Return to District Map


Nebraska Department of Roads
Estimate Summary to Contractor
Vendor ID:0083 WERNER CONSTRUCTION, INC.
Contract ID:3073A
Estimate Number:0016
Pay Period End Date:03.02.2002
Contract Location:
ROYAL - BRUNSWICKEstimate Type:PROG
Contractor:
WERNER CONSTRUCTION, INC.Date Let:01.11.2001
129 E 2ND STDate Awarded:01.18.2001
PO BOX 1087Date Contract Executed:02.08.2001
Date Notice to Proceed:02.08.2001
HASTINGS NE 68902-1087Date Work Began:04.23.2001
Phone:Date Physical Work Completed:
(402)463-4545Date Accepted:
Escrow Agent:
Surety Co:
UNIVERSAL SURETY COMPANY
Counties
ANTELOPE
Project Number PCT Fed State Project Number Description
31073A 000  0.000 F-20-5(1009)  GRAD CULV SEED BR GDRL BIT
Total to DatePrev to DateThis Estimate
Current Contract AmtTotal Earnings$2,854,779.94$2,819,291.14$35,488.80
$2,811,352.51Stockpiled Materials$.00$.00$.00
Original Contract AmtGross Earnings$2,854,779.94$2,819,291.14$35,488.80
$2,754,500.61Retainage$-25,000.00$-25,000.00$.00
Escrow Amount$.00$.00$.00
Percent CompleteSecurities Encumbered$.00$.00$.00
101.54%Net Earnings$2,829,779.94$2,794,291.14$35,488.80
Liquidated Damages$.00$.00$.00
Incentives$.00$.00$.00
Disincentives$.00$.00$.00
Other Contract Adj$.00$.00$.00
Appl of Training Adj$.00$.00$.00
Training Rates Adj$.00$.00$.00
Fuel Adj$-709.08$-709.08$.00
Bituminous Adj$.00$.00$.00
Autopay Adj$.00$.00$.00
Gasoline Adj$.00$.00$.00
Other Adj$.00$.00$.00
Price Adj$.00$.00$.00
Substandard Item Adj$.00$.00$.00
Asphalt Adj$.00$.00$.00
Diesel Fuel Adj$.00$.00$.00
Petrol Adj$.00$.00$.00
Total for Adjustments-$709.08-$709.08$.00
Payment$2,829,070.86$2,793,582.06$35,488.80
Project ManagerDiv. Head/Dist. Eng.
Becker, Roger03.13.2002Boyle, Pat03.13.2002
Constr. Estimate Eng.Materials Eng.
Bartos, Steve03.14.2002
Controller Div. Processed
Burling, Laurie03.14.2002
Detailed breakdown of stockpiled materials
Total remaining for contract:0.00
1. Contracted
2. Current
3. To date
Item Nbr        Item CodeUnit Price4. This Est
Item DescriptionUnitsQtyAmount
GROUP 1 GRADING
0001                          L006.00 150.0030.0004,500.00
COVER CROP SEEDING ha 30.0004,500.00
30.0004,500.00
0.0000.00

0002                          L022.11 6.004,812.00028,872.00
FABRIC SILT FENCE-LOW POROSITY m 4,812.00028,872.00
3,477.00020,862.00
0.0000.00

0003                          L022.12 8.0017.000136.00
FABRIC SILT FENCE-HIGH POROSITY m 17.000136.00
0.0000.00
0.0000.00

0004                          L022.25 6.702,229.00014,934.30
FABRIC SILT FENCE, TYPE COIR FIBER m 2,229.00014,934.30
1,648.21011,043.01
0.0000.00

0005                          L022.75 8.00615.0004,920.00
TEMPORARY SILT CHECK m 615.0004,920.00
337.7002,701.60
0.0000.00

0006                          0030.10 9,600.001.0009,600.00
MOBILIZATION LS 1.0009,600.00
1.0009,600.00
0.0000.00

0007                          1000.00 110.00282.00031,020.00
LARGE TREE REMOVAL EACH282.00031,020.00
886.00097,460.00
0.0000.00

0008                          1010.00 1.0032,467.00032,467.00
EXCAVATION m3 0.0000.00
0.0000.00
-32,467.000-32,467.00

0009                          1010.10 2.5454,925.000139,509.50
EXCAVATION, BORROW m3 54,925.000139,509.50
63,450.808161,165.04
0.0000.00

0010                          1011.00 1.204,370.0005,244.00
WATER kL 4,370.0005,244.00
0.0000.00
0.0000.00

0011                          1012.00 64.00160.00010,240.00
RIGHT-OF-WAY MARKERS EACH160.00010,240.00
162.00010,368.00
0.0000.00

0012                          1102.00 1.009,400.0009,400.00
REMOVE ASPHALT SURFACE m2 9,400.0009,400.00
7,380.3117,380.31
671.543671.54

0013                          1106.00 3.75146.000547.50
REMOVE DRIVEWAY m2 146.000547.50
174.428654.11
0.0000.00

0014                          1701.24 40.00327.00013,080.00
600 mm DRIVEWAY CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 327.00013,080.00
425.00017,000.00
0.0000.00

0015                          7017.00 8.00145.1001,160.80
REMOVE GUARDRAIL m 145.1001,160.80
145.5001,164.00
0.0000.00

0016                          8091.00 15.00484.0007,260.00
GRANULAR BACKFILL m3 484.0007,260.00
510.7717,661.57
0.0000.00

0409                          1010.01 1.000.0000.00
EXCAVATION (ESTABLISHED QUANTITY) m3 32,467.00032,467.00
32,467.00032,467.00
32,467.00032,467.00

GROUP 1 GRADINGContracted312,891.10
Current312,891.10
In place384,026.64
This Estimate671.54

GROUP 4 CULVERTS
0017                          P070.24 78.00120.0009,360.00
600 mm CULVERT PIPE, TYPE 2,3,4,5,6,7 OR 8 m 120.0009,360.00
120.0009,360.00
0.0000.00

0018                          P120.24 96.0034.5003,312.00
600 mm CULVERT PIPE, TYPE 2 m 34.5003,312.00
34.5003,312.00
0.0000.00

0019                          P120.36 189.3611.5002,177.64
900 mm CULVERT PIPE, TYPE 2 m 11.5002,177.64
11.5002,177.64
0.0000.00

0020                          P300.24 56.0066.5003,724.00
600 mm CULVERT PIPE, TYPE 3,4 OR 5 m 66.5003,724.00
66.5003,724.00
0.0000.00

0021                          P300.30 83.0033.0002,739.00
750 mm CULVERT PIPE, TYPE 3,4 OR 5 m 33.0002,739.00
33.0002,739.00
0.0000.00

0022                          P300.36 96.0022.5002,160.00
900 mm CULVERT PIPE, TYPE 3,4 OR 5 m 22.5002,160.00
22.5002,160.00
0.0000.00

0023                          P400.24 85.0015.0001,275.00
600 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 15.0001,275.00
15.0001,275.00
0.0000.00

0024                          P400.30 75.0021.5001,612.50
750 mm CULVERT PIPE, TYPE 2,5,7 OR 8 m 21.5001,612.50
21.5001,612.50
0.0000.00

0025                          0030.40 2,500.001.0002,500.00
MOBILIZATION LS 1.0002,500.00
1.0002,500.00
0.0000.00

0026                          4004.50 3.96120.000475.20
CAST IRON GRATE AND FRAME kg 120.000475.20
120.000475.20
0.0000.00

0027                          4015.50 1,200.003.0003,600.00
RECONSTRUCT MANHOLE EACH3.0003,600.00
3.0003,600.00
0.0000.00

0028                          4040.00 169.0042.0007,098.00
REMOVE HEADWALLS FROM CULVERTS EACH42.0007,098.00
42.0007,098.00
0.0000.00

0029                          4044.00 1,800.001.0001,800.00
PREPARATION OF STRUCTURE EACH1.0001,800.00
AT STA. 630+86.4 1.0001,800.00
0.0000.00

0030                          4044.01 3,500.001.0003,500.00
PREPARATION OF STRUCTURE EACH1.0003,500.00
AT STA. 642+90.1 1.0003,500.00
0.0000.00

0031                          4044.02 2,145.001.0002,145.00
PREPARATION OF STRUCTURE EACH1.0002,145.00
AT STA. 654+98.3 1.0002,145.00
0.0000.00

0032                          4044.03 2,356.001.0002,356.00
PREPARATION OF STRUCTURE EACH1.0002,356.00
AT STA. 831+79.8 1.0002,356.00
0.0000.00

0033                          4050.01 17.00372.0006,324.00
EXCAVATION FOR PIPE, PIPE-ARCH CULVERTS, AND HEADWALLS m3 372.0006,324.00
387.2106,582.57
0.0000.00

0034                          4051.01 24.36134.0003,264.24
EXCAVATION FOR BOX CULVERTS m3 134.0003,264.24
174.7504,256.91
0.0000.00

0035                          4101.06 348.63125.37043,707.74
CLASS 47B-20 OR AX-20 CONCRETE FOR BOX CULVERT m3 125.37043,707.74
125.37043,707.75
0.0000.00

0036                          4105.58 1,000.000.600600.00
CLASS 47B-20 CONCRETE FOR INLET AND JUNCTION BOX m3 0.600600.00
0.600600.00
0.0000.00

0037                          4107.07 1,000.004.4604,460.00
CLASS 47B-20 OR AX-20 CONCRETE FOR CONCRETE COLLARS m3 4.4604,460.00
4.4604,460.00
0.0000.00

0038                          4151.00 1.397,351.00010,217.89
REINFORCING STEEL FOR BOX CULVERT kg 7,351.00010,217.89
7,351.00010,217.89
0.0000.00

0039                          4155.50 2.0018.00036.00
REINFORCING STEEL FOR INLET AND JUNCTION BOX kg 18.00036.00
18.00036.00
0.0000.00

0040                          4157.00 2.00208.000416.00
REINFORCING STEEL FOR COLLARS kg 208.000416.00
208.000416.00
0.0000.00

0041                          4310.24 150.0030.0004,500.00
600 mm FLARED-END SECTION EACH30.0004,500.00
30.0004,500.00
0.0000.00

0042                          4310.30 200.0010.0002,000.00
750 mm FLARED-END SECTION EACH10.0002,000.00
10.0002,000.00
0.0000.00

0043                          4310.36 560.008.0004,480.00
900 mm FLARED-END SECTION EACH8.0004,480.00
8.0004,480.00
0.0000.00

0601                          4051.12 34.860.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF BOX CULVERT m3 38.4201,339.32
Gravel for Box Culvert at Sta 654+98 and 642+90 40.7501,420.55
0.0000.00

0602                          4051.13 34.860.0000.00
GRANULAR MATERIAL FOR FOUNDATION OF PIPE CULVERT AND HEADWAL m3 16.540576.58
Gravel for Culvert Pipe Foundation at Sta 644+16 14.210495.36
0.0000.00

GROUP 4 CULVERTSContracted129,840.21
Current131,756.12
In place133,007.37
This Estimate0.00

GROUP 5 SEEDING
0044                          L001.01 1,599.0020.00031,980.00
SEEDING, TYPE A ha 20.00031,980.00
21.69934,696.70
0.0000.00

0045                          L001.02 989.0010.0009,890.00
SEEDING, TYPE B ha 10.0009,890.00
9.6409,533.96
0.0000.00

0046                          L020.01 6.252,997.00018,731.25
EROSION CONTROL, TYPE A m2 2,997.00018,731.25
2,921.00018,256.26
0.0000.00

0047                          L020.09 16.00429.0006,864.00
EROSION CONTROL, TYPE AAA m2 429.0006,864.00
0.0000.00
0.0000.00

0048                          L020.10 1.603,606.0005,769.60
EROSION CONTROL, TYPE HV m2 3,606.0005,769.60
2,987.0004,779.20
0.0000.00

0049                          L021.01 17.00132.0002,244.00
EROSION CHECKS, TYPE A BALE132.0002,244.00
126.0002,142.00
0.0000.00

0050                          L021.06 16.00810.00012,960.00
EROSION CHECKS, TYPE HV BALE810.00012,960.00
390.0006,240.00
0.0000.00

0051                          L032.75 60.00135.0008,100.00
MULCH Mg 135.0008,100.00
143.3658,601.90
0.0000.00

0052                          0030.50 3,000.001.0003,000.00
MOBILIZATION LS 1.0003,000.00
1.0003,000.00
0.0000.00

GROUP 5 SEEDINGContracted99,538.85
Current99,538.85
In place87,250.02
This Estimate0.00

GROUP 6 BRIDGE AT STA. 639+21.87
0053                          0030.60 28,000.001.00028,000.00
MOBILIZATION LS 1.00028,000.00
1.00028,000.00
0.0000.00

0054                          3050.15 270.00143.30038,691.00
CONCRETE FOR PAVEMENT APPROACHES CLASS 47BD-30 m3 143.30038,691.00
143.30038,691.00
0.0000.00

0055                          3051.10 1.609,315.00014,904.00
EPOXY COATED REINFORCING STEEL FOR PAVEMENT APPROACHES kg 9,315.00014,904.00
9,315.00014,904.00
0.0000.00

0056                          6000.10 9,000.001.0009,000.00
ABUTMENT NO.1 EXCAVATION LS 1.0009,000.00
1.0009,000.00
0.0000.00

0057                          6000.11 9,000.001.0009,000.00
ABUTMENT NO.2 EXCAVATION LS 1.0009,000.00
1.0009,000.00
0.0000.00

0058                          6005.35 280.0028.6008,008.00
PRECOMPRESSED POLYURETHANE FOAM JOINT m 28.6008,008.00
28.6008,008.00
0.0000.00

0059                          6005.60 80.008.000640.00
ELASTOMERIC BEARING EACH8.000640.00
8.000640.00
0.0000.00

0060                          6007.01 70.00134.7009,429.00
CLASS I REPAIR m2 134.7009,429.00
124.8388,738.66
0.0000.00

0061                          6007.02 180.0026.9004,842.00
CLASS II REPAIR m2 26.9004,842.00
9.7131,748.34
0.0000.00

0062                          6007.03 200.004.000800.00
CLASS III REPAIR m2 4.000800.00
3.402680.40
0.0000.00

0063                          6008.40 130.00190.00024,700.00
PLACING, FINISHING, AND CURING CONCRETE OVERLAY-SF m2 190.00024,700.00
188.29224,477.96
0.0000.00

0064                          6010.22 680.0051.20034,816.00
CLASS 47B-20 CONCRETE FOR BRIDGE m3 51.20034,816.00
51.20034,816.00
0.0000.00

0065                          6010.26 740.0013.3009,842.00
CLASS 47BD-30 CONCRETE FOR BRIDGE m3 13.3009,842.00
13.3009,842.00
0.0000.00

0066                          6011.11 28,000.001.00028,000.00
PRECAST/PRESTRESSED CONCRETE SUPERSTRUCTURE LS 1.00028,000.00
AT STA. 639+21.87 1.00028,000.00
0.0000.00

0067                          6016.02 400.009.5003,800.00
CONCRETE FOR OVERLAYS-SF m3 9.5003,800.00
10.0004,000.00
0.0000.00

0068                          6030.00 30,000.001.00030,000.00
PREPARATION OF BRIDGE EACH1.00030,000.00
AT STA. 639+21.87 1.00030,000.00
0.0000.00

0069                          6105.02 30.00234.0007,020.00
ROCK RIPRAP, TYPE B Mg 234.0007,020.00
245.7747,373.22
0.0000.00

0070                          6131.50 1.504,450.0006,675.00
EPOXY COATED REINFORCING STEEL kg 4,450.0006,675.00
4,450.0006,675.00
3,360.0005,040.00

0071                          6200.00 120.00264.60031,752.00
CONCRETE PILING m 264.60031,752.00
264.60031,752.00
0.0000.00

0072                          8091.00 30.00142.8004,284.00
GRANULAR BACKFILL m3 142.8004,284.00
142.8004,284.00
0.0000.00

0123                          0096.00 -3,382.740.0000.00
DEDUCTION LS 1.000-3,382.74
Deduction for low strength in concrete - See Construction Office letter dated September 25, 2001 1.000-3,382.74
0.0000.00

0124                          0096.00 -471.890.0000.00
DEDUCTION LS 1.000-471.89
Deduction for low density on the Riprap, Type "B" 1.000-471.89
0.0000.00

GROUP 6 BRIDGE AT STA. 639+21.87Contracted304,203.00
Current300,348.37
In place296,775.95
This Estimate5,040.00

GROUP 7 GUARDRAIL
0073                          0030.70 1,659.721.0001,659.72
MOBILIZATION LS 1.0001,659.72
1.0001,659.72
0.04269.71

0074                          7011.20 49.0045.7202,240.28
W-BEAM GUARDRAIL m 45.7202,240.28
45.7202,240.28
0.0000.00

0075                          7020.00 1,250.004.0005,000.00
BRIDGE APPROACH SECTIONS EACH4.0005,000.00
4.0005,000.00
0.0000.00

0076                          7021.70 1,750.004.0007,000.00
GUARDRAIL END TREATMENT, SRT-350 EACH4.0007,000.00
4.0007,000.00
0.0000.00

GROUP 7 GUARDRAILContracted15,900.00
Current15,900.00
In place15,900.00
This Estimate69.71

GROUP 9 BITUMINOUS
0077                          0002.40 30.00772.59023,177.70
TEMPORARY SOLID LINES StaM772.59023,177.70
772.59023,177.70
0.94328.29

0078                          0002.45 27.00386.29010,429.83
TEMPORARY BROKEN LINES StaM386.29010,429.83
386.29010,429.82
-2.338-63.13

0079                          0030.90 43,500.001.00043,500.00
MOBILIZATION LS 1.00043,500.00
1.00043,500.00
0.0000.00

0080                          1020.03 15.0033.000495.00
DELINEATOR, TYPE III EACH33.000495.00
33.000495.00
0.0000.00

0081                          2001.00 9.95216.0002,149.20
GRAVEL SURFACE COURSE m3 216.0002,149.20
105.9201,053.90
0.0000.00

0082                          2021.00 50.003.000150.00
MAILBOX POST EACH3.000150.00
2.000100.00
0.0000.00

0083                          3013.10 78.00105.7008,244.60
CONCRETE CLASS 47B-20 BARRIER CURB m 105.7008,244.60
100.0007,800.00
0.0000.00

0084                          3020.26 38.00165.0006,270.00
CONCRETE CLASS 47B-25 DRIVEWAY m2 165.0006,270.00
164.8206,263.16
0.0000.00

0085                          4015.00 500.003.0001,500.00
ADJUST MANHOLE TO GRADE EACH3.0001,500.00
3.0001,500.00
0.0000.00

0086                          8111.00 315.00241.86476,187.16
SHOULDER SUBGRADE PREPARATION StaM241.86476,187.16
245.31277,273.28
0.0000.00

0087                          9000.75 18.50800.00014,800.00
ASPHALTIC CONCRETE FOR STATE MAINTENANCE PATCHING, TYPE Mg 800.00014,800.00
SP2(12.5) 304.5005,633.26
0.0000.00

0088                          9005.00 28.50500.00014,250.00
ASPHALTIC CONCRETE FOR PATCHING, TYPE Mg 500.00014,250.00
SP2(12.5) 140.4204,001.97
0.0000.00

0089                          9005.23 12.7523,660.000301,665.00
ASPHALTIC CONCRETE, TYPE SPS Mg 23,660.000301,665.00
24,032.125306,409.61
0.0000.00

0090                          9005.30 18.5029,560.000546,860.00
ASPHALTIC CONCRETE, TYPE SP2(12.5) Mg 29,560.000546,860.00
29,831.580551,884.24
0.0000.00

0091                          9009.00 3.503,774.00013,209.00
PLACEMENT OF ASPHALTIC CONCRETE FOR DRIVEWAYS ANDINTERSECTIONS m2 3,774.00013,209.00
3,794.77913,281.73
488.0991,708.35

0092                          9020.92 200.0043.2008,640.00
PERFORMANCE GRADED BINDER (58-28) FOR STATE MAINTENANCEPATCHING Mg 43.2008,640.00
18.2233,644.60
0.0000.00

0093                          9021.01 200.001,623.240324,648.00
PERFORMANCE GRADED BINDER (64-22) Mg 1,623.240324,648.00
1,975.802395,160.40
0.0000.00

0094                          9021.03 200.001,277.640255,528.00
PERFORMANCE GRADED BINDER (58-28) Mg 1,277.640255,528.00
920.452184,090.40
0.0000.00

0095                          9030.00 10.00470.0004,700.00
CONSTRUCTING ASPHALTIC CONCRETE CURB m 470.0004,700.00
467.3004,673.00
0.0000.00

0096                          9033.00 1,500.002.0003,000.00
CONSTRUCTING ASPHALTIC CONCRETE ISLAND NOSE EACH2.0003,000.00
2.0003,000.00
0.0000.00

0097                          9034.00 2.503,774.0009,435.00
PREPARATION OF INTERSECTIONS AND DRIVEWAYS m2 3,774.0009,435.00
3,068.2537,670.64
374.088935.22

0098                          9053.00 0.2699,600.00025,896.00
TACK COAT L 99,600.00025,896.00
150,075.00539,019.50
29,311.4487,620.98

0099                          9111.00 2.251,317.0002,963.25
WATER kL 1,317.0002,963.25
96.580217.31
0.0000.00

0100                          9170.00 175.0021.5903,778.25
EARTH SHOULDER CONSTRUCTION StaM21.5903,778.25
21.5903,778.25
0.0000.00

0101                          9173.00 900.008.0007,200.00
SUBGRADE PREPARATION StaM8.0007,200.00
13.35912,023.10
0.0000.00

0102                          9179.23 405.00119.03248,207.96
COLD MILLING, CLASS 3 StaM119.03248,207.96
131.34353,193.92
0.0000.00

0103                          9179.34 2.502,080.0005,200.00
COLD MILLING, CLASS 4 m2 2,080.0005,200.00
2,080.0005,200.00
0.0000.00

0104                          9188.50 25.00197.0004,925.00
SURFACING UNDER GUARDRAIL m2 197.0004,925.00
197.0004,925.00
0.0000.00

0105                          9300.50 4,000.001.0004,000.00
ASPHALT PAVEMENT SMOOTHNESS TESTING LS 1.0004,000.00
1.0004,000.00
0.0000.00

0401                          9009.75 46.620.0000.00
TEMPORARY SURFACING m2 154.4607,200.93
154.4607,200.93
0.0000.00

0402                          9179.34 3.310.0000.00
COLD MILLING, CLASS 4 m2 1,573.8005,209.28
1,573.8005,209.28
0.0000.00

0403                          9110.12 147.000.0000.00
RENTAL OF SCRAPER, FULLY OPERATED HOUR5.000735.00
627 Scraper 5.000735.00
0.0000.00

0404                          9110.02 68.250.0000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR7.000477.75
7.000477.75
0.0000.00

0405                          9110.36 68.250.0000.00
RENTAL OF TRUCK/TRAILER, FULLY OPERATED HOUR27.0001,842.75
27.0001,842.75
0.0000.00

0406                          9110.01 89.250.0000.00
RENTAL OF LOADER, FULLY OPERATED HOUR7.000624.75
966 Loader 7.000624.75
0.0000.00

0407                          9110.20 54.600.0000.00
RENTAL OF SELF-PROPELLED ROLLER, FULLY OPERATED HOUR4.000218.40
4.000218.40
0.0000.00

0408                          9173.32 0.420.0000.00
SUBGRADE TRIMMING m2 1,573.800661.00
1,573.800661.00
0.0000.00

0410                          9022.00 1.970.0000.00
ANTI-STRIPPING ADDITIVE L 9,872.00019,447.84
9,872.00019,447.84
9,872.00019,447.84

0603                          9300.60 0.41630.0000.00
SMOOTHNESS INCENTIVE-ASPHALTIC CONCRETE Mg 10,784.6604,489.65
Smoothness Incentive Pay Factor 102.25% 10,784.6604,489.65
0.0000.00

0604                          9300.77 4.500.0000.00
SMOOTHNESS INCENTIVE-PERFORMANCE GRADED BINDER Mg 593.1562,669.20
Smoothness Incentive Pay Factor 102.25% 593.1562,669.20
0.0000.00

0605                          9300.56 0.510.0000.00
SUPERPAVE QUALITY INCENTIVE Mg 29,831.58015,214.11
Superpave Quality Incentive Pay Factor 102.74% 29,831.58015,214.11
0.0000.00

GROUP 9 BITUMINOUSContracted1,771,008.95
Current1,829,799.60
In place1,832,190.45
This Estimate29,677.55

GROUP 10 GENERAL ITEMS
0106                          0001.08 0.5014,840.0007,420.00
BARRICADE, TYPE II BDAY14,840.0007,420.00
15,486.0007,743.00
0.0000.00

0107                          0001.10 2.501,640.0004,100.00
BARRICADE, TYPE III BDAY1,640.0004,100.00
3,292.0008,230.00
0.0000.00

0108                          0001.30 2.50820.0002,050.00
TYPE B HIGH INTENSITY WARNING LIGHT LDAY820.0002,050.00
840.0002,100.00
0.0000.00

0109                          0001.90 0.5020,817.00010,408.50
SIGN DAY EACH20,817.00010,408.50
17,324.0008,662.00
0.0000.00

0110                          0002.30 3.00230.000690.00
PAVEMENT MARKING REMOVAL m 230.000690.00
239.570718.71
0.0000.00

0111                          0002.39 3.00600.0001,800.00
TEMPORARY PAVEMENT MARKING, TYPE II m 600.0001,800.00
2,056.1006,168.30
0.0000.00

0112                          0003.10 175.00160.00028,000.00
FLAGGING DAY 160.00028,000.00
199.50034,912.50
0.0000.00

0113                          0003.20 275.0030.0008,250.00
FURNISHING AND OPERATING PILOT VEHICLE DAY 30.0008,250.00
33.0009,075.00
0.0000.00

0114                          0003.51 50.00148.0007,400.00
INSTALL CONCRETE PROTECTION BARRIER m 148.0007,400.00
150.0007,500.00
0.0000.00

0115                          0003.70 400.002.000800.00
TEMPORARY RUMBLE STRIP EACH2.000800.00
2.000800.00
0.0000.00

0116                          0003.75 11,000.001.00011,000.00
TEMPORARY TRAFFIC SIGNAL EACH1.00011,000.00
1.00011,000.00
0.0000.00

0117                          0010.04 1,500.001.0001,500.00
FIELD OFFICE EACH1.0001,500.00
1.0001,500.00
0.0000.00

0118                          0030.00 5,000.001.0005,000.00
MOBILIZATION LS 1.0005,000.00
1.0005,000.00
0.0000.00

0119                          9110.01 60.00180.00010,800.00
RENTAL OF LOADER, FULLY OPERATED HOUR180.00010,800.00
7.500450.00
0.50030.00

0120                          9110.02 75.0040.0003,000.00
RENTAL OF MOTOR GRADER, FULLY OPERATED HOUR40.0003,000.00
8.000600.00
0.0000.00

0121                          9110.03 55.00180.0009,900.00
RENTAL OF DUMP TRUCK, FULLY OPERATED HOUR180.0009,900.00
14.000770.00
0.0000.00

0122                          9110.07 50.00180.0009,000.00
RENTAL OF SKID LOADER, FULLY OPERATED HOUR180.0009,000.00
8.000400.00
0.0000.00

GROUP 10 GENERAL ITEMSContracted121,118.50
Current121,118.50
In place105,629.51
This Estimate30.00

Totals for contractContracted2,754,500.61
Current2,811,352.54
In place2,854,779.94
This Estimate35,488.80