| | | 1. Contracted
|
|---|
| | | 2. Current
|
|---|
| | | 3. To date
|
|---|
| Item Nbr Item Code | Unit Price | | 4. This Est
|
|---|
| Item Description | Units | Qty | Amount
|
|---|
| GROUP 1 GRADING | | |
|
| 0001 L001.01 | 2,500.00 | 4.000 | 10,000.00
|
| SEEDING, TYPE A | ha | 4.000 | 10,000.00
|
| | | 3.500 | 8,750.00
|
| | 3.500 | 8,750.00
|
| | |
|
| 0002 L006.00 | 438.00 | 4.000 | 1,752.00
|
| COVER CROP SEEDING | ha | 4.000 | 1,752.00
|
| | | 4.000 | 1,752.00
|
| | 4.000 | 1,752.00
|
| | |
|
| 0003 L032.75 | 150.00 | 20.000 | 3,000.00
|
| MULCH | Mg | 20.000 | 3,000.00
|
| | | 15.750 | 2,362.50
|
| | 15.750 | 2,362.50
|
| | |
|
| 0004 0030.10 | 10,000.00 | 1.000 | 10,000.00
|
| MOBILIZATION | LS | 1.000 | 10,000.00
|
| | | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0005 1009.00 | 4,500.00 | 1.000 | 4,500.00
|
| GENERAL CLEARING AND GRUBBING | LS | 1.000 | 4,500.00
|
| | | 1.000 | 4,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0006 1010.01 | 3.00 | 11,005.000 | 33,015.00
|
| EXCAVATION (ESTABLISHED QUANTITY) | m3 | 11,005.000 | 33,015.00
|
| | | 11,005.000 | 33,015.00
|
| | 1,005.000 | 3,015.00
|
| | |
|
| 0007 1011.00 | 1.50 | 230.000 | 345.00
|
| WATER | kL | 230.000 | 345.00
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0008 2009.51 | 1,000.00 | 7.952 | 7,952.00
|
| CRUSHED ROCK EMBEDMENT | StaM | 7.952 | 7,952.00
|
| | | 7.200 | 7,200.00
|
| | 0.000 | 0.00
|
| | |
|
| 0009 2010.00 | 20.00 | 469.000 | 9,380.00
|
| CRUSHED ROCK SURFACE COURSE | m3 | 469.000 | 9,380.00
|
| | | 425.000 | 8,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0010 4043.00 | 10.00 | 25.100 | 251.00
|
| REMOVE CULVERT PIPE | m | 25.100 | 251.00
|
| | | 25.100 | 251.00
|
| | 0.000 | 0.00
|
| | |
|
| 0011 4050.01 | 2.00 | 1,057.000 | 2,114.00
|
| EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 1,057.000 | 2,114.00
|
| | | 1,057.000 | 2,114.00
|
| | 0.000 | 0.00
|
| | |
|
| 0012 4300.24 | 34.00 | 25.000 | 850.00
|
| 600 mm CULVERT PIPE | m | 25.000 | 850.00
|
| | | 25.000 | 850.00
|
| | 0.000 | 0.00
|
| | |
|
| 0013 4300.48 | 110.00 | 11.500 | 1,265.00
|
| 1200 mm CULVERT PIPE | m | 11.500 | 1,265.00
|
| | | 11.500 | 1,265.00
|
| | 0.000 | 0.00
|
| | |
|
| 0014 4300.60 | 185.00 | 60.500 | 11,192.50
|
| 1500 mm CULVERT PIPE | m | 60.500 | 11,192.50
|
| | | 60.500 | 11,192.50
|
| | 0.000 | 0.00
|
| | |
|
| 0015 4310.24 | 150.00 | 4.000 | 600.00
|
| 600 mm FLARED-END SECTION | EACH | 4.000 | 600.00
|
| | | 4.000 | 600.00
|
| | 0.000 | 0.00
|
| | |
|
| 0016 4310.48 | 650.00 | 2.000 | 1,300.00
|
| 1200 mm FLARED-END SECTION | EACH | 2.000 | 1,300.00
|
| | | 2.000 | 1,300.00
|
| | 0.000 | 0.00
|
| | |
|
| 0017 4310.60 | 1,200.00 | 1.000 | 1,200.00
|
| 1500 mm FLARED-END SECTION | EACH | 1.000 | 1,200.00
|
| | | 1.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 1 GRADING | | Contracted | 98,716.50
|
| | Current | 98,716.50
|
| | In place | 94,852.00
|
| | This Estimate | 15,879.50
|
| | |
|
| GROUP 6 BRIDGE AT STA. 7+94.7 | | |
|
| 0018 0030.60 | 20,000.00 | 1.000 | 20,000.00
|
| MOBILIZATION | LS | 1.000 | 20,000.00
|
| | | 1.000 | 20,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0019 1043.50 | 4.00 | 2,072.000 | 8,288.00
|
| RIPRAP FILTER FABRIC | m2 | 2,072.000 | 8,288.00
|
| | | 2,072.000 | 8,288.00
|
| | 0.000 | 0.00
|
| | |
|
| 0020 6000.10 | 7,000.00 | 1.000 | 7,000.00
|
| ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 7,000.00
|
| | | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0021 6000.11 | 7,000.00 | 1.000 | 7,000.00
|
| ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 7,000.00
|
| | | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0022 6000.60 | 12,500.00 | 1.000 | 12,500.00
|
| PIER NO.1 EXCAVATION | LS | 1.000 | 12,500.00
|
| | | 1.000 | 12,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0023 6000.61 | 12,500.00 | 1.000 | 12,500.00
|
| PIER NO.2 EXCAVATION | LS | 1.000 | 12,500.00
|
| | | 1.000 | 12,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0024 6005.78 | 650.00 | 12.000 | 7,800.00
|
| EXPANSION BEARING, TFE TYPE | EACH | 12.000 | 7,800.00
|
| | | 12.000 | 7,800.00
|
| | 0.000 | 0.00
|
| | |
|
| 0025 6005.83 | 600.00 | 4.000 | 2,400.00
|
| FIXED BEARING | EACH | 4.000 | 2,400.00
|
| | | 4.000 | 2,400.00
|
| | 0.000 | 0.00
|
| | |
|
| 0026 6010.22 | 300.00 | 309.300 | 92,790.00
|
| CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 309.300 | 92,790.00
|
| | | 309.300 | 92,790.00
|
| | 0.000 | 0.00
|
| | |
|
| 0027 6010.26 | 325.00 | 124.300 | 40,397.50
|
| CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 124.300 | 40,397.50
|
| | | 124.300 | 40,397.50
|
| | 0.000 | 0.00
|
| | |
|
| 0028 6020.00 | 1.00 | 27,755.000 | 27,755.00
|
| REINFORCING STEEL FOR BRIDGE | kg | 27,755.000 | 27,755.00
|
| | | 27,755.000 | 27,755.00
|
| | 0.000 | 0.00
|
| | |
|
| 0029 6040.00 | 6,500.00 | 1.000 | 6,500.00
|
| REMOVE STRUCTURE | EACH | 1.000 | 6,500.00
|
| AT STA. 8+00.20 LT. | | 1.000 | 6,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0030 6071.12 | 85,000.00 | 1.000 | 85,000.00
|
| STEEL SUPERSTRUCTURE | LS | 1.000 | 85,000.00
|
| AT STA. 7+94.70 | | 1.000 | 85,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0031 6080.00 | 4.00 | 2,375.000 | 9,500.00
|
| STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 2,375.000 | 9,500.00
|
| | | 2,375.000 | 9,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0032 6105.02 | 36.00 | 1,945.000 | 70,020.00
|
| ROCK RIPRAP, TYPE B | Mg | 1,945.000 | 70,020.00
|
| | | 1,953.000 | 70,308.00
|
| | 0.000 | 0.00
|
| | |
|
| 0033 6200.00 | 80.00 | 482.800 | 38,624.00
|
| CONCRETE PILING | m | 482.800 | 38,624.00
|
| | | 473.813 | 37,905.04
|
| | 0.000 | 0.00
|
| | |
|
| 0034 6310.00 | 125.00 | 307.600 | 38,450.00
|
| STEEL SHEET PILING | m2 | 307.600 | 38,450.00
|
| | | 307.600 | 38,450.00
|
| | 0.000 | 0.00
|
| | |
|
| 0035 7020.00 | 1,000.00 | 4.000 | 4,000.00
|
| BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,000.00
|
| | | 4.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0036 7021.45 | 875.00 | 4.000 | 3,500.00
|
| BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 3,500.00
|
| | | 4.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | |
|
| 0402 6210.59 | 48.00 | 0.000 | 0.00
|
| PILE CUT-OFF | m | 20.000 | 960.00
|
| See 703.05 Para. 2 of the "97" Metric specs. | | 8.987 | 431.38
|
| | 0.000 | 0.00
|
| | |
|
| 0403 1010.09 | 5,349.28 | 0.000 | 0.00
|
| SPECIAL EXCAVATION | LS | 1.000 | 5,349.28
|
| | | 1.000 | 5,349.28
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 6 BRIDGE AT STA. 7+94.7 | | Contracted | 494,024.50
|
| | Current | 500,333.78
|
| | In place | 499,374.20
|
| | This Estimate | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | |
|
| 0037 0001.10 | 1.15 | 2,172.000 | 2,497.80
|
| BARRICADE, TYPE III | BDAY | 2,172.000 | 2,497.80
|
| | | 2,089.000 | 2,402.35
|
| | 0.000 | 0.00
|
| | |
|
| 0038 0001.30 | 0.65 | 362.000 | 235.30
|
| TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 362.000 | 235.30
|
| | | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
| 0039 0001.90 | 0.65 | 2,896.000 | 1,882.40
|
| SIGN DAY | EACH | 2,896.000 | 1,882.40
|
| | | 1,979.000 | 1,286.35
|
| | 0.000 | 0.00
|
| | |
|
| 0040 0030.10 | 2,000.00 | 1.000 | 2,000.00
|
| MOBILIZATION | LS | 1.000 | 2,000.00
|
| | | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
| 0401 0001.99 | 0.75 | 0.000 | 0.00
|
| CONTRACTOR FURNISHED SIGN DAY | EACH | 1,000.000 | 750.00
|
| Contractor furnished "crashworthy"signs. | | 1,194.000 | 895.50
|
| | 0.000 | 0.00
|
| | |
|
| GROUP 10 GENERAL ITEMS | | Contracted | 6,615.50
|
| | Current | 7,365.50
|
| | In place | 6,584.20
|
| | This Estimate | 0.00
|
| | |
|
| Totals for contract | | Contracted | 599,356.50
|
|---|
| | Current | 606,415.78
|
|---|
| | In place | 600,810.40
|
|---|
| | This Estimate | 15,879.50
|
|---|