Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:2252 PAULSEN, INC.
Contract ID:3261X
Estimate Number:0034
Pay Period End Date:03.29.2003
Contract Location:
IN NELIGHEstimate Type:PROG
Contractor:
PAULSEN, INC.Date Let:02.22.2001
1116 EAST HWY 30Date Awarded:03.01.2001
P O BOX 17Date Contract Executed:03.06.2001
Date Notice to Proceed:03.06.2001
COZAD NE 69130Date Work Began:04.02.2001
Phone:Date Physical Work Completed:
(308)784-3333Date Accepted:
Escrow Agent:
Surety Co:
ST. PAUL FIRE AND MARINE INSURANCE COMPANY
Counties
ANTELOPE
Project Number PCT Fed State Project Number Description
31261 000  0.000 EACNH-275-5(134)  GR CONC PAVE CULV GDRL ELEC
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$3,903,829.58$3,866,830.18$36,999.40
$3,193,674.65Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$3,903,829.58$3,866,830.18$36,999.40
$3,189,998.76Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
122.24%Net Earnings$3,878,829.58$3,841,830.18$36,999.40
Liquidated Damages-$49,630.00-$49,630.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-289.50$-289.50$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$49,919.50-$49,919.50$.00
Payment$3,828,910.08$3,791,910.68$36,999.40
Project ManagerDiv. Head/Dist. Eng.
Davis, Rob03.31.2003Boyle, Pat04.15.2003
Constr. Estimate Eng.Materials Eng.
Bartos, Steve04.15.2003
Controller Div. Processed
Burling, Laurie04.15.2003
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L020.00 2.201,820.0004,004.00
EROSION CONTROL m2 1,820.0004,004.00
1,820.0004,004.00
0.0000.00

0002                          L020.01 9.50207.0001,966.50
EROSION CONTROL, TYPE A m2 207.0001,966.50
207.0001,966.50
0.0000.00

0003                          L021.00 20.1015.000301.50
EROSION CHECKS BALE15.000301.50
15.000301.50
0.0000.00

0004                          L022.14 13.50485.0006,547.50
FABRIC SILT FENCE-LOW PROFILE LOW POROSITY m 485.0006,547.50
795.00010,732.50
0.0000.00

0005                          0030.10 15,000.001.00015,000.00
MOBILIZATION LS 1.00015,000.00
1.00015,000.00
0.0000.00

0006                          1009.00 18,000.001.00018,000.00
GENERAL CLEARING AND GRUBBING LS 1.00018,000.00
1.00018,000.00
0.0000.00

0007                          1010.01 3.005,054.00015,162.00
EXCAVATION (ESTABLISHED QUANTITY) m3 5,054.00015,162.00
5,054.00015,162.00
0.0000.00

0008                          1011.00 2.00781.0001,562.00
WATER kL 781.0001,562.00
11.36722.73
0.0000.00

0009                          1030.00 5.5010,415.00057,282.50
EARTHWORK MEASURED IN EMBANKMENT m3 10,415.00057,282.50
10,415.00057,282.50
0.0000.00

0010                          1101.00 5.902,484.00014,655.60
REMOVE PAVEMENT m2 2,484.00014,655.60
10,889.14164,245.93
27.786163.94

0011                          1106.00 4.001,676.0006,704.00
REMOVE DRIVEWAY m2 1,676.0006,704.00
2,040.3058,161.23
0.7422.97

0012                          1107.00 7.00250.0001,750.00
REMOVE WALK m2 250.0001,750.00
447.7533,134.27
0.0000.00

0013                          1108.00 7.00595.0004,165.00
REMOVE COMBINATION CURB AND GUTTER m 595.0004,165.00
822.9005,760.30
0.0000.00

0014                          1114.10 10.0027.300273.00
REMOVE RETAINING WALL m 27.300273.00
27.800278.00
0.0000.00

0015                          1122.01 5.50681.0003,745.50
REMOVE CONCRETE MEDIAN SURFACING m2 681.0003,745.50
853.5934,694.77
0.0000.00

0016                          1124.00 6,000.001.0006,000.00
REMOVE BUILDING EACH1.0006,000.00
AT STA. 15+90 RT. 0.0000.00
0.0000.00

0017                          1124.01 1.001.0001.00
REMOVE BUILDING EACH1.0001.00
AT STA. 17+03 RT. 0.0000.00
0.0000.00

0018                          1124.02 1.001.0001.00
REMOVE BUILDING EACH1.0001.00
AT STA. 23+63 RT. 0.0000.00
0.0000.00

0019                          1124.03 20,000.001.00020,000.00
REMOVE BUILDING EACH1.00020,000.00
AT STA. 24+30 RT. 1.00020,000.00
0.0000.00

0020                          1125.00 4,000.001.0004,000.00
CLEAR TRACT EACH1.0004,000.00
AT STA. 15+79.6 TO 16+64.2 RT. 1.0004,000.00
0.0000.00

0021                          1125.01 700.001.000700.00
CLEAR TRACT EACH1.000700.00
AT STA. 16+87.1 TO 17+26.4 RT. 1.000700.00
0.0000.00

0022                          1125.02 1,200.001.0001,200.00
CLEAR TRACT EACH1.0001,200.00
AT STA. 23+51.9 TO 23+91.8 RT. 1.0001,200.00
0.0000.00

0023                          1125.03 2,200.001.0002,200.00
CLEAR TRACT EACH1.0002,200.00
AT STA. 23+97.9 TO 24+37.6 RT. 1.0002,200.00
0.0000.00

0024                          1701.24 40.0023.400936.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 23.400936.00
23.400936.00
0.0000.00

0025                          1706.72 458.0011.0005,038.00
1800 mm ROUND EQUIVALENT DRIVEWAY PIPE, TYPE 2 m 11.0005,038.00
12.0005,496.00
0.0000.00

0026                          4035.00 120.004.000480.00
REMOVE FLARED-END SECTION EACH4.000480.00
4.000480.00
0.0000.00

0027                          4320.72 1,500.002.0003,000.00
1800 mm ROUND EQUIVALENT FLARED-END SECTION EACH2.0003,000.00
2.0003,000.00
0.0000.00

0028                          6105.02 32.00450.00014,400.00
ROCK RIPRAP, TYPE B Mg 450.00014,400.00
450.00014,400.00
0.0000.00

0029                          7017.00 9.0035.000315.00
REMOVE GUARDRAIL m 35.000315.00
35.000315.00
0.0000.00

403                           1010.00 3.000.0000.00
EXCAVATION m3 2,360.0007,080.00
Additional 0.0000.00
0.0000.00

407                           1135.58 2,612.100.0000.00
REMOVE CONCRETE OBSTRUCTION LS 1.0002,612.10
Drainage structure 1.0002,612.10
0.0000.00

429                           1123.75 512.750.0000.00
REMOVE CONCRETE SIGN BASE EACH3.0001,538.25
3.0001,538.25
0.0000.00

601                           1010.50 11.000.0000.00
REMOVAL OF UNSUITABLE MATERIAL m3 62.000682.00
416.0004,576.00
0.0000.00

GROUP 1 GRADINGContracted209,390.10
Current221,302.45
In place270,199.58
This Estimate166.91

GROUP 3 CONCRETE PAVEMENT
0030                          L001.02 3,160.002.1006,636.00
SEEDING, TYPE B ha 2.1006,636.00
2.3707,489.20
0.0000.00

0031                          L010.00 6.002,062.00012,372.00
SODDING m2 2,062.00012,372.00
11,133.87866,803.27
0.0000.00

0032                          L032.80 520.005.6702,948.40
HYDROMULCH Mg 5.6702,948.40
5.6702,948.40
0.0000.00

0033                          0030.30 79,000.001.00079,000.00
MOBILIZATION LS 1.00079,000.00
1.00079,000.00
0.0000.00

0034                          2001.00 25.00174.0004,350.00
GRAVEL SURFACE COURSE m3 174.0004,350.00
364.7709,119.25
16.470411.75

0035                          2009.10 1,600.002.8394,542.40
GRAVEL EMBEDMENT StaM2.8394,542.40
2.8394,542.40
0.0000.00

0036                          3011.23 65.0090.4005,876.00
CONCRETE CLASS 47B-25 CURB, TYPE 1 m 90.4005,876.00
122.3107,950.15
0.0000.00

0037                          3013.10 70.0026.4001,848.00
CONCRETE CLASS 47B-20 BARRIER CURB m 26.4001,848.00
9.100637.00
0.0000.00

0038                          3014.12 72.00184.70013,298.40
COMBINATION CONCRETE CLASS 47B-25 CURB AND GUTTER m 184.70013,298.40
0.0000.00
0.0000.00

0039                          3016.21 34.001,507.00051,238.00
CONCRETE CLASS 47B-20 SIDEWALKS m2 1,507.00051,238.00
1,819.84061,874.55
245.9268,361.48

0040                          3020.26 35.001,978.00069,230.00
CONCRETE CLASS 47B-25 DRIVEWAY m2 1,978.00069,230.00
3,268.816114,408.57
0.0000.00

0041                          3040.12 150.0026.3003,945.00
CONCRETE PAVEMENT REPAIR, TYPE B, FULL DEPTH m2 26.3003,945.00
0.0000.00
0.0000.00

0042                          3040.13 150.0061.4009,210.00
CONCRETE PAVEMENT REPAIR, TYPE C, FULL DEPTH m2 61.4009,210.00
0.0000.00
0.0000.00

0043                          3075.41 28.7525,735.000739,881.25
230 mm CONCRETE PAVEMENT, CLASS 47B-25 m2 25,735.000739,881.25
37,207.6391,069,719.62
1,240.29635,658.51

0044                          3089.25 29.007,763.000225,127.00
TEMPORARY SURFACING m2 0.0000.00
646.68818,753.96
0.0000.00

0045                          3221.05 180.0040.2007,236.00
CONCRETE PAVEMENT, CLASS PR-25 m2 40.2007,236.00
JOINT REPAIR 0.0000.00
0.0000.00

0046                          7503.14 7.003,400.00023,800.00
100 mm YELLOW PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 3,400.00023,800.00
4,738.20033,167.40
0.0000.00

0047                          8029.84 1.5025,536.00038,304.00
BITUMINOUS FOUNDATION COURSE 100 mm m2 25,536.00038,304.00
37,207.63955,811.45
1,240.2961,860.44

0048                          9000.75 25.00500.00012,500.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 500.00012,500.00
SP2(12.5) 164.2604,106.50
0.0000.00

0049                          9005.00 34.00100.0003,400.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 100.0003,400.00
SP4(12.5) 0.0000.00
0.0000.00

0050                          9005.45 35.002,420.00084,700.00
ASPHALTIC CONCRETE, TYPE SP4(12.5) Mg 2,420.00084,700.00
0.0000.00
0.0000.00

0051                          9020.92 210.0027.0005,670.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 27.0005,670.00
8.3001,743.00
0.0000.00

0052                          9021.04 220.00130.68028,749.60
PERFORMANCE GRADED BINDER (70-28) Mg 130.68028,749.60
0.0000.00
0.0000.00

0053                          9034.00 2.751,978.0005,439.50
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 1,978.0005,439.50
3,268.8168,989.25
0.0000.00

0054                          9053.00 0.406,730.0002,692.00
TACK COAT L 6,730.0002,692.00
0.0000.00
0.0000.00

0055                          9111.00 2.00440.000880.00
WATER kL 440.000880.00
0.0000.00
0.0000.00

0056                          9170.00 350.0030.04210,514.70
EARTH SHOULDER CONSTRUCTION StaM30.04210,514.70
44.34615,521.10
0.0000.00

0057                          9173.20 1.1526,712.00030,718.80
SUBGRADE PREPARATION m2 26,712.00030,718.80
37,207.63942,788.78
1,240.2961,426.34

0058                          9179.34 3.1222,760.00071,011.20
COLD MILLING, CLASS 4 m2 22,760.00071,011.20
19,499.94060,839.81
43.965137.17

0059                          9179.54 1.809,624.00017,323.20
COLD MILLING, CLASS 4 m2 9,624.00017,323.20
TYPE A 11,329.82120,393.68
0.0000.00

401                           3089.25 31.000.0000.00
TEMPORARY SURFACING m2 3,300.000102,300.00
Revised 2,820.13287,424.09
0.0000.00

402                           1101.25 8.200.0000.00
SAWING PAVEMENT m 130.0001,066.00
295.3982,422.27
0.0000.00

403                           2011.05 32.000.0000.00
CRUSHED ROCK FOR TEMPORARY SURFACING Mg 20.000640.00
224.0777,170.46
5.897188.70

404                           0030.01 12,000.000.0000.00
ADDITIONAL MOBILIZATION LS 1.00012,000.00
1.00012,000.00
0.0000.00

408                           1000.00 500.000.0000.00
LARGE TREE REMOVAL EACH2.0001,000.00
6.0003,000.00
0.0000.00

410                           2021.00 54.000.0000.00
MAILBOX POST EACH7.000378.00
8.000432.00
0.0000.00

419                           7500.23 89.250.0000.00
LEFT ARROW, PREFORMED PAVEMENT MARKING, TYPE 3 EACH24.0002,142.00
grooving only 52.0004,641.00
0.0000.00

420                           7508.14 6.220.0000.00
300 mm WHITE PREFORMED PAVEMENT MARKING, TYPE 4, GROOVED m 50.000311.00
grooving only 33.528208.54
0.0000.00

426                           7500.12 2.850.0000.00
300 mm WHITE LINE m 34.00096.90
painting only 34.00096.90
0.0000.00

427                           7500.33 85.000.0000.00
ARROW EACH26.0002,210.00
painting only 52.0004,420.00
0.0000.00

428                           4024.60 1,875.000.0000.00
CONCRETE FLUME EACH1.0001,875.00
1.0001,875.00
0.0000.00

602                           3300.03 -314.340.0000.00
DEDUCTION LS 1.000-314.34
For deficient thickness 0.0000.00
0.0000.00

GROUP 3 CONCRETE PAVEMENTContracted1,572,441.45
Current1,471,019.01
In place1,810,297.60
This Estimate48,044.39

GROUP 4 CULVERTS
0060                          P700.15 81.00232.10018,800.10
375 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 232.10018,800.10
213.20017,269.19
-18.900-1,530.90

0061                          P700.18 90.00179.20016,128.00
450 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 179.20016,128.00
299.31726,938.53
27.2072,448.63

0062                          P700.24 115.00284.60032,729.00
600 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 284.60032,729.00
309.53435,596.42
0.0242.76

0063                          P700.30 155.00125.40019,437.00
750 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 125.40019,437.00
125.69019,481.95
0.0000.00

0064                          P700.36 200.00110.70022,140.00
900 mm STORM SEWER PIPE, TYPE 1,7 OR 8 m 110.70022,140.00
138.20027,640.00
0.0000.00

0065                          P702.15 81.0017.4001,409.40
375 mm STORM SEWER PIPE, TYPE 1 m 17.4001,409.40
20.6001,668.60
0.0000.00

0066                          P702.18 90.00113.50010,215.00
450 mm STORM SEWER PIPE, TYPE 1 m 113.50010,215.00
112.81010,152.90
-14.050-1,264.50

0067                          P702.24 115.0044.3005,094.50
600 mm STORM SEWER PIPE, TYPE 1 m 44.3005,094.50
45.1305,189.95
0.0000.00

0068                          P702.36 200.0015.6003,120.00
900 mm STORM SEWER PIPE, TYPE 1 m 15.6003,120.00
14.7702,954.00
0.0000.00

0069                          P702.42 250.0070.20017,550.00
1050 mm STORM SEWER PIPE, TYPE 1 m 70.20017,550.00
69.61217,403.00
0.0000.00

0070                          P702.48 300.00235.80070,740.00
1200 mm STORM SEWER PIPE, TYPE 1 m 235.80070,740.00
875.865262,759.50
-30.025-9,007.50

0071                          P702.54 375.00111.00041,625.00
1350 mm STORM SEWER PIPE, TYPE 1 m 111.00041,625.00
109.48241,055.75
-0.820-307.50

0072                          P702.60 470.0055.20025,944.00
1500 mm STORM SEWER PIPE, TYPE 1 m 55.20025,944.00
54.84025,774.80
0.0000.00

0073                          P702.72 685.0097.90067,061.50
1800 mm STORM SEWER PIPE, TYPE 1 m 97.90067,061.50
94.69064,862.65
0.0000.00

0074                          P705.72 575.0016.1009,257.50
1800 mm STORM SEWER PIPE, TYPE 1 CLASS IV m 16.1009,257.50
18.28810,515.60
0.0000.00

0075                          P775.48 450.0030.40013,680.00
1200 mm ROUND EQUIVALENT STORM SEWER PIPE, TYPE 1 m 30.40013,680.00
30.11013,549.50
0.0000.00

0076                          0030.40 50,000.001.00050,000.00
MOBILIZATION LS 1.00050,000.00
1.00050,000.00
0.0000.00

0077                          1119.00 335.0024.0008,040.00
REMOVE INLET EACH24.0008,040.00
25.0008,375.00
0.0000.00

0078                          1119.50 395.002.000790.00
REMOVE JUNCTION BOX EACH2.000790.00
2.000790.00
-1.000-395.00

0079                          4002.00 3.003,249.0009,747.00
CAST IRON COVER AND FRAME kg 3,249.0009,747.00
3,306.0009,918.00
134.000402.00

0080                          4004.50 3.00925.0002,775.00
CAST IRON GRATE AND FRAME kg 925.0002,775.00
3,775.00011,325.00
120.000360.00

0081                          4018.00 450.001.000450.00
TAPPING EXISTING STRUCTURE EACH1.000450.00
0.0000.00
0.0000.00

0082                          4035.00 100.008.000800.00
REMOVE FLARED-END SECTION EACH8.000800.00
8.000800.00
0.0000.00

0083                          4040.00 120.007.000840.00
REMOVE HEADWALLS FROM CULVERTS EACH7.000840.00
7.000840.00
0.0000.00

0084                          4043.50 32.00385.20012,326.40
REMOVE SEWER PIPE m 385.20012,326.40
391.31012,521.92
14.910477.12

0085                          4045.00 700.001.000700.00
REMOVE STRUCTURE EACH1.000700.00
AT STA. 19+03.1, 16.0 m RT. 1.000700.00
0.0000.00

0086                          4045.01 1,400.001.0001,400.00
REMOVE STRUCTURE EACH1.0001,400.00
AT STA. 21+09.5 1.0001,400.00
0.0000.00

0087                          4050.01 10.001,003.00010,030.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 1,003.00010,030.00
1,003.00010,030.00
5.00050.00

0088                          4102.11 550.0051.10028,105.00
CLASS 47B-20 OR AX-20 CONCRETE FOR RETAINING WALL m3 35.80019,690.00
82.33545,284.25
0.0000.00

0089                          4105.59 800.00175.050140,040.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 175.050140,040.00
228.600182,880.00
-6.429-5,143.20

0090                          4107.07 750.0016.06012,045.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 16.06012,045.00
4.2403,180.00
0.0000.00

0091                          4130.06 750.001.200900.00
CLASS 47B-20 OR AX-20 CONCRETE FOR PIPE CULVERT PLUG m3 1.200900.00
0.170127.50
0.0000.00

0092                          4152.00 1.202,785.7003,342.84
REINFORCING STEEL FOR RETAINING WALL kg 1,996.7002,396.04
4,789.0605,746.87
0.0000.00

0093                          4155.50 1.407,533.00010,546.20
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 7,533.00010,546.20
8,835.06012,369.08
-226.790-317.51

0094                          4157.00 1.40638.560893.98
REINFORCING STEEL FOR COLLARS kg 638.560893.98
153.000214.20
0.0000.00

0095                          4310.15 300.002.000600.00
375 mm FLARED-END SECTION EACH2.000600.00
2.000600.00
0.0000.00

0096                          4310.18 300.006.0001,800.00
450 mm FLARED-END SECTION EACH6.0001,800.00
7.0002,100.00
0.0000.00

0097                          4310.24 360.004.0001,440.00
600 mm FLARED-END SECTION EACH4.0001,440.00
4.0001,440.00
0.0000.00

0098                          4310.36 575.001.000575.00
900 mm FLARED-END SECTION EACH1.000575.00
1.000575.00
0.0000.00

0099                          4310.72 1,500.001.0001,500.00
1800 mm FLARED-END SECTION EACH1.0001,500.00
1.0001,500.00
0.0000.00

0100                          4320.48 1,000.001.0001,000.00
1200 mm ROUND EQUIVALENT FLARED-END SECTION EACH1.0001,000.00
1.0001,000.00
0.0000.00

0101                          4852.72 1,650.0016.10026,565.00
JACKING 1800 mm STORM SEWER PIPE, TYPE m 16.10026,565.00
1 CLASS IV 18.28830,175.20
0.0000.00

411                           W760.00 1,755.600.0000.00
WATER MAIN RELOCATION EACH2.0003,511.20
2.0003,511.20
0.0000.00

412                           4042.65 503.210.0000.00
RECONSTRUCT WATER SERVICE EACH4.0002,012.84
4.0002,012.84
0.0000.00

413                           4039.10 105.000.0000.00
REMOVE AND RELAY REINFORCED CONCRETE SEWER PIPE m 46.3004,861.50
1200mm pipe 46.3004,861.50
0.0000.00

414                           4039.10 137.300.0000.00
REMOVE AND RELAY REINFORCED CONCRETE SEWER PIPE m 12.1901,673.69
900mm pipe 12.1901,673.69
0.0000.00

415                           4976.20 1,274.440.0000.00
SANITARY SEWER MODIFICATION EACH4.0005,097.76
4.0005,097.76
0.0000.00

416                           4018.50 299.250.0000.00
TAPPING EXISTING PIPE EACH1.000299.25
1.000299.25
0.0000.00

418                           4015.50 945.000.0000.00
RECONSTRUCT MANHOLE EACH1.000945.00
1.000945.00
0.0000.00

421                           4094.01 226.040.0000.00
CMU WALL m2 35.0007,911.40
modular wall 35.2807,974.69
0.0000.00

422                           4043.50 42.000.0000.00
REMOVE SEWER PIPE m 671.46028,201.32
1200mm corrugated metal 671.46028,201.32
0.0000.00

GROUP 4 CULVERTSContracted702,182.42
Current747,334.58
In place1,031,281.61
This Estimate-14,225.60

GROUP 4A WATER MAIN & SANITARY SEWER CONSTRUCTION
0102                          W100.00 200.0027.0005,400.00
CURB STOP AND BOX EACH27.0005,400.00
25 mm 30.0006,000.00
0.0000.00

0103                          W175.01 160.0027.0004,320.00
25 mm CORPORATION STOP EACH27.0004,320.00
30.0004,800.00
0.0000.00

0104                          W176.26 36.00399.00014,364.00
25 mm WATER SERVICE m 399.00014,364.00
383.10013,791.60
0.0000.00

0105                          W176.71 55.0027.0001,485.00
WATER SERVICE CONNECTION EACH27.0001,485.00
25 mm 30.0001,650.00
0.0000.00

0106                          W205.04 38.0015.820601.16
100 mm WATER MAIN PIPE m 15.820601.16
10.830411.55
0.0000.00

0107                          W205.06 40.0012.780511.20
150 mm WATER MAIN PIPE m 12.780511.20
19.220768.80
0.0000.00

0108                          W205.08 50.001,232.69061,634.50
200 mm WATER MAIN PIPE m 1,232.69061,634.50
1,221.13061,056.50
0.0000.00

0109                          W205.12 65.00117.2307,619.95
300 mm WATER MAIN PIPE m 117.2307,619.95
117.7607,654.40
0.0000.00

0110                          W220.06 400.006.0002,400.00
150 mm GATE VALVE, M.J. EACH6.0002,400.00
6.0002,400.00
0.0000.00

0111                          W220.08 540.0021.00011,340.00
200 mm GATE VALVE, M.J. EACH21.00011,340.00
18.0009,720.00
0.0000.00

0112                          W220.12 905.003.0002,715.00
300 mm GATE VALVE, M.J. EACH3.0002,715.00
3.0002,715.00
0.0000.00

0113                          W221.06 130.006.000780.00
150 mm WATER VALVE BOX EACH6.000780.00
6.000780.00
0.0000.00

0114                          W221.08 130.0021.0002,730.00
200 mm WATER VALVE BOX EACH21.0002,730.00
18.0002,340.00
0.0000.00

0115                          W221.12 130.003.000390.00
300 mm WATER VALVE BOX EACH3.000390.00
3.000390.00
0.0000.00

0116                          W222.06 1,600.006.0009,600.00
150 mm FIRE HYDRANT EACH6.0009,600.00
6.0009,600.00
0.0000.00

0117                          W355.04 260.006.0001,560.00
100 mm SLEEVE EACH6.0001,560.00
4.0001,040.00
0.0000.00

0118                          W355.08 300.002.000600.00
200 mm SLEEVE EACH2.000600.00
1.000300.00
0.0000.00

0119                          W355.12 350.001.000350.00
300 mm SLEEVE EACH1.000350.00
1.000350.00
0.0000.00

0120                          W356.05 200.006.0001,200.00
100 mm X 100 mm TEE EACH6.0001,200.00
4.000800.00
0.0000.00

0121                          W356.14 210.006.0001,260.00
200 mm X 150 mm TEE EACH6.0001,260.00
7.0001,470.00
0.0000.00

0122                          W356.16 225.009.0002,025.00
200 mm X 200 mm TEE EACH9.0002,025.00
6.0001,350.00
0.0000.00

0123                          W356.19 300.001.000300.00
300 mm X 150 mm TEE EACH1.000300.00
1.000300.00
0.0000.00

0124                          W356.20 400.002.000800.00
300 mm X 300 mm TEE EACH2.000800.00
2.000800.00
0.0000.00

0125                          W356.50 400.002.000800.00
CROSS EACH2.000800.00
200 mm 2.000800.00
0.0000.00

0126                          W357.14 140.0012.0001,680.00
100 mm - 45 DEGREE BEND EACH12.0001,680.00
10.0001,400.00
0.0000.00

0127                          W357.40 170.0014.0002,380.00
200 mm - 45 DEGREE BEND EACH14.0002,380.00
12.0002,040.00
0.0000.00

0128                          W357.41 190.005.000950.00
200 mm - 90 DEGREE BEND EACH5.000950.00
6.0001,140.00
0.0000.00

0129                          W357.42 275.001.000275.00
300 mm - 90 DEGREE BEND EACH1.000275.00
1.000275.00
0.0000.00

0130                          W357.51 260.002.000520.00
300 mm - 11 1/4 DEGREE BEND EACH2.000520.00
1.000260.00
0.0000.00

0131                          W358.19 95.006.000570.00
200 mm X 100 mm REDUCER EACH6.000570.00
4.000380.00
0.0000.00

0132                          W358.23 120.001.000120.00
300 mm X 200 mm REDUCER EACH1.000120.00
1.000120.00
0.0000.00

0133                          W722.51 5.001,255.9106,279.55
ABANDON WATER MAIN m 1,255.9106,279.55
619.0003,095.00
0.0000.00

0134                          W800.24 140.004.000560.00
REMOVE VALVE EACH4.000560.00
- WATER 5.000700.00
0.0000.00

0135                          W800.33 175.007.0001,225.00
REMOVE HYDRANT EACH7.0001,225.00
FIRE 8.0001,400.00
0.0000.00

0136                          W800.40 50.001.00050.00
REMOVE BEND EACH1.00050.00
150 mm - 45 DEGREE 1.00050.00
0.0000.00

0137                          W800.93 35.00196.0006,860.00
BORING 25 mm WATER SERVICE m 196.0006,860.00
82.6002,891.00
0.0000.00

0138                          0030.40 20,000.001.00020,000.00
MOBILIZATION LS 1.00020,000.00
1.00020,000.00
0.0000.00

0139                          1090.03 7.004.60032.20
ABANDON SEWER PIPE m 4.60032.20
0.0000.00
0.0000.00

0140                          1117.00 350.005.0001,750.00
REMOVE MANHOLE EACH5.0001,750.00
5.0001,750.00
0.0000.00

0141                          4016.00 2,600.001.0002,600.00
MANHOLE EACH1.0002,600.00
AT STA. 15+71.90, 11 m LT. 1.0002,600.00
0.0000.00

0142                          4016.01 3,000.001.0003,000.00
MANHOLE EACH1.0003,000.00
AT STA. 16+31.00, 10.6 m LT. 1.0003,000.00
0.0000.00

0143                          4016.02 3,200.001.0003,200.00
MANHOLE EACH1.0003,200.00
AT STA. 16+71.00, 11.24 m LT. 1.0003,200.00
0.0000.00

0144                          4016.03 3,200.001.0003,200.00
MANHOLE EACH1.0003,200.00
AT STA. 17+84.33, 11.68 m LT. 1.0003,200.00
0.0000.00

0145                          4016.04 2,800.001.0002,800.00
MANHOLE EACH1.0002,800.00
AT STA. 21+17.66, 11.36 m LT. 1.0002,800.00
0.0000.00

0146                          4016.05 2,800.001.0002,800.00
MANHOLE EACH1.0002,800.00
AT STA. 22+28.63, 14.16 m LT. 0.0000.00
0.0000.00

0147                          4042.55 350.002.000700.00
CONNECT SANITARY SERVICE EACH2.000700.00
3.0001,050.00
0.0000.00

0148                          4043.50 28.0099.0602,773.68
REMOVE SEWER PIPE m 99.0602,773.68
103.6602,902.48
0.0000.00

0149                          4731.08 59.00101.9506,015.05
200 mm SANITARY SEWER PIPE m 101.9506,015.05
106.3406,274.06
0.0000.00

0150                          4795.98 82.002.000164.00
300 mm PLUG EACH2.000164.00
2.000164.00
0.0000.00

0151                          4795.99 40.006.000240.00
100 mm PLUG EACH6.000240.00
4.000160.00
0.0000.00

0152                          4796.00 45.001.00045.00
150 mm PLUG EACH1.00045.00
0.0000.00
0.0000.00

0153                          4796.01 70.003.000210.00
200 mm PLUG EACH3.000210.00
3.000210.00
0.0000.00

0154                          4805.20 425.00134.09056,988.25
500 mm STEEL CASING m 134.09056,988.25
134.09056,988.25
0.0000.00

417                           6960.01 2,053.800.0000.00
ADDITIONAL LS 1.0002,053.80
Miscellaneous water line fittings 1.0002,053.80
0.0000.00

423                           W600.03 89.250.0000.00
ADJUST VALVE BOX TO GRADE EACH5.000446.25
5.000446.25
0.0000.00

424                           W600.21 456.210.0000.00
ADJUST FIRE HYDRANT TO GRADE EACH4.0001,824.84
4.0001,824.84
0.0000.00

425                           4016.06 2,808.750.0000.00
MANHOLE EACH1.0002,808.75
at Sta 24+50.25- 13.6m lt 1.0002,808.75
0.0000.00

431                           4976.05 10,881.070.0000.00
ADDITIONAL WORK LS 1.00010,881.07
Adjustments for retaining wall 0.0000.00
0.0000.00

GROUP 4A WATER MAIN & SANITARY SEWER CONSTRUCTIONContracted262,773.54
Current280,788.25
In place256,471.28
This Estimate0.00

GROUP 7 GUARDRAIL
0155                          0030.70 2,000.001.0002,000.00
MOBILIZATION LS 1.0002,000.00
1.0002,000.00
0.0000.00

0156                          7011.20 55.00167.6009,218.00
W-BEAM GUARDRAIL m 167.6009,218.00
167.6009,218.00
0.0000.00

0157                          7020.00 1,400.001.0001,400.00
BRIDGE APPROACH SECTIONS EACH1.0001,400.00
1.0001,400.00
0.0000.00

0158                          7024.25 2,300.001.0002,300.00
GUARDRAIL END TREATMENT, TYPE I EACH1.0002,300.00
1.0002,300.00
0.0000.00

409                           7025.48 63.000.0000.00
GUARDRAIL POSTS EACH90.0005,670.00
88.0005,544.00
0.0000.00

GROUP 7 GUARDRAILContracted14,918.00
Current20,588.00
In place20,462.00
This Estimate0.00

GROUP 8B ELECTRICAL
0159                          A001.01 450.002.000900.00
PULL BOX, TYPE PB-1 EACH2.000900.00
2.000900.00
0.0000.00

0160                          A001.12 350.0014.0004,900.00
PULL BOX, TYPE PB-5 EACH14.0004,900.00
10.0003,500.00
1.000350.00

0161                          A001.16 450.002.000900.00
PULL BOX, TYPE PB-6 EACH2.000900.00
1.000450.00
0.0000.00

0162                          A003.10 275.004.0001,100.00
TRAFFIC SIGNAL, TYPE TS-1 EACH4.0001,100.00
4.0001,100.00
0.0000.00

0163                          A006.75 650.004.0002,600.00
PEDESTAL POLE, TYPE PP-3048 EACH4.0002,600.00
4.0002,600.00
0.0000.00

0164                          A008.91 1,500.0050.00075,000.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-1.8-0.25F EACH50.00075,000.00
50.00075,000.00
0.0000.00

0165                          A009.15 1,800.001.0001,800.00
STREET LIGHTING UNIT, TYPE SL-BT-12.2-3.7-0.25F EACH1.0001,800.00
1.0001,800.00
0.0000.00

0166                          A070.10 7.002,446.00017,122.00
38 mm CONDUIT IN TRENCH m 2,446.00017,122.00
2,418.00016,926.00
0.0000.00

0167                          A070.14 7.0015.000105.00
50 mm CONDUIT IN TRENCH m 15.000105.00
100.000700.00
0.0000.00

0168                          A072.10 6.75647.0004,367.25
38 mm CONDUIT UNDER ROADWAY m 647.0004,367.25
577.0003,894.75
0.0000.00

0169                          A074.14 45.0081.0003,645.00
50 mm CONDUIT, JACKED m 81.0003,645.00
20.000900.00
0.0000.00

0170                          A077.12 2.0096.000192.00
2/C #14 AWG TRAFFIC SIGNAL CABLE m 96.000192.00
111.000222.00
0.0000.00

0171                          A079.50 1.0096.00096.00
GROUNDING CONDUCTOR m 96.00096.00
111.000111.00
0.0000.00

0172                          A080.10 3.00368.0001,104.00
STREET LIGHTING CABLE, NO. 2 USE m 368.0001,104.00
603.0001,809.00
0.0000.00

0173                          A080.22 1.503,093.0004,639.50
STREET LIGHTING CABLE, NO. 6 BARE m 3,093.0004,639.50
2,953.0004,429.50
0.0000.00

0174                          A080.24 1.708,911.00015,148.70
STREET LIGHTING CABLE, NO. 6 USE m 8,911.00015,148.70
8,256.00014,035.20
0.0000.00

0175                          A501.75 450.002.000900.00
INSTALL FLASHER CONTROLLER EACH2.000900.00
2.000900.00
0.0000.00

0176                          A600.00 200.004.000800.00
REMOVE LIGHTING UNIT EACH4.000800.00
4.000800.00
0.0000.00

0177                          A610.00 400.001.000400.00
REMOVE TRAFFIC SIGNAL EACH1.000400.00
AT US-275 & 6TH ST. 1.000400.00
0.0000.00

0178                          A610.01 400.001.000400.00
REMOVE TRAFFIC SIGNAL EACH1.000400.00
AT US-275 & 3RD ST. 1.000400.00
0.0000.00

0179                          A620.02 200.001.000200.00
REMOVE LIGHTING CONTROL CENTER EACH1.000200.00
1.000200.00
0.0000.00

0180                          0030.81 20,000.001.00020,000.00
MOBILIZATION LS 1.00020,000.00
1.00020,000.00
0.0000.00

0181                          3970.00 220,000.001.000220,000.00
RELOCATION LS 1.000220,000.00
OF ELECTRIC SYSTEM 1.000220,000.00
0.0000.00

405                           6960.01 19,309.410.0000.00
ADDITIONAL LS 1.00019,309.41
electrical work 1.00019,309.41
0.0000.00

406                           A020.30 1,679.900.0000.00
LIGHTING CONTROL CENTER, TYPE R EACH3.0005,039.70
3.0005,039.70
0.0000.00

GROUP 8B ELECTRICALContracted376,319.45
Current400,668.56
In place395,426.56
This Estimate350.00

GROUP 10 GENERAL ITEMS
0182                          0001.08 0.507,546.0003,773.00
BARRICADE, TYPE II BDAY7,546.0003,773.00
35,964.00017,982.00
594.000297.00

0183                          0001.10 3.002,896.0008,688.00
BARRICADE, TYPE III BDAY2,896.0008,688.00
21,191.00063,573.00
918.0002,754.00

0184                          0001.30 2.50192.000480.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY192.000480.00
823.0002,057.50
-73.000-182.50

0185                          0001.90 0.407,957.0003,182.80
SIGN DAY EACH7,957.0003,182.80
29,519.00011,807.60
-512.000-204.80

0186                          0002.30 3.501,500.0005,250.00
PAVEMENT MARKING REMOVAL m 1,500.0005,250.00
1,986.3006,952.05
0.0000.00

0187                          0002.31 1.207,000.0008,400.00
TEMPORARY PAVEMENT MARKING m 7,000.0008,400.00
7,749.0009,298.80
0.0000.00

0188                          0003.10 150.0090.00013,500.00
FLAGGING DAY 90.00013,500.00
5.500825.00
0.0000.00

0189                          0010.04 2,500.001.0002,500.00
FIELD OFFICE EACH1.0002,500.00
1.0002,500.00
0.0000.00

0190                          0030.00 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

0191                          9110.01 60.0020.0001,200.00
RENTAL OF LOADER, FULLY OPERATED HOUR20.0001,200.00
12.500750.00
0.0000.00

0192                          9110.02 60.0010.000600.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR10.000600.00
0.0000.00
0.0000.00

0193                          9110.03 45.0020.000900.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR20.000900.00
21.000945.00
0.0000.00

0194                          9110.07 25.0020.000500.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR20.000500.00
0.0000.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted51,973.80
Current51,973.80
In place119,690.95
This Estimate2,663.70

Totals for contractContracted3,189,998.76
Current3,193,674.65
In place3,903,829.58
This Estimate36,999.40