| | | 1. Contracted
|
---|
| | | 2. Current
|
---|
| | | 3. To date
|
---|
Item Nbr Item Code | Unit Price | | 4. This Est
|
---|
Item Description | Units | Qty | Amount
|
---|
GROUP 1 GRADING | | |
|
0001 L001.01 | 2,500.00 | 4.000 | 10,000.00
|
SEEDING, TYPE A | ha | 4.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0002 L006.00 | 438.00 | 4.000 | 1,752.00
|
COVER CROP SEEDING | ha | 4.000 | 1,752.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0003 L032.75 | 150.00 | 20.000 | 3,000.00
|
MULCH | Mg | 20.000 | 3,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0004 0030.10 | 10,000.00 | 1.000 | 10,000.00
|
MOBILIZATION | LS | 1.000 | 10,000.00
|
| | 1.000 | 10,000.00
|
| | 0.000 | 0.00
|
| | |
|
0005 1009.00 | 4,500.00 | 1.000 | 4,500.00
|
GENERAL CLEARING AND GRUBBING | LS | 1.000 | 4,500.00
|
| | 1.000 | 4,500.00
|
| | 0.000 | 0.00
|
| | |
|
0006 1010.01 | 3.00 | 11,005.000 | 33,015.00
|
EXCAVATION (ESTABLISHED QUANTITY) | m3 | 11,005.000 | 33,015.00
|
| | 8,000.000 | 24,000.00
|
| | 0.000 | 0.00
|
| | |
|
0007 1011.00 | 1.50 | 230.000 | 345.00
|
WATER | kL | 230.000 | 345.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0008 2009.51 | 1,000.00 | 7.952 | 7,952.00
|
CRUSHED ROCK EMBEDMENT | StaM | 7.952 | 7,952.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0009 2010.00 | 20.00 | 469.000 | 9,380.00
|
CRUSHED ROCK SURFACE COURSE | m3 | 469.000 | 9,380.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0010 4043.00 | 10.00 | 25.100 | 251.00
|
REMOVE CULVERT PIPE | m | 25.100 | 251.00
|
| | 25.100 | 251.00
|
| | -25.100 | -251.00
|
| | |
|
0011 4050.01 | 2.00 | 1,057.000 | 2,114.00
|
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS | m3 | 1,057.000 | 2,114.00
|
| | 1,057.000 | 2,114.00
|
| | 894.000 | 1,788.00
|
| | |
|
0012 4300.24 | 34.00 | 25.000 | 850.00
|
600 mm CULVERT PIPE | m | 25.000 | 850.00
|
| | 25.000 | 850.00
|
| | 0.000 | 0.00
|
| | |
|
0013 4300.48 | 110.00 | 11.500 | 1,265.00
|
1200 mm CULVERT PIPE | m | 11.500 | 1,265.00
|
| | 11.500 | 1,265.00
|
| | 0.000 | 0.00
|
| | |
|
0014 4300.60 | 185.00 | 60.500 | 11,192.50
|
1500 mm CULVERT PIPE | m | 60.500 | 11,192.50
|
| | 60.500 | 11,192.50
|
| | 60.500 | 11,192.50
|
| | |
|
0015 4310.24 | 150.00 | 4.000 | 600.00
|
600 mm FLARED-END SECTION | EACH | 4.000 | 600.00
|
| | 4.000 | 600.00
|
| | 0.000 | 0.00
|
| | |
|
0016 4310.48 | 650.00 | 2.000 | 1,300.00
|
1200 mm FLARED-END SECTION | EACH | 2.000 | 1,300.00
|
| | 2.000 | 1,300.00
|
| | 0.000 | 0.00
|
| | |
|
0017 4310.60 | 1,200.00 | 1.000 | 1,200.00
|
1500 mm FLARED-END SECTION | EACH | 1.000 | 1,200.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
GROUP 1 GRADING | | Contracted | 98,716.50
|
| | Current | 98,716.50
|
| | In place | 56,072.50
|
| | This Estimate | 12,729.50
|
| | |
|
GROUP 6 BRIDGE AT STA. 7+94.7 | | |
|
0018 0030.60 | 20,000.00 | 1.000 | 20,000.00
|
MOBILIZATION | LS | 1.000 | 20,000.00
|
| | 1.000 | 20,000.00
|
| | 0.000 | 0.00
|
| | |
|
0019 1043.50 | 4.00 | 2,072.000 | 8,288.00
|
RIPRAP FILTER FABRIC | m2 | 2,072.000 | 8,288.00
|
| | 2,072.000 | 8,288.00
|
| | 852.000 | 3,408.00
|
| | |
|
0020 6000.10 | 7,000.00 | 1.000 | 7,000.00
|
ABUTMENT NO.1 EXCAVATION | LS | 1.000 | 7,000.00
|
| | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
0021 6000.11 | 7,000.00 | 1.000 | 7,000.00
|
ABUTMENT NO.2 EXCAVATION | LS | 1.000 | 7,000.00
|
| | 1.000 | 7,000.00
|
| | 0.000 | 0.00
|
| | |
|
0022 6000.60 | 12,500.00 | 1.000 | 12,500.00
|
PIER NO.1 EXCAVATION | LS | 1.000 | 12,500.00
|
| | 1.000 | 12,500.00
|
| | 0.000 | 0.00
|
| | |
|
0023 6000.61 | 12,500.00 | 1.000 | 12,500.00
|
PIER NO.2 EXCAVATION | LS | 1.000 | 12,500.00
|
| | 1.000 | 12,500.00
|
| | 0.000 | 0.00
|
| | |
|
0024 6005.78 | 650.00 | 12.000 | 7,800.00
|
EXPANSION BEARING, TFE TYPE | EACH | 12.000 | 7,800.00
|
| | 12.000 | 7,800.00
|
| | 0.000 | 0.00
|
| | |
|
0025 6005.83 | 600.00 | 4.000 | 2,400.00
|
FIXED BEARING | EACH | 4.000 | 2,400.00
|
| | 4.000 | 2,400.00
|
| | 0.000 | 0.00
|
| | |
|
0026 6010.22 | 300.00 | 309.300 | 92,790.00
|
CLASS 47B-20 CONCRETE FOR BRIDGE | m3 | 309.300 | 92,790.00
|
| | 309.300 | 92,790.00
|
| | 0.000 | 0.00
|
| | |
|
0027 6010.26 | 325.00 | 124.300 | 40,397.50
|
CLASS 47BD-30 CONCRETE FOR BRIDGE | m3 | 124.300 | 40,397.50
|
| | 124.300 | 40,397.50
|
| | 9.500 | 3,087.50
|
| | |
|
0028 6020.00 | 1.00 | 27,755.000 | 27,755.00
|
REINFORCING STEEL FOR BRIDGE | kg | 27,755.000 | 27,755.00
|
| | 27,755.000 | 27,755.00
|
| | -1,247.500 | -1,247.50
|
| | |
|
0029 6040.00 | 6,500.00 | 1.000 | 6,500.00
|
REMOVE STRUCTURE | EACH | 1.000 | 6,500.00
|
AT STA. 8+00.20 LT. | | 1.000 | 6,500.00
|
| | 0.000 | 0.00
|
| | |
|
0030 6071.12 | 85,000.00 | 1.000 | 85,000.00
|
STEEL SUPERSTRUCTURE | LS | 1.000 | 85,000.00
|
AT STA. 7+94.70 | | 1.000 | 85,000.00
|
| | 0.000 | 0.00
|
| | |
|
0031 6080.00 | 4.00 | 2,375.000 | 9,500.00
|
STRUCTURAL STEEL FOR SUBSTRUCTURE | kg | 2,375.000 | 9,500.00
|
| | 2,375.000 | 9,500.00
|
| | 0.000 | 0.00
|
| | |
|
0032 6105.02 | 36.00 | 1,945.000 | 70,020.00
|
ROCK RIPRAP, TYPE B | Mg | 1,945.000 | 70,020.00
|
| | 1,953.000 | 70,308.00
|
| | 823.000 | 29,628.00
|
| | |
|
0033 6200.00 | 80.00 | 482.800 | 38,624.00
|
CONCRETE PILING | m | 482.800 | 38,624.00
|
| | 473.813 | 37,905.04
|
| | 0.000 | 0.00
|
| | |
|
0034 6310.00 | 125.00 | 307.600 | 38,450.00
|
STEEL SHEET PILING | m2 | 307.600 | 38,450.00
|
| | 307.600 | 38,450.00
|
| | 0.000 | 0.00
|
| | |
|
0035 7020.00 | 1,000.00 | 4.000 | 4,000.00
|
BRIDGE APPROACH SECTIONS | EACH | 4.000 | 4,000.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0036 7021.45 | 875.00 | 4.000 | 3,500.00
|
BREAKAWAY CABLE TERMINAL | EACH | 4.000 | 3,500.00
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0402 6210.59 | 48.00 | 0.000 | 0.00
|
PILE CUT-OFF | m | 20.000 | 960.00
|
See 703.05 Para. 2 of the "97" Metric specs. | | 8.987 | 431.38
|
| | 0.000 | 0.00
|
| | |
|
GROUP 6 BRIDGE AT STA. 7+94.7 | | Contracted | 494,024.50
|
| | Current | 494,984.50
|
| | In place | 486,524.92
|
| | This Estimate | 34,876.00
|
| | |
|
GROUP 10 GENERAL ITEMS | | |
|
0037 0001.10 | 1.15 | 2,172.000 | 2,497.80
|
BARRICADE, TYPE III | BDAY | 2,172.000 | 2,497.80
|
| | 2,092.000 | 2,405.80
|
| | 79.000 | 90.85
|
| | |
|
0038 0001.30 | 0.65 | 362.000 | 235.30
|
TYPE B HIGH INTENSITY WARNING LIGHT | LDAY | 362.000 | 235.30
|
| | 0.000 | 0.00
|
| | 0.000 | 0.00
|
| | |
|
0039 0001.90 | 0.65 | 2,896.000 | 1,882.40
|
SIGN DAY | EACH | 2,896.000 | 1,882.40
|
| | 1,979.000 | 1,286.35
|
| | 72.000 | 46.80
|
| | |
|
0040 0030.10 | 2,000.00 | 1.000 | 2,000.00
|
MOBILIZATION | LS | 1.000 | 2,000.00
|
| | 1.000 | 2,000.00
|
| | 0.000 | 0.00
|
| | |
|
0401 0001.99 | 0.75 | 0.000 | 0.00
|
CONTRACTOR FURNISHED SIGN DAY | EACH | 1,000.000 | 750.00
|
Contractor furnished "crashworthy"signs. | | 1,191.000 | 893.25
|
| | 21.000 | 15.75
|
| | |
|
GROUP 10 GENERAL ITEMS | | Contracted | 6,615.50
|
| | Current | 7,365.50
|
| | In place | 6,585.40
|
| | This Estimate | 153.40
|
| | |
|
Totals for contract | | Contracted | 599,356.50
|
---|
| | Current | 601,066.50
|
---|
| | In place | 549,182.82
|
---|
| | This Estimate | 47,758.90
|
---|