00
EROSION CHECKS, TYPE AA BALE24.000408.00
66.0001,122.00
0.0000.00

0009                          L021.22 16.0012.000192.00
EROSION CHECKS, TYPE AAA BALE12.000192.00
12.000192.00
0.0000.00

0010                          L022.11 6.20365.0002,263.00
FABRIC SILT FENCE-LOW POROSITY m 365.0002,263.00
146.700909.54
0.0000.00

0011                          L022.25 6.25266.0001,662.50
FABRIC SILT FENCE, TYPE COIR FIBER m 266.0001,662.50
0.0000.00
0.0000.00

0012                          L022.75 27.0058.0001,566.00
TEMPORARY SILT CHECK m 58.0001,566.00
17.100461.70
0.0000.00

0013                          0030.10 8,500.001.0008,500.00
MOBILIZATION LS 1.0008,500.00
1.0008,500.00
0.0000.00

0014                          1009.00 2,200.001.0002,200.00
GENERAL CLEARING AND GRUBBING LS 1.0002,200.00
1.0002,200.00
0.0000.00

0015                          1010.01 3.9211,727.00045,969.84
EXCAVATION (ESTABLISHED QUANTITY) m3 11,727.00045,969.84
11,727.00045,969.85
0.0000.00

0016                          1011.00 1.001,185.0001,185.00
WATER kL 1,404.0001,404.00
0.0000.00
0.0000.00

0017                          1012.00 60.009.000540.00
RIGHT-OF-WAY MARKERS EACH9.000540.00
9.000540.00
0.0000.00

0018                          1030.00 3.9215,927.00062,433.84
EARTHWORK MEASURED IN EMBANKMENT m3 20,057.00078,623.44
20,057.00078,623.44
0.0000.00

0019                          1102.00 2.396,877.00016,436.03
REMOVE ASPHALT SURFACE m2 6,877.00016,436.03
6,609.13515,795.82
0.0000.00

0020                          1106.00 3.00396.0001,188.00
REMOVE DRIVEWAY m2 396.0001,188.00
463.5641,390.69
0.0000.00

0021                          1109.00 7.00155.2001,086.40
REMOVE CURB m 155.2001,086.40
170.2001,191.40
0.0000.00

0022                          1300.24 35.0036.5001,277.50
600 mm DRIVEWAY CULVERT PIPE m 36.5001,277.50
TYPE 3,4 OR 5 51.0001,785.00
51.0001,785.00

0023                          1701.24 35.0036.5001,277.50
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 36.5001,277.50
44.0001,540.00
0.0000.00

0408                          6103.00 2.980.0000.00
GEOGRID m2 4,215.61612,562.54
Furnishing and Installing 4,215.61612,562.54
0.0000.00

GROUP 1 GRADINGContracted167,392.06
Current197,611.20
In place179,285.70
This Estimate1,785.00

GROUP 4 CULVERT
0024                          P300.24 67.0012.300824.10
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 12.300824.10
17.4001,165.80
0.0000.00

0025                          0030.40 500.001.000500.00
MOBILIZATION LS 1.000500.00
0.585292.50
0.0000.00

0026                          4035.25 175.003.000525.00
REMOVE AND SALVAGE FLARED-END SECTION EACH3.000525.00
3.000525.00
0.0000.00

0027                          4050.01 50.005.000250.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 5.000250.00
5.000250.00
0.0000.00

0028                          4362.24 275.003.000825.00
INSTALL 600 mm METAL FLARED-END SECTION EACH3.000825.00
3.000825.00
0.0000.00

GROUP 4 CULVERTContracted2,924.10
Current2,924.10
In place3,058.30
This Estimate0.00

GROUP 5 SEEDING
0029                          L001.01 1,323.001.5001,984.50
SEEDING, TYPE A ha 3.0003,969.00
9.98913,215.45
0.0000.00

0030                          L001.02 1,289.0011.00014,179.00
SEEDING, TYPE B ha 12.00015,468.00
11.42714,729.41
0.0000.00

0031                          L020.02 1.601,254.0002,006.40
EROSION CONTROL, TYPE B m2 1,254.0002,006.40
6,829.42010,927.07
0.0000.00

0032                          L032.75 55.0062.5003,437.50
MULCH Mg 75.0004,125.00
94.0685,173.74
0.0000.00

0033                          0030.50 500.001.000500.00
MOBILIZATION LS 1.000500.00
1.000500.00
0.0000.00

GROUP 5 SEEDINGContracted22,107.40
Current26,068.40
In place44,545.67
This Estimate0.00

GROUP 6 BRIDGE AT STA. 10401+39.4
0034                          0030.60 5,500.001.0005,500.00
MOBILIZATION LS 1.0005,500.00
1.0005,500.00
0.0000.00

0035                          6007.01 48.00203.3009,758.40
CLASS I REPAIR m2 203.3009,758.40
194.3409,328.32
0.0000.00

0036                          6007.02 166.00101.60016,865.60
CLASS II REPAIR m2 101.60016,865.60
119.06719,765.12
0.0000.00

0037                          6007.03 400.005.0002,000.00
CLASS III REPAIR m2 5.0002,000.00
4.6001,840.00
0.0000.00

0038                          6008.40 45.00203.3009,148.50
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 203.3009,148.50
194.3208,744.40
0.0000.00

0039                          6010.26 800.007.4005,920.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 7.4005,920.00
7.5006,000.00
0.0000.00

0040                          6016.02 560.0018.20010,192.00
CONCRETE FOR OVERLAYS-SF m3 18.20010,192.00
18.74010,494.40
0.0000.00

0041                          6020.00 2.20704.0001,548.80
REINFORCING STEEL FOR BRIDGE kg 704.0001,548.80
704.0001,548.80
0.0000.00

GROUP 6 BRIDGE AT STA. 10401+39.4Contracted60,933.30
Current60,933.30
In place63,221.04
This Estimate0.00

GROUP 7 GUARDRAIL
0042                          0030.70 3,040.001.0003,040.00
MOBILIZATION LS 1.0003,040.00
1.0003,040.00
0.0000.00

0043                          7011.20 33.88152.4005,163.31
W-BEAM GUARDRAIL m 152.4005,163.31
152.4005,163.31
0.0000.00

0044                          7017.00 6.30226.0001,423.80
REMOVE GUARDRAIL m 226.0001,423.80
254.4001,602.72
0.0000.00

0045                          7017.50 6.181,319.9008,156.98
REMOVE & SALVAGE GUARDRAIL m 1,568.9009,695.80
1,571.1009,709.40
0.0000.00

0046                          7018.01 10.471,235.00012,930.45
RESET GUARDRAIL m 1,450.00015,181.50
1,450.02015,181.71
0.0000.00

0047                          7020.00 958.758.0007,670.00
BRIDGE APPROACH SECTIONS EACH8.0007,670.00
8.0007,670.00
0.0000.00

0048                          7023.00 1,272.0012.00015,264.00
TERMINAL ANCHORAGE SECTIONS EACH16.00020,352.00
16.00020,352.00
0.0000.00

0049                          7024.27 1,486.758.00011,894.00
GUARDRAIL END TREATMENT, TYPE II EACH8.00011,894.00
8.00011,894.00
0.0000.00

GROUP 7 GUARDRAILContracted65,542.54
Current74,420.41
In place74,613.14
This Estimate0.00

GROUP 8B ELECTRICAL
0050                          A070.10 8.00114.000912.00
38 mm CONDUIT IN TRENCH m 114.000912.00
97.100776.80
0.0000.00

0051                          A072.10 8.0048.000384.00
38 mm CONDUIT UNDER ROADWAY m 48.000384.00
45.900367.20
0.0000.00

0052                          A080.22 1.00148.000148.00
STREET LIGHTING CABLE, NO. 6 BARE m 148.000148.00
178.600178.60
0.0000.00

0053                          A080.24 2.00296.000592.00
STREET LIGHTING CABLE, NO. 6 USE m 296.000592.00
357.200714.40
0.0000.00

0054                          A700.20 1,350.003.0004,050.00
RELOCATE STREET LIGHTING UNIT EACH3.0004,050.00
4.0005,400.00
0.0000.00

0055                          0030.81 750.001.000750.00
MOBILIZATION LS 1.000750.00
0.911683.25
0.0000.00

GROUP 8B ELECTRICALContracted6,836.00
Current6,836.00
In place8,120.25
This Estimate0.00

GROUP 9 BITUMINOUS
0056                          P402.15 73.50201.30014,795.55
375 mm CULVERT PIPE, TYPE 3,4,5 OR 6 m 241.80017,772.30
253.80018,654.30
0.0000.00

0057                          0002.55 23.00463.00010,649.00
OVERLAY BROKEN LINES StaM463.00010,649.00
456.33510,495.70
0.0000.00

0058                          0002.60 26.00909.00023,634.00
OVERLAY SOLID LINES StaM909.00023,634.00
1,191.09830,968.56
0.0000.00

0059                          0030.90 41,500.001.00041,500.00
MOBILIZATION LS 1.00041,500.00
1.00041,500.00
0.0000.00

0060                          1020.03 18.6058.0001,078.80
DELINEATOR, TYPE III EACH58.0001,078.80
61.0001,134.60
0.0000.00

0061                          1020.20 24.5040.000980.00
INSTALL CHEVRONS EACH40.000980.00
40.000980.00
0.0000.00

0062                          1033.00 2,500.002.7206,800.00
ROADWAY GRADING StaM2.7206,800.00
2.7206,800.00
0.0000.00

0063                          2001.00 10.57590.0006,236.30
GRAVEL SURFACE COURSE m3 590.0006,236.30
389.5004,117.00
0.0000.00

0064                          2009.10 200.007.8711,574.20
GRAVEL EMBEDMENT StaM7.8711,574.20
6.0501,210.00
0.0000.00

0065                          2020.00 7.5058.000435.00
SPECIAL SURFACE COURSE FOR MAILBOX TURNOUTS m2 58.000435.00
56.000420.00
0.0000.00

0066                          2021.00 50.002.000100.00
MAILBOX POST EACH2.000100.00
1.00050.00
0.0000.00

0067                          3012.06 75.70153.70011,635.09
CONCRETE CLASS 47B-25 MEDIAN CURB m 153.70011,635.09
152.80011,566.96
0.0000.00

0068                          3017.40 42.00146.0006,132.00
CONCRETE CLASS 47B-20 MEDIAN SURFACING m2 146.0006,132.00
146.0186,132.76
0.0000.00

0069                          3019.23 650.001.000650.00
CONCRETE CLASS 47B-25 ISLAND NOSE EACH1.000650.00
1.000650.00
0.0000.00

0070                          4024.55 175.0025.1004,392.50
FLUME SPILLWAY m 25.1004,392.50
25.3004,427.50
0.0000.00

0071                          4024.70 2,500.003.0007,500.00
CONCRETE FLUME, TYPE I EACH3.0007,500.00
3.0007,500.00
0.0000.00

0072                          4024.73 2,650.006.00015,900.00
CONCRETE FLUME, TYPE IV EACH6.00015,900.00
6.00015,900.00
0.0000.00

0073                          4763.26 200.0020.0004,000.00
UNDERDRAIN HEADWALL EACH20.0004,000.00
0.0000.00
0.0000.00

0074                          4764.35 27.80144.0004,003.20
100 mm PERFORATED PIPE UNDERDRAIN m 144.0004,003.20
0.0000.00
0.0000.00

0075                          8022.00 200.0080.76516,153.00
HYDRATED LIME Mg 80.76516,153.00
91.00018,200.00
0.0000.00

0076                          8101.50 3.506,009.00021,031.50
STABILIZED SUBGRADE m2 6,009.00021,031.50
6,711.37423,489.81
0.0000.00

0077                          8111.00 350.0016.7435,860.05
SHOULDER SUBGRADE PREPARATION StaM16.7435,860.05
13.7554,814.25
0.0000.00

0078                          9000.75 17.26750.00012,945.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 750.00012,945.00
SP2 364.0006,282.63
0.0000.00

0079                          9005.00 27.261,200.00032,712.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 1,200.00032,712.00
SP2 93.8802,559.17
0.0000.00

0080                          9005.30 17.2649,590.000855,923.40
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 49,590.000855,923.40
49,020.980846,102.12
0.0000.00

0081                          9009.00 2.504,331.00010,827.50
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 4,331.00010,827.50
4,331.96010,829.90
0.0000.00

0082                          9009.75 50.0084.0004,200.00
TEMPORARY SURFACING m2 84.0004,200.00
0.0000.00
0.0000.00

0083                          9020.91 173.0040.5007,006.50
PERFORMANCE GRADED BINDER (64-22) FOR STATE MAINTENANCEPATCHING Mg 40.5007,006.50
17.1622,969.03
0.0000.00

0084                          9021.01 173.002,742.660474,480.18
PERFORMANCE GRADED BINDER (64-22) Mg 2,742.660474,480.18
2,372.139410,380.05
0.0000.00

0085                          9030.00 6.501,422.0009,243.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 1,638.00010,647.00
1,631.20010,602.80
0.0000.00

0086                          9034.00 2.501,284.0003,210.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,284.0003,210.00
836.3102,090.78
0.0000.00

0087                          9053.00 0.26109,322.00028,423.72
TACK COAT L 109,322.00028,423.72
121,417.10031,568.45
0.0000.00

0088                          9111.00 2.50980.0002,450.00
WATER kL 980.0002,450.00
0.0000.00
0.0000.00

0089                          9170.00 182.00293.32953,385.88
EARTH SHOULDER CONSTRUCTION StaM293.32953,385.88
306.61755,804.29
0.0000.00

0090                          9173.15 32.50274.7768,930.22
TRENCHED WIDENING StaM274.7768,930.22
277.7669,027.39
0.0000.00

0091                          9179.23 515.00148.53776,496.56
COLD MILLING, CLASS 3 StaM148.53776,496.56
148.73076,595.95
0.0000.00

0092                          9188.50 25.003,960.00099,000.00
SURFACING UNDER GUARDRAIL m2 4,455.000111,375.00
3,392.34484,808.60
0.0000.00

0093                          9300.50 4,500.001.0004,500.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0004,500.00
1.0004,500.00
0.0000.00

0409                          9005.30 34.480.0000.00
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 1,776.64061,258.55
1,776.64061,258.55
0.0000.00

0410                          4024.74 2,782.500.0000.00
CONCRETE FLUME, TYPE V EACH2.0005,565.00
2.0005,565.00
0.0000.00

6001                          9300.56 0.4970.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 49,478.86024,590.99
Superpave Quality Incentive Pay Factor 102.88% 49,478.86024,590.99
0.0000.00

6002                          9300.60 0.5420.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 14,663.8277,947.79
Smoothness Incentive Pay Factor 103.14% 14,663.8277,947.79
0.0000.00

6003                          9300.77 5.43220.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 718.5283,903.19
Smoothness Incentive Pay Factor 103.14% 718.5283,903.19
0.0000.00

GROUP 9 BITUMINOUSContracted1,888,774.14
Current2,008,795.42
In place1,866,398.12
This Estimate0.00

GROUP 10 GENERAL ITEMS
0094                          0001.08 0.5031,522.00015,761.00
BARRICADE, TYPE II BDAY31,522.00015,761.00
38,229.00019,114.50
0.0000.00

0095                          0001.10 2.251,240.0002,790.00
BARRICADE, TYPE III BDAY1,240.0002,790.00
4,811.00010,824.75
42.00094.50

0096                          0001.30 2.25612.0001,377.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY612.0001,377.00
297.000668.25
0.0000.00

0097                          0001.75 5.00630.0003,150.00
TEMPORARY SIGN DAY EACH630.0003,150.00
126.000630.00
0.0000.00

0098                          0001.90 0.507,370.0003,685.00
SIGN DAY EACH7,370.0003,685.00
19,535.0009,767.50
300.000150.00

0099                          0002.30 1.64270.000442.80
PAVEMENT MARKING REMOVAL m 270.000442.80
302.000495.28
0.0000.00

0100                          0002.39 1.704,050.0006,885.00
TEMPORARY PAVEMENT MARKING, TYPE II m 4,050.0006,885.00
0.0000.00
0.0000.00

0101                          0002.47 4.50175.000787.50
TEMPORARY PAVEMENT MARKING SURFACE PREPARATION m 175.000787.50
0.0000.00
0.0000.00

0102                          0003.10 175.0090.00015,750.00
FLAGGING DAY 90.00015,750.00
114.50020,037.50
0.0000.00

0103                          0003.20 275.0030.0008,250.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 30.0008,250.00
32.0008,800.00
0.0000.00

0104                          0003.51 75.00117.0008,775.00
INSTALL CONCRETE PROTECTION BARRIER m 117.0008,775.00
106.6808,001.00
0.0000.00

0105                          0003.56 20.00117.0002,340.00
RELOCATE CONCRETE PROTECTION BARRIER m 117.0002,340.00
106.7802,135.60
0.0000.00

0106                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
1.0001,500.00
0.0000.00

0107                          0030.00 10,000.001.00010,000.00
MOBILIZATION LS 1.00010,000.00
0.9369,360.00
0.0000.00

0108                          9110.01 65.0055.0003,575.00
RENTAL OF LOADER, FULLY OPERATED HOUR55.0003,575.00
3.500227.50
0.0000.00

0109                          9110.02 60.0055.0003,300.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR55.0003,300.00
1.50090.00
0.0000.00

0110                          9110.03 50.0055.0002,750.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR55.0002,750.00
10.000500.00
0.0000.00

0111                          9110.07 45.0055.0002,475.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR55.0002,475.00
14.000630.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted93,593.30
Current93,593.30
In place92,781.88
This Estimate244.50

Totals for contractContracted2,308,102.85
Current2,604,641.01
In place2,465,483.00
This Estimate12,651.30